About this file
RFQ/RFP Summary: Commissioning Agent Services for Bungay Elementary School Project
This Request for Qualifications and Request for Proposals (RFQ/RFP No. 2026-04) is issued by the Seymour Public School District Bungay Elementary School Building Committee and the Town of Seymour, Connecticut, seeking a qualified commissioning agent to provide comprehensive commissioning services for the new Bungay Elementary School building project (State Project No. 124-0058N). The project involves the construction of a new approximately 71,673-square-foot elementary school building to replace the existing 59,600-square-foot facility at 35 Bungay Road, Seymour, Connecticut, which will accommodate 553 students in grades pre-kindergarten through five, as well as the subsequent demolition of the existing building. The commissioning services will encompass all project building systems including HVAC, electrical, plumbing, fire protection, building automation, lighting controls, renewable energy systems, building envelope systems, life safety systems, security systems, and indoor air quality systems throughout the design, procurement and construction, pre-occupancy, and occupancy/post-occupancy phases of the project. Sealed qualifications and proposal submissions must be received by November 10, 2026, at 10:00 a.m. at Seymour Town Hall; the submissions will be opened at that time, excluding sealed fee proposal envelopes. Interviews of qualified proposers are anticipated for the week of November 16, 2026, with anticipated contract award and commencement of services during the week of November 30, 2026. The project schedule anticipates construction documents completion by August 2027, bidding beginning in October 2027, construction starting in December 2027, and substantial completion by mid-June 2029, with commissioning completion targeted for October 2029.
The commissioning agent will be compensated through a lump sum fixed fee for base services allocated across the project phases (design and pre-construction, procurement and construction, pre-occupancy, and occupancy/post-occupancy and operations), with additional services available on an hourly rate basis subject to prior written authorization. Proposers must provide the original and three copies of their qualifications submission and fee proposal, plus one digital copy on a thumb drive; no fee information may be included in the qualifications submission, which must be separate from the fee proposal submission. The total project budget is approximately $56,346,000, with approximately $44,465,080 allocated for construction costs including potential escalation and contingencies. Proposers must demonstrate adequate professional expertise and experience in providing commissioning services for Connecticut public school projects within the past five years, particularly those eligible for State of Connecticut school building project grants and subject to Connecticut High Performance Building Standards. The commissioning agent's lead professional must hold or maintain Certified Commissioning Professional (CCP) certification by the Building Commissioning Association or equivalent certification from the Association of Energy Engineers throughout the contract term. The project will be partially funded by a school building project priority list grant from the Connecticut Department of Administrative Services, requiring compliance with Connecticut General Statutes Chapter 173 and applicable state regulations governing high-performance buildings.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEYMOUR PUBLIC SCHOOL DISTRICT
BUNGAY ELEMENTARY SCHOOL BUILDING COMMITTEE
RFQ/RFP No. 2026-04
Request for Qualifications and Request for Proposals for
Commissioning Agent Services for the
New Bungay Elementary School Building and Grounds
State Project No: 124-0058N
ISSUED: OCTOBER 15, 2026
SUBMISSION DEADLINE: NOVEMBER 10, 2026
Town of Seymour/Bungay Elementary School Building Committee Contact:
W. Kurt Miller, Town of Seymour Chief Administrative Officer
Seymour Town Hall
1 First Street
Seymour, CT 06483
Kmiller@seymourct.org
SEYMOUR PUBLIC SCHOOL DISTRICT
BUNGAY ELEMENTARY SCHOOL BUILDING COMMITTEE
REQUEST FOR QUALIFICATIONS AND REQUEST FOR PROPOSALS
The Bungay Elementary School Building Committee (the “SBC”) and the Town of Seymour, Connecticut
(“Town”) are requesting sealed qualifications and sealed proposals from qualified professional firms to provide commissioning services in connection with the design, bidding/procurement and construction, and occupancy of a school building project for the construction of the new Bungay Elementary School building and grounds and the demolition of the existing Bungay Elementary School Building (the “Existing
Building”) (the “Project”) located at 35 Bungay Road, Seymour, Connecticut 06483 (the “Property”). The selected firm will be the commissioning agent engaged by the Town and SBC for the Project (the
“Commissioning Agent” or the “CxA”). This solicitation is both a request for qualifications and a request for proposals (“RFQ/RFP”). This RFQ/RFP has been publicly advertised.
The Town and District have been awarded a school building project priority list grant from the State of
Connecticut through the Connecticut Department of Administrative Services (“CTDAS”).
The Services to be performed by the firm selected as the Commissioning Agent (the “Services”) for the
Town, SBC, Seymour Public School District (“District”), and the Seymour Board of Education, as applicable, are described in greater detail and set forth in the Instructions to Proposers and Exhibit A of this
RFQ/RFP, and will generally include, for the Project, commissioning services to ensure that the Project’s various building systems are planned, designed, installed, tested, optimized, and capable of being operated as intended and required by the District, the Project Architect’s basis of design for the Project, and the
Construction Documents for the Project, including commissioning services that are usually and customarily performed by a commissioning agent when furnished for the awarding authority in connection with a project for the construction of a new public school building that is partially funded by a priority list school building project grant administered by CTDAS and provided pursuant to Connecticut General Statutes Chapter 173 and applicable regulations of the State of Connecticut.
