Construction Agreement Summary
This is a Construction Agreement template between the City of Fort Myers, Florida and a contractor for design-build services related to the ROWTP Wellfield Expansion project, funded through SAHMW (State Aid for Houses of Worship or similar state funding mechanism). The project encompasses the design, permitting, and construction of potable water supply wellfield expansion, including siting and construction of potable water wells, raw water transmission mains, and fiber optic communication networks. The scope includes rehabilitation of existing water infrastructure assets, development of a resource management protocol integrating new and existing wells, and compliance with regulatory requirements from the City of Fort Myers, SFWMD (South Florida Water Management District), and FDEP (Florida Department of Environmental Protection). The design-build team must coordinate with a Construction Manager at Risk (CMAR) overseeing concurrent Reverse Osmosis Water Treatment Plant (ROWTP) improvements and shall provide a detailed project execution plan addressing schedule, budget optimization, and seasonal demands while minimizing impacts to surrounding residential neighborhoods. The contract specifies substantial completion and final completion timeframes measured in calendar days from the Notice to Proceed, with liquidated damages assessed at varying daily rates based on total contract amount, ranging from $904 per day for contracts under $299,999 to $10,224 plus 0.00005 of any amount over $40 million.
Pricing is established through a Schedule of Values submitted with the bid and remains firm for the initial contract term, with potential price adjustments limited to the Consumer Price Index or 3 percent maximum during renewal periods. The contractor shall maintain multiple insurance coverages including workers' compensation, commercial general liability at $1,000,000 minimum per occurrence, comprehensive automobile liability, professional liability, builders' risk insurance, and environmental/pollution liability insurance. Payment is issued within forty-five calendar days of receipt of a proper invoice, with progress payments made monthly during construction based on percentage of work completed and withheld at 10 percent until final completion. The contract is non-exclusive, allowing the City to procure similar services from other sources. The City reserves the right to purchase major equipment and materials directly from suppliers as a cost-saving measure through a Direct Material Purchase procedure, with the contractor responsible for managing coordination and compliance. Termination for convenience requires thirty days' written notice, while termination for cause requires ten days' notice. The contract documents establish order of precedence beginning with amendments, followed by permits, the agreement, solicitation addenda, plans/drawings, the original solicitation, contractor submittals, and certificates of insurance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION AGREEMENT
between
CITY OF FORT MYERS, FLORIDA
and >[Contractor]
Contents
| ARTICLE 1 – DEFINITIONS | 6 |
| ARTICLE 2 – TERM | 9 |
| ARTICLE 3 – CONTRACT DOCUMENTS | 9 |
| ARTICLE 4 – NOTICES | 9 |
| 4.1. Notices by Contractor to City. | 9 |
| 4.2. Notices by City to Contractor. | 9 |
| 4.3. Change or Address of Record | 10 |
| ARTICLE 5 - SCOPE OF SERVICES / WORK | 10 |
| ARTICLE 6 – CONTRACT AMOUNT AND TIME | 10 |
| 6.1. Contract Amount | 10 |
| 6.2. Contract Time & Liquidated Damages | 10 |
| ARTICLE 7 - RESERVED | 11 |
| ARTICLE 8 – NO THIRD-PARTY BENEFICIARIES | 11 |
| ARTICLE 9 - ASSIGNMENT, TRANSFER AND SUBCONTRACTS | 11 |
| ARTICLE 10 – REPRESENTATION OF THE CONTRACTOR | 12 |
| ARTICLE 11 – REPRESENTATION OF THE CITY | 12 |
| ARTICLE 12 - RELATIONSHIP BETWEEN PARTIES | 13 |
| ARTICLE 13 - OBLIGATIONS OF THE CONTRACTOR | 13 |
| 13.1. Contract Documents | 13 |
| 13.2. Warranty | 13 |
| 13.3. Conflicts, Errors, or Discrepancies | 13 |
| 13.4. Equipment | 13 |
| 13.5. Inspections and Testing | 13 |
| 13.6. Non-Discrimination | 14 |
| 13.7. Name Change | 14 |
| 13.8. Patents, Royalties and Copyrights | 14 |
| 13.9. Permits, Taxes, Licenses | 14 |
| 13.10. Record Retention | 15 |
| 13.11. Subcontractors | 15 |
| 13.12. Contractor to Repair Property Damage Caused by the Contractor | 15 |
| 13.13. Safety | 15 |
| 13.14. Safety Data Sheets (SDS) | 16 |
| 13.15. Contractor’s Project Manager | 16 |
| 13.16. Truth-In-Negotiations Certificate | 16 |
| 13.17. Quality Control | 16 |
| 13.18. Work Correction | 16 |
| 13.19. Reports | 16 |
| 13.20. All Drawings | 17 |
| 13.21. Qualified Personnel | 17 |
| 13.22. Removal of Personnel | 17 |
| 13.23. Equipment | 18 |
| 13.24. City’s Construction Project Management Platform Software | 18 |
| 13.25. Additional Services | 18 |
| ARTICLE 14 – OBLIGATIONS OF THE CITY | 18 |
| 14.1. Designation of City’s Representative | 18 |
| 14.2. Availability of City Information | 19 |
| 14.3. Availability of City Designated Representatives | 19 |
| 14.4. Access to City Property | 19 |
