SOLICITATION, OFFER
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
A. NAME
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder"
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED BID (RFP)
CS-22-00310
AAQ-722 DIVERSIFIED FRANCHISE ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ0722-AFN
OKLAHOMA CITY OK 73125
FAA, Mike Monroney Aeronautical Center
Attn: Jason Fox, AAQ-722 6500 S. MacArthur BLVD. BLDG 014-AHQ, RM 233A Oklahoma City, OK 73169
Jason Fox
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
405-954-3123 Jason.A.Fox@faa.gov
112/22/2021 13
PURCHASE REQUEST NO.
6973GH-22-Q-00045
10. THE CONTRACT AUTHORITY REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date) o Proposals are due on January 12, 2022 at 5:00 pm CST. Proposals will not be accepted after this timeframe.
o This acquisition is Set Aside for Total Small Business.
o The estimated price range of this procurement is $23,000 - $47,000.
o Please see the Specifications for the Building Improvements – Siding, Doors, and
Paint at the LLANO (LLO), TX VOR; Dated 08/18/201, 34 pages.
11. The Contractor shall begin performance within
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award notice to proceed. The performance period is mandatory, negotiable. (See ________________________________________________ .)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and is not required.is, B. An offer guarantee
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers must be publicly opened at that time . Sealed envelopes containing offers shall be marked to show the offeror's name and address. The solicitation number, and the date and time offers are due.
D. Offers providing less than
12B. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in item 12B.)
15 10 calendar days and complete it within ________________ ________________ calendar days after receiving x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Contract Authority acceptance after the date offers are due will not be considered and will _________________ be rejected.
Jason A Fox Highlight
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Contract Authority in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13D. Failure to insert any number means the offeror accepts the minimum in item 13D.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (MUST BE FULLY COMPLETED BY OFFEROR)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Contract Authority)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Contract Authority solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE 30C. DATE 31B. CONTRACT AUTHORITY 31C. AWARD DATE
BY
2PAGE OF
AAQ-722 DIVERSIFIED FRANCHISE ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ722-AFN
OKLAHOMA CITY OK 73125
Janice K. Hammonds
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
Continued...
x 1
Jason A Fox Highlight
Jason A Fox Highlight
Jason A Fox Highlight
Jason A Fox Highlight
Jason A Fox Highlight
Jason A Fox Highlight
Jason A Fox Highlight
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
6973GH-22-Q-00045
(A) (B) (C) (D) (E) (F)
Period of Performance: 11/18/2021 to 09/30/2022
JCN: 20011127
00001 The contractor is responsible for furnishing all materials (unless noted otherwise in the contract documents), equipment, labor, transportation, insurance, notifications, licenses, permits, fees and supervision necessary for the Building
Improvements- Siding, Floor and Painting at the
LLANO (LLO), TX VOR in accordance with the applicable drawings, specifications and conditions of the contract.
Electronic & IT: 03
Total Bid
Jason A Fox Highlight
Jason A Fox Highlight
Jason A Fox Highlight
Section -- - Terms and Conditions Terms and Conditions List
(a) The contractor is responsible for accomplishing all items of work in accordance with the applicable drawings, SOW and attachments. Additional labor, materials, equipment, and/or appurtenances not specifically detailed or specified, but required to complete the project, must be provided by the contractor as an integral part of the scope of work specified. All work performed and any materials and equipment used will be subject to approval by the Contracting Officer Representative (COR) and Contracting Officer (CO). This shall include but not be limited to testing, inspection, scheduling, reporting, and submittals.
(b) Limit work to normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated, amounting to a total of 40 hours/week. No work shall be scheduled or performed on Saturdays, Sundays, federal holidays, or during holiday maintenance moratorium periods, unless approved by the FAA in writing. Deviation from this work schedule may be discussed prior to the Notice to Proceed date during the Pre-Construction Conference. Additional changes/requests to agreed upon work schedule shall be submitted to the COR and forwarded to the CO for approval. All work beyond normal work hours shall be requested in writing to the COR 48 hours in advance.
