RSQ 26-041 ROWTP Wellfield Expansion, SAHMW Funded

This is a Request for Statement of Qualifications (RSQ) issued by the City of Fort Myers Procurement Services for design-build services related to the Reverse Osmosis Water Treatment Plant (ROWTP) Wellfield Expansion project, funded through the State Appropriations for Homes and Major Water (SAHMW) program. The City seeks a qualified design-build team to provide comprehensive design, permitting, and construction services for expanding potable water supply wellfield capacity. Key project elements include siting, design, and construction of potable water wells; raw water transmission mains; fiber optic communication networks; and rehabilitation of existing water infrastructure assets. The project must comply with City of Fort Myers Building and Utilities Departments, South Florida Water Management District (SFWMD), and Florida Department of Environmental Protection (FDEP) requirements. Submissions must be received electronically through the OpenGov portal by July 8, 2026, at 2:00 PM. The question submission deadline is June 1, 2026, at 2:00 PM. A Selection Committee meeting is scheduled for July 8, 2026, at 2:00 PM via Microsoft Teams, with a proposed City Council approval date of July 20, 2026. The contract will be awarded to the highest-ranked design-builder based on qualifications and subsequent negotiations.

Evaluation will be based on four criteria: qualifications of the team (15 points), collaborative delivery approach (20 points), builder's past performance on similar infrastructure projects (35 points), and designer's past performance (30 points). The design-builder must hold necessary Florida business licenses, have been in business for a minimum of three consecutive years, and maintain compliance with federal, state, and local laws. Required insurance includes workers' compensation, commercial general liability ($1,000,000 minimum), commercial automobile liability ($1,000,000 combined single limit), professional liability ($1,000,000 minimum), and builder's risk insurance. The design-builder must provide performance and payment bonds equal to 100 percent of the contract price. All submissions must be accompanied by a Current Capacity Certification, E-Verify affidavit, drug-free workplace certification, non-collusion affidavit, and various compliance certifications. The contract term and pricing structure will be finalized through negotiations following award, with the awarded contract subject to final City Council approval. Submissions remain valid for 180 calendar days from the solicitation opening date, and the selected design-builder must execute all required documents within 15 calendar days of receiving the Notice of Award.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RSQ 26-041

ROWTP Wellfield Expansion, SAHMW Funded

The City of Fort Myers Procurement Services utilizes an electronic bidding system to streamline the solicitation process.

City of Fort Myers Procurement Services Website https://procurement.opengov.com/portal/cityftmyers

ROWTP Wellfield Expansion, SAHMW Funded, RSQ 26-041

TABLE OF CONTENTS

1. INTRODUCTION

2. SCOPE OF WORK (SPECIFICATIONS)

3. INSTRUCTIONS TO PROPOSERS

4. INSURANCE

5. SPECIAL CONDITIONS

6. GENERAL TERMS & CONDITIONS

7. SELECTION COMMITTEE AND EVALUATION PROCESS

8. EVALUATION CRITERIA

9. DEFINITIONS

10. SUBMISSION QUESTIONNAIRE

1. INTRODUCTION

1.1. Advertisement

RSQ 26-041 ROWTP Wellfield Expansion, SAHMW Funded

The City of Fort Myers is seeking submittals for RSQ 26-041 ROWTP Wellfield Expansion, SAHMW

Funded. Submissions must be received electronically on or before Wednesday, July 8, 2026 at

2:00 pm. Interested participants are encouraged to download the solicitation documents. For more details visit https://procurement.opengov.com/portal/cityftmyers

CITY OF FORT MYERS

Marty K. Lawing, City Manager Legal Ad: News-Press/OpenGov

Mary Hagemann, City Clerk RUN DATES: Tuesday, May 12, 2026

1.2. Contact Information

Direct inquiries to the following:

Procurement Representative Name

Cathy Scott, Senior Procurement Specialist

2200 Second Street

Fort Myers, FL 33901

Email: cscott@fortmyers.gov

Phone: (239) 321-7235

Requesting Department:

Public Utilities

1.3. OpenGov Portal

The City of Fort Myers uses OpenGov (https://procurement.opengov.com/portal/cityftmyers) to administer the competitive solicitation process, including but not limited to soliciting responses, issuing addenda, posting results and issuing notification of an intended decision. There is no charge to register and download the solicitation from OpenGov. Design-Builder's are strongly encouraged to read the various Guides and Tutorials available in OpenGov well in advance of their intention of submitting a response to ensure familiarity with the use of OpenGov. The City will not be responsible for submission failures caused by the Consultant’s equipment or internet connectivity. In the event of a documented system-wide OpenGov outage, the City reserves the right to extend the deadline by addendum.

1.4. Timeline

The Proposed timeline for this solicitation (which is subject to change) is:

Release Project Date: May 12, 2026

Question Submission Deadline: June 1, 2026, 2:00pm

Submission Deadline: June 15, 2026, 2:00pm

Selection Committee: July 8, 2026, 2:00pm

Microsoft Teams meeting

Join:

https://teams.microsoft.com/meet/2634315

46122053?p=6VxBRo6zuinQ6K29Gk

Meeting ID: 263 431 546 122 053

Passcode: JW9oo6Sw

Need help? | System reference

Dial in by phone

+1 239-205-3327,,694464824# United

States, Cape Coral

Find a local number

Phone conference ID: 694 464 824#

For organizers: Meeting options | Reset dial-in PIN

Proposed Council Approval Date: July 20, 2026 https://teams.microsoft.com/meet/263431546122053?p=6VxBRo6zuinQ6K29Gk https://teams.microsoft.com/meet/263431546122053?p=6VxBRo6zuinQ6K29Gk

2. SCOPE OF WORK (SPECIFICATIONS)

2.1. Mandatory Minimum Qualifications

2.1.1. The Design-Builder shall hold any necessary license(s) authorizing them to do business in the State of Florida.

2.1.2. Design-Builder shall have been in business under the current company/firm name for a minimum of three (3) consecutive years prior to the date of submission. This requirement is reasonably related to ensuring Design-Builderstability and capacity.