| 14.5. Plans Review | 19 |
| ARTICLE 15 – TIME AND SCHEDULE OF PERFORMANACE | 20 |
| 15.1. Notice to Proceed / Purchase Order | 20 |
| 15.2. Time of Performance | 20 |
| 15.3. Contractor Work Schedule | 20 |
| 15.4. Failure to Perform in a Timely Manner | 20 |
| ARTICLE 16 - NOTICE OF CLAIM / WAIVER OF REMEDIES / NO DAMAGE FOR DELAY | 20 |
| 16.1. Notice of Claims | 20 |
| 16.2. Remedies and No Damages for Delay | 21 |
| ARTICLE 17 – INSURANCE | 21 |
| 17.1. Insurance Terms and Conditions | 21 |
| 17.2. Insurance Coverages Required | 22 |
| 17.3. Insurance Certificate Required | 25 |
| ARTICLE 18 – INDEMNIFICATION | 26 |
| ARTICLE 19 – LAWS | 28 |
| 19.1. Governing Law / Venue | 28 |
| 19.2. Antitrust | 28 |
| 19.3. Conflict of Interest | 28 |
| >19.4. Continuing Contracts | 29 |
| >19.5. Discrimination | 29 |
| 19.6. E-Verify | 29 |
| 19.7. Florida Civil Rights Act (FCRA) | 29 |
| 19.8. Florida Public Records Law | 30 |
| 19.9. Human Trafficking | 30 |
| 19.10. Immigration Laws | 31 |
| 19.11. Scrutinized Companies | 31 |
| ARTICLE 20 – IMPROPER USE OF FACILITIES | 31 |
| ARTICLE 21 – WAIVER OF BREACH | 31 |
| ARTICLE 22 – OWNERSHIP OF DOCUMENTS | 31 |
| ARTICLE 23 -HEADINGS | 32 |
| ARTICLE 24 – RESERVATION OF RIGHTS | 32 |
| ARTICLE 25 - FAILURE TO ENFORCE | 32 |
| ARTICLE 26 - FORCE MAJEURE | 32 |
| ARTICLE 27 - RESERVED | 33 |
| ARTICLE 28 - SEVERABILITY | 33 |
| ARTICLE 29 – CONTINGENT FEES PROHIBITION | 33 |
| ARTICLE 30 - PURCHASE ORDERS / ORDERING | 33 |
| 30.1. Purchase Orders | 33 |
| >30.2. Ordering | 33 |
| >ARTICLE 31 - DIRECT MATERIAL PURCHASE | 33 |
| >ARTICLE 32 – DELIVERY | 37 |
| ARTICLE 33 – ACCEPTANCE OF MATERIALS/SERVICES | 37 |
| ARTICLE 34 – DISCONTINUED ITEMS | 37 |
| ARTICLE 35- RETURNS | 37 |
| >ARTICLE 36 – INTERNET/WEB-BASED SERVICES | 37 |
| >ARTICLE 37. SOFTWARE LICENSES | 37 |
| >ARTICLE 38- PRICE ADJUSTMENT | 37 |
| ARTICLE 39 – PAYMENT | 38 |
| 39.1. Discounts | 38 |
| 39.2 Invoicing | 38 |
| 39.3. Method of Payment | 39 |
| 39.4. Payment Dispute Resolution | 40 |
| 39.5. Payment When Services Are Terminated For Convenience | 40 |
| ARTICLE 40 - TERMINATION | 40 |
| 40.1. For Convenience | 40 |
| 40.2. For Cause | 40 |
| 40.3. Non-Appropriation | 40 |
| ARTICLE 41 - DISPUTE RESOLUTION | 40 |
| ARTICLE 42- CONTRACT EXECUTION | 41 |
| ARTICLE 43 – MISCELLANEOUS CLAUSES | 41 |
| 43.1. Non-Exclusive Contract | 41 |
| 43.2. Documents | 41 |
| 43.3. Independent Contractor | 42 |
| ARTICLE 44 – EXHIBITS | 42 |
| ARTICLE 45 - ACCEPTANCE | 43 |
This CONSTRUCTION AGREEMENT is made and entered into on the effective date (the date assigned in the Notice to Proceed) between the City of Fort Myers, Florida, a municipal corporation in the State of Florida hereinafter referred to as the "City", and > hereinafter referred to as " Contractor".
RECITALS
WHEREAS, the City desires to obtain the Services of said Contractor to provide and perform Services as further described hereinafter concerning the solicitation to be referred to and identified as >Solicitation Title and Number (title, #), the Contractor hereby agrees to provide and perform the services required and necessary to complete the services and work as set forth in these documents, and WHEREAS, the Contractor hereby certifies that Contractor has been granted and possesses valid, current licenses to do business in the State of Florida, in Lee County, and the City of Fort Myers, issued by the respective State Boards and Government Agencies responsible for regulating and licensing the Services to be provided and performed by the Contractor pursuant to this Agreement; and NOW, THEREFORE in consideration of the mutual covenants, terms and provisions contained herein, the parties hereto agree that with the mutual acceptance of this Agreement, as indicated hereinafter by the execution of this Agreement by both parties, that a Contract shall exist between both parties consisting of:
ARTICLE 1 – DEFINITIONS
ADDENDA - A written change, addition, alteration, correction, or revision to a solicitation.
ADDITIONAL SERVICES - Any additional services that the City may request and authorize, in writing, which are not included in the initial Scope of Services.
AMENDMENT/SUPPLEMENTAL AGREEMENT - A formal, written change to an executed contract that modifies, adds to, or deletes terms, conditions, scope of work, period of performance, pricing, or other provisions. [All Contract Amendments must be executed by authorized representatives of both the Contractor and the City to be valid and enforceable. Verbal agreements or informal communications shall not be considered binding amendments.
APPROVAL - When applied to approval from the City, this term shall mean approval which is, at a minimum, evidenced by a written document authored or initialed by the City and subject to the formalities imposed by specific provisions in this Contract.
BONDS - Solicitation, Performance, and Payment Bonds and other instruments of security furnished by the Contractor and their Surety in accordance with the Contract Documents and in accordance with Florida Law.
