S02_512-23-901 Exterior Granite Repair_Speciifcations.pdf
PDF 20 MB Posted
- Attached to
- Z1DA--512-23-901 Repair Exterior Granite
- Solicitation number
- 36C24524R0037
About this file
This document is the Specifications for the Exterior Granite Repair (Project #512-23-901) under Solicitation 36C24524R0037 issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 5.
The Specifications detail the required work for repairing the exterior granite at a facility in Baltimore. Key elements include repair and replacement of deteriorated granite panels, sealants, caulking, and related site work. The work is to be completed within 180 calendar days of the contract award. Pricing is to be submitted on a fixed-price basis. The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB). The anticipated award date is September 30, 2023.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LRS Federal Exterior Granite Repair Design
Glenn Burnie, MD Baltimore Veterans Affairs Medical Center
10 N Greene Street
Baltimore, MD
100% Construction Documents – 10/25/2023
00 01 01 - 1
SECTION 00 01 01
PROJECT TITLE PAGE
PROJECT MANUAL
FOR
EXTERIOR GRANITE REPAIR DESIGN
OFFICE OF CONSTRUCTION AND FACILITIES MANAGEMENT
ARCHITECT'S PROJECT NUMBER: 512-23-901.
U.S. DEPARTMENT OF VETERANS AFFAIRS
BALTIMORE VETERANS AFFAIRS MEDICAL CENTER
10 N GREENE STREET
BALTIMORE, MARYLAND, 21201
DATE: 9/21/2023
PREPARED BY: EWINGCOLE
- - - END - - -
12/15/2023
00 01 02 - 1
SECTION 00 01 02
PROJECT INFORMATION
PART 1 GENERAL
1.1 PROJECT IDENTIFICATION
A. Project Name: Baltimore VA Medical Center, located at: 10 N Greene
Street, Baltimore, Maryland, 21201.
B. Architect's Project Number: 512-23-901.
C. The Owner, hereinafter referred to as Owner: U.S. Department of
Veterans Affairs.
1.2 PROJECT DESCRIPTION
A. Summary Project Description: Develop complete drawings, specifications, cost estimates, project phasing site visits and construction administration, associated with repairing the exterior granite facade at Baltimore Veterans Affairs Medical Center, including correcting the building envelope, upgrading finishes, correcting architectural systems, and modernizing the facility.
1.3 PROJECT CONSULTANTS
A. The Architect, hereinafter referred to as Architect: EwingCole.
1. Address: 810 Light Street.
2. City, State, Zip: Baltimore, Maryland, 21230.
3. Phone/Fax: (410) 837-5040.
B. The Envelope Consultant, hereinafter referred to as Envelope
Consultant: [Wiss Janey Elstner].
1. Address: 2941 Fairview Park Drive, Suite 300.
2. City, State, Zip: Falls Church, Virginia 22042.
3. Phone/Fax: (703) 641-4601.
1.4 PROCUREMENT TIMETABLE
A. The Owner reserves the right to change the schedule or terminate the entire procurement process at any time.
1.5 PROCUREMENT DOCUMENTS
A. Availability of Documents: Complete sets of procurement documents may be obtained electronically.
00 01 02 - 2
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
- - - E N D - - -
00 01 03 - 1
SECTION 00 01 03
PROJECT DIRECTORY
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Identification of project team members and their contact information.
1.2 OWNER:
A. Name: U.S. Department of Veterans Affairs.
1. Veterans Affairs Primary Contact: Myron Lee Draper.
2. Email: myron.draper@va.gov.
B. Primary Contact: All correspondence from the Contractor to the
Architect will be through LRS Federal LLC., unless alternate arrangements are mutually agreed upon at preconstruction meeting.
1. Title: President.
2. Name: Thomas E. Scott, PMP,CCM.
3. Email: Tscott@LRSfederal.com.
1.3 CONSULTANTS:
A. Architect: Design Professional of Record. All correspondence from the Contractor regarding construction documents authored by
Architect's consultants will be through this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.
1. Company Name: EwingCole.
a. Address: 810 Light Street.
b. City, State, Zip: Baltimore, Maryland, 21230.
c. Phone/Fax: (410) 837-5040.