The Project building systems for which the Commissioning Agent will provide the Services generally include, but are not limited to: heating, ventilation, air conditioning, and refrigeration systems; building automation systems and associated controls; indoor air quality systems; electrical systems; plumbing systems; sensor lighting controls; lighting and daylight controls; domestic hot water system; renewable energy systems; water using systems; life safety systems, including fire protection and fire alarm systems;
energy management and/or efficiency systems; emergency power systems and automatic transfer switching;
building envelope systems; security systems; and communications systems.
Please see Sections 5 through 8 of the following Instructions to Proposers for important details about the
RFQ/RFP submission process and requirements. This RFQ/RFP, with Instructions to Proposers and other documents that are part of this RFQ/RFP are available for downloading on the Connecticut Department of
Administrative Services Contracting Portal which may be accessed at https://portal.ct.gov/das/ctsource/bidboard?language=en_US (“State Portal”) and on SBC’s website
(“Committee Website”) at the following URL: https://www.seymourschools.org/district-infomation/bungay-building-committee-information, and may be examined at the offices of the Town of
Seymour Chief Administrative Officer, located at the office of the Seymour First Selectwoman, Seymour
Town Hall, at 1 First Street, Seymour, CT 06483, by contacting W. Kurt Miller, Town of Seymour Chief
Administrative Officer via email at kmiller@seymourct.org. Legal notice of this RFQ/RFP, inviting sealed qualifications and sealed proposals has been published in a local newspaper.
https://portal.ct.gov/das/ctsource/bidboard?language=en_US https://www.seymourschools.org/district-infomation/bungay-building-committee-information https://www.seymourschools.org/district-infomation/bungay-building-committee-information mailto:kmiller@seymourct.org
Sealed qualifications submissions and sealed fee proposals submitted by proposers in response to this
RFQ/RFP (together, “Submissions”) must be received by Town of Seymour Chief Administrative
Officer W. Kurt Miller, on behalf of the SBC, at the office of the Seymour First Selectwoman, located in
Seymour Town Hall at 1 First Street, Seymour, CT 06483, no later than NOVEMBER 10, 2026, at
10:00 am. Submissions from Proposers are required to include responses to both the Request for
Qualifications and the Request for Proposals included in this RFQ/RFP, in accordance with the requirements set forth in the Instructions to Proposers. Proposers must respond to both the RFQ and the RFP separately.
Responses must be submitted in separate sealed envelopes, clearly marked with the name of the Proposer, and the words, as applicable:
“Response to Request for Qualifications for Commissioning Agent Services for New Bungay
Elementary School RFQ/RFP No. 2026-04” or
“Response to Request for Proposals for Commissioning Agent Services for New Bungay Elementary
School RFQ/RFP No. 2026-04” with the Proposer’s name. Each sealed envelope shall include the original and three (3) copies of the enclosed qualifications submission or fee proposal, as applicable, together with one copy in pdf format submitted on a thumb drive. No fee or hourly rate information shall be included with any qualifications submission in response to the RFQ, and may only be included in the proposer’s sealed envelope containing their proposal in response to the Request for Proposals.
Submissions will be opened (excluding the sealed envelopes containing Fee Proposals) at the Office of the
Seymour First Selectwoman, located in Seymour Town Hall at 1 First Street, Seymour, CT 06483, at
10:00 am on November 10, 2026. After Submissions have been opened on behalf of the SBC, no
Submission may be modified or withdrawn for ninety (90) days after the date such Submissions were opened.
Any questions and requests for information concerning this solicitation shall be submitted only by email to
Town of Seymour Chief Administrative Officer W. Kurt Miller, on behalf of the SBC, at kmiller@seymourct.org, cc’d to Jack Butkus, Senior Program Manager for Arcadis U.S., Inc., at john.butkus@arcadis.com, no later than 4:00 pm on October 27, 2026. Responses to questions and requests for information by the SBC will be provided by addendum to this RFQ/RFP, posted on the State Portal and on the Committee Website no later than November 5, 2026. Under no circumstances will the SBC respond to non-written questions or requests for information.
No Proposer or prospective Proposer shall have any contact or communication with any member of the SBC or any Town, District, or Seymour Board of Education officer, representative, employee, or member of any board, commission, or committee regarding this procurement during the pendency of this procurement, except as expressly provided and permitted in this RFQ/RFP and the Instructions to Proposers. Failure to comply with these conditions will result in the disqualification of the noncomplying Proposer.
The SBC, for itself, the District, and the Town, reserves the right to amend or withdraw this RFQ/RFP for any reason, to accept or reject any or all qualifications or proposals submitted, to waive any informalities or non-material deficiencies in any such submission(s), and to make an award (or make no award) of a contract in connection with this RFQ/RFP, all as determined by the SBC and/or the
Town, in their discretion, to be in the best interests of the Town and District. Submissions, including qualifications submissions and/or proposals, may be rejected for irregularities of any kind, including, without limitation, alteration of form, additions not called for, conditional proposals, and incompleteness. Submitted qualifications or submitted proposals may also be rejected if, in the opinion of the SBC or Town, the same do not meet the standard of quality established by this RFQ/RFP. Any or all Submission of qualifications and/or proposals may be rejected if there is any reason to believe that collusion exists among two or more parties submitting qualifications or proposals. The foregoing provisions are for illustrative purposes and shall in no way limit the right of the SBC or Town to reject any and all qualifications or proposals submitted, in whole or in part.
Attached Exhibits:
Exhibit A: Scope of Services
Exhibit B: Form of Contract
Exhibit C: Insurance Requirements
Exhibit D: Non-collusion Affidavit
Exhibit E: Fee Proposal Form
Exhibit F: Seymour Public School District’s Educational Specifications for the Project dated
September 30, 2025 (Rev.2)
Exhibit G: Project Program Confirmation Conceptual Plans prepared by Tecton Architects, Inc.
