(210-VI-NEH, May 2001)

Construction Specification 8—Mobilization and Demobilization

1. Scope The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.

2. Equipment and material Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.

Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.

This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.

3. Payment Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.

Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.

4. Items of work and construction details

Mobilization/Demobilization is a single lump sum bid item. The contractor and NRCS representative will identify an onsite staging area prior to mobilization.

NRCS-Minnesota (210-VI-NEH, May 2005) MN2-1

Minnesota Construction Specification 2—Clearing and Grubbing

The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.

2. Protection of existing vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.

Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the engineer.

Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.

Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk. All roots 1-inch or larger in diameter that are cut, broken, or otherwise severed during construction operations shall have the end smoothly cut perpendicular to the root.

Roots exposed during excavation or other operations shall be covered with moist earth or backfilled as soon as possible to prevent the roots from drying out.

3. Marking The limits of the area(s) to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunk about 6 feet above the ground surface.

4. Clearing and grubbing All trees not marked for preservation and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials shall be cleared from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger shall be grubbed out to a depth of at least 2 feet below subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.

5. Disposal All materials cleared and grubbed from the designated areas shall be disposed of at locations shown on the drawings or in a manner specified in section 6. The contractor is responsible for complying with all local rules and regulations and the payment of any and all fees that may result from disposal at locations away from the project site.

6. Measurement and Payment

Method—For items of work for which specific lump sum prices are established in the contract, payment for clearing and grubbing is made at the contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

NRCS-Minnesota (210-VI-NEH, May 2005) MN2-2

8. Construction details

Clearing and grubbing are included in one line item on the bid schedule and shall be paid by the lump sum method.

NRCS-Minnesota (210-VI-NEH, May 2005) MN6-1

Minnesota Construction Specification 6—Seeding, Sprigging, and Mulching

1. Scope The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, inoculants, lime, and other soil amendments; and anchoring mulch in designated areas as specified.

2. Material Seed—All seed shall conform to the current rules and regulations of the state where it is being used and shall be from the latest crop available. It shall meet or exceed the standard for purity and germination listed in section 6.

Seed shall be labeled in accordance with the state laws and the U.S. Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed will be accepted with a test date of more than 9 months before the delivery date to the site.

Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable shall be as defined in the current State laws relating to agricultural seeds. Each type of seed shall be delivered in separate sealed containers and fully tagged unless exception is granted in writing by the engineer.

Inoculants—The inoculant for treating legume seeds shall be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and shall not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, shall be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer shall be used except four times the amount shall be used when seed is applied using a hydraulic seeder. Seed shall be sown within 24 hours of treatment and shall not remain in the hydraulic seeder longer than 4 hours.

Mulch tackifiers—Asphalt emulsion tackifiers shall conform to the requirements of ASTM D 977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Nonasphaltic tackifiers required because of environmental considerations shall be as specified in section 6.

Straw mulch material—Straw mulch shall consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in section 6. The mulch material shall be air-dry, reasonably light in color, and shall not be musty, moldy, caked, or otherwise of low quality.

The use of mulch that contains noxious weeds is not permitted. The contractor shall provide a method satisfactory to the engineer for determining weight of mulch furnished.

Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh, are other mulching materials that may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer's recommendations for methods of application.

3. Seeding mixtures, sod, sprigs, and dates of planting The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting

NRCS-Minnesota (210-VI-NEH, May 2005) MN6-2 shall be as shown on the plans or as specified in section 6.

4. Seedbed preparation and treatment Areas to be treated shall be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed shall be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and moisture conditions, disking or cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, the seedbed shall be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.

If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.

Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations shall be removed or disposed of as specified in section 6.

Seedbed preparation shall be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the engineer.

5. Seeding, sprigging, fertilizing, mulching, and stabilizing All seeding or sprigging operations shall be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application shall be as specified in section 6. Unless otherwise specified, seeding or sprigging shall be accomplished within 2 days after final grading is completed and approved.

The rate, amount, and kind of mulching or mesh shall be as specified in section 6. Mulches shall be applied uniformly to the designated areas. They shall be applied to areas seeded not later than 2 working days after seeding has been performed. Straw mulch material shall be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it shall have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it shall be operated on the contour. Hand methods shall be used where equipment cannot safely operate to perform the work required.

The tackifier shall be applied uniformly over the mulch material at the specified rate, or it shall be injected into the mulch material as it is being applied. Mesh or netting stabilizing materials shall be applied smoothly, but loosely on the designated areas. The edges of these materials shall be buried or securely anchored using spikes or staples as specified in section 6.

The contractor shall maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance shall consist of the repair of areas damaged by water erosion, wind, fire, or other causes. Such areas shall be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas shall be re-fertilized, re-seeded, and re-mulched before the new application of the mesh or netting.

6. Measurement and payment

Method —For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as

NRCS-Minnesota (210-VI-NEH, May 2005) MN6-3 outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.

7. Construction details Seed all disturbed areas. Mulch all the areas as described in the plan

Mulch the areas with clean straw free of weed seed as described in section 5. Seeding, sprigging, mulching, and stabilizing.

The seeding mixture shall consist of the following species, varieties and rates of Pure Live Seed per acre.

Nurse Crop—Seed Oats at rate of 1 bushel per acre.

Common Name Scientific Name Sod/Bunch Lbs Per Acre Side-oats Grama Bouteloua curtipendula Sod 4 Switchgrass Panicum virgatum Sod 4 Western Wheatgrass Pascoptrum smithii Sod 4 Canada Wildrye Eltmus canadensis Bunch 4

Seeding dates Spring May 1st -- Sept 1st Summer N/A Dormant Nov. 1 – Freeze-up

No permanent seeding will take place during the period of Sept 1st through October 31th. A cover crop shall be seeded during this time, with a permanent seeding done as soon as possible at the next seeding window.

Seeding Method—Apply seed uniformly at the specified rate by broadcasting or drilling. Harrow lightly following the seeding operation to cover the seed unless the cultipacker seeder equipment cannot operate then cover the seed by hand using a rake or similar tool or a drag behind an ATV.

Mulch Certification—Mulch shall consist of clean grain oat or wheat straw that is certified by the Minnesota Crop Improvement Association (MCIA) to be noxious weed free. For information on obtaining certified mulch or getting a source of straw mulch certified go to the web address:

http://www.mncia.org/noxious-weed-seed-free-forage-mulch

Payment will be lump sum for each of the following

• Disturbed Area Seeding and Mulching

Seeding of a cover crop is subsidiary to Disturbed area seeding and will not result in additional payment.

NRCS-Minnesota (210-VI-NEH, May 2005) MN21-1

Minnesota Construction Specification 21—Excavation

1. Scope The work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials.

2. Classification Excavation will be classified as common excavation or rock excavation in accordance with the following definitions or will be designated as unclassified.

Common excavation shall be defined as the excavation of all materials that can be excavated, transported, and unloaded by the use of heavy ripping equipment and wheel tractor-scrapers with pusher tractors or that can be excavated and dumped into place or loaded onto hauling equipment by means of excavators having a rated capacity of one cubic yard and equipped with attachments (such as shovel, bucket, backhoe, dragline or clam shell) appropriate to the character of the materials and the site conditions.

Rock excavation shall be defined as the excavation of all hard, compacted or cemented materials the accomplishment of which requires blasting or the use of excavators larger than defined for common excavation. The excavation and removal of isolated boulders or rock fragments larger than one cubic yard in volume encountered in materials otherwise conforming to the definition of common excavation shall be classified as rock excavation.

Excavation will be classified according to the above definitions by the Engineer, based on his judgment of the character of the materials and the site conditions.

The presence of isolated boulders or rock fragments larger than one cubic yard in size will not in itself be sufficient cause to change the classification of the surrounding material.

For the purpose of this classification, the following definitions shall apply:

Heavy ripping equipment shall be defined as a rear-mounted, heavy duty, single-tooth, ripping attachment mounted on a tractor having a power rating of 200-300 net horsepower (at the flywheel).

Wheel tractor-scraper shall be defined as a self-loading (not elevating) and unloading scraper having a struck bowl capacity of l2-20 yards.

Pusher tractor shall be defined as a track type tractor having a power rating of 200-300 net horsepower (at the flywheel) equipped with appropriate attachments.

Unclassified Excavation. Items designated as "Unclassified Excavation" shall include all materials encountered regardless of their nature or the manner in which they are removed. When excavation is unclassified, none of the definitions or classifications stated in Section 2 of this specification shall apply.

3. Blasting The transportation, handling, storage, and use of dynamite and other explosives shall be directed and supervised by a person of proven experience and ability in blasting operations.

NRCS-Minnesota (210-VI-NEH, May 2005) MN21-2

Blasting shall be done in such a way as to prevent damage to the work or unnecessary fracturing of the foundation and shall conform to any special requirements in Section 10 of this specification.

4. Use of excavated materials To the extent they are needed, all suitable materials from the specified excavations shall be used in the construction of required permanent earthfill or rockfill. The suitability of materials for specific purposes will be determined by the Engineer. The Contractor shall not waste or otherwise dispose of suitable excavated materials.

5. Disposal of waste materials All surplus or unsuitable excavated materials will be designated as waste and shall be disposed of at the locations shown on the drawings or shall be disposed of by the Contractor at sites of his own choosing away from the site of the work.

6. Bracing and shoring Excavated surfaces too steep to be safe and stable if unsupported shall be supported as necessary to safeguard the work and workmen, to prevent sliding or settling of the adjacent ground, and to avoid damaging existing improvements. The width of the excavation shall be increased if necessary to provide space for sheeting, bracing, shoring, and other supporting installations. The Contractor shall furnish, place and subsequently remove such supporting installations.

7. Structure and trench excavation Structure or trench excavation shall be completed to the specified elevations and to sufficient length and width to include allowance for forms, bracing and supports, as necessary, before any concrete or earthfill is placed or any piles are driven within the limits of the excavation.

8. Borrow Excavation When the quantities of suitable materials obtained from specified excavations are insufficient to construct the specified fills, additional materials shall be obtained from the designated borrow areas.

The extent and depth of borrow pits within the limits of the designated borrow areas shall be as directed by the Engineer.

Borrow pits shall be excavated and finally dressed in a manner to eliminate steep or unstable side slopes or other hazardous or unsightly conditions.

9. Overexcavation Excavation in rock beyond the specified lines and grades shall be corrected by filling the resulting voids with portland cement concrete made of materials and mix proportions approved by the Engineer. Concrete that will be exposed to the atmosphere when construction is completed shall contain not less than 6 sacks of cement per cubic yard of concrete. Concrete that will be permanently covered shall contain not less than 4-1/2 sacks of cement per cubic yard. The concrete shall be placed and cured as specified by the Engineer.

Excavation in earth beyond the specified lines and grades shall be corrected by filling the resulting voids with approved compacted earthfill, except that, if the earth is to become the subgrade for riprap, rockfill, sand or gravel bedding, or drainfill, the voids may be filled with material conforming to the specifications for the riprap, rockfill, bedding or drainfill.

NRCS-Minnesota (210-VI-NEH, May 2005) MN21-3

The cost of unauthorized excavation and the backfill required to replace unauthorized excavation shall be borne by the Contractor.

10. Measurement and payment Method—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract prices for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.

11. Construction details

Excavation and related items are subsidiary to the line items that included excavation. No separate payment will be made for excavation.

NRCS-Minnesota (210-VI-NEH, May 2005) MN23-1

Minnesota Construction Specification 23—Earthfill

The work consists of the construction of earth embankments, other earthfills, and earth backfills required by the drawings and specifications.

Earthfill is composed of natural earth materials that can be placed and compacted by construction equipment operated in a conventional manner.

Earth backfill is composed of natural earth material placed and compacted in confined spaces or adjacent to structures (including pipes) by hand tamping, manually directed power tampers or vibrating plates, or their equivalent.

2. Material specifications All fill material shall be obtained from required excavations and designated borrow areas. The selection, blending, routing, and disposition of material in the various fills shall be subject to approval by the engineer.

Fill materials shall contain no frozen soil, sod, brush, roots, or other perishable material. Rock particles larger than the maximum size specified for each type of fill shall be removed prior to compaction of the fill.

The types of material used in the various fills shall be as listed and described in the specifications and drawings.

3. Foundation preparation Foundations for earthfill shall be stripped to remove vegetation and other unsuitable material or shall be excavated as specified.

Except as otherwise specified, earth foundation surfaces shall be graded to remove surface irregularities and shall be scarified parallel to the axis of the fill or otherwise acceptably scored and loosened to a minimum depth of 2 inches. The moisture content of the loosened material shall be controlled as specified for the earthfill, and the surface material of the foundation shall be compacted and bonded with the first layer of earthfill as specified for subsequent layers of earthfill.

