Attachment 6 TECHNICAL AND DELIVERABLE MILESTONE SCHEDULE (SAMPLE)

View the file

Other files

File Type Posted
Q A_Phase_VI_Jan_2014.docx DOCX document
PHVI_Proposal_Attach_7.doc DOC document
PHVI_Proposal_Attach_4.doc DOC document
PHVI_Proposal_Attach_5.doc DOC document
PHVI_Proposal_Attach_3.doc DOC document
PHVI_Proposal_Attach_9.pdf PDF
PHVI_Proposal_Attach_8.xlsx XLSX spreadsheet
PHVI_Proposal_Attach_2.doc DOC document
PHVI_Proposal_Attach_10.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Technical and Deliverable Milestone Schedule
Item No.Task No.Activity/DeliverableQuarter No.Expected Completion Date/MosPayable MilestoneProjected Federal PaymentProjected Partner Cost-SharingTotal
(per proposal)TITLE
11Research, summarize, and document current in-field welding and coating practices19 monthsList of current in-field welding and coating practices and their level of interaction and overlap submitted$16,984$0$16,984
26Project Website & 1st Quarterly Status Report13 monthsCreate project website & Submit 1st quarterly report$2,704$0$2,704
First Payable Milestone13 monthsSUBTOTAL$19,688$0$19,688
31Research, summarize, and document current in-field welding and coating practices29 monthsList of current in-field welding and coating practices and their level of interaction and overlap submitted$9,844$0$9,844
42Develop protocols to improve communication and coordination between welding and coating215 monthsProtocol to improve communication and coordination between in-field welders and coating appliers submitted$13,899$0$13,899
562nd Quarterly Status Report26 monthsSubmit 2nd quarterly report$2,704$0$2,704
Second Payable Milestone26 monthsSUBTOTAL$26,447$0$26,447
61Research, summarize, and document current in-field welding and coating practices39 monthsList of current in-field welding and coating practices and their level of interaction and overlap submitted$9,952$0$9,952
72Develop protocols to improve communication and coordination between welding and coating315 monthsProtocol to improve communication and coordination between in-field welders and coating appliers submitted$14,170$0$14,170
863rd Quarterly Status Report39 monthsSubmit 3rd quarterly report$2,704$0$2,704
Third Payable Milestone39 monthsSUBTOTAL$26,826$0$26,826
92Develop protocols to improve communication and coordination between welding and coating415 monthsProtocol to improve communication and coordination between in-field welders and coating appliers$14,170$0$14,170
103Fabricate in-field welded and coated test sections415 monthsSet of fabricated, in-field welded and coated test sections using the existing and improved protocols/procedures$22,007$42,500$64,507
1164th Quarterly Status Report412 monthsSubmit 4th quarterly report$2,704$0$2,704
Fourth Payable Milestone412 monthsSUBTOTAL$38,881$42,500$81,381
122Develop protocols to improve communication and coordination between welding and coating515 monthsProtocol to improve communication and coordination between in-field welders and coating appliers submitted$14,170$0$14,170
133Fabricate in-field welded and coated test sections515 monthsSet of fabricated, in-field welded and coated test sections using the existing and improved protocols/procedures submitted$19,256$42,500$61,756
144Perform laboratory coating and accelerated corrosion testing521 monthsResults from laboratory coating and accelerated corrosion testing at GTI's analytical coating and corrosion laboratory submitted$15,604$0$15,604
1565th Quarterly Status Report515 monthsSubmit 5th quarterly report$2,704$0$2,704
Fifth Payable Milestone515 monthsSUBTOTAL$51,734$42,500$94,234
164Perform laboratory coating and accelerated corrosion testing621 monthsResults from laboratory coating and accelerated corrosion testing at GTI's analytical coating and corrosion laboratory submitted$15,467$305,871$321,338
1766th Quarterly Status Report618 monthsSubmit 6th quarterly report$2,704$0$2,704
618 monthsSUBTOTAL$18,171$305,871$324,042
184Perform laboratory coating and accelerated corrosion testing721 monthsResults from laboratory coating and accelerated corrosion testing at GTI's analytical coating and corrosion laboratory$18,368$0$18,368
195Draft a set of recommendations to be submitted to the appropriate standard development organizations724 monthsSet of clear, concise recommendations to be submitted to the appropriate standard development organizations (e.g., NACE/SSPC, AWS, API, AGA, etc.) for incorporation into the relevant consensus guides, standards, and recommended practices manuals$10,798$0$10,798
2067th Quarterly Status Report721 monthsSubmit 7th quarterly report$2,704$0$2,704
Seventh Payable Milestone721 monthsSUBTOTAL$31,870$0$31,870
215Draft a set of recommendations to be submitted to the appropriate standard development organizations824 monthsSet of clear, concise recommendations to be submitted to the appropriate standard development organizations (e.g., NACE/SSPC, AWS, API, AGA, etc.) for incorporation into the relevant consensus guides, standards, and recommended practices manuals$12,084$0$12,084
2268th Quarterly Status Report824 monthsSubmit 8th quarterly report$2,704$0$2,704
235Draft a set of recommendations to be submitted to the appropriate standard development organizations923 monthsSet of clear, concise recommendations to be submitted to the appropriate standard development organizations (e.g., NACE/SSPC, AWS, API, AGA, etc.) for incorporation into the relevant consensus guides, standards, and recommended practices manuals$10,798$0
246Prepare and Submit Draft Final Report923 monthsSubmit draft final report$0$0$0
256Address Comments and Submit Final Report924 monthsSubmit draft report$2,715$0$2,715
Eighth Payable Milestone824 monthsSUBTOTAL$28,301$0$17,503
266Prepare & Present Paper at public eventn/aTBDPrepare & Present Paper at public event$1,080$0$1,080
276Peer Review - Washington, DC January or February Annuallyn/aTBDPrepare presentation for, travel to and present. Submit presentation file.$1,000$0$1,000
286Peer Review - Washington, DC January or February Annuallyn/aTBDPrepare presentation for, travel to and present. Submit presentation file.$1,000$0$1,000
SUBTOTAL$3,080$0$3,080
GRAND TOTALS$244,998$390,871$625,071

&L&"Times New Roman,Bold"Contractor Team: TBD

&18SAMPLE&C&"Arial,Bold"&22SAMPLE&16

&18SAMPLE&R&"Times New Roman,Bold"RITA-RS-14-01 Full Proposal Attachment 6 Page &P of &N &L&"Arial,Bold"&16SAMPLE&C&"Arial,Bold"&16SAMPLE&R&"Arial,Bold"&16SAMPLE