Exhibit H: A preliminary Project Schedule (as of October 9, 2026), prepared by Arcadis U.S., Inc. (for information and reference purposes only)
INSTRUCTIONS TO PROPOSERS
1. INTRODUCTION
The SBC and Town are requesting sealed qualifications and sealed proposals from qualified professional firms to provide the commissioning Services for and in connection with the design, construction, occupancy, and closeout of the Project. This RFQ/RFP is both a request for qualifications and a request for proposals for commissioning Services necessary for the Project.
Proposers are required to respond to both the RFQ and RFP in accordance with the requirements set forth in these Instructions to Proposers. Please see Sections 5 through 8 of these Instructions to Proposers for important details about the submission process and requirements.
This RFQ/RFP, including all exhibits that are a part of this RFQ/RFP, may be downloaded from the State
Portal at the following URL link: https://portal.ct.gov/das/ctsource/bidboard?language=en_US and from the
Committee Website at the following URL link: https://www.seymourschools.org/district-infomation/bungay-building-committee-information.
This RFQ/RFP includes, among other exhibits: the District’s Educational Specifications for the Project dated
September 30, 2025 (Rev. 2) (the “Educational Specifications”), furnished by Construction Solutions
Group, LLC and appended as Exhibit F; Project Program Confirmation Conceptual Plans prepared by
Tecton Architects, Inc. (“Tecton”), which are subject to change and further development, and which are appended as Exhibit G; and a preliminary Project Schedule prepared by Arcadis U.S., Inc. (“Arcadis”), which is appended as Exhibit H (both Exhibits G and H are provided for information and reference purposes only).
The SBC is the school building committee established by the Town for the Project.
2. PROJECT BACKGROUND, SCHEDULE, AND BUDGET
The existing Bungay Elementary School building (the Existing Building) is located at 35 Bungay Road, Seymour, Connecticut (the Property), and was originally constructed in 1952 with subsequent renovations in
1971 and 1996. The renovations included the addition of single-story classroom spaces and various facility updates. The current building encompasses a total of 59,600 square feet. The current student population of the Bungay Elementary School is 465 and the school serves Pre-Kindergarten through Grade 5. The Property where the Existing Building is located is a 19.2-acre site. The Existing Building and Bungay Elementary
School facilities have various shortcomings and limitations that affect students and school staff daily, are inadequate to best serve the educational and instructional needs of students and school staff, and are inadequate to provide for the safety, physical needs and comfort of the students and staff, including, but not limited to, the social and emotional needs of the student population.
This Project will include the construction of a new Bungay Elementary School building that will be approximately 71,673 square feet, school facilities, and improvements to school grounds at the Property
(collectively the “New Building”), on the same Property where the Existing Building is located. The New
Building will replace the Existing Building, will be used by the District for grades Pre-Kindergarten through
Fifth grade, will accommodate the District’s enrollment projections (553 students), and will serve as a twenty-first century learning environment which addresses the needs identified by students, staff, administrators, and SBC members. The Project will include the demolition and removal of the Existing
Building after construction of the New Building is complete.
https://portal.ct.gov/das/ctsource/bidboard?language=en_US
It is anticipated that the Project will be constructed in the following phases:
1. First Phase – Conduct any environmental remediation for the New Building location that is required by applicable Connecticut law; sitework; and construction of the New Building, facilities, and grounds while the Existing Building continues to be used and occupied by the
District.
2. Second Phase – FF&E, Technology, and “move in” to transition to the New Building, including relocation of technology, furniture, equipment, and all items of personal property required by the
District from the Existing Building to the New Building.
3. Third Phase – Demolition and removal of the Existing Building including any necessary abatement and/or environmental remediation.
4. Fourth Phase – Sitework and construction of athletic fields and/or playground equipment on the former location of the Existing Building, and landscaping.
Additional information is provided in the District’s Educational Specifications for the Project and the Project
Program Confirmation Conceptual Plans appended as Exhibit G.
The project delivery method for this Project will be a “construction manager at-risk” (“CMR”) for the
Project, pursuant to a construction management agreement with a guaranteed maximum price (“GMP”) between CMR and the Town and SBC together as “Owner.”
In addition to engaging the selected Proposer as the Commissioning Agent for the Project, and a construction management firm as the CMR, the Town and SBC have engaged Tecton Architects, Inc., which, together with its subconsultants, will be the Project design team for the Project (the “Architect”) and will provide all architecture and design services (except those to be provided by other consultants directly engaged by the
Town and SBC), as well as other project and construction administration services. The Town and SBC have also engaged Arcadis U.S., Inc., as the Owner’s Project Manager and Owner’s Representative for the Project
(the “OPM”).
In addition to the CxA, the CMR, the OPM, and the Architect, the SBC and Town intend to engage the following professionals and consultants for the Project: a land surveyor for site survey and wetlands delineation; a vendor/contractor for materials and testing laboratory and inspection services during construction; if required for the Project, a third-party envelope consultant to review design documents and to perform building envelope inspections and testing; if required for the Project, a third-party independent code consultant; if required for the Project, a third-party structural review consultant; and a contractor or vendor to provide move-in services for the District after the Work for the New Building is complete. All design professional and consultant services required for the Project, other than services by the CxA, CMR, OPM, the Town’s and SBC’s land surveyor, third-party envelope consultant, third-party code consultant, and third-party structural review consultant, are anticipated by the SBC and Town to be provided by the Architect and its subconsultants, including without limitation, the following to the extent each is required for the Project:
structural engineering; mechanical engineering; electrical engineering; plumbing engineering; fire protection engineering; civil engineering; land survey; traffic study; landscape design; geotechnical engineering and/or surveyor and borings consulting; environmental consulting; abatement consulting; cost estimating; early education architectural services and furniture, fixtures and equipment (“FF&E”) design; lighting design;
kitchen food service design; security, technology, data, and communications design; acoustical design; code compliance consulting; and sustainability consulting.
