This is a Statement of Work (SOW) for Project 578-22-026, Replace 2nd Floor Roofs of Building 200 at Edward Hines Jr. Veterans Affairs Hospital in Hines, Illinois. The project addresses Facility Condition Assessment deficiencies by replacing and repairing the 2nd floor roof system, including partial replacement of inverted membrane roof pavers, repair of drains and flashings, removal of a gypsum plank deck and replacement with steel decking and new TPO single-ply roofing, installation of fall protection handrails, stairs, and crossover steps, removal of abandoned equipment and vegetation, and comprehensive roof cleaning. The work must maintain compliance with the existing Hydro-Tech roof warranty and accommodate the hospital's continuous 24/7 operations.
The base bid scope must be completed within 360 calendar days of Notice to Proceed, with an alternate bid option providing completion within 300 calendar days by excluding deductive alternate 1 (located in Gridlines D-F and 5-10). The contractor must submit comprehensive preconstruction documentation within 30 days of NTP including logistics, security, phasing, and construction safety plans; maintain infection control barriers using Edge Guard rigid panels with negative pressure monitoring; coordinate all work with the Contracting Officer's Representative; obtain contractor badging and PIV credentials; provide certified payroll and waste reports with each invoice; submit all shop drawings and submittals seven calendar days before construction; maintain OSHA 30-hour certified site superintendents and OSHA 10-hour certified personnel; and complete closeout documentation including as-built drawings and warranties within 30 days of punch list acceptance. The Department of Veterans Affairs Veterans Health Administration is the contracting agency, with Martin Pint (Engineering Service) as the primary point of contact.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Replace 2nd Floor Roof of Building 200 Project 578-22-026
February 2, 2026
Attachments:
1. Hines Documents for Construction
2. PCRA - Pre-Construction Risk Assessment
3. ILSM - Interim Life Safety Measures
4. ICRA - Infection Control Risk Assessment
5. Specifications Book
6. Drawings – Bid Set
7. Roof Photos (Current Conditions)
8. Room Photos (Current Conditions)
References:
1. VA’s Technical Information Library (TIL)
2. Master Construction Specifications (PG-18-1)
3. Standard Details (PG-18-4)
4. Environmental Planning Guidance (PG-18-17)
5. 2011 Asbestos Survey for EHVAH Edward Hines Veterans Affairs Hospital
6. 2013 Historic Preservation Plan for the EHVAH
7. 2020 Statement of Conditions Survey for the EHVAH
8. 2022 Facility Condition Assessment for the EHVAH (available on request)
A) Mission
The Engineering Service’s mission is total oversight and management of the Environment of Care, as it pertains to the physical infrastructure and base plant operations, at the Edward Hines VA Hospital. Engineering support is for customers that includes, but is not limited to, patients, visitors, clinical staff, and administrative employees.
B) Goals
The goals of this project are to:
1. Replace, repair, and maintain selected areas of the existing protected membrane roofing system including replacing pavers and replacing or maintaining flashings and drains.
2. Removing unused equipment and supports.
3. Install fall protection handrail system where required.
4. Install stairs between roof levels, and crossover steps for pipe and obstacle locations.
5. Remove the current single-ply roof area and existing gypsum plank deck and replace with a new steel deck and single-ply roof system. (Deductive bid item)
6. Remove vegetation and accumulated trash and debris from the roof areas and dispose of properly.
7. Accomplish the work in accordance with Hydro-Tech requirement and procedures to maintain the existing warranty.
C) Current Conditions
The inverted membrane roof system has been damaged by contractors and maintenance personnel, requiring replacement of ballast pavers. Roof drains have been damaged, strainers are missing, and existing equipment flashings need to be repaired. Railings, stairs, and crossovers are inadequate, unsafe, or non-existent. Abandoned equipment and supports need to be removed and the roofing system patched. Vegetation growing on the roof system could ultimately damage the roof system. Trash, debris, and other unneeded materials are safety hazards, unsightly, and could damage the roofing system.
