This is a Request for Quote (RFQ) for furnishings and installation services at Fort Eisenhower (formerly Fort Gordon), Georgia, specifically for Vincent Hall Phase 1 and the Maintenance and Continuous Audit (MCA) 2 building at the Cyber Center of Excellence (CCoE) headquarters. The solicitation number is W912DY26QA181, issued by the U.S. Army Corps of Engineers (USACE) Huntsville Center on June 22, 2026, with an offer due date of June 22, 2026 at 12:00 PM Central Standard Time. The procurement is unrestricted (not set-aside), classified under NAICS 337126 (Office Furniture Manufacturing), and utilizes FAR Part 12 procedures for commercial products and services. The estimated award date is August 10, 2026.

The contractor must provide all furnishings, materials, equipment, labor, supervision, and management to coordinate delivery, load and unload items, place and install furnishings in designated rooms, assemble items as required, secure and store items as designated, and properly dispose of packaging materials. The contract includes four required line items: (1) Furnishings for Ft Gordon Vincent Hall Phase 1; (2) Furnishings for Ft. Cavazos Building 10001 (MCA2), available as an option exercisable anytime between contract award and furniture installation completion; (3) Storage for Vincent Hall Phase 1 (optional, six months maximum at firm fixed price per month); and (4) Storage for Ft. Cavazos MCA2 (optional, six months maximum at firm fixed price per month). Specific installation dates are required: Vincent Hall Phase 1 installation from December 7, 2026 through February 1, 2027; MCA2 installation from March 29, 2027 through April 26, 2027. All quotes must include furnishings pricing, shipping (FOB Destination), installation labor and costs, and six-month storage options. Contractors must submit completed Attachment #1 (Line Item Pricing) in Excel format and Attachment #7 (Technical Documents Checklist) in Word format, along with technical documentation demonstrating compliance with the Furniture Item Descriptions (FID) specifications. The solicitation requires submission of company information including CAGE code, DUNS number, and proof of active SAM registration with no exclusions. Contractors are expected to hold prices firm for 60 calendar days from the solicitation response date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31b. NAME OF CONTRACTING OFFICER (Type or print) 30c. DATE SIGNED

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

NOTE: OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30.

1. REQUISITION NUMBER PAGE 1 OF

2. CONTRACT NUMBER

7. FOR SOLICITATION

INFORMATION CALL:

3. AWARD/EFFECTIVE

DATE

a. NAME

TRAVIAN JAMES

4. ORDER NUMBER 5. SOLICITATION NUMBER

W912DY26QA181

b. TELEPHONE NUMBER (No collect calls)

256-895-1757

6. SOLICITATION ISSUE

DATE

8. OFFER DUE DATE/

LOCAL TIME

22 JUN 2026

12:00 PM

9. ISSUED BY CODE W912DY 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:

W2V6 USA ENG SPT CTR HUNTSVIL

300 SECURE GATEWAY, KO CONTRACTING DIVISION

REDSTONE ARSENAL, AL 35898-0000

UNITED STATES

TRAVIAN JAMES, EMAIL: TRAVIAN.A.JAMES@USACE.ARMY.MIL TELEPHONE:

256-895-1757

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

WOMEN-OWNED SMALL

BUSINESS (WOSB)

ECONOMICALLY

DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

8(A)

NORTH AMERICAN

INDUSTRY CLASSIFICATION

STANDARD (NAICS):

337126

SIZE STANDARD:

11. DELIVERY FOR FREE ON

BOARD (FOB) DESTINATION

12. DISCOUNT TERMS 13a. THIS CONTRACT IS A

RATED ORDER UNDER

13b. RATING

14. METHOD OF SOLICITATION REQUEST

UNLESS BLOCK IS MARKED

SEE SCHEDULE

THE DEFENSE PRIORITIES

AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

REQUEST

FOR QUOTE

(RFQ)

INVITATION

FOR BID

(IFB)

FOR

PROPOSAL

(RFP)

15. DELIVER TO CODE 16. ADMINISTERED BY CODE

SEE SCHEDULE

17a. CONTRACTOR/

OFFEROR

CODE FACILITY

CODE

18a. PAYMENT WILL BE MADE BY CODE

TELEPHONE NUMBER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

OFFER BELOW IS CHECKED SEE ADDENDUM

19.