2.1.3. Neither Design-Builder nor any principal, officer, or stockholder shall be in arrears or in default of any debt or contract involving the City, (as a party to a contract, or otherwise); nor have failed to perform faithfully on any previous contract with the City.

2.1.4. Design-Builder shall inform the City of any relevant legal or ethical issues. Specifically, disclosing:

2.1.4.1. Judgments: Any court decisions against them.

2.1.4.2. Pending Lawsuits: Any legal actions that are currently underway.

2.1.4.3. Criminal Activities: Any criminal conduct, especially if it involves moral turpitude

(actions that are morally reprehensible).

Design-Builder shall be given a chance to explain or provide additional information regarding these issues if applicable. This allows them to clarify any concerns and provide context.

To demonstrate qualifications to perform the Work, each Design Builder shall be prepared to submit within five (5) days of City’s request written evidence, such as financial data, previous experience, present commitments, and other such data as may be requested. Each Solicitation shall contain evidence of the Design-Builder’s qualifications to do business in the State of

Florida, or covenant to obtain such qualification, prior to award of the contract.

The Design-Builder shall maintain the Minimum Qualifications Requirements during the term of the Contract and any contract renewals.

The City will evaluate such disclosures solely for purposes of determining responsibility and capacity to perform, in accordance with applicable law.

2.2. Project Management

• Provide all project coordination including developing a preliminary project schedule, managing Design-Builder and subs work, tracking project status and budget, preparing monthly invoicing, providing monthly project status updates, etc.

• Prepare and submit a quality assurance and quality control plan, indicating how the

Design-Builder intends to assure quality and timeliness in performance of the work.

• Facilitate and attend progress meetings.

2.3. Preliminary Design

• Conduct a raw water transmission main route analysis extending from existing raw water transmission main to the selected well sites.

• Draft a Preliminary Design Report summarizing the RWM Route analysis. Identify required permits for any major crossings (e.g. railway, water, highway).

• Provide an opinion of probable construction cost.

2.4. Property Acquisition

Design-Builder shall support property acquisition. All acquisition decision and negotiations will be performed by the City.

2.5. Design Services

• Well Drilling

• Raw Water Main

• Well Site Surface Assets

2.6. Permitting

• Coordinate any and all required permits. Agency payments will be made by the City.

2.7. Additional Services

• Loan Administration, Compliance, and Oversight

• Funding Assistance

3. INSTRUCTIONS TO PROPOSERS

3.1. Procurement Information

Procurement Services is the official source for obtaining information regarding City solicitations.

It is the responsibility of Design-Builder monitor and obtain solicitation updates and current award information both prior to and after the scheduled opening date. Information is updated as it becomes available. The City reserves the right to issue an award or a recommendation of award at any time following the scheduled solicitation opening date.

3.2. Introduction

To be considered, electronic submissions must be completed in accordance with the instructions outlined in this solicitation and submitted within the specified timeframe. The portal will automatically lock at the submission deadline. The City reserves the right to accept or reject any or all submissions and to waive irregularities or technicalities, as deemed in the best interest of the City. All decisions made by the City regarding these matters shall be final and binding.

3.3. Americans With Disabilities Act

Persons with disabilities requiring special accommodations to participate in this solicitation process should contact Procurement Services at least seven (7) days before the required accommodation.

Contact Information:

Procurement Services

2200 Second Street, Fort Myers, FL 33901

Email: ProcurementServices@fortmyers.gov

Phone: (239) 321-7240

3.4. Incorporation of Procurement Policy and Ordinance

This solicitation is issued in accordance with, and governed by, the provisions and procedures outlined in Chapter 38, Articles III and IV of the City of Fort Myers Code of Ordinances.

The City’s Procurement Policy and Ordinance (38-61 thru 68) are hereby incorporated by reference into this solicitation and any contract awarded as a result of this solicitation. By participating in this solicitation, Design-Builder agrees to be bound by the City’s Procurement

Ordinance and Policy in all matters related to this solicitation and any subsequent contracts.

Any appeals related to this solicitation must comply with the requirements specified in the City’s

Code of Ordinances and Procurement Policy.

3.5. Solicitation Documents

Visit the Fort Myer's OpenGov portal and follow the link to Active Solicitations to access solicitation information. It is the responsibility of the Design-Builder to ensure correct mailto:ProcurementServices@fortmyers.gov https://fortmyers.gov/DocumentCenter/View/14396/City-of-Fort-Myers-Procurement-Policy-PDF https://www.fortmyers.gov/1515/Procurement-Ordinances registration information is provided. The City will not be held liable for any issues arising from incorrect or incomplete contact information. All submittals must be prepared using the solicitation documents provided in this solicitation. The City assumes no responsibility for errors or misinterpretations resulting from the use of incomplete or unofficial solicitation documents.