2. Primary Contact:
a. Title: Managing Principal.
b. Name: David Gaudreau.
c. Email: dgaudreau@ewingcole.com.
B. Structural Consultant:
1. Company: Wiss Janey Elstner.
a. Address: 2941 Fairview Park Drive, Suite 300.
b. City, State, Zip: Falls Church, Virginia 22042.
2. Primary Contact:
a. Title: Senior Principal.
b. Name: Matthew C. Farmer, PE.
00 01 03 - 2
c. Email: mfarmer@wje.com.
C. Electrical Engineering Consultant:
1. Company Name: LRS Federal.
a. Address Line 1: 565 Benfield Blvd..
b. City: Severina Park.
c. State: Maryland.
d. Zip Code: 21146.
2. Primary Contact:
a. Title: Senior Electrical Engineer.
b. Name: Jay Malhorta.
c. Email: jmalhorta@lrsfederal.com.
D. Sustainability Consultant:
1. Company Name: Lorax.
a. Address Line 1: 16 W. Hamilton Street.
b. City: Baltimore.
c. State: Maryland.
d. Zip Code: 21201.
2. Primary Contact:
a. Title: Principal.
b. Name: Katie Fink.
c. Email: katie@loraxllc.com.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
00 01 07 - 1
SECTION 00 01 07
SEALS AND SIGNATURES PAGE
OWNER’S AGENT
Lee Draper
Myron Lee Draper, P.E.
Department of Veterans Affairs
VAMHCS - Baltimore
10 N. Greene St.
Baltimore, MD 21201
ARCHITECT OF RECORD
EwingCole
810 Light Street
Baltimore, Maryland, 21230
__________________________________ 9/21/2023
Architect of Record Signature Date
STRUCTURAL ENGINEER OF RECORD
Wiss Janney, Elstner Associates, Inc.
2941 Fairview Park Drive
Falls Church, Virginia 22042
Structural Engineer of Record Signature Date
ELECTRICAL ENGINEER OF RECORD
Jay Malhotra
LRS Federal
565 Benfield Road | Suite 400
Severna Park, MD 21146
Electrical Engineer of Record Signature Date
100% Construction Documents – 12/15/2023
00 01 10 - 1
SECTION 00 01 10
TABLE OF CONTENTS
Division Section Title
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 01 Project Title Page
00 01 02 Project Information
00 01 03 Project Directory
00 01 07 Seals and Signatures Page
00 01 10 Table of Contents
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements
01 22 00 Unit Prices
Remainder of Division by Others
DIVISION 02 - EXISTING CONDITIONS
02 41 00 Demolition
DIVISION 03 – CONCRETE
03 01 30 Maintenance of Cast in Place Concrete
03 10 00 Concrete Forming and Accessories WJE
03 20 00 Concrete Reinforcing WJE
03 30 00 Cast-In-Place Concrete WJE
DIVISION 04 – MASONRY
04 01 00 Maintenance Of Masonry
04 43 13 Calcium Silicate Masonry Units
04 43 16 Stone Fabrications
DIVISION 05 – METALS
05 50 00 Metal Fabrications
05 75 00 Decorative Formed Metal (Column Covers)
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 14 16 Cold Fluid-Applied Waterproofing WJE
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable
07 42 13 Metal Composite Material Wall Panels
07 60 00 Flashing and Sheet Metal
07 92 00 Joint Sealants WJE
07 95 13 Expansion Joint Cover Assemblies
DIVISION 08 – OPENINGS
08 41 13 Aluminum-Framed Entrances and Storefronts
08 42 33 Revolving Door Entrances
08 71 00 Door Hardware By Others
08 80 00 Glazing
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing
100% Construction Documents – 12/15/2023
00 01 10 - 2
09 26 00 Veneer Plastering (Repair)
09 29 00 Gypsum Board
09 54 23 Linear Metal Ceilings
09 68 13 Tile Carpeting
09 91 00 Painting
DIVISION 10 – SPECIALTIES – NOT USED
DIVISION 11 – EQUIPMENT – NOT USED
DIVISION 12 – FURNISHINGS – NOT USED
DIVISION 13 - SPECIAL CONSTRUCTION – NOT USED
DIVISION 14 - CONVEYING EQUIPMENT – NOT USED
DIVISION 21 - FIRE SUPPRESSION – NOT USED
DIVISION 22 – PLUMBING – NOT USED
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) – NOT USED
DIVISION 26 – ELECTRICAL
26 05 11 – Requirements for Electrical Installations
26 05 19 – Low Voltage Electrical Power Conductors and Cables
26 05 26 – Grounding and Bonding for Electrical Systems
26 05 33 – Raceway and Boxes for Electrical Systems
26 08 00 – Commissioning of Electrical Systems
26 09 23 – Lighting Controls
26 27 26 – Wiring Devices
26 56 00 – Exterior Lighting
DIVISION 27 – COMMUNICATIONS – NOT USED
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY – NOT USED
DIVISION 31 – EARTHWORK – NOT USED
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 23 Cement And Concrete For Exterior Improvements
DIVISION 33 – UTILITIES – NOT USED
DIVISION 34 – 50 – RESERVED/NOT USED
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 - GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of components of existing structures, and furnish labor and materials and perform work for replacing the exterior granite facade at Baltimore Veterans Affairs Medical Center including correcting the building envelope, upgrading finishes, correcting architectural systems, and modernizing the facility as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of LRS Federal, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
01 00 00 -2
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, alterations, walks necessary removal of existing components and construction and certain other items.
1. Project scope is inclusive of removal of existing granite facade and replacement with a combination of cast stone and composite metal panels. Replacement of main lobby doors is included. Listed below are deduct alternates that are included in the base bid.
B. Deduct Alternates:
1. Soffit Repair, Refinish and Accent.
2. Exterior Lighting Replacement.
3. Curtain Wall Mullion Cap Refinishing.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
01 00 00 -3
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Guards:
1. The General Contractor shall provide unarmed guards at the project site if determined necessary by the VA.
2. The Contractor shall provide the guards and VA police with communication devices as directed.
3. The general Contractor shall install equipment for recording guard rounds to ensure systematic checking of the premises.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall coordinate the install of permanent cores with the VA and their Locksmith.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access
01 00 00 -4 to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. No permits shall be issued for parking. General Contractor is responsible for their own parking arrangements.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The
01 00 00 -5 temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be determined by the COR.
E. Workers are subject to rules of Medical Center Applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work
01 00 00 -6 days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Building will be occupied during performance of work; but immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
01 00 00 -7
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
01 00 00 -8
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
01 00 00 -9
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, soffits, mechanical and electrical work, paving, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
01 00 00 -10
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers
01 00 00 -11 within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers or suppliers.
e. Names, addresses and phone numbers of sources of spare parts.
f. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
g. Starting point and duration of warranty period.
h. Summary of maintenance procedures required to continue the warranty in force.
i. Cross-reference to specific pertinent Operation and Maintenance manuals.
j. Organizations, names and phone numbers of persons to call for warranty service.
k. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
01 00 00 -12
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive
01 00 00 -13 to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
E. Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a) Code 1-Life Safety Systems
Fire suppression systems.
Fire alarm system(s).
b) Code 1 Doors
Overhead doors not operational, causing a security, fire or safety problem.
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
c) Code 1-Electrical
Power failure (entire area or any building operational after
1600 hours).
01 00 00 -14
Security lights.
Smoke detectors.
d) Code 2-Electrical
Power failure (no power to a room or part of building).
Receptacle and lights not operational (in a room or part of building).
e) Code 3-Electrical
Exterior lights not operational.
f) Code 3- Plumbing
Exterior wall hydrants.
g) Code 3-Interior
Floors damaged.
Paint chipping or peeling.
h) Code 1-Roof Leaks
Damage to property is occurring.
i) Code 2-Water (Exterior)
No water to facility.
j) Code 3
All work not listed above.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
01 00 00 -15
Warranty Tags
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
1.13 TEMPORARY USE OF EXISTING ELEVATORS
A. Contractor will not be allowed the use of existing elevators. Outside type hoist shall be used by Contractor for transporting materials and equipment.
