S02 - Attachment 15 - Quality Control Requirements Plan SCE 11-19-2018.docx

DOCX document 19 KB Posted

Attached to
Z2DA--VAMC Garland Roof Replacement 549-157R (VA-21-00007690)
Solicitation number
36C77621R0023_1
Issued by

About this file

This document outlines quality control requirements for a federal construction contract to replace roofs at the Veterans Affairs Medical Center in Garland, Texas. The contractor must establish and maintain an effective quality control system that complies with FAR clauses and covers all onsite and offsite design and construction operations, including work by subcontractors and consultants. Key responsibilities of the contractor include submitting a Quality Control Plan within 15 days of the notice to proceed that details the quality control organization, personnel qualifications and responsibilities, procedures for submittals, testing, tracking deficiencies, and reporting. The plan requires acceptance by the Contracting Officer's Representative prior to starting any design or construction work. The contract also specifies additional requirements for a Design Quality Control Plan, including independent technical reviews and use of discipline-specific checklists during design and quality control reviews.

View the file

Other files

File Type Posted
S02 - Attachment 11- Section 01 33 23 - Shop Drawings- Products-and Samples.docx DOCX document
S02 - Attachment 2 - Statement of Work - Garland Roof Replacement - Final (12-3-2020 YMR).docx DOCX document
S02 - Attachment 1 - Spec 001121 - RFP to DB (12-29-2020 YMR).doc DOC document
S02 - Attachment 14 - Section 01 32 16.16 - Network Analysis Schedules (Design-Build Only).docx DOCX document
S02 - Attachment 7- Contractor Safety and Environmental Record Evaluation Form.docx DOCX document
S02 - Attachment 8- Past Performance Questionnaire.docx DOCX document
S02 - Attachment 6 - VHA Master Specifications.docx DOCX document
S02 - Attachment 12 - Section 01 35 26 - Safety Requirements.docx DOCX document
S02 - Attachment 13 - Section 01 57 19 - Temporary Evironmental Controls.doc DOC document
S02 - Attachment 10 - Section 01 42 19 - Reference Standards.docx DOCX document
S02 - 36C77621R0023_1.docx DOCX document
S02 - Attachment 9 - Release of Claims.docx DOCX document
S02 - Attachment 18 - Section 01 32 16 Project Schedules.doc DOC document
S02 - Attachment 5 - Labor Standards Wage Determination - Dallas County TX.pdf PDF
S02 - Attachment 16- Section 07 51 00 - Built-Bituminous Roofing.docx DOCX document
S02 - Attachment 17 - Section 07 72 00 - Roofing Accessories.docx DOCX document
S02 - Attachment 3 - Drawings.pdf PDF
S02 - Attachment 4 - Construction Wage Determination - Dallas County TX.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY CONTROL PLAN REQUIREMENTS

1.1 GENERAL REQUIREMENTS

Establish and maintain an effective quality control (QC) system in compliance with the Contract Clause titled "Inspection of Construction." QC consists of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. Cover all design and construction operations, both onsite and offsite, and be keyed to the proposed design and construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

1.2 QUALITY CONTROL PLAN

Submit to the COR no later than fifteen (15) calendar days after receipt of Notice to Proceed, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of the Contract Clause titled "Inspection of Construction." Design and construction will be permitted to begin only after the COR acceptance of the CQC Plan.

1.2.1 Content of the CQC Plan

Include, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, designers of record, consultants, Architect-Engineers (A-E), fabricators, suppliers, and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement all aspects of the work specified.

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, designers of record, consultants, Architect-Engineers (A-E), offsite fabricators, and suppliers.

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test.

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats.

i. A list of the definable features of design and construction work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable feature under a particular section.

1.2.2 Additional Requirements for Design Quality Control (DQC) Plan

The following additional requirements apply to the Design Quality Control (DQC) plan:

(1) Provide and maintain a Design Quality Control (DQC) Plan as an effective quality control program which will assure that all services required by this design-build contract are performed and provided in a manner that meets professional architectural and engineering quality standards. As a minimum, all documents must be technically reviewed by competent, independent reviewers identified in the DQC Plan. The same element that produced the product shall not perform the independent technical review (ITR). Correct errors and deficiencies in the design documents prior to submitting them to the Government.

(2) Include the design in the master project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. This should be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. Include review and correction periods associated with each item. This should be a forward planning as well as a project monitoring tool. The schedule reflects calendar days and not dates for each activity. If scheduled changes are proposed by the contractor, submit a proposed revised schedule to the COR and Contracting Officer reflecting the changes within seven (7) calendar days for review and acceptance. Include in the DQC Plan the discipline-specific checklists to be used during the design and quality control of each submittal. Submit at each design phase as part of the project documentation these completed checklists.

(3) Implement the DCQC Plan by the DB A/E member who has the responsibility of being cognizant of and assuring that all documents on the project have been coordinated. This individual must be a person who has verifiable engineering or architectural design experience and is a registered professional engineer or architect. Notify the Contracting Officer & COR, in writing, of the name of the individual, and the name of an alternate person assigned to the position.

1.2.3 Acceptance of Plan

COR acceptance of the Contractor's plan is required prior to the start of design and construction. Acceptance is conditional and will be predicated on satisfactory performance during the design and construction. The Government reserves the right to require the Contractor to make changes in his CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

1.2.4 Notification of Changes

The Contractor will notify the Contracting Officer & COR in writing of all proposed changes for CO / COR for review and acceptance.

1.3 COORDINATION MEETING

After the Pre-Work Conference, before start of design or construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer or Authorized Representative and discuss the Contractor's quality control system. Submit the CQC Plan a minimum of thirty (30) calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations, design activities, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the contractor and submitted to the COR within 48 hours. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which may require corrective action by the Contractor

-END-