CHANGE ORDER - A written directive issued after contract execution that modifies the scope of work, contract price, contract time, or other terms and conditions of the construction contract. A Change Order must be authorized in writing by the City, approved by City Council, and executed by the Contractor before the additional or revised work is performed.
Construction Change Order: A written directive issued after contract execution that modifies the scope of work, contract price, or contract time of a construction contract. Must be approved in writing by the City and executed prior to performing revised work.
Purchase Order (PO) Change Order: A written change to a previously issued Purchase Order (goods/services) that adjusts quantities, delivery schedules, or pricing. Must be authorized under City procurement procedures. Becomes an official amendment to the original PO once approved.
CITY – The City of Fort Myers, a municipal corporation within the State of Florida, its officers, officials, agents, and representatives. Also known as Owner.
COMMENCEMENT DATE - is the Notice to Proceed Date shown in the Notice to Proceed.
CONTRACT ADMINISTRATOR – The City employee designated in the Contract Documents who is responsible for the day-to-day administration and oversight of the contract on behalf of the City. The Contract Administrator serves as the primary point of contact for the Contractor, monitors contractor performance, ensures compliance with contract terms, reviews invoices or applications for payment, and coordinates with other departments as necessary. The Contract Administrator does not have authority to amend the contract, approve Change Orders, or bind the City unless expressly authorized in writing.
CONTRACT PRICE - The total monies payable by City to the Contractor under the terms and conditions of the Contract Documents.
CONTRACT TIME - The number of calendar days in the Construction Phase stated in the Contract Documents for the completion of the Work, including Saturdays, Sundays and Holidays, commencing with the date of Notice to Proceed, and ending with scheduled date of Final Acceptance.
DAY - One (1) calendar day when used in the Contract, measured from midnight to the next midnight.
DEFECTIVE - Work that is unsatisfactory, deficient, or faulty; that fails to conform to the requirements of the Contract Documents; that does not meet applicable standards, tests, inspections, or approvals referenced in the Contract; or that has been damaged prior to final payment, unless such damage is the City's responsibility after Substantial Completion.
DRAWINGS/PLANS - Drawings and plans showing the character and scope of the Work to be performed, and which have been prepared or approved by the AE and are referred to in the Contract Documents. “Plans” generally refer to an overall subject, while “Drawings” refer to specifics.
EFFECTIVE DATE - The date indicated in the Notice to Proceed on which it becomes effective, but if no such date is indicated, it is the date on which the Contract is executed by the final party.
FINAL COMPLETION - The point at which all work required under the contract, including punch list items, cleanup, testing, inspections, and submission of all closeout documentation (such as warranties, as-builts, O&M manuals, and lien releases), has been fully and satisfactorily completed by the Contractor. Final Completion must be verified and accepted in writing by the City and is a prerequisite for Final Acceptance and final payment.
NOTICE OF AWARD - The written notice by the City to the apparent successful Contractor notifying them that they were the top choice for the project and should expect to be contacted by the Department to begin negotiations.
NOTICE TO PROCEED - A written notice given by the City to the Contractor (with a copy to AE, if applicable) fixing the date on which the Contract Time will commence to run and on which the Contractor shall start to perform his obligations under the Contract Documents.
PROCUREMENT MANAGER - Chief Procurement Officer representing the City.
PROJECT - The total construction of which the Work to be provided under the Contract Documents may be the whole, or a part as indicated elsewhere in the Contract Documents.
PROJECT MANAGER - The Project Manager is the individual designated in writing by the City to act as the City's representative and liaison for this Agreement. The Project Manager shall provide coordination, guidance, review, recommendations, and communication between the City and the Consultant regarding the Professional Services, work, and materials to be provided under this Agreement, including all authorized Amendments, Supplemental Agreements, and Change Orders.
The Contractor refers to the individual or firm providing Professional Services under this Agreement, who, by executing this Agreement, assumes full legal responsibility for performing all required services, work, and materials. This includes the work of all Subconsultants and Subcontractors engaged by the Contractor.
The Project Manager shall not issue any verbal or written instruction to the Contractor that modifies or affects:
1. The Scope of Services to be performed;
2. The schedule for commencement or completion of services;
3. The compensation due to the Consultant.
The Project Manager is responsible for reviewing all Contractor requests related to payment for completed work and expenses and shall make recommendations based on the terms of this Agreement and any approved Amendments, Supplemental Agreements, or Change Orders.
SITE – The area on which the Contractor's construction Work is to be performed and such other areas that may be designated as such by the Final Construction Documents, and upon which the Project and associated improvements are to be constructed by the Contractor.
SOLICITATION - An Invitation to Bid, Request for Proposals, Request for Statement of Qualifications, or any document used to obtain submissions for the purpose of entering into a contract.
SCOPE - Written technical descriptions of materials, equipment, services, construction, standards, and workmanship as requested to explain the needs of the City.
SUBCONTRACTOR - Any individual, firm, or entity engaged by the Contractor to perform a portion of the work or provide services, labor, or materials under the terms of the Contract. Subcontractors are not in direct contractual privity with the City and shall operate under the supervision and responsibility of the Contractor. The Contractor remains fully liable for the performance of all Subcontractors and must obtain prior written approval from the City before engaging any Subcontractor, as required by the Contract Documents.
SUBMITTAL - all documents, drawings, diagrams, schedules, samples, test results, and related data prepared by the Contractor or its team. This includes work by Subconsultants/Subcontractors, manufacturers, suppliers, or distributors.
Submittals show details of the Work and may include brochures, product sheets, charts, and instructions. They describe materials, equipment, or systems proposed for use.