Solicitation documents, including all attachments, specifications, and exhibits are provided solely to facilitate the preparation and submission of responses. The City reserves the right to cancel any solicitation at any time without obligation.

3.6. Responsibilities of the Respondent

Each Design-Builder is responsible for the following actions before submitting an offer:

• Obtain solicitation documents exclusively from OpenGov. Documents sourced from other platforms or sources are not guaranteed to be accurate.

• The Design-Builder will examine all solicitation documents to fully understand the requirements. If additional clarification is needed, submit questions through the

OpenGov Q&A module.

• Design-Builder who intend to submit a proposal are encouraged to "follow" the project.

By doing so, you will be notified by email of communications relating to the project.

• The Design-Builder will review, understand, and factor into their bid/proposal all addenda and answers to questions that are submitted via the OpenGov portal. See

"Questions and Addenda Guidelines". All addenda and updates will be made available exclusively via OpenGov. Design-Builder is advised to regularly check the portal for any updates related to this solicitation.

• Evaluate all Federal, State, and Local laws, ordinances, codes, and regulations that could impact the cost, progress, performance, or execution of the work.

• The Design-Builder will study and carefully align observations with the solicitation documents to ensure consistency.

• The Design-Builder will notify the Procurement Services Department by email to procurementservices@fortmyers.gov and submit a question through the E-Procurement

Q&A tab of any conflicts, errors, or discrepancies in the solicitation documents.

Response Timeline Questions related to document format or processes will be addressed within two (2) business days or the solicitation may be placed on hold. This timeline does not apply to project-specific questions that require input from project managers or subject matter experts.

• The draft contract intended for award is part of the solicitation as an attachment. This draft contains standard legal language and may be modified. Any exceptions to the standard contract should be submitted as a question in the Q&A module before the question deadline. If the question deadline has passed, exceptions should be clearly noted in the Submission Questionnaire. Exceptions to the draft contract may impact the evaluation of the submittal.

• The City reserves the right to make modifications to the draft contract for specific solicitations before execution.

3.7. Cone of Silence

Design-Builder to this solicitation or persons acting on their behalf may not contact, between the release of the solicitation and the end of the 72-hour period following the City posting the notice of intended award, excluding Saturdays, Sundays, and state holidays, any employee of the city concerning any aspect of this solicitation, except in writing to the Procurement Officer or as provided in the solicitation documents. Violation of this provision may be grounds for rejecting a response.

3.8. Prohibition Against Considering Social, Political, or Ideological Interests

In accordance with Florida Statute Section 287.05701, an awarding body is prohibited from:

requesting documentation of or considering a Design-Builder’s social, political, or ideological interests when determining whether the Design-Builder is responsible; giving preference to a

Design-Builder based on their social, political, or ideological interests.

This ensures that all evaluations and awards are conducted solely on the basis of objective criteria and the best interests of the City.

3.9. Submission Guidelines

3.9.1. Official Submission Portal

All submissions must be made electronically through the City’s Bid Portal in OpenGov. The portal will keep all files locked until the solicitation officially closes.

3.9.2. Judgment on Disclosure

City reserves the right to exercise its own judgment regarding the disclosure of records. City may take any actions it deems necessary, including filing a declaratory action, to comply with

Federal or Florida public records laws.

Except as provided under the Americans with Disabilities Act for individuals requiring special accommodations, all proposals for this solicitation must be submitted electronically. Paper responses will be deemed non-responsive.

3.9.3. Instructions for Uploading Submissions

3.9.3.1. Submission Process Log into your OpenGov account and navigate to the solicitation for which you wish to submit a response. Click on “Draft Response”, complete the required information, upload your submission along with all required attachments, and submit your response.

The Design-Builder must clearly identify any variances from the Solicitation requirements, no matter how minor. Any exceptions to the scope of work must be specifically noted and thoroughly explained in the Design-Builder’s questionnaire. If no variances are identified in the submittal, the City will assume that: a) the materials, equipment, or services offered fully comply with the Solicitation specifications, b) TheDesign-Builder agrees to all terms and conditions outlined in the attached Draft Contract. Failure to disclose variances may result in the

Design-Builder being held to full compliance of the Solicitation requirements.

3.9.3.2. Responsibility for Timely Submission The Design-Builder is solely responsible for ensuring their submittals are complete, uploaded, and submitted via the e-Procurement Portal before the specified due date and time. The City is not responsible for any delays or failures in submission caused by any occurrence.

Design-Builder is responsible for uploading their submittals directly into the OpenGov

Submission Portal. The authorized representative who binds the Design-Builder to the submittal must sign the qualification statement. A submittal is considered timely only if received through the OpenGov portal by the precise date and time specified in the solicitation timeline. The official time will be determined by the OpenGov portal's time clock. The portal will not accept submittals after the deadline.

Design-Builder shall prepare their responses in a clear and concise manner, ensuring that all required content is complete. Special attention should be given to the specific information, instructions, and requirements outlined in the solicitation document to ensure responsiveness.

Incomplete responses or those lacking key information may be rejected. To facilitate the review process, each section or tab of the response should be properly labeled to correspond with the solicitation requirements.

City is not responsible for any expenses incurred by Design-Builder in the preparation and submission of their proposals, including costs associated with presentations or other activities related to the solicitation process.

Ownership of Submittals All submittals received in response to this solicitation will become the property of the City and will not be returned to the Design-Builder.

3.9.4. Submission Requirements

Document Format A single PDF document, signed by an authorized representative, must be submitted via the OpenGov portal under the Proposal question of the "Submission

Questionnaire".

Title Page – Introduction include the following: Name of the individual or firm, Address, Email address, Telephone number, Name of contact person, Date, Solicitation number and title.

Table of Contents Include page numbers and bookmark each section for easy navigation.

Letter of Transmittal Two (2) page limit. Content: Briefly state the Design-Builder's understanding of the services to be provided. Make a positive commitment to perform the work. Provide the names, titles, addresses, and telephone numbers of authorized representatives.

Mandatory Minimum Qualification Documentation Provide documentation to verify compliance with the "Minimum Qualifications" section. Ensure all documentation is clear and specific.

Evaluation Criteria Place responses to the evaluation criteria in the order it is stated under the "Evaluation Phase" section.

Required Documents

Corporate Submissions Must be signed in the corporate name by the President or

Vice-President (or other authorized officer with evidence of signing authority). The corporate seal must be affixed and attested by the Secretary or Assistant Secretary.

Include the corporate address and state of incorporation.

Partnership Submissions Must be signed in the partnership name by a partner, with the title noted under the signature. Include the partnership's official address.

Litigation History Provide details of any current litigation or outstanding judgments involving the Design-Builder in the respective question under the Submission

Questionnaire.

3.9.5. Instructions for Uploading Submissions

Submission Process Log into your OpenGov account and navigate to the solicitation for which you wish to submit a response. Click on “Draft Response”, complete the required information, upload your submission along with all required attachments, and submit your response.

Responsibility for Timely Submission The Design-Builder is solely responsible for ensuring their submittals are complete, uploaded, and submitted via the e-Procurement Portal before the Official due date and time. The City is not responsible for any delays or failures in submission caused by any occurrence.

Official Time The time clock in OpenGov will serve as the “Official Time” for determining the actual closing time of the solicitation. Submissions received after the specified date and time will not be accepted.

3.9.6. Mandatory Minimum Qualification Documentation

Design-Builder must provide clear and specific documentation to verify that all mandatory minimum qualifications, as outlined in the section titled "Mandatory Minimum Qualifications," have been met.

3.9.7. Required Documents

See the "Submission Questionnaire" section for a detailed list of required documents.

3.9.8. Partnership Submittals

Must be executed in the partnership name and signed by a partner. The title of the signing partner must appear under the signature, and the official address of the partnership must be included below the signature.

3.9.9. Litigation History

The Design-Builder must disclose whether they are involved in any current litigation or have any outstanding judgments. Include relevant details in the submittal.

3.9.10. Binding Submissions

All submissions shall remain binding for a period of one hundred eighty (180) calendar days following the opening date.

3.10. Questions and Addenda

3.10.1. Submission of Questions

All questions regarding the meaning or intent of the solicitation documents shall be submitted through the OpenGov Portal. Only questions received before the deadline specified in the solicitation timeline shall be considered. Written responses to questions will be binding via addenda or the "Questions & Answers" feature in OpenGov. Oral or other informal interpretations or clarifications have no legal effect. Any addenda issued electronically during the solicitation period shall become part of the solicitation and will be incorporated into the resulting contract.

3.10.2. Authority of Addenda and Revisions

Revisions to the solicitation and responses provided via the "Questions & Answers" feature are authoritative and shall be considered addenda to the solicitation. All information provided in this solicitation, including addenda and answers to questions, will be incorporated into the solicitation and any resulting contract. It is the responsibility of the Design-Builder to review all addenda, revisions, and published answers to questions.

Requests for interpretations must be submitted through the OpenGov Portal. Failure to review and comply with the latest addenda or interpretations will not relieve the Design-Builder of their obligations under the solicitation or the resulting contract. No oral interpretations will be provided. All official interpretations will be issued as written addenda and made available via

OpenGov. The City is not responsible for the distribution of addenda or other solicitation-related information to Design-Builder who fails to register in OpenGov.

3.10.3. Modification of Solicitation Documents

The City reserves the right to issue addenda to modify the solicitation documents as necessary.

Design-Builders are strongly encouraged to attend any pre-submittal meetings to gain clarity on the solicitation requirements.

The absence of details or the omission of specific descriptions within the Solicitation or any addenda shall be interpreted as requiring adherence to the highest standards of best commercial practices. All interpretations and clarifications of this Solicitation shall be governed by the terms and conditions set forth in this Contract.

3.11. Modification and Withdrawal of Submissions

3.11.1. Modifying or Withdrawing Submissions

Submissions may be modified or withdrawn by the Design-Builder through the OpenGov portal at any time before the opening of the Solicitations.

3.11.2. Withdrawal Due to Material Mistake

If, within twenty-four (24) hours after Submissions are opened, a Design-Builder files a duly signed written notice with the City and promptly demonstrates to the City's reasonable satisfaction that a material and substantial mistake occurred in the preparation of its

Submission, the Design-Builder may withdraw its Submission. In such cases:

• The Submission security, if applicable, will be returned.

• The Design-Builder shall thereafter be disqualified from further participation in the Work to be provided under the Contract.

3.12. Opening Submissions for Non-Construction

Non-construction-related submittals will be opened privately. Results will be posted in accordance with Florida Statute 119.07(1) and Article I, Section 24(a) of the Florida State

Constitution.

3.13. Reserved Rights

3.13.1. Request for Additional Information

The City reserves the right to request additional information from the Design-Builder after the closing date. This may include but is not limited to

• Information necessary to evaluate, clarify, or substantiate any aspect of the submittal.

• Evidence of financial resources and the ability to provide and maintain the required system and/or services. Additionally, the City may conduct investigations into the qualifications of any

Design-Builder, which may include background checks performed by the Fort Myers Police

Department.

3.13.2. Flexible Award Options

The City reserves the right to:

• Make awards based on individual items, groups of items, all-or-none, or a combination thereof, potentially involving one or more suppliers.

• Reject any or all submittals or waive informalities or technicalities in the submittals received.

3.13.3. Rejection of Submittals

The City reserves the right to:

• Reject any and all Submissions;

• Waive any and all informalities;

• Negotiate contract terms with the Successful Design-Builder;

• Disregard nonconforming, non-responsive, unbalanced, or conditional submittals;

• Reject any submittal if it is determined that awarding to the Design-Builder is not in the City’s best interest, including cases where a) The Solicitation is not responsive; b) The Design-Builder is unqualified or has questionable financial ability; c) The Design-Builder fails to meet any other relevant standards or criteria established by the City.

3.14. Irrevocable Offer

By submitting a response to this Solicitation, the Design-Builder agrees that their submission constitutes an irrevocable offer to the City after the opening date. This offer shall remain valid for a period of one hundred eighty (180) calendar days from the date of the opening. The

Design-Builder agrees to provide the goods and services described in this Solicitation under the terms, conditions, and pricing outlined in their submission.

The City, at its sole discretion, reserves the right to release any submission from this commitment during the validity period.

3.15. Award of Contract

3.15.1. Formal Award

Contracts will be awarded in accordance with the City’s Procurement Code, Chapter 38, Article 3 of the City of Fort Myers Code of Ordinances. The contract will be awarded to the highest-ranked Design-Builder based on evaluation criteria and presentation results. The award is contingent upon successful contract negotiation and final approval by the City Council.

The contract will include this Solicitation, any addenda, the Design-Builder’s submittal, and the established Purchase Order. This Contract shall be governed by and construed in accordance with the laws of the State of Florida. Venue for any legal action arising out of or relating to this contract shall be in a court of competent jurisdiction located in Lee County, Florida.

3.15.2. Purchase Order

The Purchase Order (PO) will be issued by the City to the selected Design-Builder within the time specified for acceptance, in conjunction with the contract.

3.16. Form of Contract

The City’s intended format for the awarded Contract is attached to this solicitation.

Any exceptions to the terms of this standard Contract must be brought up as a question in

OpenGov and resolved prior to the solicitation closing so everyone responds to the same terms and conditions.

The final executed Contract may differ in pagination or numbering from the draft provided.

The City reserves the right to revise or alter the language of the Draft Contract after responses are received and prior to execution. Revisions may be made to address the specific requirements or circumstances of the solicitation.

3.17. Execution of Contract

The successful Design-Builder shall, within fifteen (15) calendar days after the issuance of a

Notice of Award and receipt of the Contract from Procurement Services, sign and enter into a

Contract with the City. Simultaneously, the Design-Builder shall provide: any required bonds;

Indemnities; and Updated insurance certificates as specified in the Solicitation.

Electronic signatures are accepted under the Florida Uniform Electronic Transaction Act (F.S.

668.50)

Failure to meet the established deadline for submitting the required documents may result in cancellation of the award at the City’s discretion.

3.18. Debriefing of Proposers

Not later than thirty (30) days after City Council approval of a selection or shortlist, a proposer may submit a written request to the applicable contracting agent for a debriefing on the evaluation of their proposal. The contracting agent will schedule a meeting with the Proposer for the debriefing. However, at the Proposer’s request, the debriefing may be conducted via telephone conference. The debriefing shall include the following minimum information:

• Key requirements of the solicitation.

• The overall ranking of all proposals.

• The significant weaknesses or deficiencies in the proposal in response to the requirements of the solicitation.

• If requested, an explanation of the score received for each evaluation criteria will be provided, including costs, if applicable.

• If applicable, a summary of the rationale for award.

• Responses to any relevant questions of the Proposer.

3.19. Protest Procedure

The City’s protest policy and procedure are outlined in the City of Fort Myers Procurement

Policy, which can be accessed at the following link:

City of Fort Myers Procurement Policy (PDF)

For details, refer to Page 20, Item F of the policy document.

https://www.cityftmyers.com/DocumentCenter/View/14396/City-of-Fort-Myers-Procurement-Policy-PDF

4. INSURANCE

Insurance Coverages Required.

Insurance will be provided by the Design-Builder. If required, the awarded Design-Builder (and its subcontractors to the same extent and on the same terms as set forth below for Design-

Builder) shall maintain the following coverages and furnish the certificate of insurance on the policies and renewals thereof which indicate that insurance coverage has been obtained meeting the requirements of the contract.

4.1. Insurance Terms and Conditions

4.1.1. The Design-Builder shall obtain and maintain such insurance as will protect the City from:

(1) claims under workers' compensation laws, disability benefit laws, or other similar employee benefit laws; (2) claims for damages because of bodily injury, occupational sickness or disease or death of his or her employees including claims insured by usual personal injury liability coverage; (3) claims for damages because of bodily injury, sickness or disease, or death of any person other than his employees including claims insured by usual personal injury liability coverage; and (4) from claims for injury to or destruction of tangible property including loss or use resulting there from; any or all of which claims may arise out of, or result from, the services, work and operations carried out pursuant to and under the requirements of this

Agreement, whether such services, work and operations be by the Design-Builder, its employees, or by any Subcontractor/Subconsultants, or anyone employed by or under the supervision of any of them, or for whose acts any of them may be legally liable.

4.1.2. Subcontractor/Subconsultants. Unless expressly specified otherwise in this solicitation, a

Design-Builder and its Subcontractor/Subconsultants of any tier will be required at their own expense to maintain in effect at all times during the performance of the work insurance coverages with limits not less than those set forth below with insurers and under forms of policies satisfactory to the City. It shall be the responsibility of the Design-Builder to maintain the required insurance coverages and to assure that Subcontractor/Subconsultants maintain required insurance coverages at all times. Failure of a Design-Builder to maintain adequate coverage shall not relieve it of any contractual responsibility or obligation. The requirements specified herein as to types, limits, and City’s approval of insurance coverage to be maintained by a Design-Builder and its Subcontractor/Subconsultants are not intended to and shall not in any manner limit or qualify the liabilities and obligations assumed by the Design-Builder and its

Subcontractor/Subconsultants under a contract. Any insurance carried by the City that may be applicable shall be deemed to be excess insurance and the Design-Builder's insurance primary for all purposes despite any conflicting provision in the Design-Builder's policies to the contrary.

4.1.3. The Design-Builder shall obtain, have, and maintain during the entire period of this

Agreement, all such insurance policies as are set forth and required herein.

4.1.4 The insurance coverage to be obtained by the Design-Builder, as set forth in Agreement for: (1) Worker's Compensation; (2) Commercial General Liability; (3) Commercial Automobile

Liability; and (4) Professional Liability is understood and agreed to cover any and all of the services or work set forth in Attachment "A” of this Agreement, or in any and all subsequently executed Change Orders, or Supplemental Agreements. If the total amount of insurance coverage established in, and required by, a Change Order or Supplemental Agreement exceeds the amount of insurance coverage carried by the Design-Builder, then the Design-Builder shall be required and expected to acquire such additional insurance, and the compensation established for the Change Order, or Supplemental Agreement, shall include consideration of any additional premium cost incurred by the Design-Builder to obtain such additional insurance coverage.

4.1.5. The purchasing of any insurance on the behalf of the City shall not waive any defense under Sovereign Immunity.

4.1.6. Additional Insureds. All insurance coverages furnished under a contract except Workers’

Compensation, Employers’ Liability and any Professional Liability Policy shall include the City and its officers, elected officials, and employees as additional insureds with respect to the activities of the Design-Builder and its Subcontractor/Subconsultants. The City shall not by reason of their inclusion under these policies incur liability to the insurance carrier for payment of premium for these policies.

4.1.7. Waiver of Subrogation. The Design-Builder and its Subcontractor/Subconsultants shall require their insurance carriers, with respect to all insurance policies, to waive all rights of subrogation against the City, its officers, elected officials, agents, and employees and against other Design-Builder and Subcontractor/Subconsultants.

4.2. Insurance Certificate Required

4.2.1. Certificates of Insurance. Prior to commencing work at the jobsite, and as a condition precedent to the Design-Builder and their Subcontractor/Subconsultants initiation of performance, the Design-Builder and its Subcontractor/Subconsultants shall furnish the City with certificates of insurance as evidence that policies providing the required coverage and limits of insurance are in full force and effect. The certificates shall provide that any company issuing an insurance policy for the work under a contract shall provide not less than 30 days advance notice in writing to the City prior to cancellation, termination, or material change of any policy of insurance (except for notice of non-payment of premium for which not less than

10 days advance notice in writing shall be required). In addition, the Design-Builder shall immediately provide written notice to the City upon receipt of notice of cancellation of an insurance policy or a decision to terminate an insurance policy. All certificates of insurance shall clearly state that all applicable requirements have been satisfied, including certification that the policies are of the “occurrence” type. Certificates of insurance for a Design-Builder and

Subcontractor/Subconsultants-furnished insurance and notices of any cancellations, terminations, or alterations of such policies shall be mailed to the Procurement Services at the address set forth for delivery of the Solicitation.

4.2.2. All such insurance certificates shall be in a form and underwritten by insurance companies acceptable to the City and licensed in the State of Florida.

4.2.3. Each Certificate of Insurance submitted to the City shall be an original and shall be executed by an authorized representative of the insurance company affording coverage.

4.2.4. Each Certificate of Insurance shall specifically include all of the following:

• The name and type of policy and coverages provided; and

• The amount or limit applicable to each coverage provided and the deductible amount, if any, applicable to each type of insurance coverage being provided; and

• The date of expiration of coverage; and

• The designation of the City, both as an additional insured to the GL & AL on a primary and non-contributory basis, to include both premises/ongoing operations and products/completed operations hazards, and as a certificate holder. (This requirement is exempted for Professional Liability Insurance and for Workers' Compensation

Insurance); and

• A specific reference to this Agreement and the Project to which it pertains. (This requirement may be exempted for Professional Liability Insurance); or In the event the

Design-Builder has, or expects to enter into an agreement for Professional Services other than those provided for in this Agreement; the Design-Builder may elect to submit a Certificate of Insurance containing the following statement:

"This policy covers the services or work provided or performed by the Named Insured for any and all projects undertaken for the City pursuant to one or more written Professional

Services Agreements, or written Supplemental Agreements or Change Orders thereto, and the limit of liability shown shall not be intended or construed as applying to only one project."