D) Justification
The project is in keeping with the vision statement of the Veterans Affairs, “To provide veterans the world-class benefits and services they have earned - and to do so by adhering to the highest standards of compassion, commitment, excellence, professionalism, integrity, accountability, and stewardship.” This project is necessary to correct the following FCA deficiencies.
1) FCA Record Number 279417 is graded as “F” – In general, 2nd and 3rd floor roofs are Hydrotech inverted membrane roof system installed in 2012 with new insulation and roof pavers is failing.
2) FCA Record Number 363906 is graded as “D” – Approximately 30% of the insulated concrete pavers on the 2nd Floor roof are broken or cracked. Replace broken and cracked pavers.
3) FCA Record Number 363908 is graded as “D” – Replace parapet handrails where façade repair occurred. Provide permanent handrails at 2nd Floor parapets.
In addition to the FCA deficiencies, the following items are included – The single ply roof area on the second floor, east side of the building, is constructed on top of a gypsum plank deck that is in questionable condition and has been deemed a safety hazard. Stairs are needed to transition between different roof levels for maintenance and operations personnel. Crossovers are also required to allow personnel to cross over piping, conduit, parapet wall, equipment frames, etc.
E) Objectives
The objectives of this project are to:
1) Repair and maintain the existing inverted membrane roof system by partial replacement of pavers and spot repairs of drains and flashings, etc.
2) Provide a structurally sound roof deck in the existing TPO roof area by removing the existing gypsum plank deck and replacing with steel decking and new TPO roof.
| 3) | Correct safety deficiencies by installing handrails, stairs, and crossovers. |
| 4) | Preserve the integrity of the existing roof system by removing vegetation growing in gaps around the ballast pavers. |
| 5) | Provide a clean and safe roof by removing unneeded equipment, trash and debris from the roof. |
| 6) | Perform the work in a manner least likely to interfere with the daily operations of this clinic. |
F) Acronyms and Definitions
The following is a listing of acronyms and/or definitions to terms that may be used in this document.
| ABAAS | Architectural Barriers Act Accessibility Standards |
| ACM | Asbestos Containing Material |
| A/E | Architect and Engineer (firm) |
| AHU | Air Handling Unit |
| BAS | Building Automation System |
| CCE | Construction Cost Estimate |
| CCD | Contract Completion Date |
| CLIN | Contract Line-Item Number |
| CO | Contracting Officer |
| COR | Contracting Officers Representative as delegated by the CO |
| CS | Contracting Specialist assigned by the CO |
| EHRM | Electronic Healthcare Records Management |
| EHVAH | Edward Hines Veterans Affairs Hospital |
| FCA | Facilities Condition Assessment |
| GC | General Contractor (firm) |
| GLAC | Great Lakes Acquisition Center |
| HEFP | Healthcare Environment and Facilities Program |
| HVAC | Heating/Ventilation/Air Conditioning |
| IDIQ | Indefinite Delivery Indefinite Quantity |
| LF | Linear or Lineal Feet |
| MATOC | Multiple Award Task Order Contracting |
| MEP | Mechanical/Electrical/Plumbing |
| NTP | Notice to Proceed |
| OIT | Office of Information & Technology |
| PCAC | VHA Program Contracting Activity Central |
| PDT | Project Delivery Team – Typically CO/CS, COR, and EHVAH staff |
| PIV | Personal Identity Verification |
| POP | Period of Performance |
| QCM | Quality Control Manager |
| RFI | Request for Information |
| SF | Square Feet |
| TAB | Testing and Balancing |
| TIL | Technical Information Library |
| TO | Task Order |
| TR | Telecom Room |
| VA | Department of Veteran Affairs |
| VA-SEPS | VA Space and Equipment Planning Systems |
| WAP | Wireless Access Point |
G) Requirements
Where a conflict exists between the Statement of Work (SOW) requirements and the requirements of other associated contract documents, the SOW requirements shall prevail.