SUBSTANTIAL COMPLETION - The stage in the progress of the Work when the Project, or a designated portion thereof, is sufficiently complete in accordance with the Contract Documents so that the City can occupy or utilize the Work for its intended purpose. Substantial Completion shall be established by a written certificate issued by the City or its designated representative and may be subject to the completion of minor punch list items. Substantial Completion triggers the start of certain obligations, such as the warranty period, and may allow for partial release of retainage, as permitted by the contract.
SUPPLEMENTAL CONDITIONS - The part of the Contract Documents which amends or supplements General Conditions.
SURETY - A pledge or guarantee by an insurance company, bank, individual, or corporation on behalf of the Contractor that protects against default or failure of the contracted Contractor to satisfy the contractual obligations.
UNDERGROUND FACILITIES - All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels or other such facilities or attachments, and any encasements containing such facilities which have been installed underground to furnish any of the following services or materials, electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, sewage and drainage removal, traffic or other control systems or water.
WORK - The entire completed construction, or the various separately identified parts thereof, required to be furnished under the Contract Documents. Work is the result of performing services, furnishing labor and furnishing and incorporating materials and equipment into the construction, all as required by the Contract Documents.
ARTICLE 2 – TERM
This Agreement will be in effect on the effective date and shall end >__ days later, unless amendments have otherwise been executed.
The City has the right to cancel or terminate this contract as described in these documents.
ARTICLE 3 – CONTRACT DOCUMENTS
The Contract Documents, which comprise the entire agreement between the City and the Contract Manager concerning the Work consist of this document plus: Attachment A-Scope of Services, Attachment B-Bid Schedule/ Schedule of Values and also incorporate by reference in order of precedence:
1) Amendments created after execution of the Contract 2) Permits (if applicable), 3) This Agreement 4) Solicitation addenda and written questions/answers via OpenGov Q&A incorporated by reference 5) Plans/Drawings, incorporated by reference 6) Solicitation, incorporated by reference 7) Contractor(s) submittal, incorporated by reference 8) Certificates of Insurance, incorporated by reference.
If there is a conflict between the contract and solicitation the more stringent applies.
ARTICLE 4 – NOTICES
4.1. Notices by Contractor to City.
All notices required and/or made pursuant to this Agreement to be given by the Contractor to the City shall be in writing and shall be given to the following electronic email addresses of record:
procurementservices@fortmyers.gov, cc@fortmyers.gov, and legalservice@fortmyers.gov.
Copy to:
City Attorney's Office, City of Fort Myers, 2200 Second Street, Fort Myers, FL 33901
4.2. Notices by City to Contractor.
All notices required and/or made pursuant to this Agreement to be given by the City to the Contractor shall be made in writing and shall be provided electronically to the email address below:
Contractor’s Name: >[Contractor] Point if Contact: >[contact] Mailing Address: >[address] Phone: >[phone] Email: >[email]
4.3. Change or Address of Record
Either party may change its address of record by written notice to the other party given in accordance with the requirements of this Article.
ARTICLE 5 - SCOPE OF SERVICES / WORK
The Contractor hereby agrees to provide and perform the Services required necessary to complete the services and work as set forth in these documents.
ARTICLE 6 – CONTRACT AMOUNT AND TIME
Contractor shall complete all Work as specified or indicated in the Contract Documents.
6.1. Contract Amount
City shall pay Contractor for completion of the Work in accordance with the Contract Documents in the amount of Contract Amount ($xxxx.xx).
6.2. Contract Time & Liquidated Damages
6.2.1. Substantial/Final Completion. The Work will be substantially completed within >___ calendar days from the date of the Notice to Proceed and finally completed within >___ calendar days from the date of the Notice to Proceed.
6.2.2. Liquidated Damages. Liquidated Damages
The "Commencement Date” shall be established in the Notice to Proceed to be issued by the City. Contractor shall commence the work upon the issuance of the Notice to Proceed. No Work shall be performed at the Project site prior to the Commencement Date. Any Work performed by Contractor prior to the commencement Date shall be at the sole risk of Contractor.
The Work shall be substantially completed within the time agreed upon by the City and Contractor. The date of substantial completion of the Work (or designated portions thereof) is the date certified by the City when construction is sufficiently complete, in accordance with the Contract Documents, so the City can occupy or utilize the Work (or designated portions thereof) for the use for which it is intended. The Work shall reach final completion and be ready for final acceptance by the City within the time specified.
The Work under this contract will be substantially completed within Substantial Completion calendar days after the notice to proceed is issued and final completion will occur within final completion calendar days after notice to proceed is issued.
The City and Contractor recognize that since time is of the essence for any work under this Agreement, the City will suffer financial loss if the Work is not substantially completed with the time specified. Should Contractor fail to substantially complete the Work within the specified time period, the City shall be entitled to assess as liquidated damages but not as a penalty, an amount specified below for each calendar day thereafter until substantial completion is achieved:
Total Contract Amount Per Day $299,999 and under......................................................$904 $300,000 but less than $2,000,000..............................$1,685 $2,000,000 but less than $5,000,000...........................$2,667 $5,000,000 but less than $10,000,000.........................$3,813 $10,000,000 but less than $20,000,000.......................$5,021 $20,000,000 but less than $40,000,000.......................$7,442 $40,000,000 and over...............$10,224 plus 0.00005 of any amount over $40 million (Round to nearest whole dollar) The Project shall be deemed to be substantially completed on the date the Architect/Engineer issues a Certificate of Substantial Completion pursuant to the terms hereof. Contractor hereby expressly waives and relinquishes any right which it may have to seek the above noted liquidated damages as a penalty, which the parties agree represents a fair and reasonable estimate of the City’s actual damages at the time of contracting if Contractor fails to substantially complete the Work in a timely manner.
When any period of time is referenced by days herein, it shall be computed to exclude the first day and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a legal Holiday, such day shall be omitted from the computation, and the last day shall become the next succeeding day which is not a Saturday, Sunday or legal holiday.
