This Addendum No. 2, issued by the Connecticut Department of Administrative Services (DAS) Construction Services on October 22, 2026, modifies the contract documents for the Solnit South Chiller Replacement project located at 915 River Road, Middletown, Connecticut (BI-YS-184). The original bid due date remains November 24, 2026 at 10:00 a.m., and prospective bidders must acknowledge receipt of all addenda on the Bid Proposal Form or face disqualification. A pre-bid walkthrough was conducted on October 20, 2026, with minutes and attendance logs attached to this addendum. The Request for Information (RFI) deadline is November 10, 2026 at 10:00 a.m., with all questions to be submitted via email to the consulting Architect/Engineer (AI Engineers Inc., sahmetovic@aiengineers.com) with copies to the DAS/CS Project Manager (Alan Ladson and Rahul Abraham).

The addendum clarifies five key project requirements: a project schedule is not required until after contract award; permit fees are waived by the owner; preventative maintenance is not required post-completion; an 18-month workmanship and material warranty is required from the date of Substantial Completion (superseding the one-year warranty referenced in the original contract documents); and no project schedule must accompany the initial bid submission. Bidders are directed to submit all inquiries in writing only, with copies distributed to both the project architect/engineer and DAS project managers to ensure comprehensive communication and documentation throughout the bidding process.

View the file

Other files

File Type Posted
2623BIYS184_Oct_30_26_solicitation_doc.pdf PDF
00 40 14 CertOfAuthority 20231001.docx DOCX document
RWR Womens Locker Room Bid Set 10-23-26.pdf PDF
2623BIYS184_Oct_20_26_solicitation_doc.pdf PDF
00 45 20 Named Sub Signature Page 20251001.docx DOCX document
00 11 16 DAS-CS Invitation to Bid.pdf PDF
Addenda 1.pdf PDF
00 41 00 DAS-CS Bid Proposal Form LOCKED 07.01.2026.docx DOCX document
2623BIYS184_Nov_3_26_solicitation_doc.pdf PDF
00 45 14 GC Bidder Qual Statement 20251001.docx DOCX document
2623BIYS184_Nov_19_26_solicitation_doc.pdf PDF
2623BIYS184_Oct_28_26_solicitation_doc.pdf PDF
2623BIYS184_Nov_4_26_solicitation_doc.pdf PDF
00 40 16 DAS Update Stmt Reqts 20251001.docx DOCX document
2623BIYS184_Nov_11_26_solicitation_doc.pdf PDF
00 40 15 DAS Prequal Cert Reqts 20251001.docx DOCX document
2623BIYS184_Nov_6_26_solicitation_doc.pdf PDF
2623BIYS184_Nov_12_26_solicitation_doc.pdf PDF
Drawings.pdf PDF
2623BIYS184_Nov_18_26_solicitation_doc.pdf PDF
2623BIYS184_Nov_17_26_solicitation_doc.pdf PDF
00 43 16 BidBond 20240924.docx DOCX document
2623BIYS184_Nov_5_26_solicitation_doc.pdf PDF
RFQ-RFP 2026-04 for Commissioning Agent Services - Bungay ES Project.pdf PDF
2623BIYS184_Nov_10_26_solicitation_doc.pdf PDF
2623BIYS184_Nov_13_26_solicitation_doc.pdf PDF
2623BIYS184_Oct_29_26_solicitation_doc.pdf PDF
2623BIYS184_Oct_15_26_solicitation_doc.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Connecticut Department of

Administrative Services

Bid Addendum

Addendum No.: 02 Date Of Addendum: 10/22/2026

CT DAS 6030 (Rev. 08.09.2024) 6000 Bid Phase Forms

CT DAS Construction Services Office of Legal Affairs, Policy, and Procurement Solnit South Chiller Replacement

915 River Road, Middletown, CT 06457

BI – YS – 184

Original Bid Due Date / Time: 11/24/2026 10:00 AM

Previous Addendums: Addendum 01 10/19/2026

TO: Prospective Bid Proposers:

This Addendum forms part of the “Contract Documents” and modifies or clarifies the original “Contract Documents” for this Project dated 1-30-2026. Prospective Bid Proposers shall acknowledge receipt of the total number the Addenda issued for this Project on the space provided on Section 00 41 00 Bid Proposal Form.

Failure to acknowledge receipt of the total number the Addenda issued for this Project on the space provided on Section 00 41 00 Bid Proposal Form shall subject Bid Proposers to disqualification.

The following clarifications are applicable to drawings and specifications for the project referenced above.

Item 1:

Question: Is a project schedule required with the bid?

Answer: No, Schedule not required until contractor is awarded the project.

Item 2:

Question: What is the RFI deadline?

Answer: November 10 @ 10am

Item 3:

Question: Are permit fees waived?

Answer: Yes.

Item 4:

Question: Are we required to provide preventative maintenance once the job is done? If so, for how long? This would be separate from our 1 Year Workmanship Warranty.

Answer: No preventative maintenance required. 18-month workmanship and material warranty is required from date of Substantial Completion.

Item 5:

Attached are the pre-bid meeting minutes and attendance log from the walkthrough held on site on 10/20/2026.

All questions must be emailed (not verbal or by phone) to the consulting Architect/Engineer (AI Engineers Inc, Email:

sahmetovic@aiengineers.com) with copies sent to the DAS/CS Project Manager (Alan Ladson, Email: Alan.Ladson@ct.gov and Rahul Abraham, Email: Rahul.Abraham@ct.gov)

End of Addendum 02

Alison Kulas Alison Kulas, Paralegal Specialist State of Connecticut Department of Administrative Services, Construction Services Office of Legal Affairs, Policy, and Procurement 450 Columbus Boulevard, Suite 1307 Hartford, CT 06103 mailto:Alan.Ladson@ct.gov

LadsonA Tardy

LadsonA Text Box

TARDY

LadsonA Text Box

TARDY

Item 1:
Item 2:
Item 3:
Item 4:
Item 5: