1.1 PROJECT BACKGROUND

The USDA-NRCS is conducting a project near Austin, MN. This project will include retrofitting 2 existing earthen dikes by installing steel sheet piling to act as a rodent barrier. The dike will be reconstructed by stripping the topsoil, adding fill and reshaping the side slopes. 3 rock crossings will also be constructed to allow vehicular access to the site. Lastly, 6 separate areas will be searched for existing tile. Tile, if found, will be removed. Disturbed areas will be prepped for seeding and seeded. Site is located in Lansing Township, Sections 20 & 29 in Mower County, Minnesota.

1.2 PROJECT LOCATION

The project is located in the sections 20 & 29 of Lansing Township (T-103N R-18W). The site is approximately 2 miles northwest of Austin, Minnesota. Access to the site is off County Road 27 (240th Street). See attached maps.

1.3 MATERIALS

A. Supply equipment as indicated in plans and specifications.

B. Certification of materials by NRCS required before installation.

1.4 EXECUTION

A. Pre-implementation conference with NRCS

B. Installation of materials

a. Installation of materials

• Construction will be completed as described in the engineering plans no later than November 30th, 2022. A notice to proceed must be issued by the Contracting Officer prior to starting work.

• After construction has been completed, all disturbed areas of the site must be prepared for seeding and seeded prior to November 30th, 2022.

a. PROTECTION All materials and equipment shall be properly protected against harm from normal weather conditions and the public.

b. CLEANUP

Work areas are to be kept clean during progress of work and until completion.

END OF STATEMENT OF WORK

USDA-NRCS Johnson/Summer WRE Wetland Restoration Mower County, MN

STATEMENT OF WORK

1.1 PROJECT BACKGROUND
1.2 PROJECT LOCATION
1.3 MATERIALS
1.4 EXECUTION
a. PROTECTION
b. CLEANUP