Upon receipt and approval of such a Certificate of Insurance, a separate Certificate of

Insurance will not be required for each separate agreement.

• An identifying statement indicating the identification of any services or work that is included in, or required under, the Scope Of Professional Services set forth in

Attachment “A” that is specifically excluded or exempted from coverage under the provisions, terms, conditions or endorsements of the Design-Builder's insurance policies. A statement which indicates any and all deductible amounts applicable to each type of insurance coverage required. In the absence of any such statements of deductible amount, or coverage statement of exclusions or exemptions, the City will proceed with the understanding, stipulation, and condition that there are no deductible amounts, or exclusions or exemptions to the insurance coverage provided.

• Name of the Project and/or Project Number should be clearly indicated.

• Each Certificate of Insurance shall be issued by an insurance agent and/or agency duly authorized to do so by, and on behalf of, the insurance company affording the insurance coverage indicated on each Certificate of Insurance.

• If the initial or any subsequently issued Certificate of Insurance expires prior to completion of the work or termination of this Agreement, it is the Design-Builder's responsibility to furnish the City a renewal or replacement Certificate of Insurance, including all endorsements, not later than thirty (30) calendar days prior to the date of their expiration. Failure of the Design-Builder to provide the City with such renewal certificates shall be considered justification for the City to terminate this Agreement.

4.2.5. It is vitally important that all insurance coverages required under this Agreement be in effect throughout the entire period of this Agreement. If any of the insurance coverages required by this Agreement should reach the date of expiration indicated on the Certificate of

Insurance on record with the City, without the City having received satisfactory evidence in the form of a Certified Binder or a Certificate of Insurance, that the required insurance coverage has either been renewed or replaced, then the Design-Builder, unless notified in writing by the

City to continue, shall therefore automatically and without further notice from the City, stop performing all previously authorized services and work until such date as the City shall receive and approve satisfactory documentation that the expired insurance coverage has been renewed or replaced. During any time period that the Design-Builder shall fail to comply with the insurance requirements set forth in the Agreement, the City shall not be required to make, nor shall it make payment on any invoices submitted by the Design-Builder. Payment for any such invoices shall be made promptly by the City after the City receives and approves the renewal or replacement Certificates of Insurance. During any time period that the Design-Builder's services or work is suspended, as provided above, for failure to comply with the insurance requirements set forth in the Agreement, the Design-Builder shall not be entitled, as a result of such suspension, to any additional compensation or time to provide and perform the required services or work.

4.3. Comprehensive Automobile Liability

This insurance shall be written in comprehensive form and shall protect the Design-Builder and the additional insureds against all claims for injuries to members of the public and damage to property of others arising from the use of motor vehicle and shall cover operation on or off the site of all motor vehicles licensed for highway use, whether they are owned, non-owned, or hired. The liability limits shall not be less than:

4.3.1. Minimum limits of $1,000,000 combined single limit liability.

4.3.2. Coverage shall include owned vehicles, hired, leased, non-owned vehicles, employee non-ownership.

4.3.3. Notice of Cancellation and/or Restriction - The policy must be endorsed to provide the

City with thirty (30) days prior written notice of cancellation and/or restriction.

4.4. Commercial General Liability

This insurance shall be an “occurrence” type policy written in comprehensive form and shall protect the Design-Builder and the additional insureds against all claims arising from bodily injury, sickness, disease, or death of any person or damage to property of the City or others arising out of any act or omission of the Design-Builder or its agents, employees, or subcontractors. This policy shall also include protection against claims insured by usual bodily injury liability coverage, a “contractual liability” endorsement to insure the contractual liability assumed by the Design-Builder under its contract with the City, and “Completed Operations and

Products Liability” coverage (to remain in force for 2 years after final payment and subsequent to project completion). If the Design-Builder’s work, or work under its direction, requires blasting, explosive conditions, or underground operations, the comprehensive general liability coverage shall contain no exclusion relative to blasting, explosion, collapse of structures, or damage to underground property. The liability limits shall not be less than:

4.4.1. Minimum limits of $1,000,000 per occurrence combined single limit; $1,000,000 aggregate. This shall include premises and/or Operations, Independent Contractors, and

Subcontractors and/or Completed Operations, Broad Form Property Damage, and a Contractual

Liability Endorsement.

4.4.2. Contractual coverage applicable to this specific Agreement including any hold harmless and/or such indemnification agreement excluding professional acts.

4.4.3. Notice of Cancellation and/or Restriction - The policy must be endorsed to provide the

City with thirty (30) days prior written notice of cancellation and/or restriction.

4.5. Workers Compensation and Employer’s Liability

This insurance shall protect the Design-Builder against all claims under applicable state worker’s compensation laws. The Design-Builder shall also be protected against claims for injury, disease, or death of employees that, for any reason, may not fall within the provisions of a worker’s compensation law. This policy shall include an “all states” or “other states” endorsement. Exemption certificates shall be accepted if valid during the term of the contract, but only for those eligible corporate officers pursuant to Chapter 440 of the Florida Statutes.

Proof of workers’ compensation coverage must still be provided for all employees, subcontractors not eligible for exemption. The liability limits shall not be less than:

4.5.1. Employer's Liability with a minimum limit per accident in accordance with statutory requirements, or a minimum limit of $1,000,000 for each accident which limit is greater.

4.5.2. Notice of Cancellation and/or Restriction - The policy must be endorsed to provide the

City with thirty (30) days prior written notice of cancellation and/or restriction.

4.6. Professional Liability

The Design-Builder shall also purchase, maintain, and keep in full force, effect, and good standing, a professional liability/errors and omissions insurance policy having minimum limits of

$1,000,000, with a maximum deductible of $100,000 per claim and in the annual aggregate, or the Design-Builder shall provide the City with policy coverage wherein the insurer agrees to pay claims (up to the limits of coverage), and will thereafter recover the deductible from the insured

Design-Builder. The errors and omissions policy shall be in effect and shall insure the Design-

Builder's performance on City projects.

Coverage must include the following:

4.6.1. A minimum combined single limit of $1,000,000 aggregate

4.6.2. Should the Professional Liability Insurance Policy issued pursuant to the above requirements and limits be written, so as to provide an applicable deductible amount, or other exclusion or limitation as to the amount of coverage to be provided within the minimum coverage limits set forth above, the City shall hold the Design-Builder responsible and liable for any such difference in the amount of coverage provided by the insurance policy. In the event of any such deductible amount, exclusion or limitation, the Design-Builder shall be required to provide written documentation that is acceptable to the City establishing that the Design-Builder has the financial resources readily available to cover damages, injuries and/or losses which are not covered by the policy's deductible amounts, exclusions and/or limitations as stated above.

4.6.3. Employer's Liability with a minimum limit per accident in accordance with statutory requirements, or a minimum limit of $1,000,000 for each accident which limit is greater.

4.6.4. Notice of Cancellation and/or Restriction - The policy must be endorsed to provide the

City with thirty (30) days prior written notice of cancellation and/or restriction.

4.7. Fire and Extended Coverage Insurance (Builder's Risk)

4.7.1. The Design-Builder shall take out and maintain, as applicable, at their expense during the life of their Contract, “all risk” type Builder’s Risk Insurance satisfactory to the City, which shall protect the Design-Builder and the City as their interests may appear, for the following hazards to the Work, encompassing buildings and structures while in the course of construction including foundations, additions, attachments and all permanent fixtures belonging to and constituting a part of said buildings or structures, as well as materials and equipment suitably stored at the site and Design-Builder's construction equipment, materials, and temporary structures:

• Fire and lightning, vandalism, and malicious mischief.

• Extended coverage including windstorm, hail, explosion, riot, riot-attending strike, civil commotion, aircraft, vehicle, and smoke damage.

• The policy or policies shall also cover machinery if the cost of the machinery is included in the Contract. The amount of insurance must, at all times, be equal to the total

Contract Price shown in the Submittal for the construction of reverse osmosis wellfield production improvements, and other structures, plus the actual cash value of the insured property not shown in the Submittal, such as Design-Builder's construction equipment. The policy shall be in the name of the City, AE, and Design-Builder as their interests may appear, and shall also cover the interests of all

Subcontractor/Subconsultants performing work.

4.7.2. The Design-Builder shall provide the City with satisfactory evidence certifying that the foregoing insurance is in force; and such evidence shall include provisions that the insurance shall not be cancelled, allowed to expire, or be materially changed without giving the City thirty

(30) days advance notice.

4.8. Contractor Pollution/Environmental Liability

4.8.1. Such insurance shall cover the Design-Builder for liability resulting from pollution or other environmental impairment arising out of, or in connection with, work performed under this Agreement, or which arises out of, or in connection with this Agreement, including coverage for clean-up of pollution conditions and third-party bodily injury and property damage claims arising from pollution conditions. Such insurance shall also include transportation coverage and non-owned disposal site coverage. Coverage must either be on an occurrence basis; or, if on a claims-made basis, the coverage must respond to all claims reported within three years following the period for which coverage is required, and which would have been covered had the coverage been on an occurrence basis. Coverage shall not exclude the assessment, removal, remediation, transport and/or handling of hazardous materials, including but not limited to mold, asbestos, and lead. Said pollution liability policy shall include and list as "Additional Insured" the CITY and the CITY's council members, officials, officers, agents and employees; the insurance afforded to these additional insureds shall provide primary coverage for all claims covered thereby (including as applicable those arising from both ongoing and completed operations) on a non-contributory basis. Design- Builder shall obtain all necessary endorsements to support these requirements. The minimum limits (inclusive of any amounts provided by an umbrella or excess policy) shall be:

Minimum limits of $1,000,000 per occurrence and in the aggregate.

4.8.1. Such insurances shall cover the Design-Builder for liability resulting from pollution or other environmental impairment arising out of, or in connection with, work

5. SPECIAL CONDITIONS

5.1. PROCUREMENT REQUIREMENTS

This Agreement/Contract and the Owner's solicitation and award of the Agreement/Contract are subject to requirements contained in Chapter 62-503 (Revolving Loan Program) and /or Chapter

62-552, Florida Administrative Code as applicable.

5.2. RESOLUTION OF PROTESTS AND CLAIMS/DISPUTES

Resolution of Protests Concerning the Owner's Solicitation and/or Award of this

Agreement/Contract:

5.2.1 Protests concerning the Owner's solicitation and/or award of this…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .