S02-657-23-104JC-Prep For CT A259-BID SE-Specs_03092026.pdf

PDF 6 MB Posted

Attached to
Z2DA--657-23-104JC, Prepare Site for New Computed Tomography Unit, Room A259
Solicitation number
36C25526R0098
Issued by

About this file

This document is a comprehensive 100% contract bid specification for the preparation of an existing space to accommodate a new Computed Tomography (CT) unit in Room A259 at the Veterans Affairs Saint Louis Health Care System. The project encompasses selective demolition, installation of a dedicated HVAC system, abatement of asbestos-containing materials, electrical modifications, plumbing alterations, fire protection modifications, and structural work as needed. The scope includes preparation of approximately 3 radiators assumed to contain asbestos insulation and backing material, with a contract performance period of 210 calendar days after notice to proceed.

The specifications integrate multiple construction divisions covering general requirements, site safety and infection control, asbestos abatement, HVAC systems installation and commissioning, structural requirements, and mechanical/electrical systems. Key technical sections address HVAC common work results, motor requirements, noise and vibration control, testing and balancing, insulation, commissioning, and direct-digital control systems. The document mandates compliance with federal standards including OSHA regulations, EPA requirements for asbestos handling and disposal, NFPA codes for fire safety, and VA-specific design standards. Critical requirements include a full-time Site Safety and Health Officer with specific certifications, infection control risk assessments classified as Class IV, preparation of detailed activity hazard analyses, comprehensive decontamination procedures, and final air clearance testing by an independent industrial hygienist. The contractor must coordinate with VA operations to maintain facility functionality during construction, manage hazardous materials according to EPA protocols, and provide extensive documentation including as-built drawings, warranty management plans, and operation and maintenance manuals upon project completion.

View the file

Other files

File Type Posted
36C25526R0098 0004.docx DOCX document
S06-657-23-104JC-VAMC CT Shielding Design 05_03_26.pdf PDF
36C25526R0098 0003.docx DOCX document
S06-657-23-104JC-New CT - Naeotom Alpha typical Final 04242026.pdf PDF
36C25526R0098 0002.docx DOCX document
36C25526R0098 0001.docx DOCX document
S06-657-23-104JC Pre-Bid Sign In 04102026.pdf PDF
S02_657-23-104JC -BID SET - Drawings_03092026.pdf PDF
36C25526R0098_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

100% CONTRACT DOCUMENTS FOR BIDDING

SPECIFICATIONS

PREPARE SITE FOR NEW CT

Building 1, Room A259

AT

THE VETERANS AFFAIRS

SAINT LOUIS HEALTH CARE SYSTEM

(VASTLHCS)

915 GRAND BLVD, ST LOUIS, MO 63106

PREPARED FOR

DEPARTMENT OF VETERANS AFFAIRS

06 MARCH 2026

Project No. 657-23-104JC

PREPARED BY

THINKFORM DESIGN ARCHITECT LLC

38 EAST BROAD STREET, SUITE 3, HOPEWELL, NEW JERSEY 08525

PH: 855.821.0274 ThinkFormArchitects.com

ABOVE GROUP INC.

400 EAST PRATT STREET, 8TH FLOOR, BALTIMORE, MD 21202

PH: 443.788.4200 AboveGroupInc.com

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, SUITE 4100, STONEHAM, MA 02180

PH: 781.275.6050 I Mabbett.com

06-01-24 Prepare Site for New CT, Rm A259 100% Contract Docs for Bidding Project No. 657-23-104JC 06 March 2026

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24 01 33 23 Shop Drawings, Product Data, and Samples 11-23 01 35 26 Safety Requirements for Major Projects 05-24 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17

DIVISION 02 – EXISTING CONDITIONS

02 82 11 Traditional Asbestos Abatement 01-21 02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 01-21 04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17 06 20 00 Finish Carpentry 01-21

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 40 00 Roofing and Siding Panels 01-21 07 60 00 Flashing and Sheet Metal 01-21 07 84 00 Firestopping 01-21

