S02 - Att3 - Specs.pdf

PDF 25 MB Posted

Attached to
Construct EHRM Infrastructure Upgrades - Baltimore, MD Federal contract opportunity
Solicitation number
36C77626R0040_1
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This is a comprehensive specification document for the EHRM Infrastructure Upgrades project at Baltimore VA Medical Center in Baltimore, Maryland (Project #512-22-700). The specifications establish detailed requirements across multiple construction disciplines and include general requirements, safety protocols, quality control procedures, commissioning requirements, and technical specifications for all work components.

The project encompasses infrastructure upgrades including facility fiber distribution to telecommunications rooms with redundant fiber runs, additional data drops and electrical outlets throughout the facility, power distribution upgrades, HVAC distribution enhancements, and physical security upgrades. Key contractual requirements include: development of a comprehensive Accident Prevention Plan (APP) with Activity Hazard Analyses (AHAs) submitted 15 days before the preconstruction safety conference; a Quality Control Plan addressing three-phase control (Preparatory, Initial, and Follow-Up) for all definable features of work; detailed project scheduling using Network Analysis System (NAS) with cost-loaded activities submitted within 7 days of Notice to Proceed; and a fully developed Commissioning Plan addressing systems startup, pre-functional checklists, and Systems Functional Performance Testing. The contractor must obtain an approved Infection Control Risk Assessment (ICRA) plan from the VA Infection Control team before commencing work, phase construction to minimize disruptions to veterans and VA staff, and maintain normal working hours of 8:00 AM to 4:30 PM Monday through Friday unless approved otherwise by the Contracting Officer. Specific technical requirements address fire suppression systems, HVAC systems, electrical distribution, communications infrastructure, security systems, and all associated testing, balancing, and commissioning activities, with extensive documentation and quality assurance protocols throughout the construction and post-occupancy warranty phases.

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15 AUGUST 2025

EHRM

INFRASTRUCTURE

UPGRADES

PROJECT #: 512-22-700

BALTIMORE VA MEDICAL CENTER –

BALTIMORE, MARYLAND

SPECIFICATIONS

DIV 00-28

100% SUBMITTAL

CONSTRUCTION DOCUMENTS 2

EHRM INFRASTRUCTURE UPGRADES PROJECT #: 512-22-700

BALTIMORE VA MEDICAL CENTER – BALTIMORE, MD PUB. DATE: 08-15-2025

SEALS PAGE 00 01 07 - 01

SECTION 00 01 07

SEALS PAGE

CERTIFICATION

The technical material and data contained in these Contract Documents were prepared under the supervision and direcƟon of the undersigned, whose seal, as a licensed professional to pracƟce as such, is affixed below.

James M. King Registered Architect Division 0-4 & 7-10

Dante Valdez, S.E.

Structural Engineer Division 3 5

Joshua Wood, P.E.

Mechanical Engineer Division 21-23

Ryan Litzko, P.E.

Electrical Engineer Division 25-28

Kris Good, RCDD Division 27-28

Joshua Wood, P.E.

8/

/2

IN

8/15/2025

BALTIMORE VA MEDICAL CENTER – BALTIMORE, MD PUB. DATE: 08-07-2024

TABLE OF CONTENTS 00 01 10 - 01

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 07 Seals Page 08-25 00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24 01 33 23 Shop Drawings, Product Data, and Samples 11-23 01 35 26 Safety Requirements 05-24 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 35 Special Inspections 06-21 01 57 19 Temporary Environmental Controls 01-21 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21 07 22 00 Roof and Deck Insulation 01-21 07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Retarding 01-21 07 81 00 Applied Fireproofing 07-23 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22

TABLE OF CONTENTS 00 01 10 - 02

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 08 - OPENINGS

08 14 00 Interior Wood Doors 01-21 08 34 53 Security Doors & Frames 01-21 08 71 00 Door Hardware 03-24

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparations for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 66 00 Static Dissipative Sealer for Concrete Substrates 01-21 09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21 10 26 00 Wall and Door Protection 01-21 10 44 13 Fire Extinguisher Cabinets 08-18 10 60 00 Hot Aisle Containment System (HACS) 05-25

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16 21 13 13 Wet-Pipe Sprinkler Systems 06-15 21 22 00 Clean Agent Fire Suppression System 05-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23 23 05 12 General Motor Requirements for HVAC Equipment 03-23 23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 03-23 23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23 23 07 11 HVAC Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 09 23 Direct Digital Control System for HVAC 03-23

TABLE OF CONTENTS 00 01 10 - 03

SECTION NO DIVISION AND SECTION TITLES DATE

23 21 13 Hydronic Piping 03-23 23 21 23 Hydronic Pumps 03-23 23 23 00 Refrigerant Piping 03-24 23 25 00 HVAC Water Treatment 04-23 23 31 00 HVAC Ducts & Casings 03-23 23 36 00 Air Terminal Units 03-23 23 64 00 Packaged Water Chillers 03-24 23 65 00 Cooling Towers 03-23 23 81 23 Computer-Room Air-Conditioners 03-23 23 81 43 Air-Source Unitary Heat Pumps 03-23 23 82 16 Air Coils 03-23 23 84 00 Humidity Control Equipment 03-24

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 05 73 Overcurrent Protective Device Coordination Study 11-22 26 08 00 Commissioning of Electrical Systems 11-22 26 09 23 Lighting Controls 11-22 26 22 00 Low-Voltage Transformers 11-22 26 24 16 Panelboards 11-22 26 25 11 Busways 11-22 26 27 26 Wiring Devices 11-22 26 29 21 Enclosed Switches and Circuit Breakers 11-22 26 33 53 Static Uninterruptible Power Supply 11-22 26 41 00 Lightning Protection Devices 11-22 26 43 13 Surge Protective Devices 11-22 26 51 00 Interior Lighting 11-22

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19 27 05 26i Grounding and Bonding for Communications Systems 12-22 27 05 33i Raceways and Boxes for Communications Systems 12-22 27 05 36i Cable Trays for Communication Systems 12-22 27 05 53i Identification for Communication Systems 12-22 27 08 00 Commissioning of Communications Systems 11-16 27 10 00i Structured Cabling 12-22 27 11 00 Telecommunications Room Fittings 06-15 27 11 16i Communications Cabinets, Racks, Frames, and Enclosures 12-22 27 11 19i Communications Termination Blocks and Patch Panels 12-22 27 11 26i Communications Rack-Mounted Power Protection & Power Strips 12-22 27 13 13i Communications Copper Backbone Cabling 12-22 27 13 13.13i Communications Copper Cable Splicing and Terminations 12-22

TABLE OF CONTENTS 00 01 10 - 04

SECTION NO DIVISION AND SECTION TITLES DATE

27 13 23i Communications Optical Fiber Backbone Cabling 12-22 27 13.23.13I Communications Optical Fiber Splicing & Terminations 12-22 27 15 00 Communications Structured Cabling 01-16 27 15 13i Communications Copper Horizontal Cabling 12-22 27 16 19i Communications Patch Cords, Station Cords, and Cross Connect Wire 12-22