B. Use of existing elevators for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
The COR will ascertain that elevators are in proper condition.
Contractor may use elevators determined best by the COR and only during days and hours authorized by the COR. Personnel for operating elevators will not be provided by the Department of Veterans
Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a) Entrance jambs, heads soffits and threshold plates.
b) Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c) Finish flooring.
3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractors expense.
4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.
01 00 00 -16
5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.
6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.
1.14 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1. *Contractor may have for use of Contractor's workers, such toilet accommodations as may be assigned to Contractor by Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.15 AVAILABILITY AND USE OF UTILITY SERVICES
A. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
B. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
01 00 00 -17
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
1.16 NEW TELEPHONE EQUIPMENT
A. The contractor shall coordinate with the work of installation of telephone equipment by others. This work shall be completed before the building is turned over to VA.
1.17 TESTS
A. As per specification Sections; test for adhesion of installed products for compatibility of the following and as directed.
1. Air barriers.
2. Metal wall panels.
3. Flashing.
4. Backup substrates.
5. Other components in direct contact with each other as part of the granite repair.
1.18 RELOCATED EQUIPMENT AND ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items indicated by symbol "R” or otherwise shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. Contractor shall employ services of an installation engineer, who is an authorized representative of the manufacturer of this equipment to
01 00 00 -18 supervise assembly and installation of existing equipment, required to be removed and reinstalled.
F. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.19 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Provide three 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 1200 mm (four feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign. Brace posts with 50 x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white gloss paint.
Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
D. Detail Drawing of construction sign showing required legend and other characteristics of sign is shown on the drawings.
1.20 SAFETY SIGN
A. Provide a Safety Sign where directed by COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm
(three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR.
D. Drawing details in VA Signage Design Manual, Section 11 Specialty Signs
(found on VA TIL) show required legend and other characteristics of sign and are shown on the drawings.
E. Post the number of accident free days on a daily basis.
01 00 00 -19
1.21 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at selected milestones including electronic indexing, navigation, storage and remote access to the documentation, as per these specifications. The commercial photographer or the subcontractor used for this work shall meet the following qualifications:
1. Demonstrable minimum experience of three (3) years in operation providing documentation and advanced indexing/navigation systems including a representative portfolio of construction projects of similar type, size, duration and complexity as the Project.
2. Demonstrable ability to service projects throughout North America, which shall be demonstrated by a representative portfolio of active projects of similar type, size, duration and complexity as the
Project.
B. Photographic documentation elements:
1. Provide no less than 400 photos and a maximum of 500 photos.
2. Each digital image shall be taken with a professional grade camera with minimum size of 6 megapixels (MP) capable of producing
200x250mm (8 x 10 inch) prints with a minimum of 2272 x 1704 pixels and 400x500mm (16 x 20 inch) prints with a minimum 2592 x 1944 pixels.
3. Indexing and navigation system shall utilize actual AUTOCAD construction drawings, making such drawings interactive on an on-line interface. For all documentation referenced herein, indexing and navigation must be organized by both time (date-stamped) and location throughout the project.
4. Documentation shall combine indexing and navigation system with inspection-grade digital photography designed to capture actual conditions throughout construction and at critical milestones.
Documentation shall be accessible on-line through use of an internet connection. Documentation shall allow for secure multiple-user access, simultaneously, on-line.
5. Before construction, the building pad, adjacent streets, roadways, parkways, driveways, curbs, sidewalks, landscaping, adjacent
01 00 00 -20 utilities and adjacent structures surrounding the building pad and site shall be documented. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings. If site work or pad preparation is extensive, this documentation may be required immediately before construction and at several pre-determined intervals before building work commences.
6. Construction progress for all trades shall be tracked at pre-determined intervals, but not less than once every thirty (30) calendar days (“Progressions”). Progression documentation shall track both the exterior and interior construction of the building.
Exterior Progressions shall track 360 degrees around the site and each building. Interior Progressions shall track interior improvements beginning when stud work commences and continuing until
Project completion.