ITEM NUMBER

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

SEE CONTINUATION

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

SEE CONTINUATION

26. TOTAL AWARD AMOUNT (For Government Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

ARE ARE NOT ATTACHED

ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH

AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND

ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS

SPECIFIED

29. AWARD OF CONTRACT: REFERENCE OFFER

DATED . . YOUR OFFER ON SOLICITATION

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS: SEE CONTINUATION

30a. SIGNATURE OF OFFEROR/CONTRACTOR

30b. NAME AND TITLE OF SIGNER (Type or print)

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

Created On:

08 May 2026, 10:51 AM Central Daylight Time

W912DY26QA181

Continuation of Supplies or Services and Prices/Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price

Amount

0001 Furnishings: Ft Gordon_Vincent Hall PH1 The contractor shall provide furnishings in support of the Huntsville Center Centrally Managed Furnishings Program for Ft Gordon Vincent Hall PH1, in accordance with the attached Line Items, Item Descriptions and Statement of Work. **Please submit quotes valid for 120 days.

1 Lot

Option Line Item

Furnishings: ATT1-Ft Gordon_MCA2 PN88725 The contractor shall provide furnishings in support of the Huntsville Center Centrally Managed Furnishings Program for Ft. Cavazos Bldg. 10001, in accordance with the attached Line Items, Item Descriptions and Statement of Work. **Please submit quotes valid for 120 days. **This Option is Exercisable anytime between Contract Award and Furniture Install Completion Dates.

1 Lot

Line Item

Storage: Ft Gordon_Vincent Hall PH1 ***Option: This line item may be unilaterally exercised at the discretion of the Contracting Officer. Storage shall be a Firm Fixed Price amount of $ per month, for a total amount of $ for six months. Contractors shall take into account all costs necessary to store furnishings secure from theft, damage, and weather elements in case of any contingency en-route to installation.

Storage shall include all costs to place furnishings into and remove furnishings from storage (ie. double handling, transportation, etc.). The quoted cost should include all costs necessary to complete delivery and installation of furniture at the terminal location. **This Option is Exercisable anytime between Contract Award and Furniture Install Completion Dates.

6 Months

Line Item

Storage: Ft Gordon_MCA2 PN88725 ***Option: This line item may be unilaterally exercised at the discretion of the Contracting Officer. Storage shall be a Firm Fixed Price amount of $ per month, for a total amount of $ for six months. Contractors shall take into account all costs necessary to store furnishings secure from theft, damage, and weather elements in case of any

6 Months contingency en-route to installation.

Storage shall include all costs to place furnishings into and remove furnishings from storage (ie. double handling, transportation, etc.). The quoted cost should include all costs necessary to complete delivery and installation of furniture at the terminal location. **This Option is Exercisable anytime between Contract Award and Furniture Install Completion Dates.

Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.

2017-01

52.204-13 System for Award Management- Maintenance. (Deviation 2026- O0038)

2026-02

52.222-50 Combating Trafficking in Persons. (Deviation 2026-O0038)

2026-02

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.

2024-05

52.232-33 Payment by Electronic Funds Transfer-System for Award Management.

2018-10

52.232-40 Providing Accelerated Payments to Small Business Subcontractors.

2023-03

52.233-3 Protest after Award. (Deviation 2026-O0038)

2026-02

52.233-4 Applicable Law for Breach of Contract Claim. (Deviation 2026- O0038)

2026-02

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials.

2011-09

252.203-7002 Requirement to Inform Employees of Whistleblower Rights.

2022-12

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

2023-01

252.223-7008 Prohibition of Hexavalent Chromium.

2023-01

252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.

2023-01

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

252.232-7010 Levies on Contract Payments. 2006-12

252.247-7023 Transportation of Supplies by Sea.

2024-10

FAR Clauses Incorporated by Full Text

Number Title Effective Alternate Variation

Date Deviation Effective Date

52.212-4 Terms and Conditions- Commercial Products and Commercial Services. (Deviation 2026-O0038)

2026-02

Terms and Conditions-Commercial Products and Commercial Services (Feb 2026) (Deviation 2026-O0038)

(a) Definitions. The clause at Federal Acquisition Regulation (FAR) 52.202-1, Definitions, is incorporated by reference.