(c) The contractor must coordinate and report each day's work in advance with the Resident Engineer/COR.
The contractor will not be allowed access to or to work at the site without the RE/COR on site to serve as an escort.
(d) By submission of this offer, the offeror attests that all representations and certifications as reflected in the System for Award Management (SAM) are current and accurate as of the date the offer is submitted. The offeror shall provide immediate written notice to the Contracting Officer if at any time prior to award the offeror learns that any certification or representation in SAM was erroneous when this offer was submitted or has become erroneous by reason of changed circumstances.
(e) Specific attention is invited to AMS paragraph 3.2.2.3.1.2.2, Communications with Offerors. The FAA may communicate with one or more Offerors at any time during the RFQ process. Communications with one Offeror do not necessitate communications with other Offerors, since communications will be Offeror-specific. Information determined to have common application and not considered prejudicial to Offerors will be communicated to all Offerors.
(f) It is anticipated that price analysis will be based on adequate price competition; therefore, vendors are not required to submit cost or pricing data with its quote. However, if after receipt of offers it is determined that adequate price competition does not exist, uncertified, yet detailed, cost or pricing data may be required.
(g) Inspection and Acceptance. The Contractor must only tender for acceptance those supplies or services that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or re-performance of nonconforming services at no increase in contract price. If repair, replacement or re-performance will not correct the defects or is not possible to correct the defects in a time period deemed reasonable by the Government, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights.
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(h) The Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier. (see clause 3.10.1-20 in the QVL SIR 6973GH-20-R-00040 Amendment 1)
(i) This RFQ will be awarded on the basis of the lowest priced quotation received.
(j) This RFQ is not to be construed as a contract or a commitment of any kind. The Government shall not be liable for payment of any costs attributed to the preparation and submission of quotes.
(k) Clause List: the clauses from the QVL SIR 6973GH-20-R-00040 are applicable to this requirement. The clauses listed below are in addition to the clauses on the QVL SIR.
3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)
This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:
https://fast.faa.gov/contractclauses.cfm.
(End of clause)
3.2.2.3-55 AVAILABILITY AND USE OF UTILITY SERVICES (JUL 2004)
3.2.2.3-56 SCHEDULES FOR CONSTRUCTION CONTRACTS (JUL 2004)
3.2.2.3-58 LAYOUT OF WORK (MAR 2009)
3.2.5-5 ANTI-KICKBACK PROCEDURES (OCT 2019)
3.3.1-40 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (JAN 2021)
3.4.1-6 ADDITIONAL BOND SECURITY (APR 1996)
3.6.1-1 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (OCT 2019)
3.6.1-7 LIMITATIONS ON SUBCONTRACTING (JUL 2021)
3.6.2-44 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS
ACT (JAN 2019)
3.6.4-23 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND
VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (JAN 2021)
3.2.2.3-44 PHYSICAL DATA (JUL 2004)
Data and information the FAA (we, us) provides or refers to below is for the Contractor's (your) information. We are not responsible for your interpretation of or conclusions based on the data or information. Further, we do not warrant construction methodology which may be included in these documents.
(a) The descriptions of physical conditions on the drawings and in the specifications are the result of site investigations by the on-site engineer.
(b) Other relevant information it is the Contractor's responsibility to obtain weather patterns for the area, inspect the site in a manner which will provide the Contractor sufficient information concerning the site conditions in order to complete the project within the stated amount of time.
(End of clause)
3.2.2.3-60 SPECIFICATIONS, DRAWINGS, AND MATERIAL OFFERS (MAR 2009) - ALTERNATE
II (JUL 2004)
(a) If either the specifications or the drawings (but not both) mention tasks, the Contractor (you) must assume that the tasks are in both. If the drawings and specifications differ, the specifications govern. If there is a discrepancy in the figures, in the drawings, or in the specifications, submit the matter promptly to the Contracting Officer (CO), who will promptly determine which governs, and notify you in writing. Any adjustment you make without the CO's determination is at your own risk and expense. From time to time the CO will provide necessary detailed drawings and other information, unless otherwise provided.