7. As-built condition of pre-foundation utilities and site utilities shall be documented prior to pouring footers, placing concrete and/or backfilling. This process shall include all underground and in-slab utilities within the building(s) envelope(s) and utility runs in the immediate vicinity of the building(s) envelope(s). This may also include utilities enclosed in slab-on-deck in multi-story buildings. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive site utility plans.
8. As-built conditions of mechanical, electrical, plumbing and all other systems shall be documented post-inspection and pre-insulation, sheet rock or dry wall installation. This process shall include all finished systems located in the walls and ceilings of all buildings at the Project. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings.
9. As-built conditions of exterior skin and elevations shall be documented with an increased concentration of digital photographs as directed by the COR in order to capture pre-determined focal points, such as waterproofing, window flashing, radiused steel work, 01 00 00 -21 architectural or Exterior Insulation and Finish Systems (EIFS) detailing. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive elevations or elevation details.
10. As-built finished conditions of the interior of each building including floors, ceilings and walls shall be documented at certificate of occupancy or equivalent, or just prior to occupancy, or both, as directed by the COR. Overlapping photographic techniques shall be used to ensure maximum coverage. Indexing and navigation accomplished through interactive architectural drawings.
11. Miscellaneous events that occur during any Contractor site visit, or events captured by the Department of Veterans Affairs independently, shall be dated, labeled and inserted into a Section in the navigation structure entitled “Slideshows,” allowing this information to be stored in the same “place” as the formal scope.
12. Customizable project-specific digital photographic documentation of other details or milestones. Indexing and navigation accomplished through interactive architectural plans.
13. Monthly (29 max) exterior progressions (360 degrees around the project) and slideshows (all elevations and building envelope). The slideshows allow for the inclusion of Department of Veterans Affairs pictures, aerial photographs, and timely images which do not fit into any regular monthly photopath.
14. Weekly (21 Max) Site Progressions - Photographic documentation capturing the project at different stages of construction. These progressions shall capture underground utilities, excavation, grading, backfill, landscaping and road construction throughout the duration of the project.
15. Regular (8 max) interior progressions of all walls of the entire project to begin at time of substantial framed or as directed by the
COR through to completion.
16. Detailed Exact-Built of all Slabs for all project slab pours just prior to placing concrete or as directed by the COR.
17. Detailed Interior exact built overlapping photos of the entire building to include documentation of all mechanical, electrical and
01 00 00 -22 plumbing systems in every wall and ceiling, to be conducted after rough-ins are complete, just prior to insulation and or drywall, or as directed by COR.
18. Finished detailed Interior exact built overlapping photos of all walls, ceilings, and floors to be scheduled by COR prior to occupancy.
19. In event a greater or lesser number of images than specified above are required by the COR, adjustment in contract price will be made in accordance with clause entitled "CHANGES" (FAR 52.243-4).
C. Images shall be taken by a commercial photographer and must show distinctly, at as large a scale as possible, all parts of work embraced in the picture.
D. Coordination of photo shoots is accomplished through COR. Contractor shall also attend construction team meetings as necessary. Contractor’s operations team shall provide regular updates regarding the status of the documentation, including photo shoots concluded, the availability of new Progressions or Exact-Builts viewable on-line and anticipated future shoot dates.
E. Contractor shall provide all on-line domain/web hosting, security measures, and redundant server back-up of the documentation.
F. Contractor shall provide technical support related to using the system or service.
G. Upon completion of the project, final copies of the documentation (the
“Permanent Record”) with the indexing and navigation system embedded
(and active) shall be provided in an electronic media format, typically a DVD or external hard-drive. Permanent Record shall have Building
Information Modeling (BIM) interface capabilities. On-line access terminates upon delivery of the Permanent Record.
1.22 FINAL ELEVATION DIGITAL IMAGES
A. A minimum of four (4) images of each elevation shall be taken with a minimum 6 MP camera, by a professional photographer with different settings to allow the COR to select the image to be printed. All images are provided to the RE on a CD.
B. Photographs shall be taken upon completion, including landscaping. They shall be taken on a clear sunny day to obtain sufficient detail…