(b) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post acceptance rights-

(1) Within a reasonable time after the defect was discovered or should have been discovered;

and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(c) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.

C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(d) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(e) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal, or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause FAR 52.233-1, Disputes, which is incorporated in this contract by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. When an excusable delay occurs, the Contractor shall-

(1) Notify the Contracting Officer in writing as soon as possible;

(2) Remedy the delay as quickly as possible; and

(3) Notify the Contracting Officer when the occurrence is over.

(g) Invoice. The Government will handle invoices according to the Prompt Payment Act (31 U.S.

C. 3903) and 5 CFR part 1315. The Contractor shall submit invoices to the address designated in the contract to receive invoices. An invoice must include the information required by 5 CFR part 1315.9(b).

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees, and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark, or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment-

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act ( 31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.

(3) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date that appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(4) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall-

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the-

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable;

(D) Contractor point of contact; and

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(5) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by FAR part

33 if-

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see FAR part 32).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a termination for cause.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures for interest credits prescribed in FAR part 32 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon-

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. The Government will send a cure notice to the Contractor, unless the reason for the termination is late delivery. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered under this contract are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C.

chapter 87, Kickbacks; 49 U.S.C. 40118, Government-financed air transportation; and 41 U.S.

C. chapter 21 relating to procurement integrity.

(r) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services;

(2) The Disputes, Payments, Invoice, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) Other contract clauses incorporated in the solicitation or contract;

(4) Addenda to this solicitation or contract;

(5) Solicitation provisions incorporated in the solicitation;

(6) Other paragraphs of this clause;

(7) Other documents, exhibits, and attachments; and

(8) The specification.

(s) Unauthorized obligations.

(1) Except as stated in paragraph (s)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government-authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an "I agree" click box or other comparable mechanism (e.g., "click-wrap" or "browse-wrap" agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (s)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(t) Comptroller General examination of record. This paragraph applies if this contract was awarded using other than sealed bid procedures and is in excess of the simplified acquisition threshold on the date of award of this contract.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor's directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices, at all reasonable times, the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR part 4, longer period required by statute, or periods specified in other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This clause does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(u) Incorporation by reference. The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of clause)

DFARS Clauses Incorporated by Full Text

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.225-7001 Buy American and Balance of Payments Program.

2024-02

BUY AMERICAN AND BALANCE OF PAYMENTS PROGRAM-BASIC (FEB 2024)

(a) Definitions. As used in this clause-

"Commercially available off-the-shelf (COTS) item"-

(1) Means any item of supply (including construction material) that is-

(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" in section 2.101 of the Federal Acquisition Regulation (FAR));

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Component" means an article, material, or supply incorporated directly into an end product.

"Critical component" means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at

FAR 25.105.

"Critical item" means a domestic construction material or domestic end product that is deemed critical to the U.S. supply chain. The list of critical items is at FAR 25.105.

"Domestic end product" means-

(1) For an end product that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured end product mined or produced in the United States; or

(ii) An end product manufactured in the United States if-

(A) The cost of its qualifying country components and its components that are mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029, unless an alternate percentage is established for a contract in accordance with FAR 25.101(d), or award is made before January 1, 2030, for a foreign end product that exceeds 55 percent domestic content (see Defense Federal Acquisition Regulation Supplement 225.103(b)(ii)). The cost of components includes transportation costs to the place of incorporation into the end product and U.S. duty (whether or not a duty-free entry certificate is issued). Components of unknown origin are treated as foreign. Scrap generated, collected, and prepared for processing in the United States is considered domestic. A component is considered to have been mined, produced, or manufactured in the United States (regardless of its source in fact) if the end product in which it is incorporated is manufactured in the United States and the component is of a class or kind for which the Government has determined that-

(1) Sufficient and reasonably available commercial quantities of a satisfactory quality are not mined, produced, or manufactured in the United States ; or

(2) It is inconsistent with the public interest to apply the restrictions of the Buy American statute; or

(B) The end product is a COTS item; or

(2) For an end product that consists wholly or predominantly of iron or steel or a combination of both, an end product manufactured in the United States, if the cost of iron and steel not produced in the United States or a qualifying country constitutes less than 5 percent of the cost of all the components used in the end product (produced in the United States or a qualifying country means that all manufacturing processes of the iron or steel must take place in the United States or a qualifying country, except metallurgical processes involving refinement of steel additives). The cost of iron and steel not produced in the United States or a qualifying country includes but is not limited to the cost of iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings, not produced in the United States or a qualifying country, utilized in the manufacture of the end product and a good faith estimate of the cost of all iron or steel components not produced in the United States or a qualifying country, excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the end product contains multiple components, the cost of all the materials used in such end product is calculated in accordance with the explanation of cost of components in paragraph (1)(ii)(A) of this definition.

"End product" means those articles, materials, and supplies to be acquired under this contract for public use.

"Foreign end product" means an end product other than a domestic end product.

"Predominantly of iron or steel or a combination of both" means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

"Qualifying country" means a country with a reciprocal defense procurement memorandum of understanding or international agreement with the United States in which both countries agree to remove barriers to purchases of supplies produced in the other country or services performed by sources of the other country, and the memorandum or agreement complies, where applicable, with the requirements of section 36 of the Arms Export Control Act (22 U.S.C. 2776) and with 10 U.S.C. 2457. Accordingly, the following are qualifying countries:

Australia

Austria

Belgium

Canada

Czech Republic

Denmark

Egypt

Estonia

Finland

France

Germany

Greece

Israel

Italy

Japan

Latvia

Lithuania

Luxembourg

Netherlands

Norway

Poland

Portugal

Slovenia

Spain

Sweden

Switzerland

Turkey

United Kingdom of Great Britain and Northern Ireland.

"Qualifying country component" means a component mined, produced, or manufactured in a qualifying country.

"Qualifying country end product" means-

(1) An unmanufactured end product mined or produced in a qualifying country; or

(2) An end product manufactured in a qualifying country if-

(i) The cost of the following types of components exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029, unless an alternate percentage is established for a contract:

(A) Components mined, produced, or manufactured in a qualifying country.

(B) Components mined, produced, or manufactured in the United States .

(C) Components of foreign origin of a class or kind for which the Government has determined that sufficient and reasonably available commercial quantities of a satisfactory quality are not mined, produced, or manufactured in the United States. Components of unknown origin are treated as foreign; or

(ii) The end product is a COTS item.

"Steel" means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

" United States " means the 50 States, the District of Columbia , and outlying areas.

(b) This clause implements 41 U.S.C chapter 83, Buy American. In accordance with 41 U.S.C.

1907, the component test of the Buy American statute is waived for an end product that is a COTS item (see FAR 12.505(a)(1)). Unless otherwise specified, this clause applies to all line items in the contract.

(c) The Contractor shall deliver only domestic end products unless, in its offer, it specified delivery of other end products in the Buy American-Balance of Payments Program Certificate provision of the solicitation. If the Contractor certified in its offer that it will deliver a qualifying country end product, the Contractor shall deliver a qualifying country end product or, at the Contractor's option, a domestic end product.

(d) The contract price does not include duty for end products or components for which the Contractor will claim duty-free entry.

(End of clause)

252.232-7006 Wide Area WorkFlow Payment Instructions.

2023-01

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause-

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web- Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC Issue By DoDAAC Admin DoDAAC

Inspect By DoDAAC Ship To Code Ship From Code Mark For Code Service Approver (DoDAAC) Service Acceptor (DoDAAC) Accept at Other DoDAAC LPO DoDAAC DCAA Auditor DoDAAC Other DoDAAC(s)

(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

Addendum to Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.

(Deviation 2026-O0038)

2026-02

52.222-90 Addressing DEI Discrimination by Federal Contractors.

(Deviation 2026-O0038)

2026-04

52.223-23 Sustainable Products. (Deviation 2026-O0038)

2026-02

52.232-90 Fast Payment Procedure.

(Deviation 2026-O0038)

2026-02

52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation 2026-O0038)

2026-04

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.204-7003 Control of Government Personnel Work Product.

1992-04

DFARS Clauses Incorporated by Full Text

Number Title Effective

Alternate Deviation

Variation Effective Date

252.225-7021 Trade Agreements. 2024-02

TRADE AGREEMENTS-BASIC (FEB 2024)

(a) Definitions. As used in this clause-

" Caribbean Basin country end product"-

(1) Means an article that-

(i) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or

(ii) In the case of an article that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different article of commerce with a name, character, or use distinct from that of the article or articles from which it was transformed. The term refers to a product offered for purchase under a supply contract, but for purposes of calculating the value of the end product includes services (except transportation services) incidental to its supply, provided that the value of those incidental services does not exceed the value of the product itself; and

(2) Excludes products, other than petroleum and any product derived from petroleum, that are not granted duty-free treatment under the Caribbean Basin Economic Recovery Act (19 U.S.C.

