RFQ2602SelectionCommitteeConsolidatedScoresheet.pdf
PDF 152 KB Posted
- Attached to
- Wiley M. Nash Water Reclamation Facility Headworks Floodproofing & Lift Station No. 1 Relocation
- Solicitation number
- RFQ-26-02
- Issued by
- Volusia County, Florida
About this file
This is a Selection Committee Consolidated Evaluation Scoresheet for RFQ-26-02, issued by the City of DeLand, Florida on October 8, 2026, for the Wiley M. Nash Water Reclamation Facility Headworks Floodproofing and Lift Station No. 1 Relocation project. The City requested qualifications from professional engineering firms to provide planning, design, permitting, bidding and funding assistance, and construction services for the facility upgrade and lift station relocation project. Qualifications were due August 27, 2026 at 2:00 p.m., with questions accepted through August 20, 2026. The project scope includes replacement and floodproofing of WRF headworks facilities, modernization of electrical distribution and standby power systems, elevation of critical equipment above anticipated flood elevations, site drainage improvements, and relocation of Lift Station No. 1 approximately 500 feet to a higher elevation with new submersible pumps and telemetry systems. Shortlisted firms were to receive limited site access prior to presentations and interviews. The Selection Committee, composed of Corey McMillen, Jim Ailes, Lynn Jarrell, Scott Zender, and Doug Larkins, evaluated two firms, with Mead & Hunt, Inc. ranked first with 8 total points and Sawcross, Inc. ranked second with 4 total points. On a motion by Jim Ailes, seconded by Scott Zender, the committee voted unanimously to enter into negotiations with the top-ranked firm, Mead & Hunt, Inc.
The project is federally funded under the Florida Department of Environmental Protection Supplemental Appropriation for Hurricanes Helene, Milton, and Wildfires (SAHMW), FDEP SRF Project #WW64114, subject to Davis-Bacon Act prevailing wage requirements, Copeland Act anti-kickback provisions, and Section 3 and M/WBE provisions. The successful consultant must maintain Professional Liability Insurance of $3 million per claim and Comprehensive General Liability and Auto Liability of $1 million combined single limit, plus Workers' Compensation coverage. Permits are required from the City of DeLand, St. Johns River Water Management District, and FDEP. Under Florida's Consultants' Competitive Negotiations Act, any consultant selected to develop the design criteria package is prohibited from subsequently proposing or performing design services as part of a design-build team.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ2602NamesOnlyTab.pdf | ||
| RFQ2602PMN.pdf | ||
| RFQ2602Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Wiley M. Nash Water Reclamation Facility Headworks Floodproofing Lift Station No. 1 Relocation
RFQ-26-02
POSTING DATE: October 8, 2026 POSTED BY: Corey McMillen
Mead & Hunt Sawcross, Inc.
Jim Ailes 1 2
Lynn Jarrell 1 2
Scott Zender 1 2
Doug Larkins 1 2
TOTAL POINTS
4 8
RANKING
1 2
SELECTION COMMITTEE CONSOLIDATED EVALUATION SCORESHEET
*** Motion by Jim Ailes, Second by Scott Zender to enter into negotiations with the top ranked firm [Unanimous vote]: Mead & Hunt, Inc.
▼Committee Member▼
Scoresheet
File details come from the government source that posted it. Updated .