This document is an Addendum #1 to Invitation to Bid (ITB) #S-63500-00011572 for the New Bonneville Hatchery Heap Pump Systems for On-Station Houses, issued by the Oregon Department of Fish and Wildlife (ODFW). The project involves the installation of new heat pump systems for eight on-station houses at the Bonneville Hatchery. The scope of work includes installing seven 3-ton and one 5-ton heat pumps with compatible indoor air handlers and heat strips, as well as new programmable thermostats, line sets, and other related equipment. A pre-bid meeting will be held on October 2, 2024, and the contractor must provide AHRI certification and complete the installation by November 27, 2024 for substantial completion and November 29, 2024 for final completion.
The pricing terms are not explicitly stated, but the addendum clarifies that a bid bond/security is not required, and there is an exception to the Buy America, Build America (BABA) requirement due to the type of federal funding. The document also provides answers to questions from prospective offerors regarding efficiency ratings, insurance requirements, and other contract details.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1
ITB #S-63500-00011572
New Bonneville Hatchery Heap Pump Systems for On-Station Houses
October 7, 2024:
This addendum modifies the Invitation to Bid (ITB) document(s) for work only to the extent indicated herein. All other areas not specifically mentioned or affected by this addendum shall remain in full force. This addendum shall be added as a part of the original ITB document(s) and shall become part of the work required.
Deleted language is shown within [brackets and strikethrough] New language is show in Bold and Underlined.
ADDENDUM
1. Changes to the Invitation to Bid document (s).
a. Section 1: General Information, 1.2 Scope of Work, III. Project Description, Description of Work and Tasks, Tasks:
Contractor will:
Details for seven single level 1200 sqft homes:
1. Contractor will install seven, minimum 2.5 ton 3ton, 18 SEER, HSPF 9.5 heat pumps with compatible indoor air handlers and 10kw heat strips. Heat pump must be capable of normal operations range down to 20-degree Fahrenheit or colder before fully relying on emergency heat.
2. Both indoor and outdoor units to be from same manufacturer. AHRI certification will be required once awarded.
3. Install new programable thermostats on all units.
4. Install new line set from indoor to outdoor equipment.
5. Dispose of old equipment.
6. Install transitions to existing ductwork.
7. Install new unit pads/stilts.
8. Install new condensate drain pump/system(s).
9. Contractor will handle any permits needed.
10. Start up and test system operations
11. Contractor will clean up the worksite
Details for one 2275 sqft home:
1. Install one, minimum 4-ton 5-ton, 18 SEER, HSPF 9.5 heat pump with compatible indoor air handler and 15kw heat strips. Heat pump must be capable of normal operations range down to 20-degree Fahrenheit or colder before fully relying on emergency heat.
ADDENDUM #1 – ITB#S-63500-00011572 2
2. Both indoor and outdoor units to be from same manufacturer. AHRI certification will be required.
3. Add 2 registers in the basement
4. Install new programable thermostat.
5. Install New line set from indoor to outdoor equipment.
6. Dispose of old equipment.
7. Install transitions to existing ductwork.
8. Install new unit pads/stilts.
9. Install new condensate drain pump/system(s).
10. Contractor will handle any permits needed.
11. Start up and test system operations
12. Contractor will clean up the worksite
b. Section 1: General Information, 1.2 Scope of Work, IV. Deliverable and Schedule
IV.DELIVERABLES AND SCHEDULE:
• Pre-bid meeting will be held on October 2, 2024 at 11:00am at the following location: 70319 NE Chinook Ct, Cascade Locks, OR 97014.
• Contractor will provide AHRI certification for all products within 5 business days post award.
• Contractor will complete the uninstallation and disposal of the old heat-pump and the installation of the new heat-pumps on the ODFW residential buildings no later than November 27, 2024 for substantial and November 29, 2024 for final.
c. Section 1: General Information, 1.2 Scope of Work, VI. Deliverable Review
VI. DELIVERABLE REVIEW
When deliverables are confirmed to be operational after install and testing and all required certifications are received, ODFW will accept. Non-operational heat pumps will be rejected.
The prospective Offerors have until Close of Business on 10/8/2024, to submit written questions or protests regarding this Addendum.
Closing Date and Time: Remain unchanged
Addendum prepared by:
Rocky Smith rocky.d.smith@ofdfw.oregon.gov
END OF ADDENDUM No. 1 mailto:rocky.d.smith@ofdfw.oregon.gov
QUESTIONS AND ANSWERS:
Following are questions asked received by Offerors and ODFW’s answers. The answers and clarifications provided below by ODFW are for informational purposes ONLY and DO NOT constitute a change to the terms, conditions, technical specifications or requirements of the ITB.
Question 1: For the efficiency ratings listed, are those the old SEER and HSPF ratings or the new
SEER2/HSPF2 ratings?
Answer 1: Old SEER and old HSPF
Question 2: Does this project need to comply with BABA?
Answer 2: No, there is an exception to BABA with the type of federal funding we have.
Question 3: Is a bid bond/security required?
Answer 3: No
Question 4: Is the following insurance required: Workman’s Compensation no less than $5,000,000?
Answer 4: Yes
| The prospective Offerors have until Close of Business on 10/8/2024, to submit written questions or protests regarding this Addendum. |
| Closing Date and Time: Remain unchanged |