2703(b)). These exclusions presently consist of-

(i) Textiles, apparel articles, footwear, handbags, luggage, flat goods, work gloves, leather wearing apparel, and handloomed, handmade, or folklore articles that are not granted duty-free status in the Harmonized Tariff Schedule of the United States (HTSUS);

(ii) Tuna, prepared or preserved in any manner in airtight containers; and

(iii) Watches and watch parts (including cases, bracelets, and straps) of whatever type, including, but not limited to, mechanical, quartz digital, or quartz analog, if such watches or watch parts contain any material that is the product of any country to which the HTSUS column 2 rates of duty (HTSUS General Note 3(b)) apply.

"Commercially available off-the-shelf (COTS) item"-

(1) Means any item of supply (including construction material) that is-

(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" in section 2.101 of the Federal Acquisition Regulation);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Component" means an article, material, or supply incorporated directly into an end product.

"Designated country" means-

(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, North Macedonia, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan (known in the World Trade Organization as "the Separate Customs Territory of Taiwan, Penghu, Kinmen, and Matsu" (Chinese Taipei)), Ukraine, or the United Kingdom);

(2) A Free Trade Agreement country (Australia, Bahrain, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Panama, Peru, or Singapore);

(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or

(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).

"Designated country end product" means a WTO GPA country end product, a Free Trade Agreement country end product, a least developed country end product, or a Caribbean Basin country end product.

"End product" means those articles, materials, and supplies to be acquired under this contract for public use.

"Free Trade Agreement country end product" means an article that-

(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement country; or

(2) In the case of an article that consists in whole or in part of materials from another country, has been substantially transformed in a Free Trade Agreement country into a new and different article of commerce with a name, character, or use distinct from that of the article or articles from which it was transformed. The term refers to a product offered for purchase under a supply contract, but for purposes of calculating the value of the end product includes services (except transportation services) incidental to its supply, provided that the value of those incidental services does not exceed the value of the product itself.

"Least developed country end product" means an article that-

(1) Is wholly the growth, product, or manufacture of a least developed country; or

(2) In the case of an article that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different article of commerce with a name, character, or use distinct from that of the article or articles from which it was transformed. The term refers to a product offered for purchase under a supply contract, but for purposes of calculating the value of the end product includes services (except transportation services) incidental to its supply, provided that the value of those incidental services does not exceed the value of the product itself.

"Nondesignated country end product" means any end product that is not a U.S.-made end product or a designated country end product.

"Qualifying country" means a country with a reciprocal defense procurement memorandum of understanding or international agreement with the United States in which both countries agree to remove barriers to purchases of supplies produced in the other country or services performed by sources of the other country, and the memorandum or agreement complies, where applicable, with the requirements of section 36 of the Arms Export Control Act (22 U.S.C. 2776) and with 10 U.S.C. 2457. Accordingly, the following are qualifying countries:

Australia

Austria

Belgium

Canada

Czech Republic

Denmark

Egypt

Estonia

Finland

France

Germany

Greece

Israel

Italy

Japan

Latvia

Lithuania

Luxembourg

Netherlands

Norway

Poland

Portugal

Slovenia

Spain

Sweden

Switzerland

Turkey

United Kingdom of Great Britain and Northern Ireland.

"Qualifying country end product" means-

(1) An unmanufactured end product mined or produced in a qualifying country; or

(2) An end product manufactured in a qualifying country if-

(i) The cost of the following types of components exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029, unless an alternate percentage is established for a contract:

(A) Components mined, produced, or manufactured in a qualifying country.

(B) Components mined, produced, or manufactured in the United States .

(C) Components of foreign origin of a class or kind for which the Government has determined that sufficient and reasonably available commercial quantities of a satisfactory quality are not mined, produced, or manufactured in the United States; or

(ii) The end product is a COTS item.

" United States " means the 50 States, the District of Columbia , and outlying areas.