ARTICLE 7 - RESERVED
ARTICLE 8 – NO THIRD-PARTY BENEFICIARIES
Both parties explicitly agree, and this Agreement states that no third-party beneficiary status or interest is conferred to, or inferred to, any other person or entity.
ARTICLE 9 - ASSIGNMENT, TRANSFER AND SUBCONTRACTS
The Contractor shall not assign or transfer any of its rights, benefits, or obligations, except for transfers that result from:
9.1. the merger or consolidation of the Contractor with a third party; or
9.2. the disestablishment of the Contractor 's professional practice and the establishment of the successor Contractor. Nor shall the Contractor subcontract any of its service obligations hereunder to third parties without prior written approval of the City. The Contractor shall have the right, subject to the City’s prior written approval, to employ other persons and/or firms to serve as Subcontractor to City in connection with the Contractor performing services and work pursuant to the requirements of this Agreement. The Contractor must notify the Procurement Services Department of any change, complete a new vendor registration form, provide an updated W-9, provide an updated certificate of insurance, provide a new E-Verify Memorandum of Understanding, and provide written notification of such change on official company letterhead.
ARTICLE 10 – REPRESENTATION OF THE CONTRACTOR
In order to induce City to enter into this Agreement Contractor makes the following representations:
10.1. Contractor has familiarized themselves with the nature and extent of the Contract Documents, Work, site, locality, and all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance or furnishing of the Work.
10.2. Contractor has correlated the results of all such observations, examinations, tests, reports and studies with the terms and conditions of the Contract Documents.
10.3. Contractor has given City written notice of all conflicts, errors, or discrepancies that he has discovered in the Contract Documents, and the written resolution thereof by City is acceptable to Contractor.
ARTICLE 11 – REPRESENTATION OF THE CITY
The Contractor in providing and performing the services and work required pursuant to this Agreement, and Amendments thereto, shall only represent the City in the manner and to the extent specifically set forth in writing in this Agreement or Amendments thereto, and as provided in any written Supplemental Agreement(s), and Change Order(s) issued there under.
In the event the Contractor’s services or work involves construction contract administrative support services, the Contractor is not authorized to act on the City’s behalf, and shall not act on the City’s behalf, in such a manner as to result in change(s) to (1) the cost or compensation to be paid the construction Contractor, or (2) the time for completing the work as required and agreed to in the construction contract, or (3) the scope of the work set forth in the construction contract documents, unless such representation is specifically provided for, set forth and authorized in this Agreement or Amendment thereto.
The City will neither assume nor accept any obligation, commitment, responsibility or liability, which may result from representation by the Contractor, not specifically provided for and authorized as stated hereinabove.
ARTICLE 12 - RELATIONSHIP BETWEEN PARTIES
This Contract does not create an employer/employee relationship between the City and Contractor. Contractors are independent of the City and will be in control of the means and the method in which the requested work is performed. Contractor will be solely responsible for payment of all federal, state, and local income tax, and self-employment taxes, arising from this Contract. The City will not make deductions from payments due, for such taxes, or for social security, unemployment insurance, worker’s compensation, or other employment or payroll taxes. Contractor will also be responsible for the performance of their Subcontractors.
ARTICLE 13 - OBLIGATIONS OF THE CONTRACTOR
13.1. Contract Documents
Contractor has familiarized themselves with the nature and extent of the Contract Documents, Work, site, locality, and all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance or furnishing of the Work.
13.2. Warranty
See Construction Supplemental Conditions 16.1.
13.3. Conflicts, Errors, or Discrepancies
See Construction Supplemental Conditions 4.3.
13.4. Equipment
The Contractor is solely responsible for all damage or loss by fire, theft or otherwise, to materials, tools, equipment, and consumables, left on City property by the Contractor.
13.5. Non-Discrimination
Contractor certifies that they will:
13.5.1. Implement an employment nondiscrimination policy prohibiting discrimination in the performance of the contract in the hiring, discharging, promoting or demoting, matters of compensation, or any other employment-related decision or benefit on account of actual or perceived race, ethnicity, color, religion, gender, disability, age, military status, sexual orientation, gender identity, gender expression, or marital or familial status;
13.5.2. Not discriminate in the performance of the contract on account of actual or perceived race, ethnicity, color, religion, national origin, gender, disability, age, military status, sexual orientation, gender identity, gender expression, or marital or familial status;
13.5.3. Provide a harassment-free workplace, with any allegation of harassment given priority attention and action by management;
13.5.4. Incorporate the foregoing requirements in all subcontracts related to its contract with the City.
13.6. Name Change
If a firm changes its legal business structure through a merger, acquisition, or sale; has a legal name change, a change in principal location of conducting business; a change in status with the Secretary of State filing, a change in officers, or any other change that affects the structure of the business; a change in the level of service being offered, the nature of the products or service offered; or any deviation from what was presented by the firm to the City when being considered for this contract; the firm shall immediately notify the City's Procurement Services Department at procurementservices@fortmyers.gov.
13.7. Record Retention
See Construction Supplemental Conditions 19.
13.8. Subcontractors
See Construction Supplemental Conditions 8.5.
13.9. Contractor to Repair Property Damage Caused by the Contractor See Construction Supplemental Conditions 8.14.3.
13.10. Safety
See Construction Supplemental Conditions 8.14.
13.11. Safety Data Sheets (SDS)
Contractor will supply Safety Data Sheets (SDS) with each initial delivery of any materials defined by the State of Florida or the Federal Government as being toxic, harmful, or hazardous.
