This document is a Pre-Construction Checklist for a federal construction contract opportunity. It outlines key requirements and procedures for the contractor, including:

The authority and roles of the Contracting Officer and VA Project Manager in overseeing the project and making changes. The contractor must submit a schedule of costs, progress chart, and daily logs. Payment requests must include payroll sheets. The contractor is responsible for protecting the work site and repairing any damage. Safety violations may result in work being stopped. The Contracting Officer has the sole authority to make changes to the contract. Subcontractors must be approved, and labor standards provisions must be followed. All correspondence from the contractor must reference the contract number, project title, and name.

View the file

Other files

File Type Posted
36C25224B0011 0004.docx DOCX document
36C25224B0011 0003.docx DOCX document
36C25224B0011 0002.docx DOCX document
S02 - Att1 Final SOW Rev1 578-15-001.pdf PDF
S02 - Att2 Patient Lift Locations.pdf PDF
36C25224B0011 0001.docx DOCX document
S02 - Att1 - Bid Drawings 43-63.pdf PDF
S02 - Att11- Interim Life Safety Measures ILSM.pdf PDF
S02 - Att7 - Cutting Welding and Other Hot Work.pdf PDF
S02 - Att - Wage Determination IL 20240009 7-26.24.pdf PDF
S02 - Att1 - Bid Drawings 22-42.pdf PDF
S02 - Att12 - Infection Control Barrier Sample.pdf PDF
S02 - Att - Final SOW Install Patient Lifts Construction 578-15-001.pdf PDF
S02 - Att10a - Infection Control Risk Assessment ICRA - Level 1.pdf PDF
S02 - Att10c - ICRA Compiled Locations List.pdf PDF
S02 - Att1- Bid Drawings 1-21.pdf PDF
S02 - Att4 - Contractor Badging - Fingerprint Request Form.pdf PDF
S02 - Att2 - Project Manual Bid Specs.pdf PDF
S02 - Att3 - Contractor Parking.pdf PDF
S02 - Att13 - No Smoking Policy 10-1-19.pdf PDF
S02 - Att9b - PCRA Compiled Locations List.pdf PDF
36C25224B0011_1.docx DOCX document
S02 - Att9a - Pre-Construction Risk Assessment PCRA.pdf PDF
S02 - Att8 - Above Ceiling Entry and Wall Construction Permits.pdf PDF
S02 - Att6 - Safety and Health During Construction Activities.pdf PDF
S02 - Att10b - Infection Control Risk Assessment ICRA - Level 2.pdf PDF
S02 - Att1 - Bid Drawings 64-83.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-CONSTRUCTION CHECKLIST

PROJECT: __________________________________________________

DATE: ____________________ CONTRACT: _____________________

1. AUTHORITY OF GOVERNMENT PERSONNEL.

☐ a. The Contracting Officer is the only person authorized to bind the U.S.

Government, and then only to the extent of the authority invested in him/her by the appointment.

☐ b. The VA Project Manager is designated as the Contracting Officer's representative for the purpose of technical supervision and acceptance. The VA Project Manager is responsible for the inspection of the work called for in the contract schedules, including related specifications and contract terms regarding on-site work requirements. Pursuant to the delegation of authority (attached), the Project Manager does not have the authority to make changes to the contract in amount or time.

☐ c. The VA Project Manager for this project is _________________

☐ d. No other office or individual has the authority to act in any manner on behalf of the U.S. Government in the performance of this contract. The VA Project Manager will refer any changes or questions regarding this contract to the Contracting Officer.

2. CONTRACT PROGRESS SCHEDULES AND REPORTS:

☐ a. The Contractor shall submit a schedule of cost to the Contracting Officer within 10 calendar days after date of receipt of the Notice to Proceed.

The approved cost schedule will be one of the bases for determining progress payments for work completed. In accordance with FAR 52.236-1, Performance of Work by the Contractor, the schedule must indicate what portion(s) of the work the contractor intends to perform with his/her own workforce to meet the 15% requirement.

☐ b. The Contractor shall submit a progress chart, with in l O calendar days after issuance of a Notice to Proceed, which indicates the anticipated installation of work versus the elapsed contract time, which shall be represented in the form of a bar graph. The starting date of the schedule shall be the date of the Notice to Proceed and the ending date shall be the original contract completion date.

☐ c. Submittals, samples, and shop drawings. Project Engineer will explain distribution procedures

3. PAYMENT REQUESTS:

☐ a. Payments shall be made monthly by the VA according to the value of completed work from the Contractor's approved Schedule of Costs. All invoices should be submitted to Austin Texas as outlined in the contract. In accordance with the Prompt Payment Act, the fourteen (14) day timeframe for payment shall commence on the date a proper invoice is received by the CO. Included with the pay request shall be the payroll sheets for the Contractor and Subcontractors.

4. PROTECTION OF SURROUNDING AREA:

☐ a. In performing this contract, the Contractor shall provide for protecting the lives and health of employees and other persons, preventing damage to property, materials, supplies, equipment and avoiding work interruptions.

☐ b. Any damage caused by the Contractor or his personnel will be restored and repaired at the expense of the Contractor.

5. DAILY LOGS:

☐ a. The Contractor shall provide the VA Project Manager with daily logs.

Project Engineer will explain frequency. The daily log shall identify the number of laborers, supervisors and each branch of work and will be used to verify payrolls submitted.

6. SAFETY:

☐ a. The VA Safety Officer has the authority to stop work if a serious safety violation is being committed.

7. CHANGES:

☐ a. The Contracting Officer (CO), from information furnished by the COTR may, by a written order, make changes to the drawings and/or specifications that are within the general scope of the contract. No other person is authorized to make revisions, changes, or deletions from the contract.

☐ b. Proposals for changes in work shall be submitted to the Contracting Officer according to the requirements contained in Clauses 52.243-4 and 852.236-88 of the General Conditions. Proposals more than $1,000 must include:

1. Itemized breakdown of labor and material costs.

2. List of subcontractors performing the work.

3. Overhead & Profit percentages.

☐ c. Change Orders (Proceed Orders): There may be some instances (as described in Clause 52.343-4 of the General Conditions) where the need to proceed with a change in work is necessary. In these cases, written authorization will be issued by the Contracting Officer (CO) to proceed with the work. An equitable adjustment will be negotiated within 30 calendar days.

8. SUBCONTRACTORS:

☐ a. The Contractor shall submit a list of subcontractors which will include names and addresses and the nature of work involved (SF 1413). The Contracting Officer reserves the right to disapprove any proposed Subcontractor who has had prior record of unsatisfactory work at this site, or any Federal or non-Federal Agency.

9. LABOR STANDARDS PROVISONS AND PAYROLLS:

☐ a. A copy of the rates and wages shall be posted by the Contractor in a prominent place at the work site.

☐ b. Apprentices will be permitted to work only under a Bona Fide apprenticeship program. Concurrent with or prior to the first payroll listing, certificates of apprenticeship from a recognized council shall be submitted to the Contracting Officer.

10. CORRESPONDENCE:

a. All correspondence from the Contractor shall bear:

☐ (1) Contract Number

☐ (2) Project Title

☐ (3) Project Name

11. OTHER TOPICS SPECIFIC TO THIS PROJECT:

{Signature of Contracting Officer, (CO) Date

Signature of Project Manager, (COR) Date

Signature of Contractor Date:

PROJECT: 578-15-001 Install Patient Lifts, Multiple Locations
DATE:
CONTRACT:
c The VA Project Manager for this project is: Burt Jimenez
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 1:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 2:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 3:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 4:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 5:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 6:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 7:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 8:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 9:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 10:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 11:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 12:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 13:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 14:
Check Box1: Yes
Check Box2: Yes
Check Box3: Yes
Check Box4: Yes
Check Box5: Yes
Check Box6: Yes
Check Box7: Yes
Check Box8: Yes
Check Box9: Yes
Check Box10: Yes
Check Box11: Yes
Check Box12: Yes
Check Box13: Yes
Check Box14: Yes
Check Box15: Yes
Check Box16: Yes
Check Box17: Yes
Check Box18: Yes
Check Box19: Yes
Check Box20: Yes
Check Box21: Off

File details come from the government source that posted it. Updated .