"U.S.-made end product" means an article that-

(1) Is mined, produced, or manufactured in the United States ; or

(2) Is substantially transformed in the United States into a new and different article of commerce with a name, character, or use distinct from that of the article or articles from which it was transformed.

"WTO GPA country end product" means an article that-

(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or

(2) In the case of an article that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different article of commerce with a name, character, or use distinct from that of the article or articles from which it was transformed. The term refers to a product offered for purchase under a supply contract, but for purposes of calculating the value of the end product includes services (except transportation services) incidental to its supply, provided that the value of those incidental services does not exceed the value of the product itself.

(b) Unless otherwise specified, this clause applies to all items in the Schedule.

(c) The Contractor shall deliver under this contract only U.S.-made, qualifying country, or designated country end products unless-

(1) In its offer, the Contractor specified delivery of other nondesignated country end products in the Trade Agreements Certificate provision of the solicitation; and

(2)(i) Offers of U.S.-made, qualifying country, or designated country end products from responsive, responsible offerors are either not received or are insufficient to fill the Government's requirements; or

(ii) A national interest waiver has been granted.

(d) The contract price does not include duty for end products or components for which the Contractor will claim duty-free entry.

(e) The HTSUS is available at http://www.usitc.gov/tata/hts/bychapter/index.htm. The following sections of the HTSUS provide information regarding duty-free status of articles specified in the definition of "Caribbean Basic country end product" within paragraph (a) of his clause:

(1) General Note 3(c), Products Eligible for Special Tariff Treatment.

(2) General Note 17, Products of Countries Designated as Beneficiary Countries Under the United States - Caribbean Basin Trade Partnership Act of 2000.

(3) Section XXII, Chapter 98, Subchapter II, Articles Exported and Returned, Advanced or Improved Abroad, U.S. Note 7(b).

(4) Section XXII, Chapter 98, Subchapter XX, Goods Eligible for Special Tariff Benefits Under the United States-Caribbean Basin Trade Partnership Act.

Solicitation Provisions

FAR Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.204-7 System for Award Management- Registration. (Deviation 2026- O0038)

2026-02

DFARS Provisions Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.203-7005 Representation Relating to Compensation of Former DoD Officials.

2022-09

252.204-7024 Notice on the Use of the Supplier Performance Risk System.

2023-03

252.225-7055 Representation Regarding Business Operations with the Maduro Regime.

2022-05

FAR Provisions Incorporated by Full Text

Number Title Effective Date

Alternate Deviation

Variation Effective

52.212-1 Instructions to Offerors- 2026-02

Commercial Products and Commercial Services. (Deviation 2026-O0038)

Instructions to Offerors-Commercial Products and Commercial Services (Feb 2026) (Deviation 2026-O0038)

(a) Submission of offers. Submit signed and dated offers to the office specified in this solicitation at or before the exact time specified in this solicitation. As a minimum, offers shall include-

(1) The solicitation number;

(2) The name, address, telephone number of the Offeror;

(3) The Offeror's Unique Entity Identifier (UEI) and, if applicable, Electronic Funds Transfer (EFT) indicator;

(4) Information necessary to evaluate the factors contained in the provision at 52.212-2 or as described in the solicitation;

(5) Responses to provisions that require Offeror completion of information, representations, and certifications (other than those collected via the System for Award Management (SAM)); and

(6) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and any solicitation amendments.

(b) Period for acceptance of offers. The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers, unless another time period is specified in an addendum to the solicitation.

(c) Late submissions, modifications, revisions, and withdrawals of offers.

(1) Offerors are responsible for submitting offers and any modifications or revisions to the Government office designated in the solicitation by the time specified in the solicitation.

(2) Any offer, modification, or revision received after the time specified for receipt of offers is "late" and will not be considered unless it is received before award is made and the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition. However, a late modification of an otherwise successful offer that makes its terms more favorable to the Government will be considered at any time it is received and may be accepted.

(3) If an emergency or unanticipated event interrupts normal Government processes so that offers cannot be received at the Government office designated for receipt of offers by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation or other notice of an extension of the closing date, the time specified for receipt of offers will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(4) Offerors may withdraw their offers by written notice to the Government received at any time before award.

(d) Contract award (not applicable to Invitation for Bids). The Government intends to evaluate offers and award a contract without discussions with Offerors.