This SOW presumes the Contractor will not need access to the Hines LAN or any VA Sensitive Information to execute the contract.
The awarded Contractor will adhere to all codes, standards, guidelines, and design requirements found in the VA’s Technical Information Library (TIL) including but not limited to the following:
1) Pre-bid site visit:
a. A pre-bid site walk through is encouraged and should be coordinated by the CO. The intent of this walkthrough is to give the Contractor access to the project site so that an accurate evaluation of the project requirements and site assessment can be made.
b. The Contractor shall coordinate with the COR to schedule the site visit seven (7) calendar days prior to the requested date.
c. Exploratory demolition is permitted but must be coordinated with the COR.
2) RFI Submittals:
a. The Contractor shall submit any RFI’s resulting from the site visit within five (5) working days after the inspection to the CO.
b. Unless otherwise stated the Contractor shall allow the COR and CO ten (10) working days to respond to an RFI.
3) Infection Control Barrier (ICB):
a. Temporary construction partitions shall be smoke-tight and built of noncombustible materials that will not contribute to the development or spread of fire.
b. Barriers shall not obstruct access to emergency services and for fire, police, and other emergency forces.
c. The Contractor shall provide and install a rigid infection control panel system manufactured by Edge Guard out of Bement, Illinois or an approved equal. http://www.edge-guard.com/home.html. Salient details of the infection control barrier are:
1. The ICB must be fire-resistant.
2. The barrier must be water resistant; capable of being cleaned and sanitized.
3. Installation of the barrier shall not:
a. Generate dust outside the barrier.
b. Generate excess noise outside the barrier.
c. Generates excess fumes outside the barrier.
4. Demobilization of the barrier shall not:
a. Generate dust outside the barrier.
b. Generate excess noise outside the barrier.
c. Generates excess fumes outside the barrier.
d. Require floor, wall, or ceiling repairs upon removal.
5. The barrier should be environmentally responsible.
a. The materials should be reusable.
b. The materials should not contribute to unnecessary waste to our landfills.
d. Fire-resistant plastic sheeting may be used to supplement the rigid infection control panel system. COR approval is required.
1. The Contractor shall submit an RFI requesting approval during the bid period.
e. Wood studs, plywood, OSB, particle board, pressboard, or other flammable materials are not allowed at Hines.
f. Manometers shall be installed on the ICB adjacent to every entrance of the work zone to monitor negative pressure within the work zone. See Attachment 1.
g. All doors to rooms inside the work zone but directly impacted by the work shall have their doors shut and the perimeters taped to prevent the migration of dust and debris into these rooms.
h. Cover all sprinkler heads (daily), signs, data transmitters, and light fixtures. Cover the supply and return diffusers within the work zone to prevent the spread of dust and fumes to other areas outside the work zone.
i. Rigid infection control panel system and manometers are to be submitted and approved by the COR prior to installation.
j. The following is a manner acceptable to Hines Infection Control to maintain negative pressure inside an infection control barrier with no reasonable access to discharge air to the exterior.
1. Install a floor-to-ceiling infectious control barrier (ICB) meeting the fire-rating required.
2. Cover all sprinkler heads (daily), signs, data transmitters, and light fixtures. Cover the supply and return diffusers within the work zone to prevent the spread of dust and fumes to other areas outside the work zone.
3. Place the air scrubber inside the ICB with a HEPA filter. The air scrubber will draw air from inside the ICB.
4. Place a flapper valve connection on the ICB near to the ceiling.
5. Route the filtered air from the scrubber via a collapsible duct to the flapper valve thus maintaining negative pressure inside the ICB.
6. If the power should accidentally get cutoff, the flapper valve will swing close thereby maintaining the integrity of the ICB.
4) The Contractor shall post and maintain the final signed PCRA, ICRA, ILSM and Emergency Contact Information (when issued) at the entrance to the ICB for the duration of the project. See Attachment 1. The Contractor will update the postings when new documents are issued.
