(x)
RFQ-PA-13-00016
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PHILADELPHIA PA 19103-2029
R3
1650 ARCH STREET
CONTRACTS BRANCH 3PM10
US ENVIRONMENTAL PROTECTION AGENCY
REGION III
04/18/2013000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/04/2013
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Facility Hazardous Waste Removal and Emergency Response Services for the U.S. EPA
Environmental Science Center Fort Meade, MD
This purpose of this amendment is to revise the date for the closing of the Request for
Quotation (RFQ) and to provide responses to technical questions.
Vendor shall provide signed copy of amendment with their quotation.
1. The date for the closing of the RFQ is revised to read on or before April 30, 2013, 5:00PM Eastern Time.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Alexandra Rajkowski-Reyes
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
RFQ-PA-13-00016/000001
tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text
Arajkows Typewritten Text
Arajkows Typewritten Text X
Arajkows Typewritten Text
Arajkows Typewritten Text
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
RFQ-PA-13-00016/000001
2. See attachment for responses to questions.
3. All other terms and conditions as previously stated remain the same.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110RFQ-PA-13-00016/000001
tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text tgillesp Typewritten Text tgillesp
Facility Hazardous Waste Removal and Emergency Response Services for the U.S. EPA
Environmental Science Center Fort Meade, MD
Technical Questions
1. What is the dollar value of the current contract?
Response: The total obligated amount is $639,017.94
2. Who is the current contractor?
Response: The current contractor is Environmental Management Services Inc.
3. Under the current contract, what is the number of contractor personnel assigned to it?
Response: Currently, there are three (3) people assigned to in-house technician duties, with varying days and hours assigned to work. The contractor has to submit a monthly staffing plan for COTR approval, typically 150 – 250 hours per month.
4. Is subcontracting allowed?
Response: Subcontracting is allowable in accordance with the terms and conditions of the Request for Quotation. The prime contractor retains legal and management responsibility for overall contract performance.
RFQ-PA-13-00016/000001