Earth abutment surfaces shall be free of loose, uncompacted earth in excess of 2 inches in depth normal to the slope and shall be at such a moisture content that the earthfill can be compacted against them to produce a good bond between the fill and the abutments.

Rock foundation and abutment surfaces shall be cleared of all loose material by hand or other effective means and shall be free of standing water when fill is placed upon them. Occasional rock outcrops in earth foundations for earthfill, except in dams and other structures designed to restrain the movement of water, shall not require special treatment if they do not interfere with compaction of the foundation and initial layers of the fill or the bond between the foundation and the fill.

Foundation and abutment surfaces shall be no steeper than one horizontal to one vertical unless otherwise specified. Test pits or other cavities shall be filled with compacted earthfill conforming to the specifications for the earthfill to be placed upon the foundation.

NRCS-Minnesota (210-VI-NEH, May 2005) MN23-2

4. Placement Earthfill shall not be placed until the required excavation and foundation preparation have been completed and the foundation has been inspected and approved by the engineer. Earthfill shall not be placed upon a frozen surface nor shall snow, ice, or frozen material be incorporated in the earthfill matrix.

Earthfill shall be placed in approximately horizontal layers. The thickness of each layer before compaction shall not exceed the maximum thickness specified in section 9 or shown on the drawings.

Materials placed by dumping in piles or windrows shall be spread uniformly to not more than the specified thickness before being compacted.

Hand compacted earth backfill shall be placed in layers whose thickness before compaction does not exceed the maximum thickness specified for layers of earth backfill compacted by manually directed power tampers.

Earth backfill shall be placed in a manner that prevents damage to the structures and allows the structures to assume the loads from the earth backfill gradually and uniformly. The height of the earth backfill adjacent to a structure shall be increased at approximately the same rate on all sides of the structure.

Earthfill and earth backfill in dams, levees, and other structures designed to restrain the movement of water shall be placed to meet the following additional requirements:

(a) The distribution of materials throughout each zone shall be essentially uniform, and the earthfill shall be free from lenses, pockets, streaks, or layers of material differing substantially in texture, moisture content, or gradation from the surrounding material. Zone earthfills shall be constructed concurrently unless otherwise specified.

(b) If the surface of any layer becomes too hard and smooth for proper bond with the succeeding layer, it shall be scarified parallel to the axis of the fill to a depth of not less than 2 inches before the next layer is placed.

(c) The top surface of embankments shall be maintained approximately level during construction with two exceptions: A crown or cross-slope of about 2 percent shall be maintained to ensure effective drainage, or as otherwise specified for drainfill or sectional zones.

(d) Dam embankments shall be constructed in continuous layers from abutment to abutment except where openings to facilitate construction or to allow the passage of streamflow during construction are specifically authorized in the contract.

(e) Embankments built at different levels as described under (c) or (d) above shall be constructed so that the slope of the bonding surfaces between embankment in place and embankment to be placed is not steeper than 3 feet horizontal to 1 foot vertical. The bonding surface of the embankment in place shall be stripped of all material not meeting the requirements of this specification and shall be scarified, moistened, and recompacted when the new earthfill is placed against it. This ensures a good bond with the new earthfill and obtains the specified moisture content and density at the contact of the inplace and new earthfills.

5. Control of moisture content During placement and compaction of earthfill and earth backfill, the moisture content of the material being placed shall be maintained within the specified range.

The application of water to the earthfill material shall be accomplished at the borrow areas insofar as

NRCS-Minnesota (210-VI-NEH, May 2005) MN23-3 practicable. Water may be applied by sprinkling the material after placement on the earthfill, if necessary. Uniform moisture distribution shall be obtained by disking.

Material that is too wet when deposited on the earthfill shall either be removed or be dried to the specified moisture content prior to compaction.

If the top surface of the preceding layer of compacted earthfill or a foundation or abutment surface in the zone of contact with the earthfill becomes too dry to permit suitable bond, it shall either be removed or scarified and moistened by sprinkling to an acceptable moisture content before placement of the next layer of earthfill.

6. Compaction Earthfill—Earthfill shall be compacted according to the following requirements for the class of compaction specified:

Class A compaction—Each layer of earthfill shall be compacted as necessary to provide the density of the earthfill matrix not less than the minimum density specified in Section 9 or identified on the drawings. The earthfill matrix is defined as the portion of the earthfill material finer than the maximum particle size used in the compaction test method specified.

Class B compaction—Each layer of earthfill shall be compacted to a mass density not less than the minimum density specified.

Class C compaction—Each layer of earthfill shall be compacted by the specified number of passes of the type and weight of roller or other equipment specified or by an approved equivalent method. Each pass shall consist of at least one passage of the roller wheel or drum over the entire surface of the layer.

Earth backfill—Earth backfill adjacent to structures shall be compacted to a density equivalent to that of the surrounding inplace earth material or adjacent required earthfill or earth backfill.

Compaction shall be accomplished by hand tamping or manually directed power tampers, plate vibrators, walk-behind, miniature, or self-propelled rollers. Unless otherwise specified heavy equipment including backhoe mounted power tampers or vibrating compactors and manually directed vibrating rollers shall not be operated within 2 feet of any structure. Towed or self-propelled vibrating rollers shall not be operated within 5 feet of any structure. Compaction by means of drop weights operating from a crane or hoist is not permitted.

The passage of heavy equipment will not be allowed:

• Over cast-in-place conduits within 14-days after placement of the concrete

• Over cradled or bedded precast conduits within 7 days after placement of the concrete cradle or bedding

• Over any type of conduit until the backfill has been placed above the top surface of the structure to a height equal to one-half the clear span width of the structure or pipe or 2 feet, whichever is greater, except as may be specified in section 9.

Compacting of earth backfill adjacent to structures shall not be started until the concrete has attained the strength specified in section 9 for this purpose. The strength is determined by compression testing of test cylinders cast by the engineer for this purpose and cured at the work site in the manner specified in ASTM C 31 for determining when a structure may be put into service.

NRCS-Minnesota (210-VI-NEH, May 2005) MN23-4

When the required strength of the concrete is not specified as described above, compaction of earth backfill adjacent to structures shall not be started until the following time intervals have elapsed after placement of the concrete.

Time interval Structure (days)

Vertical or near-vertical walls with earth loading on one side only 14 Walls backfilled on both sides simultaneously 7 Conduits and spillway risers, cast-in-place (with inside forms in place) 7 Conduits and spillway risers, cast-in-place (inside forms removed) 14 Conduits, pre-cast, cradled 2 Conduits, pre-cast, bedded 1 Cantilever outlet bents (backfilled both sides simultaneously) 3

7. Reworking or removal and replacement of defective earthfill Earthfill placed at densities lower than the specified minimum density or at moisture contents outside the specified acceptable range of moisture content or otherwise not conforming to the requirements of the specifications shall be reworked to meet the requirements or removed and replaced by acceptable earthfill. The replacement earthfill and the foundation, abutment, and earthfill surfaces upon which it is placed shall conform to all requirements of this specification for foundation preparation, approval, placement, moisture control, and compaction.

8. Measurement and payment Method—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract prices for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.

9. Construction details

Earthfill and related items are subsidiary to the line items in the bid schedule that include earthfill and shall be paid by the lump sum method.

NRCS-Minnesota (210-VI-NEH, May 2005) MN26-1

Minnesota Construction Specification 26—Topsoiling

The work consists of furnishing and spreading topsoil to specified depths at locations shown on the drawings.

2. Quality of topsoil Topsoil shall consist of friable surface soil reasonably free of grass, roots, weeds, sticks, rocks, or other unsuitable material. Additional quality requirements, if any, are in section 6 of this specification.

3. Furnishing Topsoil shall be salvaged from designated earth surfaces that will be disturbed by construction activities. After designated sites have been cleared and grubbed, the topsoil shall be removed from the designated areas and stockpiled at locations shown on the drawings or acceptable to the engineer. Unsuitable material encountered during removal of topsoil shall be disposed of at locations shown on the drawings or approved by the engineer, or it will be otherwise hauled and disposed of at locations removed from the construction site. The contractor is responsible for complying with all local rules and regulations and the payment of any and all fees that may result from the disposal at locations outside the construction work limits.