5) Material Lead time:
a. Material lead times shall be incorporated into the project schedule and used in conjunction with the baseline for the project start date.
b. The contractor shall make an informed bid submission by working with suppliers and considering all potential long-lead items involved with the project reasonably known or considered to impact the start, performance, and completion of the project.
c. For delays in the material delivery not caused by the government, the contractor shall bear the cost of temporary materials, equipment, labor, and services for the time between the end of the period of performance and the final installation of the contract’s specified materials and equipment.
6) EHVAH Permits:
a. Unless otherwise stated the Contractor shall submit for all required VA permits (i.e. above ceiling or dig) fourteen (14) calendar days prior to the event based on the approved project schedule with the COR.
7) Project Pay Applications:
a. Pay applications shall be initiated by the contractor in the form of a draft “pencil draw” submission to the COR.
1. Prior to submission the contractor will review the amounts, date of the application, the application number, and the purchase order (PO) for the project are correct.
2. The COR may question the pencil draw and request revisions.
3. Upon approval by the COR, the application will be reviewed by the CO.
4. Upon approval by the CO, the application will be submitted into the electronic Invoice Payment Processing System (IPPS). Approval within IPPS can take days or sometime weeks to be processed.
b. All submitted project pay applications require certified payroll and waste report documents to be current with each pay submission.
1. Certified payroll documents shall be submitted to the COR weekly.
2. Waste reports shall be submitted even when no waste has been produced. The contractor shall validate this by submitting a quantity of zero on the waste report.
3. Approval of all invoices will require documents to be current.
c. With each invoice submission, an updated, full schedule shall be submitted noting any changes in non-critical and critical paths, modifications approved, delays by the government, delays by the contractor, issuance dates for Letters of Concern and Letters of Cure, and other elements that impact the project completion date.
d. Submission of a 3-week look-ahead schedule will not be accepted.
8) Work outside of normal business hours or weekends:
a. The Contractor shall request approval in writing via email fourteen (14) calendar days in advance for work outside of normal business hours. This includes weekend work.
b. No work shall take place without written or e-mail confirmation from the project COR.
9) Utility Shutdowns:
a. The Contractor shall provide twenty-one (21) calendar days’ advance notice for any planned utility shutdowns to all allow the station to notify staff/visitors and prepare contingency plans if necessary.
b. Failure to submit the shutdown requests in a timely manner is not justification for a claim of delay on the part of the government.
c. Planned utility shutdowns should be indicated on the project schedule.
10) Submittals and Shop Drawings:
a. Unless otherwise stated the Contractor shall provide shop drawings and equipment submittals for review and approval by the COR seven (7) calendar days prior to the start of construction.
b. No work shall be started prior to review and approval by the COR.
11) Certifications:
a. When applicable, the Contractor shall provide certifications for all personnel performing any welding and shall certify all welds prior to the start-up of any of the units.
b. These certifications shall be supplied to the COR and retained as a permanent record of the project folder.
c. Personnel certifications shall be provided to the COR prior to the start of construction.
d. All weld certifications shall be provided to the COR at the end of every work week when applicable.
12) OSHA Certification:
a. The Contractor shall have an OSHA 30-hour certified site superintendent on site whenever any work is being performed.
b. All contractor onsite employees and sub-contractors shall have at least OSHA 10-hour certification.
c. A copy of the OSHA certifications shall be supplied to the COR prior to the start of any work and retained as part of the project folder.
13) EPA/IEPA Notification:
a. Pursuant to 40 CFR 61.145, written NESHAP notification is required to EPA at least 10 working days before the abatement or demolition is to begin.
b. A copy of this notification and acceptance shall be provided to the COR.