Project No. 657-23-104JC 06 March 2026

00 01 10-2

SECTION NO DIVISION AND SECTION TITLES DATE

07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 32 13 ICU Sliding Glass Doors 01-21 08 71 00 Door Hardware 03-24 08 71 13.11 Low Energy Power Assist Door Operators 01-21 08 80 00 Glazing 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 16 Resilient Sheet Flooring 06-22 09 65 19 Resilient Tile Flooring 05-18 09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21 10 26 00 Wall and Door Protection 01-21

DIVISION 11 – EQUIPMENT (RESERVED)

DIVISION 12 – FURNISHINGS

12 32 00 Manufactured Wood Casework 01-21

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements 13 49 00 Radiation Protection 01-21

DIVISION 14– CONVEYING EQUIPEMENT (RESERVED)

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19

Project No. 657-23-104JC 06 March 2026

00 01 10-3

SECTION NO DIVISION AND SECTION TITLES DATE

22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 40 00 Plumbing Fixtures 05-24 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 05-23 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 05-23

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 03-23

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

03-23

23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 09 23 Direct-Digital Control System for HVAC 03-23 23 21 13 Hydronic Piping 03-23 23 23 00 Refrigerant Piping 03-24 23 31 00 HVAC Ducts and Casings 03-23 23 34 00 HVAC Fans 03-23 23 36 00 Air Terminal Units 03-23 23 37 00 Air Outlets and Inlets 03-23 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-23 23 81 00 Decentralized Unitary HVAC Equipment 03-24 23 82 16 Air Coils 03-24

DIVISION 25 – INTEGRATED AUTOMATION (RESERVED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 05 36.26 Wireways for Radiology Equipment 11-22 26 05 41 Underground Electrical Construction 11-22 26 08 00 Commissioning of Electrical Systems 11-22 26 09 23 Lighting Controls 11-22 26 22 00 Low-Voltage Transformers 11-22 26 24 16 Panelboards 11-22 26 27 26 Wiring Devices 11-22 26 29 21 Enclosed Switches and Circuit Breakers 11-22 26 43 13 Surge Protective Devices 11-22 26 51 00 Interior Lighting 03-24

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

Project No. 657-23-104JC 06 March 2026

00 01 10-4

SECTION NO DIVISION AND SECTION TITLES DATE

27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 08 00 Commissioning of Communications Systems 11-16 27 10 00 Control, Communication and Signal Wiring 06-15 27 15 00 Communications Structured Cabling 27 52 23 Nurse Call and Code Blue Systems 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 13 Conductors and Cables for Electronic Safety and Security 28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 28 31 00 Fire Detection and Alarm

DIVISION 31 – EARTHWORK (RESERVED)

DIVISION 32 – EXTERIOR IMPROVEMENTS (RESERVED)

DIVISION 33 – UTILITIES (RESERVED)

DIVISION 34 – TRANSPORTATION (RESERVED)

DIVISION 48 – Electrical Power Generation (RESERVED)

05-01-20

Project No. 657-23-104JC 06 March 2026

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

G001 COVER SHEET

G002 LIFESAFETY, ABBREVIATIONS & CODE NOTES

G003 INFECTION CONTROL RISK ASSESSMENT

G004 TYPICAL ICRA CONSTRUCTION DETAILS

G005 CONSTRUCTION SUB-SYSTEMS AND PARTITION TYPES

ABATEMENT

HA101 SECOND FLOOR ABATEMENT PLAN

STRUCTURAL

S001 GENERAL NOTES AND ABBREVIATIONS

SS101 FIRST FLOOR FOUNDATION PLAN

SS102 SECOND AND THIRD FLOOR FRAMING PLANS

S301 DETAILS AND SECTIONS

ARCHITECTURAL

AD101 FIRST FLOOR REFLECTED CEILING DEMOLITION PLAN

AD102 SECOND FLOOR DEMOLITION PLAN

A101 FIRST FLOOR PLAN

A102 SECOND FLOOR PLAN

A111 FIRST & SECOND FLOOR REFLECTED CEILING PLANS

A201 EXTERIOR ELEVATIONS

A401 DOOR LEGEND, SCHEDULE, & DETAILS

A402 INTERIOR ELEVATIONS

A501 DETAILS & CASEWORK DETAILS

A508 SEISMIC RCP DETAILS

A600 SECOND FLOOR FIN PLAN, FINISH LEGEND, NOTES & DETAILS

A605 SECOND FLOOR EQUIPMENT SCHEDULE

A606 SECOND FLOOR EQIPMENT PLAN, ELEV / SIGNAGE

A610 RIGGING PATH & ELEVATIONS

Project No. 657-23-104JC 06 March 2026

00 01 15 - 2

FIRE PROTECTION

FP001 FIRE PROTECTION LEGENDS & SYMBOLS

FP101 SECOND FLOOR FIRE PROTECTION PLAN – ROOM A259

PLUMBING

P001 PLUMBING NOTES, LEGEND & SYMBOLS

PD101 FIRST AND SECOND FLOOR PLAN – DWV PIPING DEMOLITION

PS101 FIRST AND SECOND FLOOR PLAN DWV PIPING NEW WORK

PP101 SECOND FLOOR PLAN – PRESSURE PIPING – ROOM A259

PG101 SECOND FLOOR PLAN – MED GAS- ROOM A259

P501 PLUMBING DETAILS

P801 PLUMBING SCHEDULES

MECHANICAL

M001 MECHANICAL NOTES, LEGENDS & SYMBOLS

MD100 SECOND FLOOR PLAN – MECHANICAL – DEMOLITION

MH100 FIRST FLOOR EQUIPMENT YARD – MECHANICAL

MH101 SECOND FLOOR PLAN MECHANICAL – ROOM A259

M301 MECHANICAL SECTIONS

M501 MECHANICAL DETAILS

M701 MECHANICAL CONTROLS

M801 MECHANICAL SCHEDULES

ELECTRICAL

E001 ELECTRICAL LEGEND & SYMBOLS

E002 ELECTRICAL NOTES

ED101 FLOOR PLAN – LIGHTING - DEMOLITION

ED102 FLOOR PLAN – ELECTRICAL EQUIPMENT – DEMOLITION

EL101 FLOOR PLAN – LIGHTING – NEW WORK

EL102 FLOOR PLAN - LIGHTING - PHOTOMETRICS

EP101 FLOOR PLAN – ELECTRICAL EQUIPMENT – NEW WORK

EP102 FLOOR PLAN – ELECTRICAL EQUIPMENT – NEW WORK

E501 ELECTRICAL DETAILS

E502 ELECTRICAL CT DETAILS

E601 ELECTRICAL DIAGRAMS

E801 ELECTRICAL SCHEDULES

Project No. 657-23-104JC 06 March 2026

00 01 15 - 3

FIRE ALARMS

FA001 FIRE ALARM LEGENDS & SYMBOLS

FA101 FLOOR PLAN - FIRE ALARM - NEW WORK

FA-501 FIRE ALARM DETAILS

TELECOMMUNICATIONS

T-001 TECHNOLOGY LEGEND, ABBREVIATIONS, & GENERAL NOTES

TD101 FLOOR PLAN - TECHNOLOGY - DEMOLITION

TN101 FLOOR PLAN – DATA/ACCESS CONTROL/CCTV – NEW WORK

T-501 TECHNOLOGY – DETAILS

- - - E N D - - -

11-01-21

Project No. 657-23-104JC 06 March 2026

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for site prep for new CT in Room A259 and associated spaces as required by drawings and specifications.

B. A Site visit will occur at the Pre-Bid Meeting. Only one site visit will be scheduled prior to the bid date.

Attendance is highly recommended.

C. Offices of ThinkForm Architects, as Architect-Engineers, will render certain technical services during construction.

Such services shall be considered as advisory to the

Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by the contractor, the

Contractor shall notify the COR and be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

Provide the COR with all testing reports.

Project No. 657-23-104JC 06 March 2026

01 00 00 -2

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, BASE BID: Work includes selective demolition and renovations for preparations of a new CT in Room A259.

Work will include necessary abatement, new shielding requirements, architectural changes, demolition of existing mechanical with installation of new mechanical, fire protection modifications, plumbing alterations, electrical alterations and structural as needed for the new CT and exterior equipment pads. Period of performance is 210 calendar days after the notice to proceed.

1.4 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge & documentation of flu shot and attestation of COVID-19 vaccination. They may also be subject to inspection of their personal effects when entering or leaving the project site.

a. All contractor’s and subcontractor’s employees will be required to wear one of two badges on VA property.

Project No. 657-23-104JC 06 March 2026

01 00 00 -3

Consult the COR for appropriate type and the procedure for obtaining a badge.

1) PIV-I card issued by the VA HR department.

2) Visitor Badge issued by the VA. This badge is valid for 15 site visits in a calendar year and provides no access to restricted areas, i.e. mag-locked doors.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer’s

Representative so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The

General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation.

See Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

Project No. 657-23-104JC 06 March 2026

01 00 00 -4

1. Before starting any work, the General Contractor/Sub

Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of

“sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

Project No. 657-23-104JC 06 March 2026

01 00 00 -5

b) “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.

Access shall be restricted to picking up and dropping off materials and supplies.

2. No permits shall be issued for General Contractor and its employees for parking in designated areas only.

Contractor to coordinate with VA Medical Center Facility

Manager.

1.5 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The

Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the

Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

Project No. 657-23-104JC 06 March 2026

01 00 00 -6

C. The Contractor shall, under regulations prescribed by the

Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. No areas outside the defined construction boundaries will be available to the contractor for staging, storage, preparation, etc.

1. Do not store materials and equipment in other than assigned areas. The COR may request items to be relocated at any point.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by

Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of

Contractor's materials and equipment will be permitted subject to fire and safety requirements.

E. Contractor shall be responsible for moving and storage of all furniture related to the project, including but not limited to furniture, equipment, signage, and artwork. All items become the responsibility of the contractor to store

Project No. 657-23-104JC 06 March 2026

01 00 00 -7 within the construction area or at an offsite location at the contractor’s expense. All items must be returned in the original condition and at the approval of the COR, any damaged items will be replaced at the expense of the contractor. Contractor shall provide written notice to the

COR ten calendar days prior to moving furniture.

F. Workers are subject to rules of Medical Center applicable to their conduct.

G. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

H. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by

Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

Project No. 657-23-104JC 06 March 2026

01 00 00 -8

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of

Contractor's materials and equipment will be permitted subject to fire and safety requirements.

I. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

J. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the

COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR three weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.

Arrange such phasing dates to ensure accomplishment of

Project No. 657-23-104JC 06 March 2026

01 00 00 -9 this work in successive phases mutually agreeable to COR and Contractor, as follows:

Phase I: General abatement, demolition and construction as required for the project. Refer to all documents for full scope.

Phase II: Work required for rigging new CT into position. Refer to rigging requirements as outlined within the documents.

K. Building No. 1 will be occupied during performance of work;

but immediate areas of alterations will be vacated.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by

Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

L. When a building and/or construction site is turned over to

Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

Project No. 657-23-104JC 06 March 2026

01 00 00 -10

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or

Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for

Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems

(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center

Director’s prior knowledge and written approval. Refer to electrical specifications for additional requirements.

Project No. 657-23-104JC 06 March 2026

01 00 00 -11

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 21 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical

Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;

so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction

Project No. 657-23-104JC 06 March 2026

01 00 00 -12 materials, debris and standing construction equipment and vehicles.

P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.6 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by

Project No. 657-23-104JC 06 March 2026

01 00 00 -13

Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING

SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-

4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.

They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

Project No. 657-23-104JC 06 March 2026

01 00 00 -14

1.7 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the

Government are noted on drawings or in specifications as items to be stored. Items that remain property of the

Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the

Contractor and be removed by Contractor from Medical

Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.

When rooms and spaces are vacated by the Department of

Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the

Government in advance of work to avoid interfering with

Contractor's operation.

4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl

(PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental

Protection Agency (EPA) and the Department of

Transportation (DOT) as outlined in Code of Federal

Regulation (CFR), Titled 40 and 49 respectively. The

Project No. 657-23-104JC 06 March 2026

01 00 00 -15

EPA's Toxic Substance Control Act (TSCA) Compliance

Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform Hazardous Waste

Manifest (EPA Form 8700-22), along with the Uniform

Hazardous Waste Manifest Continuation Sheet (EPA Form

8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the

Manifest to the Medical Center's Chief.

a) Copies of the following listed CFR titles may be obtained from the Government Printing Office:

40 CFR 261 ....Identification and Listing of Hazardous

Waste

40 CFR 262 ....Standards Applicable to Generators of

Hazardous Waste

40 CFR 263 ....Standards Applicable to Transporters of

Hazardous Waste

40 CFR 761 ....PCB Manufacturing, Processing, Distribution in Commerce, and use

Prohibitions

49 CFR 172 ....Hazardous Material tables and Hazardous

Material Communications Regulations

49 CFR 173 ....Shippers - General Requirements for

Shipments and Packaging

49 CRR 173 ....Subpart A General

49 CFR 173 ....Subpart B Preparation of Hazardous

Material for Transportation

49 CFR 173 ....Subpart J Other Regulated Material;

Definitions and Preparation

TSCA ..........Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7

Project No. 657-23-104JC 06 March 2026

01 00 00 -16

1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting

Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL

CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, Project No. 657-23-104JC 06 March 2026

01 00 00 -17

"Alterations", "Restoration", and "Operations and Storage

Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and

Responsibilities," which is included in General Conditions.

A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the

(appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the

Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

Project No. 657-23-104JC 06 March 2026

01 00 00 -18

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by

Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in

Project No. 657-23-104JC 06 March 2026

01 00 00 -19 accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.12 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21

Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the

Project No. 657-23-104JC 06 March 2026

01 00 00 -20 construction phase must be submitted to the Contracting

Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the

Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the

Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of

Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

Project No. 657-23-104JC 06 March 2026

01 00 00 -21

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and

Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment

Bonds must remain effective throughout the construction period

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work

Project No. 657-23-104JC 06 March 2026

01 00 00 -22 performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the

Government at the contractor’s expenses, the Contracting

Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the

Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the

Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty

Project No. 657-23-104JC 06 March 2026

01 00 00 -23 work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the

Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service

Requirements:

E. Following oral or written notification by the Contracting

Officer, the Contractor shall respond to construction warranty service requirements in accordance with the

“Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within

4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within

8 hours, initiate work within 24 hours and work continuously to completion or relief.

Project No. 657-23-104JC 06 March 2026

01 00 00 -24

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

1) Fire suppression systems.

2) Fire alarm system(s).

b) Code 1-Air Conditioning Systems

1) Air conditioning leak in part of the building, if causing damage.

2) Air conditioning system not cooling properly.

c) Code 1 Doors

1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

1) Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical

1) Power failure (entire area or any building operational after 1600 hours).

2) Security lights.

3) Smoke detectors.

f) Code 2-Electrical

1) Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).

g) Code 1-Gas

1) Leaks and pipeline breaks.

h) Code 1-Heat

Project No. 657-23-104JC 06 March 2026

01 00 00 -25

1) Power failure affecting heat.

i) Code 1-Plumbing

1) Hot water heater failure.

2) Leaking water supply pipes

j) Code 2-Plumbing

1) Flush valves not operating properly

2) Fixture drain, supply line or any water pipe leaking.

3) Toilet leaking at base.

k) Code 3- Plumbing

1) Leaky faucets.

l) Code 3-Interior

1) Floors damaged.

2) Paint chipping or peeling.

3) Casework damaged.

m) Code 1-Roof Leaks

1) Damage to property is occurring.

n) Code 2-Water (Exterior)

1) No water to facility.

o) Code 2-Water (Hot)

1) No hot water in portion of building listed.

p) Code 3

1) All work not listed above.

F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating.

Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted

Project No. 657-23-104JC 06 March 2026

01 00 00 -26 for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

Telephone number

Warranty response time priority code

1.13 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on

Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

Project No. 657-23-104JC 06 March 2026

01 00 00 -27

1. Permission to use each unit or system must be given by

COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

Project No. 657-23-104JC 06 March 2026

01 00 00 -28

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the

Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the

Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical…