This is a Solicitation, Offer, and Award (Standard Form 1442) for a sealed-bid construction contract issued by the Department of Veterans Affairs, Great Lakes Acquisition Center. The solicitation seeks bids for Project 578-22-026: Replace 2nd Floor Roofs of Building 200 at the Edwards Hines Jr. VA Medical Center in Hines, Illinois. The work includes furnishing all labor, materials, equipment, tools, supervision, and resources required to replace the second-floor roofs as specified in the contract drawings and statement of work. The base bid period of performance is 360 calendar days after notice to proceed, with a bid alternate option reducing the scope and timeline to 300 calendar days. The construction magnitude is estimated between $2,000,000 and $5,000,000, classified under NAICS 238160 (Roofing Contractors).
This procurement is 100% set-aside for CVE-verified Service-Disabled Veteran-Owned Small Business (SDVOSB) firms under 38 U.S.C. 8127. Bids are due by 1:00 PM CDT on March 31, 2026, at the Great Lakes Acquisition Center in Milwaukee, Wisconsin, with public bid opening at that time and location. Offerors must acknowledge receipt of all amendments and submit a VAAR 852.219-75 certification confirming SDVOSB status and compliance with 75% subcontracting limitations for special trade construction. A pre-bid conference is scheduled for February 26, 2026, at 10:00 AM CST at the hospital site. Bid guarantees of not less than 20% of bid price (capped at $200,000) and performance/payment bonds equal to the awarded contract value are required. Questions must be submitted in writing to Contracting Officer Donita Grace (donita.grace@va.gov) by 3:00 PM on March 9, 2026. The contract will be firm-fixed-price, and all bidders must comply with federal acquisition regulations, construction wage rates, safety/environmental certifications, and experience modification rate reporting requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
None 36C25226B0009 X 02-18-2026 578-22-026 Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee
WI
53214-1476 Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee
WI
53214-1476 Donita Grace 414-844-4860 Award is subject to the availability of funds.
Project No: 578-22-026 Replace 2nd Floor Roofs Bldg. 200
Contractor shall provide for and furnish all labor, superintendence, materials, tools, equipment, transportation, licenses, certificates, insurance, temporary protection, and other items required under the provisions of this project – Replace 2nd Floor Roof Bldg. 200 at the Edwards Hines, Jr. VAMC located at Hines, IL outlined in the contract specification and as shown on the contract drawings.
Construction magnitude range: $2,000,000 and $5,000,000 NAICS 238160 Roofing Contractors / SBA Size Standard: $19M
This procurement is 100% set-aside for CVE Verified Service-Disabled Veteran-Owned Small Business Firms (SDVOSB) per the authority 38 U.S.C 8127 (Public Law 109-461). In accordance with VAAR 819.7003(b), at the time of the submission of Bid, and prior to award of any contract, the bidder must represent to the CO that it is: (1) a SDVOSB eligible under VAAR Subpart 819-70: (2) a Small Business concern under the NAICS assigned to this acquisition; and (3) a SDVOSB listed as verified in the SBA VIP database at: https://veterans.certify.sba.gov/
Submit all questions regarding the solicitation, specifications, and/or drawings in writing to the Primary POC:
Donita Grace – Contract Specialist, no later than 3:00 PM local time March 9, 2026.
Questions received after this deadline may not be addressed. TELEPHONE INQUIRIES WILL NOT BE ACCEPTED!
Site visits will be held in accordance with FAR Clause 52.236-27. See page 7 for time and location Direct any questions to the COR, Burt Jimenez at Martin.Pint@va.gov or 708-202-8387 x27247 prior to the site visit.
NOTICE: Contractors MUST acknowledge VAAR 852.219-75 by signing the certification and submitting with bid/proposal. If certification is not included, bid/proposal will be considered non-responsive and cannot be considered for award. See page 29 - 30 for 852.219-75 VA Notice of Limitations on Subcontracting – Certificate of Compliance for Construction (JAN 2023)(Deviation).
All bidders are responsible for monitoring and downloading any amendments from Contract Opportunities at the following website: https://sam.gov/content/opportunities
If submitting as a joint-venture, officers must include a copy of the joint-venture agreement.