It is anticipated that the Project will be partially funded by a school building project priority list grant from the State of Connecticut through CTDAS.
The total Project budget is approximately $56,346,000, and includes the approximate amount of $44,465,080 for the cost of construction -- including $3,717,622 for potential construction cost escalation and $1,082,803 for contingencies. Of the $44,465,080 total Project budget for construction costs, approximately $42,912,877 may be used for the costs for construction of the New Building, facilities and grounds, and approximately
$1,552,203 is allocated for the costs of demolishing and removing the Existing Building and any hazardous materials abatement or environmental cleanup work required in relation to demolition and removal of the
Existing Building. The portion of the Project’s construction budget allocated to furnishings and equipment includes $1,447,783 for equipment and $49,039 for furnishings. The portion of the Project’s soft cost budget, which is separate from the estimated costs of construction, includes $1,000,000 allocated for FF&E and
$520,750 for technology, respectively, for items including but not limited to furniture, fixtures, network equipment, servers, computers, printers, and surface and other associated equipment, as selected by the SBC and Town.
3. SCOPE OF COMMISSIONING AGENT SERVICES
All the Services by the CxA must be provided with the highest level of professional skill, care, and judgment and in compliance with all federal, state, and local requirements. Because the Project will be partially funded by a State of Connecticut school building project grant administered by CTDAS and OGA, the firm selected as CxA is required to satisfy any requirements and conditions imposed by the State of Connecticut.
The scope of the Services to be performed and provided for the Town, SBC, District and Project by the firm selected as the CxA are those described and required in this RFQ/RFP, including Exhibit A to this RFQ/RFP and the form of Contract included as Exhibit B to this RFQ/RFP, and include all commissioning services that are usually and customarily performed and provided by a commissioning agent when furnished for the awarding authority and public school district in connection with a project for the construction of a new public school building having a similar or greater scope, magnitude, and complexity as the Project, that is partially funded by a priority list school building project grant administered by CTDAS and provided pursuant to Connecticut General Statutes Chapter 173 and applicable regulations of the State of Connecticut.
The firm selected as the CxA shall be required to work with the Architect, CMR and OPM in all aspects of the design and construction of the Project related to the commissioning of building systems as will be set forth in greater detail in the construction documents for the Project prepared by the Architect and design team. The building systems to be commissioned as part of and in connection with the Services shall include all Project building systems required by the Connecticut High Performance Building regulations, and all
Project building systems otherwise specified in Exhibit A to this RFQ/RFP.
The commissioning Services to be provided by the CxA are required to, among other things, measure and verify the quality of the construction of the Project, so as to ensure that the Project building as-constructed meets the intent of the design for the Project. The firm selected as CxA may suggest for consideration by the
SBC and OPM changes and improvements to the process(es) for the performance of the Services.
4. TIMING OF PROJECT
See the preliminary Project Schedule appended as Exhibit H (for information and reference purposes only).
The present anticipated overall Project schedule includes a standard design, bid, and construct process (with and through the CMR), such that the District can take occupancy of the New Building in July 2029 prior to and for the beginning of the 2029-2030 academic year. As of the issuance of this RFQ/RFP, the Town and
SBC anticipate that all construction documents for the Project building will be completed by the Architect and ready for bidding by the end of August 2027, including all prior estimating, review, approvals by governing authorities, pre-bid conformance review (“PCR”) by CTDAS OGA, and approval by OGA to proceed with bidding by the CMR, except those required for Project technology and FF&E design and procurement. Based on the presently anticipated Project schedule, bidding for the Project elements inclusive of building systems is estimated to begin in or about late October 2027, on-site construction is estimated to begin December 2027, and the Project is anticipated to achieve Substantial Completion by mid-June 2029, to allow for move-in before the beginning of the District’s 2029-2030 school year. Punchlist and commissioning are anticipated to begin mid-June 2029, with commissioning reaching completion by the end of October 2029. See Exhibit H.
5. IMPORTANT DATES
1. Issuance of RFQ/RFP: October 15, 2026
2. Submission of Questions/Requests for Information: By October 27, 2026 at 4:00 pm
3. Addenda/Responses to Requests for Information: By November 5, 2026
4. Deadline for Submission of Responses to RFQ and RFP: November 10, 2026 at 10:00 am
5. Interviews of qualified Proposers (if required by the SBC and by invitation only): Week of November 16, 2026
6. Anticipated Contract Award and commencement of services: Week of November 30, 2026
6. PROCESS
6.1 Responses to the RFQ and RFP
Proposers must respond to both the RFQ and the RFP separately. Sealed Submissions in response to this RFQ/RFP must be received by W. Kurt Miller, Town of Seymour Chief
Administrative Officer, on behalf of the SBC, at the office of the Seymour First Selectwoman, located in Seymour Town Hall at 1 First Street, Seymour, CT 06483, no later than NOVEMBER
10, 2026, at 10:00 am.
