Addendum #1 for RFQ# CDS/250560 is issued by the City of Ocala for the Euster Brown Rehabilitation project, dated June 17, 2025. The addendum provides clarifications and additional specifications for various aspects of the rehabilitation project, including hall bath shower requirements, HVAC equipment handling, water heater closet construction, flooring specifications, interior repairs, and detailed exterior repairs. Specifically, the document adds Item 15 for Exterior Repairs, which includes provisions for repairing/replacing front and back porch decking with specific material allowances, replacing back porch exterior steps with balusters and handrails, and installing a 4-inch thick concrete pad/landing with precise dimensional and finish specifications.
The addendum includes technical details such as allowances for decking materials (15 2x6x10 pt and 10 1x4x8 pt), with any overage requiring approval from the Rehab Inspector through a change order. The exterior step replacement must match existing width, include balusters and handrails on both sides, and the concrete landing must be high-strength with a broom finish, meeting industry standards. All exterior materials must be rated for exterior use, and steps must have closed risers. The document emphasizes the Rehab Inspector's role in approving variations from the specified requirements, ensuring strict adherence to the rehabilitation specifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum # 1
Date: June 17, 2025
To: All bidders
From: Ashley Presley, Buyer
Solicitation Number: RFQ# CDS/250560
Solicitation Title: Euster Brown Rehabilitation
SECTION 1. SOLICITATION ADDITIONS, CLARIFICATIONS AND CORRECTIONS
Item 3 Hall Bath
• Shower shall have a standard height curb. Shower base can fiberglass provided base is solid with minimal flex as determined by the Rehab Inspector.
Item 4 HVAC
• Leave existing HVAC equipment with owner.
Item 6 Water Heater
• Build closet for water heater with bi-fold door. Drywall/texture/paint exterior of closet. Texture shall match surrounding area. Install clam shell base board.
Item 8 Flooring
• Flooring pertains to hall/small bathroom.
Item 11 Interior Repairs
• Repair ceilings, plaster/drywall walls throughout.
ADD: Item 15 Exterior Repairs
• Repair/replace front/back porch decking. Allowance of 15 2x6x10 pt and 10 1x4x8 pt for decking replacement. Any overage shall be approved by the Rehab Inspector and submitted as a change order.
• Replace back porch exterior steps to include balusters and handrails both sides. Width of steps shall match existing.
• Install 4” thick concrete pad/landing at bottom of steps. Pad shall be 3’ in front of steps and the width of the steps at minimum. Concrete shall be high strength. Steps shall rest on landing. Landing shall have a broom finish to industry standards. Risers shall be closed. All material shall be exterior rated.