14) Post-Award meeting:
a. The meeting shall be coordinated through the COR and CS/CO.
b. The meeting shall take place after the Notice to Proceed has been issued but prior to the start of demolition/construction.
c. The Contractor shall schedule and attend a “Page-Turn” meeting in which the Designer of Record will be in attendance. The goal of this meeting is to clarify any confusion the Contractor may have regarding the contract documents in advance of commencing construction activities, delivery of project submittals, submission of the project schedule, the coordination of project phasing, etc.
15) Training/Experience:
a. The designated Prime Contractor SSHO must meet the requirements of all applicable OSHA standards and be capable (through training, experience, and qualifications) of ensuring that the requirements of 29 CFR 1926.16 and other appropriate Federal, State, and local requirements are met for the project. As a minimum the SSHO must have completed the OSHA 30-hour Construction Safety class and have five (5) years of construction industry safety experience or three (3) years if he/she possesses a Certified Safety Professional (CSP) or certified Construction Safety and Health Technician (CSHT) certification or have a safety and health degree from an accredited university or college.
b. The designated Prime Contractor’s On-site Superintendent shall have completed the OSHA 30-hour Construction Safety Course within the past 5 years and shall have at least 5 years of experience with projects of similar size, scope, and cost. The Superintendent shall be independent of the SSHO and must always be onsite when construction work is occurring.
c. All designated CPs shall have completed the OSHA 30-hour Construction Safety course within the past 5 years.
H) Scope of Work
The Scope of Work for this project includes all labor, management, equipment, and materials for accomplishing work in accordance with 100% Construction Documents as designed and issued by Guidon Design, Inc. Note: Contractors’ bids shall be based on the Bid Documents and any/all Request for Information (RFI) Addenda. The Bid Documents and Addenda will be combined to form the Construction Documents, which be the basis for the awarded construction contract.
All measurements/dimensions are approximate. The Contractor must verify all measurements/dimensions and material quantities required prior to submitting a proposal.
The Contractor shall inspect the area under contract prior to commencing work and identify any pre-existing damage and provide an Existing Site Conditions report with related photos to the Contracting Officer for review and approval.
Any deviation from this scope of work requires the express authorization of the Contracting Officer. The Contracting Officer Representative (COR) does not hold the authority to authorize changes to this scope of work.
1) Continued Use – The Medical Center maintains operations 24 hours a day, 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the Contractor’s responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The Discharge Lounge and Surgery Waiting Room will continue serving patients during the construction period in areas adjacent to the work area.
2) Bids—The contractor shall submit bids for the following bid categories. The project may be awarded for the complete base bid or for the base bid minus the alternate bid depending upon the availability of funds.
Base Bid: Furnish all labor, materials, equipment, tools, supervision, and all other necessary resources required for Project #578-22-026 Replace 2nd Floor Roofs of Building 200 as required by the statement of work, specificaitions and drawings The Base bid Shall include all work included or identified as deduct alternate 1 in the contract drawings. The estimated time for completion of the base bid will be 360 calendar days after Notice to Proceed.
Alternate Bid 1: All the work in the Base bid minus the work identified in the contract drawings as deduct alternate 1. All work associated with deduct alternate one in located within Gridlines D-F, and 5-10 and identified on Drawing GI001. The estimated time of completion for altenate bid 1 is 300 calendar days after Notice to Proceed.
3) Phasing – The overall project is to be completed in a single, uninterrupted phase. After project work commences, the Contractor shall ensure work stoppages due to weather are kept to a minimum. The contractor shall make every effort to resume work once the inclement weather has subsided. The contractor shall maintain communication and coordination with the COR to ensure the project stays on schedule.
a. In the event the entire Base Bid is awarded, all items of the project scope can be accomplished concurrently.
b. The contractor shall include their plan/recommendations for phasing to the COR for review and approval.
c. The east side gypsum plank deck and TPO membrane replacement (Deductive Bid Item 1) if awarded under the base bid shall be performed in phases as indicated on the Contract Drawings ( reference Drawing GI001) allowing continued partial use of the Waiting Room, Discharge Lounge, and admin spaces under the work area.
I) Constraints
1) Work hours for EHVAH Engineering staff are from 7:30 am until 4:00 pm, Monday through Friday.
2) Photographs may be taken of the work performed at the jobsite. However, photographs containing patients and/or staff are a violation of Patient Privacy and hospital policy. Both violations are subject to penalties and dismissal. Permission from the EHVAH Public Affairs Officer (PAO) is required and should be coordinated with the project COR.
3) VHA Directive 1085 implements a smoke-free policy for patients, visitors, contractors, volunteers, and vendors at VA health care facilities.
4) Maximizing Use of American-Made Goods, Products, and Materials
a. The Buy American Act required the United States government to prefer U.S.-made products in its purchases.
b. It is the policy of the United States to buy American and to maximize, consistent with law, the use of goods, products, and materials produced in the United States.
c. Material purchases should adhere to this policy to the greatest extent possible.
5) The contractor badging process is a required security procedure of all VA stations. It is the responsibility of the general or prime contractors to notify their subcontractors of this requirement. All contracted workers visiting the jobsite will need to receive a contractor’s Flash badge. This is to be done before any construction or demolition work is started on the project. Failure to obtain and display the proper badge could result in the worker being removed from the station by Hines Police.
The procedure to follow is:
a. The Contractor shall have 2 weeks’ notice from award to Notice to Proceed (NTP) to on-board team members with the necessary badging.
b. The Contractor shall fill out Contractor Badging Form – See Attachment 1.
c. Two (2) forms are personal identification are needed. Valid (unexpired) forms of ID include:
1. Current Driver’s License. Real ID is required.
2. An original social security card (not laminated). Substitutes may include:
i. Current Passport
ii. Original birth certificate (not a copy) Additional forms of identification can be found on Page 2 of the Contractor Badging Form – See Attachment 1.
d. The Contractor shall coordinate with COR and bring the completed Contractor Badging Form to Mikel Jones (Bldg. 2, Rm 119) to coordinate for fingerprints (Phone: 708 202-8387, ext. 21322; Email: mikel.jones@va.gov).
e. Once the form is approved by Mikel Jones, contractors shall take a copy of the form to Human Resources located in Building 17 for fingerprinting. The hours for fingerprinting are 8:00 AM to 3:00 PM. The other copy will stay with Hines Engineering.
f. Upon a favorable fingerprint adjudication, the contractor will schedule an appointment with HR to receive a Flash badge. The link to schedule this appointment will be provided by Mikel Jones upon notification of successful fingerprint adjudication.
J) Tasks and Responsibilities
A pre-construction (kick-off) meeting between the Contracting Officer (CO) or Contracting Specialist (CS), the Contracting Officers Representative (COR), and key GC team members will be conducted to review project objectives, scope, deliverables, communication, site access, schedule, and responsibilities. During this meeting the Notice to Proceed (NTP) should be signed. After this meeting the awarded GC firm shall provide their services according to the approved project schedule.
1) Preconstruction Period: The Contractor shall provide the following:
a. Logistics Plan: A comprehensive narrative describing the chronological planned development of the project. The Logistics Plan includes an organizational chart, hourly rates, staging plan, description of means and methods, and hours of work.
b. Construction Security Plan: Defines both physical and administrative security.
c. Construction Phasing Plan: It is the Contractor’s responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
d. Submittal Registry: The Submittal Registry shall include a listing of all documentation required for pre-approved submissions including shop drawings, technical data, product performance information, calculations, and samples.
e. Accident Prevention Plan: The APP (aka Construction Safety & Health Plan) shall interface with the Contractor's overall safety and health program.
f. Activity Hazard Analyses: AHAs are also known as Job Hazard Analyses, Job Safety Analyses, and Activity Safety Analyses.
g. Construction Schedule: WBS schedule including start/end dates, duration, and sequencing, preferably in MS Project or Primavera format (include floats).
h. Schedule of Values: A detailed Breakdown for Payment, including design stages, work performed, and work invoiced per Progress Payment submission.
1. The Schedule of Value is a representative breakdown of the contractor’s firm, fixed-price bid. Each portion of the Schedule of Values represents the amount the government paid to the contractor for that portion of the work.
2. Because the contractor’s bid was fixed, so too is the Schedule of Values. It is not fluid and does not change after submission and approval. The Schedule of Values can only be modified through a bi-lateral agreement between the government and the contractor.
3. The government will utilize the Schedule of Values as a basis of negotiations for contract modifications. This is especially true when a credit is due to the government for all or measurable parts of certain portions of the firm, fixed-price contract.
i. Existing Conditions Survey: Before any work is started, the Contractor and the COR shall conduct a thorough survey of the buildings or areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer.
j. Infection Control Plan (ICP): Narrative description of the dust control and debris disposal process including disposal destination and methodology.
k. Quality Control Plan (QCP): Describes the methods by which the Contractor will ensure all work is being accomplished in accordance with specifications and this SOW.
l. Environmental Protection Plan: The Contractor shall meet with the COR to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental protection.
m. Document Submissions. All documents included as Attachments to this SOW that are required to be filled out and signed or jointly signed by the Contractor.
n. Demolition Debris Management Plan.
o. Certificates, Licenses, and Training Documents.
p. Obtain PIV badges.
q. RFI’s: Other than those resulting directly from demolition or construction.
2) Construction Period: Along with coordinating the construction of the project, the Contractor shall provide the following during construction services:
a. Display the signed PCRA, ICRA, ILSM and Emergency Contact Information in a location coordinated with the COR.
b. Submit RFI’s during construction as necessary.
c. Attend and run weekly construction meetings.
1. Take notes and attendance, produce, and distribute minutes. Note – Failure to produce fair, unbiased meeting minutes will result CO disciplinary action.
2. Track RFI’s, submittals, and modifications through various logs.
3. Request permits and shutdowns.
4. Request inspections, reviews, and punch list.
5. Address any obstacles and work to coordinate resolutions.
d. Attend site visits, field inspections, and punch list inspections as requested by the COR.
3) Construction Close-out Period:
a. The Contractor shall provide the following:
1. Inspection and Approval by the COR and/or the CO.
2. Final Approval and Beneficial Occupancy when applicable.
3. Warranties documents and O&M Manuals.
4. As-built drawings and record submittals.
5. Staff training when applicable.
6. Contractor Release of Claims.
7. All Waste Reports submitted per Safety and Health during Construction Activities.
8. Existing Conditions Re-survey.
b. The COR shall review the Contractor’s close-out submissions for thoroughness and conformance with the contract document requirements. The COR shall also review field-marked as-built drawings for conformance with final installations.
c. The COR shall utilize these as-built drawings and specifications from the Contractor and generate as recorded drawings and specifications.
K) Deliverables
1) The Contractor shall provide all submittals required by the Specifications Book.
L) Time Frames
1) This project shall be completed within three hundred sixty (360) calendar days once Notice to Proceed is issued. NOTE: In the event Alternate Bid 1 is awarded, the over all completion date referenced in this timeline section shall be reduced by sixty (60) calendar days.
a. Phasing – This project shall be executed in one single, uninterrupted phase.
b. Pre-construction (kick-off) Meeting is when the Notice to Proceed (NTP) is signed.
c. Pre-Construction Period duration is NTP + 30 calendar days. Within this period the Contractor shall provide all materials included under Tasks and Responsibilities and the following:
1. Logistics Plan.
2. Construction Security Plan.
3. Construction Phasing Plan.
4. Submittal Registry.
5. Accident Prevention Plan.
6. Activity Hazard Analyses.
7. Construction Schedule.
8. Schedule of Values.
9. Existing Conditions Survey.
10. Infection Control Plan.
11. Quality Control Plan.
12. Environmental Protection Plan.
13. Document Submissions.
14. Demolition Debris Management Plan.
15. Certificates, Licenses, and Training Documents.
16. Obtain PIV badges.
d. Construction Period - To be determined based upon the approved schedule for construction. The estimated construction period is 300 calendar days with all product submittals to be delivered prior to the start of construction to the COR for review and approval. No demolition or construction shall be started without the review and approval from the COR for those items listed in the Pre-Construction Period unless authorized in writing by the COR or the CO.
e. Construction Closeout Period duration is NTP +330 calendar days. The Contractor shall submit all documents, drawings, and commissioning reports (if applicable) within 30 calendar days from acceptance of the completed punch list items by EHVAH. Within this period the Contractor shall provide all materials included under Tasks and Responsibilities and the following:
1. Inspection and Approval by the COR and/or the CO.
2. Final Approval and Beneficial Occupancy when applicable.
3. Warranties documents and O&M Manuals.
4. As-built drawings and record submittals.
5. Staff training when applicable.
6. Contractor Release of Claims.
7. Waste Reports.
8. Existing Conditions Re-survey
M) Performance Monitoring
The Government will periodically evaluate the Contractor’s performance by appointing a representative(s) to monitor such performance and ensure services are received. The Government representative will evaluate the Contractor’s performance through intermittent on-site inspections of the Contractor's performance.
N) Other Pertinent Information or Special Considerations.
1) All Contractor personnel shall be certified by appropriate federal and state regulatory agencies to meet federal and local certification requirements as applicable. All licenses, permits, and welding certifications shall be kept current throughout the period of performance of the contract. The Contractor shall provide the Government copies of such certificates.
2) Per VA Information Security Program policy – VA Directive and Handbook 6500 and 6500.6, Appendix A, contractor storage, generation, transmission or exchanging of VA sensitive information during this construction project is not acceptable.
3) All work shall be scheduled to meet requirements of EHVAH. All work shall be coordinated through the Contracting Officer. Local coordination shall be routed through the Contracting Officer’s Representative.
4) The Contractor shall provide to the Contracting Officer record of work certifications for all trade’s relative to this contract 5 calendar days prior to beginning work. Certifications shall include welders, pipe installers, machine operators, etc.
5) The Contractor is responsible for repairing any damages to existing utilities incurred during construction or demolition.
6) Utilities within the area and identified on existing drawings are not to be interpreted as the exact location, or as the only existing site conditions. The Contractor shall verify all existing conditions and proceed with caution around any anticipated obstructions.
7) Where any work disturbs the grass areas, sod, walls, ceilings, floors, windows, entrances or building structures, etc. or where new and old work join, the Contractor shall restore, repair, or refinish affected areas or surfaces to their original condition, or as existed before the commencement of this project. Upon completion of the contract, the Contractor shall deliver all work complete and undamaged. Any damage that may be caused by the Contractor or his work crews or subcontractors to any existing structure, grounds and utilities shall be repaired or replaced to their original condition.
8) Should a conflict exist between VA requirements and VA adopted nationally recognized codes and standards, the conflict shall be brought to the attention of the Contracting Officer. The resolution of the conflict shall be made by the authority having jurisdiction for VA to ensure system-wide consistency. All work conducted under this scope of work shall comply with the Department of Veterans Affairs Master Specifications and all applicable state and federal regulations and codes.
O) Risk Control
1) Refer to the attached ICRA form.
P) Government Furnished Equipment (GFE)/Government Furnished Information (GFI)
1) GFE.
a. There is no GFE on this project
2) GFI.
a. No additional information is intended to be supplied other than information that is requested by the Contractor.
Q) Point of Contact at the EHVAH
1) Martin Pint Engineer, Project Planning Section Engineering Service Edward Hines Jr. VA Hospital 5000 S. Fifth Avenue Building 2, Room 121 Hines, IL 60141 Martin.pint@va.gov Phone: 708-202-8387 ext. 27247
FAX: 708-202-2167