13.12. Contractor’s Project Manager
The Contractor agrees to employ and designate, in writing, a qualified and, if required by law, a licensed professional to serve as the Contractor 's Project Manager. The Contractor 's Project Manager shall be authorized and responsible to act on behalf of the Contractor with respect to directing, coordinating and administering all aspects of the work to be provided and performed under this Agreement and Amendment(s) thereto. The Contractor's Project Manager shall have the full authority to bind and obligate the Contractor on any matter arising under this Agreement and its Amendment(s) unless substitute arrangements have been furnished to the City in writing. The Contractor agrees that the Project Manager shall devote whatever time is required to satisfactorily direct, supervise and manage the work provided and performed by the Contractor throughout the entire period this Agreement is in effect. The person selected by the Contractor to serve as the Contractor 's Project Manager shall be subject to prior approval and acceptance of the City.
13.13. Truth-In-Negotiations Certificate
The City may request that the Contractor execute a "Truth-in-Negotiations Certificate". The Certificate shall state that wage rates and other factual unit costs supporting the compensation are accurate, complete and current at the time this Agreement is executed. The original contract price and any additions thereto shall be adjusted to exclude any significant sums by which the City determines the contract price was increased due to inaccurate, incomplete or non-current wage rates of other factual unit costs.
13.14. Quality Control
Contractor shall institute and maintain throughout the contract period a properly documented quality control program designed to ensure that the materials are provided in accordance with the contract. The program shall include providing daily supervision and conducting frequent inspections of the Contractor's staff and ensuring that accurate records are maintained. The records so created shall be open to inspection by the City.
13.15. Work Correction
See Construction Supplemental Conditions 16.7.
13.16. Reports
13.16.1. Contractor has studied carefully all reports of exploration and tests of subsurface conditions and drawings of physical conditions which are identified in the Supplementary Conditions (if applicable) and the Terms & Conditions, and accepts the determination set forth in the Supplementary Conditions of the extent of the technical data contained in such reports and drawings upon which Contractor is entitled to rely.
13.16.2. when requested by the City, the Contractor shall furnish progress reports as required.
13.16.3. Examinations, Investigations, and Tests see Construction Supplemental Conditions 2.4.
13.17. All Drawings
see Construction Supplemental Conditions 18.6.
13.18. Qualified Personnel
The Contractor agrees that any work to be performed relate to a work which, under Florida Statutes, requires a license, certificate of authorization or other form of legal entitlement to engage in such work, to employ and/or retain only qualified personnel to be in responsible charge of all work to be provided pursuant to this Agreement.
The Contractor shall employ people to work at the City’s facilities who are neat, clean, well-groomed and courteous.
13.19. Removal of Personnel
The Contractor agrees, within thirty (30) calendar days of receipt of a written request from the City, to promptly remove and replace the Contractor's Project Manager, or any other personnel employed or retained by the Contractor, or personnel of the Subcontractor engaged by the Contractor to provide and/or perform services and/or work pursuant to the requirements of this Agreement, who the City shall request, in writing, be removed, which request may be made by the City with or without cause. However, notwithstanding the above, nothing herein shall interfere with the Contractor's right to terminate its employees or employees’ right to terminate their employment with the Contractor.
13.20. Equipment
The Contractor is solely responsible for all damage or loss by fire, theft or otherwise, to materials, tools, equipment, and consumables, left on City property by the Contractor.
13.25. Additional Services
Should the City request the Contractor to provide and perform Services for this project, which are not set forth in the Scope, the Contractor agrees to provide and perform such Additional Services as may be agreed to in writing by both parties to this Agreement.
Such Additional Services shall constitute a continuation of the Services covered under this Agreement and shall be provided and performed in accordance with the covenants, terms, and provisions set forth in this Agreement and Amendment thereto.
Additional Services shall be administered and authorized as "Supplemental Agreements" or "Change Orders" under the Agreement. The Contractor shall not provide or perform, nor shall the City incur or accept any obligation to compensate the Contractor for any Additional Services unless, and until, a written "Supplemental Agreement" or "Change Order" shall have been agreed to and executed by both parties.
Each such "Supplemental Agreement" or "Change Order" shall set forth a comprehensive, detailed description of: (1) the Scope of the Additional Services requested; (2) the basis of compensation; and (3) the period of time and/or schedule for performing and completing said Additional Services.
The duties and obligations imposed upon the Contractor by this Agreement, and the rights and remedies available hereunder, shall be in addition to, and not a limitation of, any otherwise imposed or available by law or statute.
ARTICLE 14 – OBLIGATIONS OF THE CITY
14.1. Designation of City’s Representative
The City agrees, after the execution of this Agreement, to promptly advise the Contractor, in writing, of the person designated to serve and act as the City’s Representative. Such notification shall be provided to the Contractor by the City’s Contract Administrator.
The City agrees, after the execution of this Agreement, to promptly advise the Consultant, in writing, of the person designated to serve and act as the City’s Representative. Such notification shall be provided to the Consultant by the City’s Contract Administrator.
All services will be approved by the City’s Representative. All work modifications require written approval by the City’s Representative. No work will proceed until authorized by the City’s Representative and the Consultant has received a purchase order (PO) from Procurement Services. At times Consultant will meet the City’s Representative at the worksite, at no cost, to verify information, requirements, make recommendations, or verify specifications.
The City’s Representative assigned to this project is >[Proj Mgr] and they can be reached after a NOTICE OF AWARD is issued at >[Contact Email] or >[Contact Phone].
14.2. Availability of City Information
14.2.1. Project Guidelines and Criteria
Guidelines to the Contractor regarding requirements the City has established, or suggests relative to the Project including, but not limited to, such items as: goals, objectives, constraints, and any special financial, budgeting, space, site, operational, equipment, technical, construction, time and scheduling criteria are set forth in "Project Guidelines and Criteria" is attached and made a part of this Agreement.
14.2.2. City to Provide Pertinent Reference Material
At the Contractor’s request, the City agrees to provide to the Contractor, at no cost, all pertinent information known to be available to the City to assist the Contractor in providing and performing the required services. Such information may include, but not be limited to: previous reports, plans, drawings and specifications, maps; property, boundary, easement, right-of-way, topographic, reference monuments, control points, plats and related survey data; data prepared, or services furnished by others to the City such as sub-surface investigations, laboratory tests, inspections of natural and man-made materials, property appraisals, studies, designs and reports.
14.3. Availability of City Designated Representatives
The City agrees that the City Representative shall be available within a reasonable period of time, with reasonable prior notice given by the Contractor, to meet and/or consult with the Contractor on matters pertaining to the services to be provided and performed by the Contractor. The City further agrees to respond within a reasonable period-of-time to written requests submitted by the Contractor.
14.4. Access to City Property
The City agrees to provide the Contractor with access within a reasonable period of time to City property, facilities, buildings and structures, to enable the Contractor to provide and perform the required Services and work pursuant to this Agreement. Such rights of access shall not be exercised in such a manner, or to such an extent, as to impede or interfere with City operations, or the operations carried on by others under a lease, or other contractual arrangement with the City, or in such a manner as to adversely affect public health and safety. Such access may, or may not be, within the Contractor's normal office and/or field workdays and/or work hours.
14.5. Plans Review
If applicable, Plan reviews by City staff is only for conformance with the design concept of the project and for compliance with the information given in the contract documents, and shall not extend to means, methods, techniques, sequences, or procedures of construction or to safety precautions or programs incident. The review does not relieve the Contractor from responsibility for errors or omissions or from responsibility for having the design comply with the provisions of all codes having jurisdiction.
ARTICLE 15 – TIME AND SCHEDULE OF PERFORMANACE
15.1. Notice to Proceed / Purchase Order
See Construction Supplemental Conditions 2.5.
15.2. Time of Performance
Should the Contractor be obstructed or delayed in the execution or completion of its obligations under this Agreement and its Amendment(s), as a result of causes beyond the control of the Contractor, or its Subcontractor(s) and not due to their fault or neglect, the Contractor shall notify the City, in writing, within five (5) calendar days after the commencement of such delay, stating the cause(s) and requesting an extension of the Contractor’s time of performance. Upon receipt of the Contractor’s request for an extension of time, the City will determine with the Contractor, within 7 days, the length of extension and legitimacy of cause.
15.3. Contractor Work Schedule
The Contractor shall be required, as a condition of this Agreement, to prepare and submit to the City, on a monthly basis, commencing with the issuance of the Notice to Proceed, a Contractor’s Work Schedule. Said Schedule shall be updated at each pay request. The Work Schedule shall set forth the time and manpower scheduled for all of the various phases and/or tasks required to provide, perform and complete all of the services and work required for completion of the various phases, and/or tasks of the project services set forth and described in this Agreement, pursuant to this Agreement in such a manner that the Substantial Completion ’s planned and actual work progress can be readily determined. The Contractor’s Work Schedule of planned and actual work progress shall be updated and submitted by the Contractor to the City on a monthly basis.
15.4. Failure to Perform in a Timely Manner
Notwithstanding anything to the contrary in paragraph "Contractor Work Schedule" above, should the Contractor fail to commence, provide, perform and/or complete any of the services and work required pursuant to this Agreement in a timely and diligent manner, the City may consider such failure as justifiable cause to terminate this Agreement. As an alternative to termination, the City at its option, may, upon written notice to the Contractor, withhold any or all payments due and owing to the Contractor, not to exceed the amount of the compensation for the work in dispute, until such time as the Contractor resumes performance of his obligations in such a manner as to get back on schedule in accordance with the time and schedule of performance requirements set forth in the Agreement, or any Supplemental Agreement(s), or Change Order(s) or Amendment(s) issued thereto.
ARTICLE 16 - NOTICE OF CLAIM / WAIVER OF REMEDIES / NO DAMAGE FOR DELAY
16.1. Notice of Claims
16.1.1. The City's liability to Contractor for any claims arising out of or related to the subject matter of this contract, whether in contract or tort, including, but not limited to, claims for extension of construction time, for payment by the City of the costs, damages or losses because of changed conditions under which the work is to be performed, or for additional work, shall be governed by the following provisions:
16.1.1.1. All claims must be submitted as a Request for Change Order in the manner as provided herein;
16.1.1.2. The Contractor must submit a Notice of Claim to City and to the Engineer within 20 days of when the Contractor was or should have been aware of the occurrence of the event giving rise to the claim; and
16.1.1.3. Within 10 days of submitting its Notice of Claim, the Contractor shall submit to the City its Request for Change Order, which shall include a written statement of all details of the claim, including a description of the work affected. The Contractor agrees that the City shall not be liable for any claim that the Contractor fails to submit as a Request for Change Order as provided in this paragraph.
16.1.2. After receipt of a Request for Change Order, the City, in consultation with the Engineer, shall deliver to the Contractor its written determination of the claim. As to matters subject to the determination by City (not actions for breach of contract or tort) the City's written decision shall be final unless the Contractor, within thirty (30) days of the Contractor's receipt of the City's determination, delivers to the City a written objection thereto. If, after good faith efforts to resolve the matter, the parties are unable to agree, the matter shall be submitted to arbitration pursuant to the Construction Industry Arbitration Rules of the American Arbitration Association. Any dispute not resolved may be submitted to binding arbitration pursuant to AAA rules, unless both parties agree otherwise.
16.2. Remedies and No Damages for Delay
For work the Contractor performs with its own forces, and in addition to the adjustments provided for in "Fee", the Contractor's exclusive remedy for delays in performance of the construction caused by events beyond its control, except for delays claimed to be caused by or attributable to the City or the Engineer, including claims based on breach of contract or negligence, shall be a claim submitted in compliance with (1) above, for an extension of the scheduled construction time. In the event of a change in such work, the Contractor's claims for adjustments in the contract sum are limited exclusively to its actual costs for such changes plus 5% for profit. Except as set forth herein, the Contractor expressly agrees that the foregoing constitute its sole and exclusive remedies for delays and changes in such work and eliminate any other remedies for claim for increase in the contract price, delays, changes in the work, damages, losses or additional compensation.
ARTICLE 17 – INSURANCE
17.1. Insurance Terms and Conditions
17.1.1. The Contractor shall obtain and maintain such insurance as will protect the City from: (1) claims under workers' compensation laws, disability benefit laws, or other similar employee benefit laws; (2) claims for damages because of bodily injury, occupational sickness or disease or death of his or her employees including claims insured by usual personal injury liability coverage; (3) claims for damages because of bodily injury, sickness or disease, or death of any person other than his employees including claims insured by usual personal injury liability coverage; and (4) from claims for injury to or destruction of tangible property including loss or use resulting there from; any or all of which claims may arise out of, or result from, the services, work and operations carried out pursuant to and under the requirements of this Agreement, whether such services, work and operations be by the Contractor, its employees, or by any Subcontractor/Subcontractors, or anyone employed by or under the supervision of any of them, or for whose acts any of them may be legally liable.
17.1.2. Subcontractor/Subcontractors. Unless expressly specified otherwise in this solicitation, a Contractor and its Subcontractor/Subcontractors of any tier will be required at their own expense to maintain in effect at all times during the performance of the work insurance coverages with limits not less than those set forth below with insurers and under forms of policies satisfactory to the City. It shall be the responsibility of the Contractor to maintain the required insurance coverages and to assure that Subcontractor/Subcontractors maintain required insurance coverages at all times. Failure of a Contractor to maintain adequate coverage shall not relieve it of any contractual responsibility or obligation. The requirements specified herein as to types, limits, and City’s approval of insurance coverage to be maintained by a Contractor and its Subcontractor/Subcontractors are not intended to and shall not in any manner limit or qualify the liabilities and obligations assumed by the Contractor and its Subcontractor/Subcontractors under a contract. Any insurance carried by the City that may be applicable shall be deemed to be excess insurance and the Contractor's insurance primary for all purposes despite any conflicting provision in the Contractor's policies to the contrary.
17.1.3. The Contractor shall obtain, have, and maintain during the entire period of this Agreement, all such insurance policies as are set forth and required herein.
17.1.4.The insurance coverage to be obtained by the Contractor, as set forth in Agreement for: (1) Worker's Compensation; (2) Commercial General Liability; (3) Commercial Automobile Liability; and (4) Professional Liability is understood and agreed to cover any and all of the services or work set forth in Exhibit “A” of this Agreement, or in any and all subsequently executed Change Orders, or Supplemental Agreements. If the total amount of insurance coverage established in, and required by, a Change Order or Supplemental Agreement exceeds the amount of insurance coverage carried by the Contractor, then the Contractor shall be required and expected to acquire such additional insurance, and the compensation established for the Change Order, or Supplemental Agreement, shall include consideration of any additional premium cost incurred by the Contractor to obtain such additional insurance coverage.
17.1.5. The purchasing of any insurance on the behalf of the City shall not waive any defense under Sovereign Immunity.
17.1.6. Additional Insureds. All insurance coverages furnished under a contract except Workers’ Compensation, Employers’ Liability and any Professional Liability Policy shall include the City and its officers, elected officials, and employees as additional insureds with respect to the activities of the Contractor and its Subcontractor/Subcontractors. The City shall not by reason of their inclusion under these policies incur liability to the insurance carrier for payment of premium for these policies.
If this solicitation is funded in whole or in part by the Florida Department of Transportation, they will be included as an additional insured on all insurance certificates.
17.1.7. Waiver of Subrogation. The Contractor and its Subcontractor/Subcontractors shall require their insurance carriers, with respect to all insurance policies, to waive all rights of subrogation against the City, its officers, elected officials, agents, and employees and against other Contractor and Subcontractor/Subcontractors.
17.2. Insurance Coverages Required
Insurance will be provided by the Contractor. If required, the awarded Contractor (and its Subcontractors to the same extent and on the same terms as set forth below for Contractor) shall maintain the following coverages and furnish the certificate of insurance on the policies and renewals thereof which indicate that insurance coverage has been obtained meeting the requirements of the contract.
17.2.1. Comprehensive Automobile Liability
This insurance shall be written in comprehensive form and shall protect the Contractor and the additional insureds against all claims for injuries to members of the public and damage to property of others arising from the use of motor vehicle and shall cover operation on or off the site of all motor vehicles licensed for highway use, whether they are owned, non-owned, or hired. The liability limits shall not be less than:
17.2.1.1. Minimum limits of $1,000,000 combined single limit liability.
17.2.1.2. Coverage shall include owned vehicles, hired, leased, non-owned vehicles, employee non-ownership.
17.2.1.3. Employer's Liability with a minimum limit per accident in accordance with statutory requirements, or a minimum limit of $1,000,000 for each accident which limit is greater.
17.2.1.4. Notice of Cancellation and/or Restriction - The policy must be endorsed to provide the City with thirty (30) days prior written notice of cancellation and/or restriction.
17.2.2. Commercial General Liability
This insurance shall be an “occurrence” type policy written in comprehensive form and shall protect the Contractor and the additional insureds against all claims arising from bodily injury, sickness, disease, or death of any person or damage to property of the City or others arising out of any act or omission of the Contractor or its agents, employees, or Subcontractors.
This is the start of the file's text. The full file is on GovTribe.