X 52.211-10 X 1:00pm
CDT
03-31-2026 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
SEE ATTACHED BID SCHEDULE.
Department of Veterans Affairs 36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee
WI
53214-1476 Department of Veterans Affairs Financial Services Center PO Box 149971 Austin
TX
78714-9971
BID SCHEDULE
SOLICITATION: 36C25226B0009
Project 578-22-026: Replace 2nd Floor Roof of Building 200
STATEMENT OF BID ITEM(S)
NOTE: A SINGLE AWARD WILL BE MADE ON BID ITEM A (BASE BID), BUT IN THE EVENT THE OFFER EXCEEDS THE FUNDS AVAILABLE, A SINGLE AWARD WILL BE MADE ON BID ITEM B BASED ON AVAILABLE FUNDING. OFFERORS ARE REQUIRED TO SUBMIT PRICING FOR EACH BID ITEM LISTED.
Work location is on the campus of the Edward Hines Jr. VA Hospital at 5000 S. Fifth Avenue, Hines, IL 60141
A. BASE BID: Furnish all labor, materials, equipment, tools, supervision, and all other necessary resources required for Project #578-22-026 Replace 2nd Floor Roofs of Building 200 as required by the statement of work, specifications and drawings The Base bid Shall include all work included or identified as deduct alternate 1 in the contract drawings.
Period of Performance: All work shall be completed within Three Hundred and Sixty (360) Calendar Days after the issuance of the Notice to Proceed.
Base Bid LUMP SUM AMOUNT: ______________________________
B. BID ALTERNATE NO.1: All the work in the Base bid minus the work identified in the contract drawings as deduct alternate 1. All work associated with deduct alternate one is located within Gridlines D-F, and 5-10 and identified on Drawing GI001.
Period of Performance: All work shall be completed within Three Hundred (300) Calendar Days after the issuance of the Notice to Proceed.
Bid alternate No. 1 LUMP SUM AMOUNT: ______________________________
For Bid Deducts, bidders should ensure that the all-inclusive price after the deductions are subtracted has been entered. Do not enter the amount of the deduction.
NOTICE TO BIDDERS: Work shall not commence until all required submittals are approved by the Contracting Officer or the Contracting Officer’s Representative (COR). An approved cost-loaded, Critical Path Method (CPM) construction schedule is required prior to commencement of construction. See specifications for details. CPM schedule shall be approved by the Contracting Officer or the Contracting Officer’s Representative. See specifications for details.
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
(a) This solicitation & all associated bid documents are available to interested parties in electronic file format from https://sam.gov/content/home. No hard copy documents will be provided by the government.
(b) A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $200,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will result in rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
(c) The bidder to whom a contract is awarded will be required to furnish a Payment Bond, on form SF 25A, and a Performance Bond, on form SF 25. Each bond shall be issued for a penal sum equal to the value of the awarded contract. Copies of forms SF 25 and 25A may be obtained from the Contracting Officer upon request.
DESCRIPTION OF WORK:
PROJECT: 578-22-026 Replace 2nd Floor Roof of Building 200 Cost Range: - $2,000,000.00 - $5,000,000.00
CONTRACTOR INFORMATION
| Name of Company: | ___________________________________________ |
| Address: | ___________________________________________ |
| City, State, Zip Code: | ___________________________________________ |
| Name(s) and Title of Company | 1.) ________________________________________ |
| Legal Binding Authority(s) | 2.) ________________________________________ |
| 3.) _______________________________________ | |
| 4.) _______________________________________ |
| Primary Point of Contact: | ___________________________________________ |
| E-Mail Address: | ___________________________________________ |
| Address: | ___________________________________________ |
| City, State, Zip Code: | ___________________________________________ |
| Phone No: | ___________________________________________ |
| Fax No: | ___________________________________________ |
| TAX ID Number: | ___________________________________________ |
| DUNS Number: | ___________________________________________ |
Past Performance Point of Contact (within your company), include name and email address:
CONTRACTING OFFICER’S SPECIAL INSTRUCTIONS
INQUIRIES and RFIs:
Inquiries and all correspondence concerning this solicitation document should be submitted in writing to the Contracting Officer. YOU ARE INSTRUCTED SPECIFICALLY TO CONTACT ONLY THE CONTRACTING OFFICER ISSUING THE SOLICITATION ABOUT ANY ASPECT OF THIS REQUIREMENT.
Requests for information or clarifications to solicitation documents shall be submitted to the Contracting Officer, Donita Grace, at donita.grace@va.gov and for action no later than 3:00 PM on Monday, March 9, 2026. All RFIs or clarifications sent to the government will have the following SUBJECT Line: RFI-36C25226B0009 - [YOUR COMPANY NAME]
SITE VISIT:
The pre-bid conference will take place on Thursday, February 26, 2026, at 10:00am CST. The location is at the Edward Hines Jr. Hospital, located at 5000 S. Fifth Avenue, Hines, IL 610141. All participants will meet the Contracting Officer Representative (COR) at 10:00am - Room 126, Bldg. 2 (Bldg. with Clock tower).
BID DUE DATE and BID SUMBISSION INSTRUCTIONS:
No email bid submissions will be considered, only in person hard copy. Hard copy of bid submissions can be regular mailed or hand delivered. All submissions must be received no later than the required bid due date and time. All submissions must be received in a sealed envelope and addressed to the following:
ATTN: Donita Grace Solicitation: 36C25226B0009 Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101 Milwaukee, WI 53214-1476
BID OPENING:
The bid opening will be held in-person at the Great Lakes Acquisition Center (GLAC), Milwaukee, WI. Bid Opening will occur on Tuesday, March 31, 2026, at 1:00PM CST. Contractors will check-in at the front desk and escorted to a designated conference. It is the responsibility of all contractors to arrive prior to the Bid Opening time, as the Bid Opening will start promptly at the time listed above. GLAC address is as follows:
Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101 Milwaukee, WI 53214-1476
ADDITIONAL PRIME CONTRACTOR INFORMATION - Safety or Environmental Violations and Experience Modification Rating Information
Information provided below shall be applicable to Project 578-22-026 Replace 2nd Floor Roof of Building 200 Construction 1.) All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.
2.) All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Bidder’s/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Bidder/Offeror’s EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.
3.) Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
4.) If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead and include a letter from the NCCI indicating that is has assigned Bidder/Offeror a Unity Rating of 1.0.
5.) The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.
6.) This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
Pre-Award Contractor Safety and Environmental Record Evaluation Form
Information provided below is current and applicable to Solicitation 36C25226B0003 for Project 578-22-026 Replace 2nd Floor Roofs Bldg. 200 Construction Company Name: ______________________________________________ Address: _____________________________________________________ Telephone: ______________________ Fax: ________________________ Email: _______________________________________________________ Contact: ______________________________________________________
1. Utilizing your OSHA 300 Forms, please complete the following information:
| Category |
| 2023 |
| 2024 |
| 2025 |
Number of man hours (jobsite and office).
Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).
Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).
Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations.
Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page: http://www.osha.gov/pls/publications/publication.html.
| 2. | Provide six-digit North American Industrial Classification System (NAICS) Code for this acquisition: __________________________________ |
| 3. | Who administers your company’s Safety and Health Program? ____________________________ |
| 4. | Company’s Insurance Experience Modification Rate (EMR): ____________________________ |
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
(a) Definitions. As used in this provision— "Administrative proceeding" means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.
"Federal contracts and grants with total value greater than $10,000,000" means—
(1) The total value of all current, active contracts and grants, including all priced options; and
(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).
"Principal" means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).
(b) The offeror [ ] has [ ] does not have current active Federal contracts and grants with total value greater than $10,000,000.
(c) If the offeror checked "has" in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:
(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:
(i) In a criminal proceeding, a conviction.
(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.
(iii) In an administrative proceeding, a finding of fault and liability that results in—
(A) The payment of a monetary fine or penalty of $5,000 or more; or
(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.
(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.
(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.
(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).
(End of Provision)
2.2 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)
(a) This provision does not apply to acquisitions at or below the simplified acquisition threshold or to acquisitions of commercial products and commercial services as defined in Federal Acquisition Regulation 2.101.
(b) Certification. [Offeror shall check either (1) or (2).] _____ (1) The Offeror certifies that—
(i) It does not engage and has not engaged in any activity that contributed to or was a significant factor in the President’s or Secretary of State’s determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international-security-affairs/bureau-of-arms-control-verification-and-compliance/; and
(ii) No entity owned or controlled by the Offeror has engaged in any activity that contributed to or was a significant factor in the President’s or Secretary of State’s determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international-security-affairs/bureau-of-arms-control-verification-and-compliance/; or
(2) The Offeror is providing separate information with its offer in accordance with paragraph (d)(2) of this provision.
(c) Procedures for reviewing the annual unclassified report (see paragraph (b)(1) of this provision). For clarity, references to the report in this section refer to the entirety of the annual unclassified report, including any separate reports that are incorporated by reference into the annual unclassified report.
(1) Check the table of contents of the annual unclassified report and the country section headings of the reports incorporated by reference to identify the foreign countries listed there. Determine whether the Offeror or any person owned or controlled by the Offeror may have engaged in any activity related to one or more of such foreign countries.
(2) If there may have been such activity, review all findings in the report associated with those foreign countries to determine whether or not each such foreign country was determined to be in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or to be not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. For clarity, in the annual report an explicit certification of noncompliance is equivalent to a determination of violation. However, the following statements in the annual report are not equivalent to a determination of violation:
(i) An inability to certify compliance.
(ii) An inability to conclude compliance.
(iii) A statement about compliance concerns.
(3) If so, determine whether the Offeror or any person owned or controlled by the Offeror has engaged in any activity that contributed to or is a significant factor in the determination in the report that one or more of these foreign countries is in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. Review the narrative for any such findings reflecting a determination of violation or non-adherence related to those foreign countries in the report, including the finding itself, and to the extent necessary, the conduct giving rise to the compliance or adherence concerns, the analysis of compliance or adherence concerns, and efforts to resolve compliance or adherence concerns.
(4) The Offeror may submit any questions with regard to this report by email to NDAA1290Cert@state.gov. To the extent feasible, the Department of State will respond to such email inquiries within 3 business days.
(d) Do not submit an offer unless—
(1) A certification is provided in paragraph (b)(1) of this provision and submitted with the offer; or
(2) In accordance with paragraph (b)(2) of this provision, the Offeror provides with its offer information that the President of the United States has—
(i) Waived application under U.S.C. 2593e(d) or (e); or
(ii) Determined under 22 U.S.C. 2593e(g)(2) that the entity has ceased all activities for which measures were imposed under 22 U.S.C.2593e(b).
(e) Remedies. The certification in paragraph (b)(1) of this provision is a material representation of fact upon which reliance was placed when making award. If it is later determined that the Offeror knowingly submitted a false certification, in addition to other remedies available to the Government, such as suspension or debarment, the Contracting Officer may terminate any contract resulting from the false certification.
(End of Provision)
2.3 52.216-1 TYPE OF CONTRACT (NOV 2025) (DEVIATION)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.4 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Hand-Carried Address:
Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 Mailing Address:
Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT |
| NOV 2024 |
| 52.214-3 |
| AMENDMENTS TO INVITATIONS FOR BIDS |
| DEC 2016 |
| 52.214-4 |
| FALSE STATEMENTS IN BIDS |
| APR 1984 |
| 52.214-5 |
| SUBMISSION OF BIDS |
| DEC 2016 |
| 52.214-6 |
| EXPLANATION TO PROSPECTIVE BIDDERS |
| APR 1984 |
| 52.214-7 |
| LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS |
| NOV 1999 |
| 52.214-18 |
| PREPARATION OF BIDS—CONSTRUCTION |
| APR 1984 |
| 52.214-19 |
| CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION |
| AUG 1996 |
| 52.214-34 |
| SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE |
| APR 1991 |
| 52.214-35 |
| SUBMISSION OF OFFERS IN U.S. CURRENCY |
| APR 1991 |
| 52.228-1 |
| BID GUARANTEE |
| SEP 1996 |
| 52.228-17 |
| INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) |
| FEB 2021 |
| 52.229-11 |
| TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION |
| JUN 2020 |
2.6 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)
(a) Any protest filed by an interested party shall—
(1) Include the name, address, fax number, email and telephone number of the protester;
(2) Identify the solicitation and/or contract number;
(3) Include an original signed by the protester or the protester’s representative and at least one copy;
(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;
(5) Specifically request a ruling of the individual upon whom the protest is served;
(6) State the form of relief requested; and
(7) Provide all information establishing the timeliness of the protest.
(b) Failure to comply with the above may result in dismissal of the protest without further consideration.
(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.
(End of Provision)
2.7 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.
(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.
(End of Provision)
2.8 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019)
(a) Additive or deductive line items in the bid schedule shall be evaluated to determine the low offeror and the items to be awarded. The evaluation shall be made as follows—
(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.
(2) The low bid shall be the Bidder that—
(i) Is otherwise eligible for award; and
(ii) Offers the lowest aggregate amount for the first or base line item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive line items that provide the most features within the funds determined available.
(3) All bids shall be evaluated on the basis of the same additive or deductive line items.
(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities; and
(ii) Add that next item if an award may be made that includes that line item and is within the available funds.
(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if—
(1) It is in the best interest of the Government;
(2) Funds are available at the time of award; and
(3) The low offeror’s price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.
(c) Example: ‘‘The amount available is $100,000. Offeror A’s base bid and four additives (in the order stated in the list of priorities in the bid schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B’s base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A’s bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.’’ (End of Clause)
2.9 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) The following provisions or clauses incorporated by reference in this solicitation must be completed by the offeror or prospective contractor and submitted with the quotation or offer. Copies of these provisions or clauses are available on the Internet at the Web sites provided in the provision at FAR 52.252-1, Solicitation Provisions Incorporated by Reference, or the clause at FAR 52.252-2, Clauses Incorporated by Reference. Copies may also be obtained from the contracting officer.
[Contracting officer shall list all FAR and 48 CFR Chapter 8 (VAAR) provisions and clauses incorporated by reference that must be completed by the offeror or prospective contractor and submitted with the quotation or offer.] (End of Provision)
GENERAL CONDITIONS
4.1 52.216-18 ORDERING (AUG 2020)
(a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from through .
(b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control.
(c) A delivery order or task order is considered "issued" when—
(1) If sent by mail (includes transmittal by U.S. mail or private delivery service), the Government deposits the order in the mail;
(2) If sent by fax, the Government transmits the order to the Contractor’s fax number; or
(3) If sent electronically, the Government either—
(i) Posts a copy of the delivery order or task order to a Government document access system, and notice is sent to the Contractor; or
(ii) Distributes the delivery order or task order via email to the Contractor’s email address.
(d) Orders may be issued by methods other than those enumerated in this clause only if authorized in the contract.
(End of Clause)
4.2 52.216-19 ORDER LIMITATIONS (OCT 1995)
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than , the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor—
(1) Any order for a single item in excess of ;
(2) Any order for a combination of items in excess of ; or
(3) A series of orders from the same ordering office within days that together call for quantities exceeding the limitation in paragraph (b)(1) or (2) of this section.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.
(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
(End of Clause)
4.3 52.223-20 AEROSOLS (MAY 2024)
(a) Definitions. As used in this clause— Global warming potential means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide's global warming potential is defined as 1.0.
High global warming potential hydrofluorocarbons means any hydrofluorocarbons in a particular end use for which EPA's Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables of alternatives available at (https://www.epa.gov/snap/).
Hydrofluorocarbons means compounds that contain only hydrogen, fluorine, and carbon.
(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, or emissions of high global warming potential hydrofluorocarbons, when feasible, from aerosol propellants or solvents under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as—
(1) In-use emission rates, energy efficiency;
(2) Safety, such as flammability or toxicity;
(3) Ability to meet technical performance requirements; and
(4) Commercial availability at a reasonable cost.
(c) The Contractor shall refer to EPA's SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at https://www.epa.gov/snap/.
(End of Clause)
4.4 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is—
(i) A commercial product (as defined in paragraph (1) of the definition of ‘‘commercial product’’ at Federal Acquisition Regulation (FAR) 2.101;
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Component means any article, material, or supply incorporated directly into construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both—
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if—
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of ‘‘cost of components’’.
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate ‘‘none’’]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.