RFQ Amendment three Attachment Q and A for Yocum sailing.pdf
PDF 117 KB Posted
- Solicitation number
- RFQ6923G226Q000004
About this file
This is a Questions and Answers document for federal contract solicitation 6923G226Q000004, Amendment Three, concerning Yocum sailing fuel tanks removal and installation.
The document addresses five key inquiries from offerors regarding project specifications and contractual terms. Question 1 addresses tank material specifications, with the government confirming that fiberglass tanks (including covers) are preferred to meet EPA 40 CFR 280/6 NYCRR 613 corrosion protection requirements and reduce maintenance costs, with no indication that steel tank alternatives will be accepted. Question 2 concerns the $18,000 per day liquidated damages clause, which the government states will be deleted in Amendment Two of the solicitation per FAR clause 52.211-12. Questions 3 and 4 request clarification on fueling system location and floating dock requirements; the government directs offerors to the Engineering study included with the PR/Requisition package, with additional information available during site visits. Question 5 addresses contractor responsibility for fuel disposal costs associated with removing fuel from existing tanks, with the government confirming that any environmental disposal costs are the contractor's responsibility, though further clarification may be required.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and answers 6923G226Q000004, Amendment three- Yocum sailing fuel tanks removal and installation
Questions and Answers
Number Offeror's questions Government answers
Fiberglass tanks are being quoted as 42-48 weeks out from accepted drawings. Will USMMA accept steel tanks as an alternative?"
Fiberglass tanks (including tank covers) preferred to meet regulatory requirement(s) of corrosion protection (EPA 40 CFR 280 / 6 NYCRR 613), perform mandated routine maintenance inspections and reduce additional maintenance and regulatory cost(s) to USMMA & the government.
"The $18,000 per day liquidated damages seem excessive for the dollar amount of this project. Could you please confirm this value for our bonding company?"
Amendment two of the solicitation will delete FAR clause 52.211-12 -Liquidated damages construction (Sept 2000) in section F.4. from the solicitation 6923G226Q000004..
"Could you provide more details on the location of the fueling system? Will it be mounted on floating docks or adjacent to floating docks?"
Please refer to the Engineering study that details the option selected for the project. It is included with the PR/Requisition. If additional information is required answers may be provided during site visit.
"Does this contract require the replacement of floating docks or just the repair of docks disturbed by fuel system construction?"
Please refer to the Engineering study that details the option selected for the project. It is included with the PR/Requisition. If additional information is required answers may be provided during site visit.
The contract requires reimbursing the Owner for fuel removed from existing tanks. How is this handled if disposal of fuel incurs a cost to the contractor?"
This may be a finance inquiry. However, any disposal (including environmental disposal) associated with this project is included as part of the responsibility of the contractor. We may require further clarification.