4. Stockpiling Stockpiles of topsoil shall not conflict with the requirements of Construction Specification 5, Pollution Control, when made a part of this contract.

5. Spreading Spreading shall not be performed when the ground or topsoil is frozen, excessively wet, or otherwise in a condition detrimental to uniform spreading operations. Surfaces designated to receive a topsoil application shall be lightly scarified just before the spreading operation. Where compacted earthfills are designated to be topsoiled, the topsoil shall be placed concurrently with the earthfill and shall be bonded to the compacted fill with the compacting equipment.

Following the spreading operation, the topsoil surface shall be left reasonably smooth and without ruts or surface irregularities that could contribute to concentrated waterflow downslope.

6. Measurement and payment Method—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract prices for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.

7. Construction details Stripping, stockpiling, and re-spreading topsoil are included in one line item on the bid sheet and shall be paid by the lump sum method.

NRCS-MN (210-VI-NEH, May 2005) MN42-1

Minnesota Construction Specification 42—Concrete Pipe Conduits and Drains

1. SCOPE

The work shall consist of furnishing and installing concrete pipe or concrete drain tile and the necessary fittings as shown on the drawings.

2. MATERIALS

Reinforced concrete pressure pipe shall conform to the requirements of Material Specification 541 for the type and strength specified.

Concrete culvert pipe shall conform to the requirements of Material Specification 542 for the kind of pipe specified.

Concrete irrigation pipe, drainage pipe and drain tile shall conform to the requirements of Material Specification 543 for the kind of pipe or tile specified.

Pipe fittings shall conform to the requirements of the applicable pipe specifications.

Sealing compound for filling rubber gasket joints shall conform to the requirements of Material Specification 536.

Hot-pour joint sealer shall conform to the requirements of Material Specification 536.

Cold-applied sealing compound shall conform to the requirements of Material Specification 536.

Preformed sealing compound shall conform to the requirements of Material Specification 536.

Joint packing shall be commercial grade oakum.

Preformed expansion joint filler shall conform to the requirements of Material Specification 535.

Portland Cement Concrete for Bedding and Cradles shall conform to the requirements of Construction Specification MN-31.

3. LAYING AND BEDDING

Pipe and tile shall be laid to the line and grade shown on the drawings. Pipe shall be laid with the bell or groove at the upstream end of each section.

Concrete Cradles or Bedding. Pipe to be cradled or bedded on concrete shall be set to the specified line and grade and temporarily supported on precast concrete blocks or wedges until the cradle or bedding concrete is placed. Concrete blocks or wedges used to temporarily support the pipe during placement of bedding or cradle shall be of a class of concrete equal to or better than that used in the bedding or cradle.

Earth, Sand, or Gravel Bedding. The pipe shall be firmly and uniformly bedded throughout its entire length to the depth and in the manner specified on the drawings. The pipe shall be loaded sufficiently during backfilling around the sides to prevent its being lifted from the bedding.

NRCS-MN (210-VI-NEH, May 2005) MN42-2

Perforated pipe shall be laid with the perforations down and oriented symmetrically about a vertical centerline. Perforations shall be clear of any obstructions when the pipe is laid.

Elliptical pipe and pipe with elliptical or quadrant reinforcement shall be laid so that the vertical axis, as indicated by markings on the pipe, is in a vertical position.

4. JOINTS

Pipe joints shall conform to the details shown on the drawings and to the requirements of Sections 5 and 6 of this specification applicable to the type of joint specified. Except where unsealed joints are indicated, pipe joints shall be sound and watertight at the pressure specified.

5. JOINTING BELL AND SPIGOT PIPE

Rubber Gasket Joint, Pressure Pipe. Just before the joint is connected the connecting surfaces of the spigot and the bell or coupling band, sleeve or collar shall be thoroughly cleaned and dried, and the rubber gasket and the inside surface of bell or coupling band, sleeve or collar shall be lubricated with a light film of soft vegetable soap compound (flax soap). The rubber gasket shall be stretched uniformly as it is placed in the spigot groove to insure a uniform volume of rubber around the circumference of the pipe.

The joint shall be connected by means of a pulling or jacking force so applied to the pipe that the spigot enters squarely into the bell.

When the spigot has been seated to within 1/2 inch of its final position, the position of the gasket in the joint shall be checked around the entire circumference of the pipe by means of metal feeler gauge.

In any case where the gasket is found to be displaced, the joint shall be disengaged and properly reconnected. After the position of the gasket has been checked, the spigot shall be completely pulled into the bell and the section of the pipe shall be adjusted to line and grade.

Rubber Gasket Joints, Sewer, and Culvert Pipe or Irrigation Pipe. The pipe shall be joined in accordance with the gasket manufacturer's recommendations except as otherwise specified.

Mastic Sealed Joints. At the time of assembly the inside surfaces of the bell and the outside surfaces of the spigot shall be clean, dry and primed as recommended by the manufacturer of the sealing compound. A closely twisted gasket of joint packing of the diameter required to support the spigot at the proper grade and to make the joint concentric shall be made in one piece of sufficient length to pass around the pipe and lap at the top. The gasket shall be laid in the bell throughout the lower third of the circumference. The end of the spigot shall be laid in the bell throughout the lower third of the circumference. The end of the spigot shall be laid on the gasket and the spigot shall be fully inserted into the bell so that the pipe sections are closely fitted and aligned. The gasket then shall be lapped at the top of the pipe and thoroughly packed into the annular space between the bell and the spigot.

Hot-Pour Joint Sealer--The sealing compound shall be heated to within the temperature range recommended by the manufacturer and shall not be overheated or subjected to prolonged heating.

After the joint is assembled, with the pipe in its final location, a suitable joint runner shall be placed around the joint with an opening left at the top. Molten sealing compound shall be poured into the joint as rapidly as possible without entrapping air until the annular space between bell and spigot is completely filled. After the compound has set, the runner may be removed. Alternate joints may be poured before the pipe is lowered into the trench. In this case, the joint shall be poured with the pipe in a vertical position without the use of the runner. The compound shall have thoroughly set before

NRCS-MN (210-VI-NEH, May 2005) MN42-3 the pipe is placed in the trench, and the pipe be handled so as to cause no deformation of the joint during placement.

Cold-Applied Sealing Compound -- The annular space between bell and spigot shall be completely filled with the sealing compound. The compound shall be mixed on the job in accordance with the manufacturer's recommendations and in relatively small quantities so that setting will not be appreciable before application.

Preformed Sealing Compound -- Joint packing will not be required, except as recommended by the manufacturer of the sealing compound. Preformed strips or bands of the sealing compound shall be applied to the bell and spigot prior to assembly of the joint in accordance with the manufacturer's recommendations. Any compound extruded from the interior side of the joint during assembly shall be trimmed even with the interior surface of the pipe.

Unsealed Joints. When unsealed joints are specified, they shall conform to the details shown on the drawings.

6. JOINING TONGUE AND GROOVE PIPE

Mastic Sealed Joints. Strips or bands of preformed sealing compound shall be applied to the tongue and groove prior to assembly of the joint in accordance with the manufacturer's recommendations.

Any compound extruded from the interior side of the joint during assembly shall be trimmed even with the interior surface of the pipe.

Rubber Gasket Joints. The pipe shall be joined in accordance with the gasket manufacturer's recommendations except as otherwise specified.

Unsealed Joints. When unsealed joints are specified, they shall conform to the details shown on the drawings.

7. PRESSURE TESTING

Pressure testing of the completed conduit will not be required.

8. Measurement and payment Method—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract prices for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.

9. CONSTRUCTION DETAILS

All concrete pipe structures and components are included in the bid item on the bids sheet and shall be paid by the lump sum method.

NRCS-Minnesota (210-VI-NEH, May 2005) MN44-1

Minnesota Construction Specification 44—Corrugated Polyethylene Tubing

The work consists of furnishing and installing tubing and the necessary fittings and appurtenances as shown on the drawings and as outlined in this specification.

2. Material specifications Corrugated polyethylene tubing and fittings shall conform to the material requirements as outlined in Material Specification 548, Corrugated Polyethylene Tubing.

When perforations are specified, the water inlet area shall be a minimum of 1 square inch per lineal foot of tubing. The inlets either shall be circular perforations or slots equally spaced along the length and circumference of the tubing. Unless otherwise specified, circular perforations shall not exceed 3/16 inch in diameter, and slot perforations shall not be more that 1/8 inch wide.

Geotextile filter socks, when required, shall meet the material requirements outlined in section 8 of this specification.

Granular bedding material, when specified, shall conform to the requirements specified in section 8 of this specification.

The tubing shall be appropriately marked with ASTM or AASHTO designation.

3. Handling and storage Tubing shall be delivered to the job site and handled by means that provide adequate support to the tubing and do not subject it to undue stresses or damage. When handling and placing corrugated polyethylene tubing, care shall be taken to prevent impact blows, abrasion damage, and gouging or cutting (by metal edges and/or surface or rocks). The manufacturer's special handling requirements shall be strictly observed. Special care shall be taken to avoid impact when the pipe must be handled at a temperature of 40 degrees Fahrenheit or less.

Tubing shall be stored on a relatively flat surface so that the full length of the tube is evenly supported. Unless the tube is specifically manufactured to withstand exposure to ultraviolet radiation, it shall be covered with an opaque material when stored outdoors for 15 days or longer.

4. Excavation Unless otherwise specified or approved by the engineer, excavation for and subsequent installation of each tube line shall begin at the outlet end and progress upgrade. The trench or excavation for the tubing shall be constructed to the lines, depths, cross sections, and grade shown on the drawings.

Trench shields, shoring and bracing, or other suitable methods necessary to safeguard the contractor's employees and the works of improvement and to prevent damage to the existing improvements shall be furnished, placed, and subsequently removed by the contractor.

5. Preparing the tubing bed and blinding the tubing When a filter or envelope is specified, the shape of the bottom of the trench, gradation, and the thickness of the filter or envelope material to be placed around the tubing shall be as shown on the drawings or as specified in this specification. The filter or envelope material shall be placed in the bottom of the trench just prior to the laying of the tubing. The tubing shall then be laid and the filter

NRCS-Minnesota (210-VI-NEH, May 2005) MN44-2 or envelope material placed over the tubing as shown in Figures 4-6a, 4-6b or 4-6c. Unless otherwise specified in Section 10 or on the drawings, the gradation of the envelope material shall be:

Sieve Size % Passing 1 ½” 100 No. 60 = 30 No. 200 = 5

Aggregates meeting the requirements for MNDOT 3126, Fine Aggregate for Portland Cement Concrete or ASTM C33, Fine Aggregate for concrete are acceptable.

When a granular filter or envelope is not specified, the bottom of the trench shall be shaped to form a semicircular or trapezoidal groove in its center. This groove shall provide support for not less than a fourth of the outside circumference of the tubing. After the tubing is placed in the excavated groove, it shall be capped with friable material from the sides of the trench. The friable material shall be placed around the tubing, completely filling the trench to a depth of at least 3 inches over the top of the tubing. For material to be suitable, it must not contain hard clods, rocks, frozen soil, or fine material that will cause a silting hazard to the drain.

Tubing shall not be laid on rock foundation. In the event that boulders, rocks or ledge rock, or cemented materials that prevent satisfactory bedding are encountered at the required grade, the trench shall be excavated to a depth of at least 6 inches below grade and backfilled to grade with a sand-gravel mixture or other approved material. The bedding material shall be compacted and shaped to grade.

“Mole” type installation of corrugated tubing is an acceptable method. The bedding requirements shall be met.

Tubing placed during any day shall be blinded (place required soil material around and over pipe) and temporarily capped before construction activities are completed for that day.

6. Placement and joint connections All tubing shall be installed to grade as shown on the drawings. After the tubing is placed in the trench and blinded, allow sufficient time for the tubing to adapt to the soil temperature before backfilling.

Maximum allowable stretch of the tubing is 5 percent. Special precautions must be implemented on hot, bright days to ensure that the stretch limit is not exceeded and excessive deflection does not occur as a result of installation procedures, including backfill operations.

Unless otherwise specified in section 8 of this specification or shown on the drawings, connections are made with manufactured junctions comparable in strength with the specified tubing. All split fittings shall be securely fastened with nylon cord or plastic zip ties before any backfill is placed. All buried ends shall be supplied with end caps unless otherwise approved by the engineer.

NRCS-Minnesota (210-VI-NEH, May 2005) MN44-3

Where existing tile lines not shown on the drawings are crossed, they shall be bridged across the new trench or they shall be connected into the new tile lines, as directed by the engineer.

7. Backfilling Unless otherwise specified in section 8 of…