Response Submissions to the RFQ and the RFP must be submitted in separate sealed envelopes, clearly marked with (1) the name of the Proposer, and (2) the words, as applicable:
“Response to Request for Qualifications for Project Commissioning Agent Services for New
Bungay Elementary School RFQ/RFP No. 2026-04” or
“Response to Request for Proposals for Project Commissioning Agent Services for New Bungay
Elementary School RFQ/RFP No. 2026-04”
No fee or hourly rate information or information pertaining to the Proposer’s fees or costs for the Services for the Project shall be included with any qualifications submission in response to the RFQ, and may only be included in the Proposer’s sealed envelope containing their proposal in response to the Request for Proposals. Responses that are not submitted in this manner will be rejected.
Each sealed envelope must include the original and three (3) paper copies, and a digital copy (thumb drive is acceptable), of either the Proposer’s qualifications submission or the Proposer’s fee proposal in response to the RFP, as applicable. Responses must be delivered by U.S. Mail or hand delivered.
Facsimile (FAX) or email proposals will not be accepted by the SBC under any circumstances.
Opening of Submissions (excluding the sealed envelopes containing Fee Proposals) shall take place at the office of the Seymour First Selectwoman, located in Seymour Town Hall at 1 First Street, Seymour, CT 06483, on November 10, 2026, at 10:00 am. After Submissions have been opened on behalf of the SBC, no Submission may be modified or withdrawn for ninety (90) days after the date such Submissions were opened.
No Proposer shall have any contact or communication with any member of the SBC or any Town, District, or Seymour Board of Education officer, representative, employee, or member of any board, commission, or committee regarding this RFQ/RFP during the pendency of this procurement, except as expressly provided and permitted in this RFQ/RFP and the Instructions to Proposers. All communications between any Proposer and the SBC, Town, or District regarding this RFQ/RFP, including inquiries, questions, and/or requests for information by a Proposer, must be in writing by email ONLY, and all inquiries by Proposers may be submitted by email up to 4:00 pm on October
27, 2026, after which time no additional inquiries, questions, or requests for information will be accepted. Inquiries, questions, and requests for information regarding this RFQ/RFP shall be directed to Town of Seymour Chief Administrative Officer W. Kurt Miller, on behalf of the SBC, at kmiller@seymourct.org, cc’d to Jack Butkus, Senior Program Manager for Arcadis U.S., Inc., at john.butkus@arcadis.com. Any addenda to this RFQ/RFP, including answers to questions and requests for information by prospective Proposers, will be posted on the State Portal and Committee
Website on or before November 5, 2026.
6.2 Selection Process
Evaluation of Submissions in response to this RFQ/RFP will be the responsibility of the SBC and the
District’s Superintendent. The selection of a Proposer as the CxA for the Project will be the responsibility of the SBC, subject to the approval of the Town’s Board of Selectpersons. The SBC and/or Town may reject any or all proposals for any reason as the SBC and/or Town deem appropriate.
The evaluation and selection process will take place in two stages.
First, the SBC (with the Superintendent) will review all Submissions in response to the RFQ and, based on those Submissions and the Qualification Criteria described below, the SBC will identify all proposers which they determine to be responsible qualified proposers (the “Qualified Proposers”).
Second, the SBC will open and review (with the Superintendent) the Submissions by the Qualified
Proposers in response to the RFP. Submissions in response to the RFP from Proposers who are not identified as a Qualified Proposer, will be returned unopened to the Proposers. The SBC will evaluate the Submissions in response to the RFP submitted by the Qualified Proposers, and will determine “at least three of the most responsible qualified proposers” (“Most Qualified Proposers”) using the Qualification Criteria and the Proposal Criteria set forth below in Sections 7 and 8, respectively, giving due consideration to each Qualified Proposer’s pricing for the Services for the
Project, as well as each Qualified Proposer’s (i) experience with services of similar size and scope as the Services required for the Project, (ii) organizational and team structure for the Services for the
Project, (iii) past performance data, including, but not limited to, adherence to project schedules and project budgets and the number of change orders for projects, (iv) the approach to the Services required for the Project, and (v) documented contract oversight capabilities. Proposers are encouraged to include in their Submission in response to the RFQ, documentation that provides examples of their work on prior projects having a similar character and image as that desired for this Project by the
SBC, Town and District.
In its review of Submissions in response to this RFQ/RFP and selection of the firm to be recommended to the Town Board of Selectpersons for award of a contract for the Services as the
CxA for the Project, the SBC and Superintendent will be guided by selection of the most responsible qualified proposer that would best serve the interests of the Town and District and is best able to provide the required Services desired, taking into account cost and the requirements, terms, and conditions contained in this RFQ/RFP.
If determined to be warranted by the SBC, the SBC may conduct interviews of the Proposers determined by the SBC to be among the Most Qualified Proposers to assist the SBC in the selection process. If such interviews are to be conducted, the SBC, through the OPM, will include in the interview requests to the Most Qualified Proposers, the name(s) of the member(s) of the SBC who will conduct the interview, and the date by which the Most Qualified Proposer must submit an affidavit disclosing its relationship(s) with the interviewer(s), or, confirming that it has no relationship(s) with the interviewer(s). The names of interviewers will be released solely to enable the
Most Qualified Proposer to prepare the affidavit, and neither the Most Qualified Proposer nor its representatives shall directly or indirectly contact the interviewer(s) prior to or following the interview process. Key members of each Most Qualified Proposer’s proposed Project team for the
Services must participate in the interview and Submission discussion with the SBC, including their proposed Project team members who would likely be interfacing with the SBC, OPM, and District representatives throughout the duration of the remainder of the RFQ and RFP process, and those who would be involved in the performance of the CxA obligations under the Contract.
Final selection of the Proposer that the SBC will recommend to the Town’s Board of Selectpersons for award of the contract as CxA for the Project shall be the Proposer determined by the SBC to be the most qualified responsible proposer for the Services after consideration of price and all factors necessary for faithful performance of the Services based on the criteria and scope of Services included in this RFQ/RFP.
The SBC and Town reserve the right to negotiate with the most qualified responsible proposer and to accept modifications to the scope of the Services and/or fees proposed if such action would be in the best interests of the Town and District.
Any Submission in response to this RFQ/RFP shall constitute a declaration by the submitting
Proposer that no person or persons other than members of Proposer’s own organization are interested in the Project or in the contract proposed to be awarded through this RFQ/RFP procurement process;
that the Submission is made without any connection with any other person or persons making a proposal for the same Services and is in all respects fair and without collusion or fraud; that no persons acting for or employed by the SBC, Town, District, or Seymour Board of Education are directly or indirectly interested therein, or in the supplies or works to which it relates or will receive any part of the profit or any commission therefrom in any manner which is unethical or contrary to the best interests of the Town and District.
6.3 Form of Contract
The SBC and Town intend to use, and the firm selected as the CxA for the Project will be expected to execute, a contract substantially similar to the form of contract that is included as Exhibit B to this
RFQ/RFP (the “Contract”). If a Proposer has objections or takes exception to any of the terms and conditions of the Contract, the Proposer shall include such objections or exceptions, together with proposed revisions, in the sealed envelope containing the Proposer’s response to the RFP, provided that any such objections or exceptions and proposed revisions shall be stated on a separate document from the Fee Proposal form. The SBC will not consider any objections, exceptions or proposed revisions to the terms and conditions of the Contract not stated by a Proposer and submitted as required by this RFQ/RFP.
6.4 SBC’S and Town’s Right to Withdraw/Reject
The SBC and Town reserve the right to amend or terminate this RFQ/RFP, accept all or any part of a
Submission, reject all Submissions and not award the Contract, waive any informalities or non-material deficiencies in a Submission, and award the Contract to the Proposer that, in the judgment of the SBC and Town, will be in the best interests of the District and Town.
7. REQUEST FOR QUALIFICATIONS
7.1 Qualification Criteria
The SBC (with the Superintendent) will identify those proposers that the SBC deems to be Qualified
Proposers based on the criteria below (the “Qualification Criteria”):
7.1.1 The Proposer is a legal entity properly licensed or registered under the laws of the State of
Connecticut to perform the services that are the subject of this solicitation and is otherwise authorized to do business in the State of Connecticut.
7.1.2 The Proposer has adequate professional expertise and experience in providing building system commissioning services as the commissioning agent for Connecticut public school building projects during the past five (5) years, in particular, projects eligible for State of Connecticut school building project grants from the State through CTDAS and OGA, including projects of a similar scope, magnitude, and complexity as the Project which are subject to the
Connecticut High Performance Building Standards for State Agency and School Buildings and compliance with Connecticut General Statutes Section 16a-38k and related regulations.
7.1.3 The Proposer is able to demonstrate an adequate level of performance in providing services similar to the Services on at least three (3) prior school building projects in the State of
Connecticut that the Proposer completed within the past ten (10) years, which were similar in scope, magnitude, and complexity as the Project, including, without limitation, adherence to project schedules and project budgets to the satisfaction of past owners with such performance.
7.1.4 The Proposer is able to demonstrate that its staff proposed to be assigned to the Project and who will perform the Services (“Project Team”) has satisfactory qualifications and experience providing commissioning services substantially similar in nature to the Services on past projects of similar size, scope, and complexity as the Project, including that Project Team members have performed satisfactorily with respect to schedule, cost control, work quality and cooperation with the project owner on past projects to the satisfaction of the owners of such projects.
7.1.5 The Proposer has an adequate degree of technical expertise in building system commissioning, and the organizational, team, and management structure proposed for the
Project is satisfactory.
7.1.6 The Proposer is able to demonstrate its ability to meet the requirements, terms and conditions set forth in this RFQ/RFP.
7.1.7 The Proposer is able to demonstrate its ability to support the Town’s and District’s completion of the Project within the anticipated timeline, and to commit staff in a timely way as-required to do so.
7.1.8 The Proposer’s approach to the Project and degree of the Proposer’s demonstrated ability to develop and control project costs, quality, and schedule as well as the Proposer’s methods for doing so, is satisfactory.
7.1.9 The number, context, and, where applicable, outcomes, of claims, disputes, arbitration, and litigation proceedings involving the Proposer are acceptable.
7.2 Content of Response to RFQ
Each Proposer will be evaluated using the above Qualification Criteria. Submissions in response to the RFQ shall provide concise description of the Proposer’s ability to meet the requirements of this
RFQ/RFP, emphasizing the quality, completeness, clarity of information provided, responsiveness to the requirements, and an understanding of the Project. To assist and expedite this evaluation, each
Proposer’s Submission in response to the RFQ must provide the following information, organized as set forth below:
7.2.1 A Letter of Transmittal and Interest addressed to the Chairperson(s) of the SBC, signed by a principal of the Proposer, not to exceed three (3) pages, describing in narrative form the
Proposer and Proposer’s qualifications and why such Proposer is the best firm for the Project and the Services.
7.2.2 Proposer Information and Overview. Please provide the following:
7.2.2.1 The name and location of the Proposer, including the address of the principal office and the office which will serve the Town and SBC.
