About this file

The document is a Price Proposal (Exhibit B) for a residential rehabilitation project issued by the City of Ocala, Florida, specifically for a property located at 811 NW 11th Ave. The project involves comprehensive residential rehabilitation work, including window installation, HVAC, water heater replacement, insulation, painting (interior and exterior), bathroom remodeling, kitchen cabinet work, electrical upgrades, and exterior repairs. The Request for Quotes (RFQ# CDS/250340A) seeks qualified Florida licensed General or Building Contractors to perform the work, with a non-mandatory pre-bid meeting scheduled for 2/24/2025 at 9:30 AM EST at the project site.

The price proposal includes 15 primary line items to be bid on a lump sum basis, with an initial total bid amount of $300.00. Additional line items such as plywood sheets, lumber, and a truck load are listed as potential change-order items to be approved by the project manager. The bidding process requires contractors to upload a completed Excel Exhibit B - Price Proposal, bid on all line items, and include all direct and indirect costs. The contract will be awarded to the lowest bidder meeting all outlined requirements, with supporting documentation including Exhibits A-E covering scope of work, price proposal, work write-up, asbestos survey, and lead inspection report.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Exhibit B - PRICE PROPOSAL CONTRACT# CDS/250340A

Bidder nameBidder Location
ENTER COMPANY NAME HEREEnter Location Here
MANDATORY LINE ITEMS: Address - Name
ITEMDESCRIPTIONUOMEST QTYLUMP SUM COST
1Window InstallationLS1
2HVACLS1
3Water HeaterLS1
4Attic InsulationLS1
5WindowsLS1
6Exterior PaintLS1
7Interior PaintLS1
8Hall Bath RemodelLS1
9Master BathLS1
10Half BathLS1
11Interior RepairsLS1
12Kitchen CabinetsLS1
13ElectricalLS1
14Exterior RepairLS1
15Exterior DoorLS1
2PlumbingLS1
3Permit AllowanceLS1$ 300.00
TOTAL BID AMOUNT$ 300.00
Not Included in Lump Sum Bid to be change ordered as approved by project Manager
ITEMDESCRIPTIONUOMEST QTYEXTENDED COST
3Sheet of Plywood 4x8 (Labor and Material)EA1
4Additional Rafter/Truss Lumber (Labor & Material)LF1
17TRUCK LOAD1$ - 0
5Sheet of Plywood 4x8Sheet1

image1.png