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and Security 10-18 28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11 28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 09-11 28 13 00 Physical Access Control System 10-11 28 13 53 Security Access Detection 08-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11

BALTIMORE VA MEDICAL CENTER – BALTIMORE, MD PUB. DATE: 05-01-2020

LIST OF DRAWING SHEETS 00 01 15 - 01

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

G-001 COVER PAGE

G-002 DRAWING INDEX

STRUCTURAL

S-001 STRUCTURAL GENERAL NOTES

S-002 ABREAVIATIONS AND SYMBOLS

S-101 ROOF FRAMING PLAN – LEVEL 8

S-501 TYPICAL STRUCTURAL STEEL DETAILS

ARCHITECTURAL

A-001 ARCHITECTURAL SYMBOLS & ABBREVIATIONS

A-002 GENERAL NOTES

AS101 ICRA DETAILS

AS102 ICRA STANDARDS

001A-10P3 BLDG 001 -PARKING LVL P3 -ARCHITECTURAL PLAN

001AS-10P3 BLDG 001 -PARKING LVL P3 -PHASING PLAN

001A-P03a BLDG 001 -P-LVL 03 -DEMO, FLOOR PLAN & RCPS

001A-P03b BLDG 001 -P-LVL 03 -DEMO, FLOOR PLAN & RCPS

001A-10P2 BLDG 001 -PARKING LVL P2 -ARCHITECTURAL PLAN

001AS-10P2 BLDG 001 -PARKING LVL P2 -PHASING PLAN

001A-P02a BLDG 001 -P-LVL 02 -DEMO, FLOOR PLAN & RCPS

001A-P02b BLDG 001 -P-LVL 02 -DEMO, FLOOR PLAN & RCPS

001A-10P1 BLDG 001 -PARKING LVL P1 -ARCHITECTURAL PLAN

001AS-10P1 BLDG 001 -PARKING LVL P1 -PHASING PLAN

001A-P01 BLDG 001 -P-LVL 01 -DEMO, FLOOR PLAN & RCPS

001A-100 BLDG 001 -LVL 00 -ARCHITECTURAL PLAN

001AS-100 BLDG 001 -LVL 00 -PHASING PLAN

LIST OF DRAWING SHEETS 00 01 15 - 02

001A-100a BLDG 001 -LVL 00 -DEMO, FLOOR PLAN & RCPS

001A-100b BLDG 001 -LVL 00 -DEMO, FLOOR PLAN & RCPS

001A-100c BLDG 001 -LVL 00 -DEMO, FLOOR PLAN & RCPS

001A-100d BLDG 001 -LVL 00 -DEMO, FLOOR PLAN & RCPS

001A-101 BLDG 001 -LVL 01 -ARCHITECTURAL PLAN

001AS-101 BLDG 001 -LVL 01 -PHASING PLAN

001A-101a BLDG 001 -LVL 01 -DEMO, FLOOR PLAN & RCPS

001A-101b BLDG 001 -LVL 01 -DEMO, FLOOR PLAN & RCPS

001A-101c BLDG 001 -LVL 01 -DEMO, FLOOR PLAN & RCPS

001A-101d BLDG 001 -LVL 01 -DEMO, FLOOR PLAN & RCPS

001A-101e BLDG 001 -LVL 01 -DEMO, FLOOR PLAN & RCPS

001A-102 BLDG 001 -LVL 02 -ARCHITECTURAL PLAN

001AS-102 BLDG 001 -LVL 02 -PHASING PLAN

001A-102a BLDG 001 -LVL 02 -DEMO, FLOOR PLAN & RCPS

001A-102b BLDG 001 -LVL 02 -DEMO, FLOOR PLAN & RCPS

001A-102c BLDG 001 -LVL 02 -DEMO, FLOOR PLAN & RCPS

001A-102d BLDG 001 -LVL 02 -DEMO, FLOOR PLAN & RCPS

001A-102e BLDG 001 -LVL 02 -DATA CENTER -DEMO FLOOR PLAN & RCP

001A-102f BLDG 001 -LVL 02 -DATA CENTER -FLOOR PLAN & RCP

001A-102g BLDG 001 -LVL 02 -DEMO, FLOOR PLAN & RCPS

001A-103 BLDG 001 -LVL 03 -ARCHITECTURAL PLAN

001AS-103 BLDG 003 -LVL 03 -PHASING PLAN

001A-103a BLDG 001 -LVL 03 -DEMO, FLOOR PLAN & RCPS

001A-103b BLDG 001 -LVL 03 -DEMO, FLOOR PLAN & RCPS

001A-103c BLDG 001 -LVL 03 -DEMO, FLOOR PLAN & RCPS

001A-103d BLDG 001 -LVL 03 -DEMO, FLOOR PLAN & RCPS

001A-103e BLDG 001 -LVL 03 -DEMO, FLOOR PLAN & RCPS

001A-104 BLDG 001 -LVL 04 -ARCHITECTURAL PLAN

001AS-104 BLDG 001 -LVL 04 -PHASING PLAN

001A-104a BLDG 001 -LVL 04 -DEMO, FLOOR PLAN & RCPS

001A-104b BLDG 001 -LVL 04 -DEMO, FLOOR PLAN & RCPS

001A-104c BLDG 001 -LVL 04 -DEMO, FLOOR PLAN & RCPS

001A-104d BLDG 001 -LVL 04 -DEMO, FLOOR PLAN & RCPS

LIST OF DRAWING SHEETS 00 01 15 - 03

001A-104e BLDG 001 -LVL 04 -DEMO, FLOOR PLAN & RCPS

001A-105 BLDG 001 -LVL 05 -ARCHITECTURAL PLAN

001AS-105 BLDG 001 -LVL 05 -PHASING PLAN

001A-105a BLDG 001 -LVL 05 -DEMO, FLOOR PLAN & RCPS

001A-105b BLDG 001 -LVL 05 -DEMO, FLOOR PLAN & RCPS

001A-105c BLDG 001 -LVL 05 -DEMO, FLOOR PLAN & RCPS

001A-105d BLDG 001 -LVL 05 -DEMO, FLOOR PLAN & RCPS

001A-105e BLDG 001 -LVL 05 -DEMO, FLOOR PLAN & RCPS

001A-106 BLDG 001 -LVL 06 -ARCHITECTURAL PLAN

001AS-106 BLDG 001 -LVL 06 -PHASING PLAN

001A-106a BLDG 001 -LVL 06 -DEMO, FLOOR PLAN & RCPS

001A-106b BLDG 001 -LVL 06 -DEMO, FLOOR PLAN & RCPS

001A-106c BLDG 001 -LVL 06 -DEMO, FLOOR PLAN & RCPS

001A-106d BLDG 001 -LVL 06 -DEMO, FLOOR PLAN & RCPS

001A-106e BLDG 001 -LVL 06 -DEMO, FLOOR PLAN & RCPS

001A-107 BLDG 001 -LVL 07 -ARCHITECTURAL PLAN

001AS-107 BLDG 001 -LVL 07 -PHASING PLAN

001A-107a BLDG 001 -LVL 07 -DEMO, FLOOR PLAN & RCPS

001A-107b BLDG 001 -LVL 07 -DEMO, FLOOR PLAN & RCPS

001A-108 BLDG 001 -LVL 08 -ARCHITECTURAL PLAN

001AS-108 BLDG 001 -LVL 08 -PHASING PLAN

001A-108a BLDG 001 -LVL 08 -DEMO, FLOOR PLAN & RCPS

A-601 ROOM FINISH SCHEDULE

A-602 DOOR SCHEDULE, TYPES & DETAILS

A-603 WALL TYPES, DETAILS

AE421 INTERIOR ELEVATIONS, TR PLANVIEW & WINDOW DETAIL

AW001 IN-03.01 -ROOM NUMBER SIGN & SIGNAGE SCHEDULE

MECHANICAL

FX001 FIRE PROTECTION GENERAL NOTES, ABBREVIATION & LEGENDS

FD401 LEVEL 02 -DATA CENTER -FIRE PROTECTION -DEMOLITION RCP

FD402 LEVEL 02 -DATA CENTER -FIRE PROTECTION -DEMOLITION PLAN

FX401 LEVEL 02 -DATA CENTER -FIRE PROTECTION -FLOOR PLAN & RCP

LIST OF DRAWING SHEETS 00 01 15 - 04

FX402 LEVEL 02 -DATA CENTER -FIRE PROTECTION -PLAN

P-001 PLUMBING GENERAL NOTES

PD401 LEVEL 01 -DATA CENTER -PLUMBING -DEMOLITION PLAN

PD402 LEVEL 02-DATA CENTER-PLUMBING -DEMOLITION INTERSTITIAL

PLAN

P-401 LEVEL 02 -ZONE B -PLUMBING -FLOOR PLAN

P-402 LEVEL 02 -DATA CENTER -PLUMBING -FLOOR PLAN

P-403 LEVEL 02 -DATA CENTER -PLUMBING -INTERSTITIAL PLAN

P-404 LEVEL 07 -CENTER -PLUMBING -FLOOR PLAN

M-001 MECHANICAL GENERAL NOTES

M-002 MECHANICAL ABBREVIATIONS & LEGENDS

M-101 LEVEL P3 -OVERALL MECHANICAL PLAN

M-102 LEVEL P2 -OVERALL MECHANICAL PLAN

M-103 LEVEL P1 -OVERALL MECHANICAL PLAN

M-104 LEVEL 00 -OVERALL MECHANICAL PLAN

M-105 LEVEL 01 -OVERALL MECHANICAL PLAN

M-106 LEVEL 02 -OVERALL MECHANICAL PLAN

M-107 LEVEL 03 -OVERALL MECHANICAL PLAN

M-108 LEVEL 04 -OVERALL MECHANICAL PLAN

M-109 LEVEL 05 -OVERALL MECHANICAL PLAN

M-110 LEVEL 06 -OVERALL MECHANICAL PLAN

M-111 LEVEL 07 -OVERALL MECHANICAL PLAN

M-112 LEVEL 08 -OVERALL MECHANICAL PLAN

MH301 DATA CENTER SECTION VIEW

M-401 LEVEL P3 -ZONE C & ZONE D -FLOOR PLANS

M-402 LEVEL P2 -ZONE C & ZONE D -FLOOR PLANS

M-403 LEVEL P1 -CENTER -DEMOLITION, FLOOR PLAN & RCPS

M-404 LEVEL 00 -ZONE A -DEMOLITION, FLOOR PLAN & RCPS

M-405 LEVEL 00 -ZONE B -DEMOLITION, FLOOR PLAN & RCPS

M-406 LEVEL 00 -ZONE C -DEMOLITION & FLOOR PLAN

M-407 LEVEL 00 -ZONE C -DEMOLITION, FLOOR PLAN & RCPS

M-408 LEVEL 00 -ZONE D -DEMOLITION, FLOOR PLAN & RCPS

M-409 LEVEL 01 -ZONE A -DEMOLITION, FLOOR PLAN & RCPS

LIST OF DRAWING SHEETS 00 01 15 - 05

M-410 LEVEL 01 -ZONE B -DEMOLITION, FLOOR PLAN & RCPS

M-411 LEVEL 01 -ZONE C -DEMOLITION, FLOOR PLAN & RCPS

M-412 LEVEL 01 -ZONE D -DEMOLITION, FLOOR PLAN & RCPS

M-413 LEVEL 01 -CENTER -DEMOLITION, FLOOR PLAN & RCPS

M-414 LEVEL 02 -ZONE A -DEMOLITION, FLOOR PLAN & RCPS

M-415 LEVEL 02 -DATA CENTER -HVAC -DEMOLITION & RCP PLAN

M-416 LEVEL 02 -DATA CENTER-HVAC-DEMOLITION INTERSTITIAL PLAN

M-417 LEVEL 02 -DATA CENTER -HVAC -FLOOR PLAN

M-418 LEVEL 02 -DATA CENTER -HVAC -INTERSTITIAL PLAN

M-419 LEVEL 02 -ZONE B -DEMOLITION, FLOOR PLAN & RCPS

M-420 LEVEL 02 -ZONE C -DEMOLITION, FLOOR PLAN & RCPS

M-421 LEVEL 02 -ZONE D -DEMOLITION, FLOOR PLAN & RCPS

M-422 LEVEL 02 -CENTER -DEMOLITION, FLOOR PLAN & RCPS

M-423 LEVEL 03 -ZONE A -DEMOLITION, FLOOR PLAN & RCPS

M-424 LEVEL 03 -ZONE B -DEMOLITION, FLOOR PLAN & RCPS

M-425 LEVEL 03 -ZONE C -DEMOLITION, FLOOR PLAN & RCPS

M-426 LEVEL 03 -ZONE D -DEMOLITION, FLOOR PLAN & RCPS

M-427 LEVEL 03 -CENTER -DEMOLITION, FLOOR PLAN & RCPS

M-428 LEVEL 04 -ZONE A -DEMOLITION, FLOOR PLAN & RCPS

M-429 LEVEL 04 -ZONE B -DEMOLITION, FLOOR PLAN & RCPS

M-430 LEVEL 04 -ZONE C -DEMOLITION, FLOOR PLAN & RCPS

M-431 LEVEL 04 -ZONE D -DEMOLITION, FLOOR PLAN & RCPS

M-432 LEVEL 04 -CENTER -DEMOLITION, FLOOR PLAN & RCPS

M-433 LEVEL 05 -ZONE A -DEMOLITION, FLOOR PLAN & RCPS

M-434 LEVEL 05 -ZONE B -DEMOLITION, FLOOR PLAN & RCPS

M-435 LEVEL 05 -ZONE C -DEMOLITION, FLOOR PLAN & RCPS

M-436 LEVEL 05 -ZONE D -DEMOLITION, FLOOR PLAN & RCPS

M-437 LEVEL 05 -CENTER -DEMOLITION, FLOOR PLAN & RCPS

M-438 LEVEL 06 -ZONE A -DEMOLITION, FLOOR PLAN & RCPS

M-439 LEVEL 06 -ZONE B -DEMOLITION, FLOOR PLAN & RCPS

M-440 LEVEL 06 -ZONE C -DEMOLITION, FLOOR PLAN & RCPS

M-441 LEVEL 06 -ZONE D -DEMOLITION, FLOOR PLAN & RCPS

M-442 LEVEL 06 -CENTER -DEMOLITION, FLOOR PLAN & RCPS

LIST OF DRAWING SHEETS 00 01 15 - 06

M-443 LEVEL 07 -ZONE A -ROOF PLAN

M-444 LEVEL 07 -ZONE B -ROOF PLAN

M-445 LEVEL 07 -ZONE C -ROOF PLAN

M-446 LEVEL 07 -ZONE D -ROOF PLAN

M-447 LEVEL 07 -CENTER -ROOF PLAN

M-448 LEVEL 07 -7D-100 -FLOOR PLAN

M-449 LEVEL 08 -8D-100 -ROOF PLAN

M-501 MECHANICAL DETAILS I

M-502 MECHANICAL DETAILS II

M-503 MECHANICAL DETAILS III

M-504 HYDRONIC PROCESS FLOW DIAGRAM

M-601 MECHANICAL SCHEDULES I

M-602 MECHANICAL SCHEDULES II

M-701 MECHANICAL CONTROLS I

M-702 MECHANICAL CONTROLS II

M-703 MECHANICAL CONTROLS III

M-704 MECHANICAL CONTROLS IV

ELECTRICAL

E-001 ABBREVIATIONS, GENERAL NOTES, AND SHEET INDEX

E-002 ELECTRICAL LEGENDS

001E-100P3 BLDG 001 - LEVEL P3 - ELECTRICAL PLAN

001E-100P2 BLDG 001 - LEVEL P2 - ELECTRICAL PLAN

001E-100P1 BLDG 001 - LEVEL P1 - ELECTRICAL PLAN

001E-100 BLDG 001 - LEVEL 00 - ELECTRICAL PLAN

001E-101 BLDG 001 - LEVEL 01 - ELECTRICAL PLAN

001E-102 BLDG 001 - LEVEL 02 - ELECTRICAL PLAN

001E-103 BLDG 001 - LEVEL 03 - ELECTRICAL PLAN

001E-104 BLDG 001 - LEVEL 04 - ELECTRICAL PLAN

001E-105 BLDG 001 - LEVEL 05 - ELECTRICAL PLAN

001E-106 BLDG 001 - LEVEL 06 - ELECTRICALPLAN

001E-107 BLDG 001 - LEVEL 07 - ELECTRICAL PLAN

001E-108 BLDG 001 - LEVEL 08 - ELECTRICAL PLAN

LIST OF DRAWING SHEETS 00 01 15 - 07

001E-400P3 BLDG 001 - LEVEL P3 - ENLARGED ELECTRICAL PLANS

001E-400P2 BLDG 001 - LEVEL P2 - ENLARGED ELECTRICAL PLANS

001E-400P1a BLDG 001 - LEVEL P1 - ENLARGED ELECTRICAL PLANS

001E-400P1b BLDG 001 - LEVEL P1 - ENLARGED ELECTRICAL PLANS

001E-400P1c BLDG 001 - LEVEL P1 - ENLARGED ELECTRICAL PLANS

001E-400a BLDG 001 - LEVEL 00 - ENLARGED ELECTRICAL PLANS

001E-400b BLDG 001 - LEVEL 00 - ENLARGED ELECTRICAL PLANS

001E-400c BLDG 001 - LEVEL 00 - ENLARGED ELECTRICAL PLANS

001E-400d BLDG 001 - LEVEL 00 - ENLARGED ELECTRICAL PLANS

001E-400e BLDG 001 - LEVEL 00 - ENLARGED ELECTRICAL PLANS

001E-400f BLDG 001 - LEVEL 00 - ENLARGED ELECTRICAL PLANS

001E-401a BLDG 001 - LEVEL 01 - ENLARGED ELECTRICAL PLANS

001E-401b BLDG 001 - LEVEL 01 - ENLARGED ELECTRICAL PLANS

001E-401c BLDG 001 - LEVEL 01 - ENLARGED ELECTRICAL PLANS

001E-401d BLDG 001 - LEVEL 01 - ENLARGED ELECTRICAL PLANS

001E-401e BLDG 001 - LEVEL 01 - ENLARGED ELECTRICAL PLANS

001E-402a BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402b BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402c BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402d BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402e BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402f BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402g BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402h BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402i BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-402j BLDG 001 - LEVEL 02 - ENLARGED ELECTRICAL PLANS

001E-403a BLDG 001 - LEVEL 03 - ENLARGED ELECTRICAL PLANS

001E-403b BLDG 001 - LEVEL 03 - ENLARGED ELECTRICAL PLANS

001E-403c BLDG 001 - LEVEL 03 - ENLARGED ELECTRICAL PLANS

001E-403d BLDG 001 - LEVEL 03 - ENLARGED ELECTRICAL PLANS

001E-403e BLDG 001 - LEVEL 03 - ENLARGED ELECTRICAL PLANS

001E-403f BLDG 001 - LEVEL 03 - ENLARGED ELECTRICAL PLANS

001E-403g BLDG 001 - LEVEL 03 - ENLARGED ELECTRICAL PLANS

LIST OF DRAWING SHEETS 00 01 15 - 08

001E-404a BLDG 001 - LEVEL 04 - ENLARGED ELECTRICAL PLANS

001E-404b BLDG 001 - LEVEL 04 - ENLARGED ELECTRICAL PLANS

001E-404c BLDG 001 - LEVEL 04 - ENLARGED ELECTRICAL PLANS

001E-404d BLDG 001 - LEVEL 04 - ENLARGED ELECTRICAL PLANS

001E-404e BLDG 001 - LEVEL 04 - ENLARGED ELECTRICAL PLANS

001E-404f BLDG 001 - LEVEL 04 - ENLARGED ELECTRICAL PLANS

001E-405a BLDG 001 - LEVEL 05 - ENLARGED ELECTRICAL PLANS

001E-405b BLDG 001 - LEVEL 05 - ENLARGED ELECTRICAL PLANS

001E-405c BLDG 001 - LEVEL 05 - ENLARGED ELECTRICAL PLANS

001E-405d BLDG 001 - LEVEL 05 - ENLARGED ELECTRICAL PLANS

001E-405e BLDG 001 - LEVEL 05 - ENLARGED ELECTRICAL PLANS

001E-406a BLDG 001 - LEVEL 06 - ENLARGED ELECTRICAL PLANS

001E-406b BLDG 001 - LEVEL 06- ENLARGED ELECTRICAL PLANS

001E-406c BLDG 001 - LEVEL 06 - ENLARGED ELECTRICAL PLANS

001E-406d BLDG 001 - LEVEL 06 - ENLARGED ELECTRICAL PLANS

001E-406e BLDG 001 - LEVEL 06 - ENLARGED ELECTRICAL PLANS

001E-407 BLDG 001 - LEVEL 07 - ENLARGED ELECTRICAL PLANS

001E-408 BLDG 001 - LEVEL 08 - ENLARGED ELECTRICAL PLANS

E-501 ELECTRICAL DETAILS

E-502 ELECTRICAL DETAILS

E-503 ELECTRICAL DETAILS

E-504 ELECTRICAL DETAILS

E-505 ELECTRICAL DETAILS

E-506 ELECTRICAL DETAILS

E-507 ELECTRICAL DETAILS

E-508 ELECTRICAL DETAILS

E-509 ELECTRICAL DETAILS

EF601 DATA CENTER FIRE ALARM RISER DIAGRAM

EG601 TELECOMMUNICATIONS BONDING RISER DIAGRAMS

E-601 ONE-LINE DIAGRAM - PART 1 OF 5

E-602 ONE-LINE DIAGRAM - PART 2 OF 5

E-603 ONE-LINE DIAGRAM - PART 3 OF 5

E-604 ONE-LINE DIAGRAM - PART 4 OF 5

LIST OF DRAWING SHEETS 00 01 15 - 09

E-605 ONE-LINE DIAGRAM - PART 5 OF 5

E-701 ELECTRICAL SCHEDULES

E-702 ELECTRICAL SCHEDULES

E-711 ELECTRICAL SCHEDULES - 'A' STACK TRs

E-712 ELECTRICAL SCHEDULES - 'A' STACK TRs

E-713 ELECTRICAL SCHEDULES - 'A' STACK TRs

E-714 ELECTRICAL SCHEDULES - 'A' STACK TRs

E-721 ELECTRICAL SCHEDULES - 'B' STACK TRs

E-722 ELECTRICAL SCHEDULES - 'B' STACK TRs

E-723 ELECTRICAL SCHEDULES - 'B' STACK TRs

E-724 ELECTRICAL SCHEDULES - 'B' STACK TRs

E-731 ELECTRICAL SCHEDULES - 'C' STACK TRs

E-732 ELECTRICAL SCHEDULES - 'C' STACK TRs

E-733 ELECTRICAL SCHEDULES - 'C' STACK TRs

E-734 ELECTRICAL SCHEDULES - 'C' STACK TRs

E-741 ELECTRICAL SCHEDULES - 'D' STACK TRs

E-742 ELECTRICAL SCHEDULES - 'D' STACK TRs

E-743 ELECTRICAL SCHEDULES - 'D' STACK TRs

E-744 ELECTRICAL SCHEDULES - 'D' STACK TRs

E-751 ELECTRICAL SCHEDULES - 'E' STACK TRs

E-752 ELECTRICAL SCHEDULES - 'E' STACK TRs

E-753 ELECTRICAL SCHEDULES - 'E' STACK TRs

E-761 ELECTRICAL SCHEDULES - DATA CENTER

TELECOMMUNICATIONS

TNG001 ABBREVIATIONS, GENERAL NOTES, AND SHEET INDEX

TNG002 TELECOMMUNICATIONS LEGEND

001TN100P3 BLDG 001 - LEVEL P3 - TELECOMMUNICATIONS PLAN

001TN100P2 BLDG 001 - LEVEL P2 - TELECOMMUNICATIONS PLAN

001TN100P1 BLDG 001 - LEVEL P1 - TELECOMMUNICATIONS PLAN

001TN100 BLDG 001 - LEVEL 00 - TELECOMMUNICATIONS PLAN

001TN100i BLDG 001 - LEVEL 00 INTERSTITIAL - TELECOMMUNICATIONS

PLAN

LIST OF DRAWING SHEETS 00 01 15 - 10

001TN101 BLDG 001 - LEVEL 01 - TELECOMMUNICATIONS PLAN

001TN101i BLDG 001 - LEVEL 01 INTERSTITIAL - TELECOMMUNICATIONS

PLAN

001TN102 BLDG 001 - LEVEL 02 - TELECOMMUNICATIONS PLAN

001TN102i BLDG 001 - LEVEL 02 INTERSTITIAL - TELECOMMUNICATIONS

PLAN

001TN103 BLDG 001 - LEVEL 03 - TELECOMMUNICATIONS PLAN

001TN103i BLDG 001 - LEVEL 03 INTERSTITIAL - TELECOMMUNICATIONS

PLAN

001TN104 BLDG 001 - LEVEL 04 - TELECOMMUNICATIONS PLAN

001TN104i BLDG 001 - LEVEL 04 INTERSTITIAL - TELECOMMUNICATIONS

PLAN

001TN105 BLDG 001 - LEVEL 05 - TELECOMMUNICATIONS PLAN

001TN105i BLDG 001 - LEVEL 05 INTERSTITIAL - TELECOMMUNICATIONS

PLAN

001TN106 BLDG 001 - LEVEL 06 - TELECOMMUNICATIONS PLAN

001TN106i BLDG 001 - LEVEL 06 INTERSTITIAL - TELECOMMUNICATIONS

PLAN

001TN107 BLDG 001 - LEVEL 07 - TELECOMMUNICATIONS PLAN

001TN108 BLDG 001 - LEVEL 08 - TELECOMMUNICATIONS PLAN

001TN400P3a BLDG 001 - LEVEL P3 - ENLARGED TELECOMMUNICATIONS

PLANS

001TN400P3b BLDG 001-LEVEL P3 - ENLARGED TELECOMMUNICATIONS PLANS

001TN400P2a BLDG 001-LEVEL P2 - ENLARGED TELECOMMUNICATIONS PLANS

001TN400P2b BLDG 001-LEVEL P2 - ENLARGED TELECOMMUNICATIONS PLANS

001TN400P1 BLDG 001-LEVEL P1 - ENLARGED TELECOMMUNICATIONS PLANS

001TN400a BLDG 001-LEVEL 00 - ENLARGED TELECOMMUNICATIONS PLANS

001TN400b BLDG 001-LEVEL 00 - ENLARGED TELECOMMUNICATIONS PLANS

001TN400c BLDG 001-LEVEL 00 - ENLARGED TELECOMMUNICATIONS PLANS

001TN400d BLDG 001-LEVEL 00 - ENLARGED TELECOMMUNICATIONS PLANS

001TN401a BLDG 001-LEVEL 01 - ENLARGED TELECOMMUNICATIONS PLANS

001TN401b BLDG 001-LEVEL 01 - ENLARGED TELECOMMUNICATIONS PLANS

001TN401c BLDG 001-LEVEL 01 - ENLARGED TELECOMMUNICATIONS PLANS

001TN401d BLDG 001-LEVEL 01 - ENLARGED TELECOMMUNICATIONS PLANS

001TN401e BLDG 001-LEVEL 01 - ENLARGED TELECOMMUNICATIONS PLANS

LIST OF DRAWING SHEETS 00 01 15 - 11

001TN402a BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402b BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402c BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402d BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402e BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402f BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402g BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN403a BLDG 001-LEVEL 03 - ENLARGED TELECOMMUNICATIONS PLANS

001TN403b BLDG 001-LEVEL 03 - ENLARGED TELECOMMUNICATIONS PLANS

001TN403c BLDG 001-LEVEL 03 - ENLARGED TELECOMMUNICATIONS PLANS

001TN403d BLDG 001-LEVEL 03 - ENLARGED TELECOMMUNICATIONS PLANS

001TN403e BLDG 001-LEVEL 03-ENLARGED TELECOMMUNICATIONS PLANS

001TN404a BLDG 001-LEVEL 04 - ENLARGED TELECOMMUNICATIONS PLANS

001TN404b BLDG 001-LEVEL 04 - ENLARGED TELECOMMUNICATIONS PLANS

001TN404c BLDG 001-LEVEL 04 - ENLARGED TELECOMMUNICATIONS PLANS

001TN404d BLDG 001-LEVEL 04 - ENLARGED TELECOMMUNICATIONS PLANS

001TN404e BLDG 001-LEVEL 04 -ENLARGED TELECOMMUNICATIONS PLANS

001TN405a BLDG 001-LEVEL 05- ENLARGED TELECOMMUNICATIONS PLANS

001TN405b BLDG 001-LEVEL 05- ENLARGED TELECOMMUNICATIONS PLANS

001TN405c BLDG 001-LEVEL 05 - ENLARGED TELECOMMUNICATIONS PLANS

001TN405d BLDG 001-LEVEL 05 - ENLARGED TELECOMMUNICATIONS PLANS

001TN405e BLDG 001-LEVEL 05 - ENLARGED TELECOMMUNICATIONS PLANS

001TN406a BLDG 001-LEVEL 06 - ENLARGED TELECOMMUNICATIONS PLANS

001TN406b BLDG 001-LEVEL 06 - ENLARGED TELECOMMUNICATIONS PLANS

001TN406c BLDG 001-LEVEL 06 -ENLARGED TELECOMMUNICATIONS PLANS

001TN406d BLDG 001-LEVEL 06 -ENLARGED TELECOMMUNICATIONS PLANS

001TN406e BLDG 001-LEVEL 06- ENLARGED TELECOMMUNICATIONS PLANS

001TN407 BLDG 001-LEVEL 07 - ENLARGED TELECOMMUNICATIONS PLANS

TN501 TELECOMMUNICATIONS DETAILS

TN502 TELECOMMUNICATIONS DETAILS

TN503 TELECOMMUNICATIONS DETAILS

TN504 TELECOMMUNICATIONS DETAILS

TN505 TELECOMMUNICATIONS DETAILS

LIST OF DRAWING SHEETS 00 01 15 - 12

TN506 TELECOMMUNICATIONS DETAILS

TN507 TELECOMMUNICATIONS DETAILS

TN601 FIBER RISER DIAGRAM

TN602 FIBER RISER DIAGRAM

TN701 TELECOMMUNICATIONS SCHEDULES

TNG001 ABBREVIATIONS, GENERAL NOTES, AND SHEET INDEX

TNG002 TELECOMMUNICATIONS LEGEND

001TN100P3 BLDG 001 - LEVEL P3 - TELECOMMUNICATIONS PLAN

001TN100P2 BLDG 001 - LEVEL P2 - TELECOMMUNICATIONS PLAN

001TN100P1 BLDG 001 - LEVEL P1 - TELECOMMUNICATIONS PLAN

001TN100 BLDG 001 - LEVEL 00 - TELECOMMUNICATIONS PLAN

001TN100i BLDG 001-LEVEL 00 INTERSTITIAL-TELECOMMUNICATIONS PLAN

001TN101 BLDG 001 - LEVEL 01 - TELECOMMUNICATIONS PLAN

001TN101i BLDG 001-LEVEL 01 INTERSTITIAL-TELECOMMUNICATIONS PLAN

001TN102 BLDG 001- LEVEL 02 - TELECOMMUNICATIONS PLAN

001TN102i BLDG 001-LEVEL 02 INTERSTITIAL-TELECOMMUNICATIONS PLAN

001TN103 BLDG 001 - LEVEL 03 - TELECOMMUNICATIONS PLAN

001TN103i BLDG 001-LEVEL 03 INTERSTITIAL-TELECOMMUNICATIONS PLAN

001TN104 BLDG 001 - LEVEL 04 - TELECOMMUNICATIONS PLAN

001TN104i BLDG 001-LEVEL 04 INTERSTITIAL-TELECOMMUNICATIONS PLAN

001TN105 BLDG 001 - LEVEL 05 - TELECOMMUNICATIONS PLAN

001TN105i BLDG 001-LEVEL 05 INTERSTITIAL-TELECOMMUNICATIONS PLAN

001TN106 BLDG 001 - LEVEL 06 - TELECOMMUNICATIONS PLAN

001TN106i BLDG 001-LEVEL 06 INTERSTITIAL-TELECOMMUNICATIONS PLAN

001TN107 BLDG 001 - LEVEL 07 - TELECOMMUNICATIONS PLAN

001TN108 BLDG 001 - LEVEL 08 - TELECOMMUNICATIONS PLAN

001TN400P3a BLDG 001-LEVEL P3-ENLARGED TELECOMMUNICATIONS PLANS

001TN400P3b BLDG 001-LEVEL P3-ENLARGED TELECOMMUNICATIONS PLANS

001TN400P2a BLDG 001-LEVEL P2-ENLARGED TELECOMMUNICATIONS PLANS

001TN400P2b BLDG 001-LEVEL P2- ENLARGED TELECOMMUNICATIONS PLANS

001TN400P1 BLDG 001-LEVEL P1-ENLARGED TELECOMMUNICATIONS PLANS

001TN400a BLDG 001-LEVEL 00-ENLARGED TELECOMMUNICATIONS PLANS

001TN400b BLDG 001-LEVEL 00 - ENLARGED TELECOMMUNICATIONS PLANS

LIST OF DRAWING SHEETS 00 01 15 - 13

001TN400c BLDG 001-LEVEL 00-ENLARGED TELECOMMUNICATIONS PLANS

001TN400d BLDG 001-LEVEL 00-ENLARGED TELECOMMUNICATIONS PLANS

001TN401a BLDG 001-LEVEL 01- ENLARGED TELECOMMUNICATIONS PLANS

001TN401b BLDG 001-LEVEL 01- ENLARGED TELECOMMUNICATIONS PLANS

001TN401c BLDG 001 -LEVEL 01- ENLARGED TELECOMMUNICATIONS PLANS

001TN401d BLDG 001 LEVEL 01- ENLARGED TELECOMMUNICATIONS PLANS

001TN401e BLDG 001 -LEVEL 01- ENLARGED TELECOMMUNICATIONS PLANS

001TN402a BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402b BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402c BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402d BLDG 001-LEVEL 02 - ENLARGED TELECOMMUNICATIONS PLANS

001TN402e BLDG 001-LEVEL 02- ENLARGED TELECOMMUNICATIONS PLANS

001TN402f BLDG 001-LEVEL 02 -ENLARGED TELECOMMUNICATIONS PLANS

001TN402g BLDG 001-LEVEL 02- ENLARGED TELECOMMUNICATIONS PLANS

001TN403a BLDG 001-LEVEL 03 - ENLARGED TELECOMMUNICATIONS PLANS

001TN403b BLDG 001-LEVEL 03- ENLARGED TELECOMMUNICATIONS PLANS

001TN403c BLDG 001-LEVEL 03 - ENLARGED TELECOMMUNICATIONS PLANS

001TN403d BLDG 001-LEVEL 03 - ENLARGED TELECOMMUNICATIONS PLANS

001TN403e BLDG 001-LEVEL 03- ENLARGED TELECOMMUNICATIONS PLANS

001TN404a BLDG 001-LEVEL 04 - ENLARGED TELECOMMUNICATIONS PLANS

001TN404b BLDG 001-LEVEL 04- ENLARGED TELECOMMUNICATIONS PLANS

001TN404c BLDG 001-LEVEL 04 - ENLARGED TELECOMMUNICATIONS PLANS

001TN404d BLDG 001-LEVEL 04 - ENLARGED TELECOMMUNICATIONS PLANS

001TN404e BLDG 001-LEVEL 04 - ENLARGED TELECOMMUNICATIONS PLANS

001TN405a BLDG 001-LEVEL 05 - ENLARGED TELECOMMUNICATIONS PLANS

001TN405b BLDG 001-LEVEL 05 - ENLARGED TELECOMMUNICATIONS PLANS

001TN405c BLDG 001-LEVEL 05 - ENLARGED TELECOMMUNICATIONS PLANS

001TN405d BLDG 001-LEVEL 05 - ENLARGED TELECOMMUNICATIONS PLANS

001TN405e BLDG 001-LEVEL 05 - ENLARGED TELECOMMUNICATIONS PLANS

001TN406a BLDG 001-LEVEL 06 - ENLARGED TELECOMMUNICATIONS PLANS

001TN406b BLDG 001-LEVEL 06 - ENLARGED TELECOMMUNICATIONS PLANS

001TN406c BLDG 001-LEVEL 06 - ENLARGED TELECOMMUNICATIONS PLANS

001TN406d BLDG 001 -LEVEL 06-ENLARGED TELECOMMUNICATIONS PLANS

LIST OF DRAWING SHEETS 00 01 15 - 14

001TN406e BLDG 001-LEVEL 06-ENLARGED TELECOMMUNICATIONS PLANS

001TN407 BLDG 001 - LEVEL 07-ENLARGED TELECOMMUNICATIONS PLANS

TN501 TELECOMMUNICATIONS DETAILS

TN502 TELECOMMUNICATIONS DETAILS

TN503 TELECOMMUNICATIONS DETAILS

TN504 TELECOMMUNICATIONS DETAILS

TN505 TELECOMMUNICATIONS DETAILS

TN506 TELECOMMUNICATIONS DETAILS

TN507 TELECOMMUNICATIONS DETAILS

TN601 FIBER RISER DIAGRAM

TN602 FIBER RISER DIAGRAM

TN701 TELECOMMUNICATIONS SCHEDULES

- - - END - - -

BALTIMORE VA MEDICAL CENTER – BALTIMORE, MD PUB. DATE: 11-01-2021

GENERAL REQUIREMENTS 01 00 00 - 01

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for EHRM

INFRASTRUCTURE UPGRADES as required by drawings and specifications. Project scope includes, but is not limited to, the following infrastructure upgrades: Upgraded facility fiber throughout the building to each Telecommunications Room (TR); Provide a redundant fiber run throughout the facility to each TR; Provide redundant fiber mains to the demarcation room from the provider point; Install additional data drops; Install new electrical outlets throughout the facility;

Provide additional power in each TR; Upgrade facility power distribution as required; Upgrade facility HVAC distribution has required; and Physical Security upgrades.

B. Visits to the site by Bidders may be made only by appointment with the Contracting Officer’s

Representative (COR).

C. Offices of Spees Design Build, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by

Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by

Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, EHRM INFRASTRUCTURE UPGRADES: Work includes all general, safety, and management requirements depicted in the contract documents.

GENERAL REQUIREMENTS 01 00 00 - 02

B. ITEM II, GENERAL CONSTRUCTION: Work includes general constructions, alterations, and selective demolition depicted in the contract documents.

C. ITEM III, ELECTRICAL WORK: Work includes all labor, material, equipment, and supervision to perform the required electrical work on this project depicted in the contract documents.

D. ITEM IV, MECHANICAL WORK: Work includes all labor, material, equipment, and supervision to perform the required mechanical work on this project depicted in the contract documents.

E. ITEM V, TELECOMMUNICATIONS WORK: Work includes all labor, material, equipment, and supervision to perform the required telecommunications work on this project depicted in the contract documents.

F. ITEM VI, STRUCTURAL WORK: Work includes all labor, material, equipment, and supervision to perform the required structural work on this project depicted in the contract documents.

G. ITEM VII, SITE AND CIVIL WORK: Work includes all labor, material, equipment, and supervision to perform the required site and civil work on this project depicted in the contract documents.

H. ITEM VIII, ENVIRONMENTAL WORK: Work includes all labor, material, equipment, and supervision to perform the required environmental remediation work on this project depicted in the contract documents.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. Physical security of the construction site and installation will meet requirements depicted in the next paragraph, “Security Procedures,” the VA Design Manual “Physical Security Design

Manual for VA Life-Safety Protected Facilities,” and any other applicable VA documentation.

2. The Contractor is responsible for determining the security plan that will define both physical and administrative security procedures. Once approved by the VA, these procedures will remain effective for the entire duration of the project.

3. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

GENERAL REQUIREMENTS 01 00 00 - 03

1. General Contractor’s employees shall not enter the project site without appropriate badge.

They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting

Officer so that security escort and/or arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting

Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General

Contractor’s employees off the premises in the event of a national emergency. The General

Contractor may return to the site only with the written approval of the Contracting Officer.

C. Guards:

1. The General Contractor shall provide unarmed guards at the project site after construction hours.

2. The Contractor shall provide the guards and VA police with communication devices as directed.

3. The general Contractor shall install equipment for recording guard rounds to ensure systematic checking of the premises.

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the

Contracting officer’s representative (COR) for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.

2. The General Contractor shall install all permanent cores (Small Format Mortise Locks with interchangeable cores) at completion of the work. See Section 08 71 00, DOOR HARDWARE and coordinate.

E. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

GENERAL REQUIREMENTS 01 00 00 - 04

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law

Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

F. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Limited amounts of well-organized and unobtrusive materials and tools may be kept in the construction area during construction. The VA Medical Center COR may request items be relocated at any point.

GENERAL REQUIREMENTS 01 00 00 - 05

C. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the

Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the

Contractor at its expense upon completion of the work. With the written consent of the

Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

D. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

E. Working space and space available for storing materials shall be determined by the COR.

F. Workers are subject to rules of the VA Medical Center that are applicable to their conduct.

G. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

H. Execute work so as to interfere as little as possible with normal functioning of the VA Medical

Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to the VA Medical Center areas required to remain in operation.

3. Where access by the VA Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

GENERAL REQUIREMENTS 01 00 00 - 06

I. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the

Contractor.

J. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

a. Normal working hours for this contract will be from 8:00 AM – 4:30 PM (local time), Monday through Friday, except for weekends and established Federal Holidays.

b. Performing on-site work outside of normal working hours will require approval from the

Contracting Officer (CO) and the Contracting Officer’s Representative (COR). Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR 21 calendar days in advance of the proposed date of starting work in ICRA Class I and II work areas, and 28 calendar days in advance of the proposed date of starting work in ICRA Class III and IV work areas, as well as critical infrastructure buildings (i.e. Boiler Plant / Chiller Plant). Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to the VA Medical Center Director, COR, and Contractor.

GENERAL REQUIREMENTS 01 00 00 - 07

3. A/E recommended phasing plans, put together with input from the VA COR and Infection

Controls personnel, takes into consideration the VA Medical Center complexity and broad scope of buildings impacted by TR/TE renovations and re-cabling efforts. Phasing of TR/TE renovations and individual room Cat 6A re-cabling will be heavily influenced by the ICRA precautions required by the VA, informed by the associated patient risk levels. Critical patient care areas should be considered distinct from non-patient care areas (engineering, admin space, etc.), and the Contractor shall regularly consult with the VA on patient care area phasing plans before commencing construction work and upon completion.

4. The following tables outline healthcare and non-healthcare spaces within the scope of this project, and the recommended phasing constraints:

HEALTHCARE BUILDING

Location ICRA Class Construction Hours – TR/TEs Construction Hours – Cat 6a Re-cabling

Building 1

II

*Normal business hours, pending VA approval of Contractor work plan submitted at least 21 calendar days in advance of start of work.

*Contractor shall present work plan to the VA COR 21 calendar days in advance of work for VA pre-approval, showing max rooms that may be re-cabled in a phasing area during 1 full work shift.

III

*Normal business hours, pending VA approval of Contractor work plan submitted at least 28 calendar days in advance of start of work.

*Contractor shall present work plan at least 28 calendar days in advance of work for VA pre-approval; (3) rooms maximum may be worked on at one time to allow for equipment movement and coordination with VA staff and services. Any variations in room maximum will be on a case-by-case basis and must be approved by the VA COR in advance of construction activities.

IV

*Normal business hours, pending VA approval of Contractor work plan submitted at least 28 calendar days in advance of start of work.

*Contractor shall present work plan at least 28 calendar days in advance of work for VA pre-approval; (1) room maximum may be worked on at one time to allow for equipment movement and coordination with VA staff and services. Any variations in room maximum will be on a case-by-case

GENERAL REQUIREMENTS 01 00 00 - 08

basis and must be approved by the VA COR in advance of construction activities.

5. Contractor shall provide work plans to the VA for final approval. Contractor shall consider the following constraints in phasing:

a. Contractor shall not commence any planned phase of work without authorization from the COR and an approved outage schedule. It is the Contractor’s responsibility to review any appropriate VA phasing forms with VA COR during Pre-Construction Meeting. All subsequent planned outages will need to be documented and approved by the COR prior to the regulated outages.

b. The Government may halt work in patient care areas at no cost to the Government if work impedes patient care.

c. The Contractor will coordinate with the VA for movement of furniture from new TR/TE spaces prior to work starting.

d. Any TR/TE work that causes excessive noise and/or vibrations shall be coordinated with the VA COR and shall occur only during nights and/or weekends as approved by the VA

COR.

e. Contractor is responsible for ensuring continuous network connectivity for patient care spaces. Outages shall not exceed 1 work shift. Cable pulling shall only occur during non-working, non-peak hours, and scheduled weekends as approved by the VA COR, or as noted otherwise in the above tables.

f. Contractor is responsible for providing a work plan to the VA for approval regarding separation of existing cables and new, and all anticipated demo work.

g. Contractor to ensure that all work in the current phase is completed and approved by the VA COR before proceeding to another phase of work.

6. Taking the above into consideration, the A/E recommends the following phased sequence of construction activities. While it is ultimately up to the General Contractor to determine the construction schedule, the below offers a suggested sequence of construction activities:

PROPOSED PHASING SEQUENCE

GENERAL REQUIREMENTS 01 00 00 - 09

This section is a general overview of the sequence of construction activities pertaining to the new ductbank & fiber distribution, MCR renovation, and TR construction and renovation activities. For specific details pertaining to the individual project components, please see the indicated references directly below the general overview:

Phase 1 Overview – Campus Infrastructure

*Same-numbered items can be worked on concurrently*

1a. Civil duct-banks system installed.

1b. Build new TRs at new locations and/or expand existing TRs as required.

2a. Pull new A/B fiber backbone cables to existing, expanded, or new TRs.

2b. Install any ties from old TRs to new TRs. *Please see Reference #2 below.

2c. For new MCR construction, once commissioning is complete and approved by the VA, Contractor to install fiber ties from old MCR to new MCR. Once fiber is tested and certified, Contractor to notify

VA COR to commence with equipment migration from old MCR to new MCR. VA Requires 90-days minimum for equipment migrations. Contractor responsible for schedule coordination of this activity with the site.

2d. Unbolt existing racks and shift locations for installation of new grounded racks in existing/expanded

TRs. *Please see Reference #3 below.

2e. Install new racks, cable managers and pathways in new (and expanded/existing) TRs.

2f. Re-organize Data Center and install new cabinets.

2g. In TRs, terminate new fiber in new fiber housings in new racks.

2h. In Data Center, terminate new fiber in new fiber housings in new fiber distribution cabinets. (In cases where MCR isn’t available, identify a temporary location to coil/terminate fiber backbone in.)

3. Test new fiber and get approval (commissioning) from VA COR.

Phase 2 Overview – WAO Replacement and TR Cutovers

(VA to provide ONLY [10] new switches to OIT for TRs to maintaining existing switches in existing racks)

4. VA to activate OR relocate Core B switch to new Core B cabinet in new MCR. Patch new fiber backbones to new or relocated core switch to each TR to be fed. VA to connect B-side Core Router to A-side Core Router via 288-strand Umbilical cable between existing MCR and new MCR.

5a. Activate fiber in new TRs through B-side:

GENERAL REQUIREMENTS 01 00 00 - 10

• Existing / Expanded TRs – Provide new fiber jumpers from new fiber panels back to existing switch(es), disconnect existing fiber

• New TR/TEs – Provide temporary fiber back feed to existing TR/TE location and patch into existing switch(es), disconnect existing fiber.

5b. Submit cutover plan for VA approval and schedule the installation of new Cat 6a cables on a room/department by room/department basis from new TR racks to existing device WAOs and cutover outlets the same night. *Please see References #4, #5, #6, and #7 below.

• Identify any buildings requiring after hours work for VA support (see above tables).

• See phasing drawing sheets and above phasing parameters for specific building and phasing area work requirements.

• End users, services lines, COR, and OIT are notified and ready.

• See Reference #4 – Work Area Outlet (WAO) Cutover Steps for detailed action plan.

6. VA to relocate existing Core A switch to new Core A cabinet in new MCR. Patch new fiber backbones to new or relocated core switch to each TR to be fed.

7. Activate fiber in new TRs through the A-side.

8. Relocate any fiber…

This is the start of the file's text. The full file is on GovTribe.