7.2.2.2 Any prior name(s) by which the Proposer was known and the years during which such name(s) was used
7.2.2.3 A brief general description of Proposer’s business and its primary line of business of
Proposer.
7.2.2.4 The number of years the Proposer has been in business.
7.2.2.5 Is the Proposer an entity that is a subsidiary of another entity? If so, what is the name of the parent entity?
7.2.2.6 Name(s) of any subsidiary or other company owned or controlled by the Proposer;
7.2.2.7 The number of personnel employed by the Proposer (please include the number of staff dedicated to provide the requested Services).
7.2.2.8 Name, address, telephone number and email address of the principal contact person to receive notifications and to reply to inquiries from the Town, the SBC, or the
OPM in connection with this RFQ/RFP.
7.2.2.9 Names, titles, reporting relationships, and background and experience of the principal members of the Proposer’s company, including officers. Indicate which individuals are authorized to bind the Proposer during contract negotiations, if any, with the SBC and Town.
7.2.3 Statement of Qualifications to include, but not necessarily limited to, the following:
7.2.3.1 Background statement on the firm, principals, staff availability, location, and financial stability, and a brief summary statement as to why the Proposer believes it is the best qualified to meet the needs of Town, District, SBC and Seymour Board of
Education for the Services.
7.2.3.2 Project Team, Organization, and Experience of Key Personnel:
• Provide an explanation of the Proposer’s staffing approach for the Project.
• Provide a list of Proposer’s Project Team Members, and key personnel
(including any consultants) who will be assigned to the Project, together with each person’s qualifications and position with the Proposer or consultant firm, and a brief description of the roles and responsibilities each will have with respect to the Project and the Services, so as to demonstrate each Team
Member’s ability and experience in providing commissioning services for public school construction projects in Connecticut.
• Include a complete resume for each Team Member, including current title/position, responsibilities, and type of services performed, and time with the
Proposer (or consultant firm); educational background, academic degrees, professional associations; a brief description of relevant experience on projects similar to this Project, and their specific role, including specific information regarding their experience in particular commissioning tasks (e.g., design reviews, specification writing, commissioning management, troubleshooting, test writing, test execution, energy management, sustainable design, project phasing, testing, adjusting and balancing, building simulation, indoor air quality, O&M experience, energy-efficient equipment design and control strategy optimization, project and construction management system design (specify), and troubleshooting.
• Indicate whether the Proposer’s proposed commissioning lead and other Project
Team members are certified as a Certified Commissioning Professional (CCP) by the Building Commissioning Association or hold an equivalent commissioning certification from the Association of Energy Engineers. The CxA will be required to maintain such certification during the entire term of the
Contract, as provided in Section 2 of the form of Contract.
7.2.3.3 Relevant Prior Experience and References:
• List and describe three (3) prior public school construction projects or projects funded by State grants or other State financial assistance that the Proposer has completed as the project commissioning agent, and which demonstrate the
Proposer’s Team Members’ ability to support those project owners’ maintenance of and control over project costs and budgets, quality, and project schedules.
Include in the description of each relevant project: relevant project data, such as the project type, location, size (square feet), and scope of construction work and any features pertinent to the Services for this Project; Project Team Members involved and their responsibility for or participation in commissioning services for particular project building systems; and challenges presented by the project which are similar to anticipated challenges for this Project.
• Provide reference information for five (5) clients or owners whom the Proposer has served in connection with similar projects, for services relevant to the
Services requested, as well as the contact information for the architect or engineer(s) for each project. Include for each: client/owner and architect or engineer, their name and location; contact person and title (specific individuals);
and telephone number and email address.
7.2.4 Project Approach and Methodology: Provide a description of the Proposer’s approach for the
Services to be provided by the Proposer if selected as CxA for the Project, including the proposed technical approach to the Project, and the identification of any unusual circumstances or anticipated problems together with suggested potential solutions. The information will be used by the SBC to assess each Proposer’s understanding of the Project and the Proposer’s proposed methodology for the Services.
7.2.5 Workload Statement. Provide details on the Proposer’s current and future workload and ability to support the District’s and Town’s completion of the Project within the time schedules outlined in the RFQ/RFP. Identify projects for which the Proposer is currently under contract, the percentage of completion and the expected completion date.
7.2.6 Additional information, not included above, that the Proposer believes may be useful and applicable to this Project and helpful to the SBC’s evaluation of Submissions. Please limit response to two (2) pages.
7.2.7 Default and Litigation: (a) State whether the Proposer has ever failed to complete any project or portion of a project awarded to it. (b) State whether the Proposer has ever been declared to be in default on a contract, and if so, when, by whom, where and reason. (c) Describe any claims, disputes, arbitration or litigation proceedings that have occurred in relation to any projects performed by the Proposer in the past five (5) years and in which the Proposer may be involved, including the nature and amount of any claims against the Proposer, the status of the proceeding, and, if concluded, the outcome.
7.2.8 A fee schedule for the Services should not be included in the RFQ response.
8. REQUEST FOR PROPOSALS
8.1 Proposal Criteria
The Proposal Criteria includes the following:
8.1.1 The Proposer’s fee proposal using the form included in the RFQ/RFP as EXHIBIT E.
8.1.2 The Proposer’s proposed schedule for the Services.
8.1.3 The level of financial stability of the Proposer.
8.1.4 The level of the Proposer’s insurance coverage.
8.1.5 The degree of resources that the Proposer will devote to facilitate the Project and performance of the Services.
8.1.6 The Proposer’s objections, exceptions, and/or proposed revisions to the terms and conditions of the form of Contract submitted by the Proposer, if any.
8.2 Content of Response to RFP
Please provide the following information in the order listed below:
8.2.1 One lump sum proposed fee for all the Services during all phases of the Project (the “Base
Services”) and an amount of the lump sum proposed fee for the Base Services that is allocated to the Project’s respective phases for design and pre-construction, procurement and construction, pre-occupancy, occupancy/post-occupancy and operations, as well as the amount allocated to any Services specifically anticipated to be provided by the CxA through subconsultants, all as set forth on the fee proposal form included as EXHIBIT E in this
RFQ/RFP. The lump sum fee amount and allocated portions thereof stated on each Proposer’s
Fee Proposal Form must be inclusive of all costs the Proposer will incur in providing the Base
Services and fees proposed by the Proposer for the Base Services, excepting only reimbursable expenses that the Town and SBC expressly agree, in the agreement between the
Town and SBC (as Owner) and the CxA, will be reimbursed to the CxA in addition to payment of the CxA’s fee for the Base Services.
8.2.2 Hourly rates for each position or classification of the Proposer’s employees who will perform any of the Services for which the Proposer will be compensated on an hourly-fee basis pursuant to the Contract, or any Additional Services which are not within the scope of the
Base Services.
8.2.3 Bank references and/or financial statements reflecting financial stability.
8.2.4 Evidence of ability to satisfy insurance coverage requirements set forth in Exhibits B and C to this RFQ/RFP.
8.2.5 Descriptions of other resources of the Proposer that will help facilitate the performance and completion of the Services and the Project (submitted separately from the Proposer’s fee proposal form).
8.2.6 The Proposer’s objections, exceptions, and/or proposed revisions to the terms and conditions of the form of Contract, if any (submitted on a separate page from the other documents included as part of the Proposer’s Fee proposal submission).
8.2.7 A completed and notarized Non-Collusion Affidavit in the form included as Exhibit D to this
RFQ/RFP.
9. INSURANCE REQUIREMENTS
Prior to the execution of the Contract for the Services for the Project, the SBC and Town will require the firm selected as the CxA to provide to the SBC and Town certificates of insurance (ACORD or other approved format), and if specifically requested, policy declaration pages and policy endorsements, evidencing the insurance coverage which satisfies the requirements set forth in Section 13 of the form of
Contract included as Exhibit B to this RFQ/RFP, and the requirements set forth in Exhibit C to this
RFQ/RFP.
10. PROJECT FUNDING
The obligations of the Town and SBC under any contract executed by the Town and SBC in connection with this Project are conditioned upon and subject to the appropriation of funds for the Project.
11. ADDITIONAL INFORMATION
11.1 The SBC, Town, District, and Seymour Board of Education prohibit harassment and discrimination on the basis of race, color, religious creed, age, marital status, military or veteran status, national origin, sex, ancestry, sexual orientation, gender identity or expression, genetic information, or past or present history of mental disability, intellectual disability, learning disability, or physical disability in accordance with Title VII of the Civil Rights Act of 1964, Section 504 of the Rehabilitation Act of
1973, the Americans with Disabilities Act of 1990, and applicable state laws.
11.2 The SBC, Town, the firm selected as CxA, and the Services will be governed by the applicable
Connecticut General Statutes, Connecticut regulations, and the CTDAS rules, requirements, and policies which govern school building projects receiving State assistance and in particular, school building project grants through CTDAS.
11.3 The SBC and Town reserve the absolute right to reject the Submissions of any Proposer offering services which, in the opinion of either the SBC or Town, do not meet the standard or quality established and required by this RFQ/RFP.
11.4 Any Proposal that is conditional shall be rejected.
11.5 The SBC and Town are exempt from the payment of federal excise taxes and Connecticut sales and use taxes.
11.6 If it becomes necessary for the SBC to revise any part of this RFQ/RFP or if additional data is necessary to enable Proposers to interpret any provision of this RFQ/RFP, revisions or addenda will be posted on the State Portal and the Committee Website. The SBC may, at any time before the opening of Submissions in response to this RFQ/RFP, in its sole discretion, clarify, modify, amend, or terminate this RFQ/RFP if the SBC determines that doing so is in the Town’s and District’s best interests.
11.7 Questions regarding this RFQ/RFP should be referred to the SBC via email to W. Kurt Miller, Town of Seymour Chief Administrative Officer, at kmiller@seymourct.org, cc’d to Jack Butkus, Senior
Program Manager for Arcadis U.S., Inc., at john.butkus@arcadis.com. Any addenda to this
RFQ/RFP, including a summary of questions and answers, will be posted on the State Portal and the
Committee Website as an addendum to this RFQ/RFP on or before November 5, 2026. Under no circumstances will the SBC or Town respond to non-written questions or requests for information.
RFQ-RFP EXHIBIT A
SCOPE OF SERVICES
The firm selected by the Town of Seymour (in this Exhibit A, the “Town”) and Bungay Elementary School
Building Committee (in this Exhibit A, the “SBC”) to be the Commissioning Agent (the CxA) for the
Project, shall provide all the Services. Subject to adjustments to the scope of the Services that are agreed to in the written agreement for the Services entered into by the CxA and the Town (as the Project “Owner” under such written agreement), the Services include, at a minimum, the commissioning services and related services set forth and otherwise described in this RFQ/RFP and this Exhibit A as the Services to be provided by the CxA, as well as the performance and satisfaction of…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .