This document is the Revised Official Solicitation Price Sheet for the Unemployment Insurance System Department of Workforce Services contract opportunity. The contract requires the provision of an Unemployment Insurance System over a seven-year term. Prospective contractors must provide their total seven-year cost for the system, including all required activities and tasks, as well as costs for specific activities and tasks. The document includes tables for the total seven-year cost, a detailed cost breakdown per activity/task, and costs for state-hosted and cloud-hosted FedRAMP Moderate options, though only the total seven-year cost will be evaluated for low-cost determination.
The pricing terms indicate that all applicable expenses, such as travel, must be included in the proposed costs. Prospective contractors are required to provide any further cost breakdown during the Discussion Phase, and the proposed costs must not exceed the total seven-year cost provided. This contract opportunity is for the State of Arkansas Department of Workforce Services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S000000036 Bidders Conference.pdf | ||
| Revised MAP RFP-S000000036 ~3.pdf | ||
| Attachment A - Requirements.xlsx | XLSX spreadsheet | |
| MAP RFP Response Packet-S000000036.docx | DOCX document | |
| MAP RFP S000000036 Q & A.pdf | ||
| contgrantform~2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| S000000036 Unemployment Insurance System |
| Department of Workforce Services |
| Official Solicitation Price Sheet |
| Prospective Contractor Name |
| Instructions |
| 1. Insert your company's name on this tab in the yellow highlighted cell. |
| Table 1: |
| 1. Identify the total seven (7) year cost for the Unemployment Insurance System. This cost must include all costs associated with the activities/tasks that meet the requirements of this RFP and any additional activities/tasks identified in the Prospective Contractors proposal. |
| Table 2: |
| 1. Include information and cost related to successfully complete each activity/task. |
| Activities/tasks may either be the ones identified in the RFP or an alternative approach proposed by the Prospective Contractor. |
| 2. Include information and cost related to the cloud Hosted - FedRAMP- High option. |
| 2. Include the activity/task name, the unit of measure, and the rate. |
| 3. Calculate the total for each line. Enter the total cost in the light-green shaded cells at the end of each line. |
| 4. Add lines as necessary. |
| 5. The total cost from Table 2 must match the total seven (7) year cost provided in Table 1. |
| 6. Cost Points will be awarded based on the total seven (7) year cost provided in Table 1. |
| 7. In the event of a discrepancy, Table 1 shall govern. |
| 8. Pricing must be inclusive of all applicabe expenses such as travel, etc. |
| 9. Prospective Contractors shall provide any further breakdown of identified cost during the Discussion Phase. The cost must not exceed what is identified in Table 1. |
| Table 3: |
| 1. Include information and cost related to State Hosted and Cloud Hosted - FedRAMP -Moderate options. |
| 2. Include the activity/task name, the unit of measure, and the rate. |
| 3. Calculate the total for each line. Enter the total cost in the light-green shaded cells at the end of each line. |
| 4. Add lines as necessary. |
| 5. Table 3 will not be used for low-cost determination. |
Pricing
| S000000036 Unemployment Insurance System | ||||
| Department of Workforce Services | ||||
| Official Solicitation Price Sheet | ||||
| Prospective Contractor Name | 0 | |||
| Table 1 - Total Seven (7)-Year Cost | ||||
| Total Cost | $ - 0 | |||
| Table 2 - Cost Per Activity/Task (evaluated for low-cost determination) | ||||
| Activity/Task/Project Role | Description | Per (indicate one-time, annual, monthly, hourly) | Rate | Total Cost |
| Testing | hourly | hourly | $ 10.00 |
| Table 3 - Cost Per Hosting (State and Cloud Hosted-FedRAMP Moderate) Activity/Task (not evaluated for low-cost determination) | ||||
| Activity/Task | Description | Per (indicate one-time, annual, monthly, hourly) | Rate | Total Cost |
| Testing | hourly | hourly | $ 10.00 |