(b) Wherever in the specifications or the drawings FAA (we, our) uses "directed," "required," "ordered," "designated," "prescribed," or similar words, they refer to the CO's requirements. Similarly, "approved," "acceptable," "satisfactory," or similar words refer to the CO's approval, unless otherwise expressly stated. You must have a complete set of plans and specifications on site and available for our use.
(c) Where we use "as shown," "as indicated," "as detailed," or similar words, they refer to the drawings accompanying this contract, unless stated otherwise. The word "provided" means "provided and installed."
(d) Omissions from the drawings and specifications or the erroneous description of details of work which are necessary to carry out the intent of the drawings and specifications, or which are customarily performed, does not relieve you from performing those omitted or erroneously described details of the work. You must perform them as if fully and correctly set forth and described in the drawings and specifications.
(e) You must check all drawings we provide to you before starting work and must promptly notify the CO of any discrepancies. In general you should follow figures marked on drawings, rather than scale measurements. In general, large scale drawings have precedence over small scale drawings. You must compare all drawings and verify the figures before laying out the work. If you do not verify the figures, you will be responsible for any errors you might have avoided had you verified them.
(f) "Shop drawings" means drawings, you or any subcontractor submit to us under a construction contract, showing in detail the proposed fabrication and assembly of structural elements and the installation (that is, form, fit, and attachment details) of materials or equipment. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials you provided to explain in detail specific portions of the work the contract requires.
FAA may duplicate, use, and disclose in any manner and for any purpose shop drawings you deliver under this contract.
(g) If this contract requires material offers (for example, shop drawings, catalog cuts, certificates of conformance), you must coordinate all of your offers, and review them for accuracy, completeness, and compliance with contract requirements. You must provide evidence that you approve the submittals. If you submit materials to us without this evidence, we may return them and ask you to resubmit them. The CO will indicate whether he or she approves or disapproves your offer, and if the CO does not approve it as submitted, will indicate our reasons for rejecting it. Any work done before the CO's approval is at your risk. The CO's approval does not relieve you from responsibility for any errors or omissions in the submittals, nor from responsibility for complying with the contract requirements, except as described under (h).
(h) If you submittals vary from the contract requirements, you must describe the variations in writing, separate from the submittal, when you submit them. Send this description, a copy of the offer, and a proposal to incorporate it into the contract directly to the CO. If the CO approves a variation, the CO must issue an appropriate contract modification, unless the variation is minor or does not involve a change in price or in time of performance.
(i) You must submit to the CO for approval four copies (unless otherwise indicated) of all shop drawings as called for under the various headings of these specifications. The CO will keep three sets (unless otherwise indicated) of all offers and will return one set to you.
(j) You must insert this clause, with appropriate changes in the designation of the parties, in all subcontracts.
(k) When you finish the work under this contract, you must provide the COR & CO one (1) complete sets of all shop drawings as we finally approve them. These drawings must show all changes and revisions made up to the time you finish the work and we accept it.
(End of clause)
3.2.2.3-63 SITE VISIT (CONSTRUCTION) (JUL 2004)
(a) AMS clauses 3.2.2.3-42, Differing Site Conditions, and 3.2.2.3-43, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded under this SIR. Accordingly, FAA urges and expects offerors to inspect the site where the work will be performed.
(b) Pre-Bid Site Visit TBD. Please contact Jason Fox at Jason.A.Fox@faa.gov if a site visit is needed for proposal by December 29, 2021 with a list of attendees.
(End of provision)
3.2.2.3-68 SAFETY AND HEALTH (OCT 2014) - ALTERNATE I (JUL 2004)
(a) Before beginning work, the Contractor (you) must:
(1) Perform a hazards analysis of the work specified in this contract. Consider both the site and adjacent conditions.
Identify all significant hazards. Some of the hazards you might encounter are falling from structures, tripping, electrical shock, fire, falling objects, environmental hazards, vehicular accidents, etc.
(2) Submit a safety plan for dealing with each specific hazard identified, whether you or FAA identified it.
(3) Meet with the CO's representatives during the preconstruction conference to discuss and to develop a mutual understanding about the content and implementation of the plan.
(4) The CO or her or his representatives may require other hazards to be added to the plan. If the CO determines that your planned hazard avoidance measures are insufficient, the CO or a designated representative may require you to revise the plan. You may not begin work involving identified hazards unless you have submitted adequate plans to the CO and the CO has reviewed them. This approval does not relieve you of your liability for safe performance.
(End of clause)
3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (OCT 2021)
The Contractor must (a) begin work under this contract within 15 calendar days after the date you receive the notice to proceed, (b) perform the work diligently, and (c) complete the entire work ready for use not later than 10 calendar days after the Notice to Proceed is issued. The time allowed for completion must include final cleanup of the premises.
(End of clause)
3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (OCT 2021) -
ALTERNATE I (OCT 2021)
The Contractor (you) must
(a) begin work under this contract within 15 calendar days after the date you receive the notice to proceed,
(b) perform the work diligently, and
(c) complete the entire work ready for use not later than 10 calendar days after the Notice to Proceed is issued.. The time allowed for completion must include final cleanup of the premises.
(d) The completion date is based on the assumption that the successful offeror will receive the notice to proceed by to be determined. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds to FAA within the time specified in the offer.
(End of clause)
3.2.2.8-5 LIQUIDATED DAMAGES - CONSTRUCTION (OCT 2019)
(a) If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor must pay to FAA as liquidated damages, the sum of $670.12 for each day of delay.
(b) If FAA terminates the Contractor's right to proceed, the resulting damage will consist of liquidated damages until such reasonable time as may be required for final completion of the work, together with any increased costs to FAA in completing the work.
(c) If FAA does not terminate the Contractor's right to proceed, the resulting damage will consist of liquidated damages until the work is completed or accepted.
(End of clause)
3.2.4-1 TYPE OF CONTRACT (APR 1996)
The FAA contemplates award of a Firm Fixed Price construction contract resulting from this Screening Information Request.
(End of provision)
3.3.1-41 ELECTRONIC INVOICING - REPRESENTATION (JAN 2021)
(a) The FAA intends to use electronic invoicing as per AMS clause 3.3.1-40 "Electronic Submission of Payment Requests" for this contract when it is awarded. Offerors must indicate whether they are currently using this form of electronic invoicing on other contract(s), or can easily adapt to it upon award of the contract. [ ] Yes [ ] No
(b) If an offeror indicates "No" the offeror must explain in this space why a waiver of this requirement should be approved in the event they were awarded the contract.
(c) Waiver requests will be handled per (f) of clause 3.3.1-40.
3.6.1-17 NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE (JAN 2021)
The North American Industry Classification System (NAICS) code for this procurement is:
238990 Building and Property Specialty Trade Services.
The small business size standard as defined by the Small Business Administration (SBA) is the following:
For NAICS codes based on SBA's calculation of annual receipts, the annual average receipts cannot exceed $16.5 million.
For NAICS codes based on the number of employees, the average number of employees over the last twelve-month period cannot exceed N/A.
(End of provision)
3.6.2-14 EMPLOYMENT REPORTS ON VETERANS (JAN 2020)
Jason A Fox Highlight
(a) Unless the contractor is a State or local government agency, the contractor must report at least annually, as required by the Secretary of Labor, on:
(1) The total number of employees in the contractor's workforce, by job category and hiring location, who are disabled veterans, other protected veterans, Armed Forces service medal veterans, and recently separated veterans,
(2) The total number of new employees hired during the period covered by the report, and of the total, the number of disabled veterans, other protected veterans, Armed Forces service medal veterans, and recently separated veterans; and
(3) The maximum number and minimum number of employees of the Contractor or subcontractor at each hiring location during the period covered by the report.
(b) The above items must be reported by completing the VETS-4212 "Federal Contractor Veterans' Employment Report" (see "VETS-4212 Federal Contractor Reporting" and "Filing Your VETS-4212 Report" at http://www.dol.gov/vets/vets4212.htm).'
(c) The VETS-4212 Report must be submitted no later than September 30 of each year.
(d) The employment activity report required by paragraph (a)(2) of this clause must reflect total hires during the most recent 12-month period as of the ending date selected for the employment profile report required by paragraph (a)(1) of this clause. Contractors may select an ending date: (1) As of the end of any pay period during the period January through March 1st of the year the report is due, or (2) as of December 31, if the contractor has previous written approval from the Equal Employment Opportunity Commission to do so for purposes of submitting the Employer Information Report EEO-1 (Standard Form 100).
(e) The count of veterans reported according to paragraph (a) of this clause must be based on data known to the contractor when completing the VETS-4212. The Contractor's knowledge of veterans status may be obtained in a variety of ways, including an invitation to applicants to self-identify (in accordance with 41 CFR 60-300.42), voluntary self-disclosure by employees, or actual knowledge of veteran status by the contractor. This paragraph does not relieve the employer of liability for a determination under 38 U.S.C. 4212.
(f) Subcontracts. The Contractor must include the terms of this clause in every subcontract or purchase order of $150,000 or more unless exempted by rules, regulations, or orders of the Secretary of Labor.
(End of clause)
3.6.3-22 CONSTRUCTION WASTE MANAGEMENT (JAN 2020)
(a) In performance of this contract, the Contractor must establish a program to minimize waste generation, as well as recycle, reuse, and salvage construction and demolition (C&D) debris generated to the maximum extent possible.
Before commencing work, the Contractor must submit a Waste Management Plan to the Contracting Officer within 15 days after contract award prior to the start of construction activities. This plan must address the following:
(1) General: Provide an overall strategy for managing C&D debris associated with the project.
(2) Waste Identification: Indicate anticipated types and quantities by weight of demolition, site-clearing and construction waste generated by the Project. Include estimated quantities by weight and assumptions for estimates.
A site assessment may be necessary to estimate the types of materials that will be generated during construction and/or demolition. If a site visit is needed, the Contractor must notify the FAA of this as soon as possible, with the FAA arranging in turn for the contractor site visit to take place as soon as possible.
(3) Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, estimated total weight of each type of waste, final disposition for each waste type, and handling and transportation procedures.
(4) Salvaged Materials: For each type of material that is salvaged or recycled, describe the type of material, source, estimated quantity, and receiving entity. Include names, addresses, and telephone numbers for the receiving individuals and/or organizations.
(5) Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
(6) Handling and Transportation Procedures: Include method that will be used for separating recyclable waste including sizes of containers, container labeling, and designated location on Project site where materials separation will be located.
(b) This plan must be found acceptable by the FAA Contracting Officer's Representative (COR) or the COR's designated representative prior to the Contractor receiving a Notice-to-Proceed. The plan's acceptability will be promptly determined by the FAA based on the knowledge of the site(s) covered under the Plan. The Contract must implement the approved Waste Management Plan during the term of the contract.
(c) The Contractor must document all C&D disposal and diversion efforts and submit a Construction and Demolition Debris Diversion Report to the CO and COR monthly. A copy of the report must also be submitted to the EOSH Services construction waste management address at 9-AJW-ConstructionWaste@faa.gov.
The monthly Construction and Demolition Debris Diversion Report must contain the following information:
(1) FAA facility name and address, report date and reporting period, contract number, and project name;
(2) Pick up date;
(3) Waste material type;
(4) Disposed C&D waste weight in short tons less container weight, method of waste material disposal, and reason why waste was not diverted;
(5) Recycled waste weight in short tons less container weight;
(6) Composted waste (off-site) weight in short tons less container weight;
(7) Reused materials weight in short tons less container weight; and
(8) Total weight of C&D waste (i.e., sum of disposed, recycled, composted, and reused waste) in short tons less container weight.
The Contractor must ensure that facilities used for recycling, reuse, and disposal are authorized for the intended use to the required extent by federal, state, and local regulations.
(d) If the value of this contract when awarded is less than $150,000, this clause does not take effect in this contract.
(End of Clause)
3.6.4-18 CERTIFICATION REGARDING STEEL AND MANUFACTURED PRODUCTS (APR 2021)
In accordance with 49 USC Section 50101, the offeror/contractor certifies that: (Check one) [ ] The steel and manufactured goods, including components and subcomponents provided in accordance with this contract are entirely produced in United States (or deemed United States produced pursuant to International Agreement) [ ] The cost of components and subcomponents produced in the United States is more than 60 percent of the cost of all components of the facility or equipment and final assembly of the facility or equipment has occurred in the United States.
(End of clause)
3.6.4-22 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (JAN 2021)
(a) Definitions. As used in this provision-
Backhaul, Covered telecommunications equipment or services, Critical technology, Interconnection Arrangements, Reasonable inquiry, Roaming and Substantial or essential component have the meanings provided in AMS clause 3.6.4-23 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibitions.
(1) Section 889(a) (1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in this prohibition will be construed to-
(i) Prohibit the head of the agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(2) Section 889(a) (1) (B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2020 from entering into a contract or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential part of any system or as critical technology as part of any system.
This prohibition applies to any entity that uses covered telecommunications equipment or services, including uses not in support of the Government. Nothing in this prohibition will be construed to-
(i) Prohibit the head of the agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures: The offeror must review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from Federal awards for covered telecommunications equipment or services.
(d) Representations.
(1) The Offeror represents that it [ ] will, [ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation.
(2) After conducting a reasonable inquiry for purposes of this representation, the Offeror represents that it does [ ] does not [ ] use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror must provide the additional disclosure information required at paragraph (e) if the Offeror indicates "does".
(e) Disclosures. Disclosure for the representation in paragraph (d) (1) of this provision If the Offeror has responded "will" in the representation in paragraph (d) (1) of this provision, the Offeror must provide the following information as part of the offer--
(1) For covered equipment
Jason A Fox Highlight
(i) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known;
(ii) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(iii) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b) (1) of this provision.
(2) For covered services-
(i) If the service is related to item maintenance, a description of all covered telecommunications services offered (include on the item being maintained: brand, model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable; or
(ii) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed uses of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
Disclosure for representation in paragraph (d) (2) of this provision. If the Offeror has responded "does" to paragraph
(d) (2) of this provision, the offeror must provide the following information as part of the offer-
(3) For covered equipment
(i)The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known;
(ii) A description of all covered telecommunications equipment offered (include brand; model number, such as original equipment manufacturer (OEM) number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(iii) Explanation of the proposed use of covered telecommunications equipment and services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b) (2) of this provision.
(4) For covered services-
(i)If the service is related to item maintenance, a description of all covered telecommunications services offered (include on the item being maintained: brand, model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(ii) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed uses of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(End of Provision)
3.6.4-24 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES- REPRESENTATION
(JAN 2021)
(a) Definitions. As used in this provision, "covered telecommunications equipment or services" and "reasonable inquiry" have the meanings per the clause 3.6.4-23 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment".
(b) Procedures. The offeror must review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for covered telecommunications equipment or services.
(c) Representation.
(1) The offeror represents that it [ ] does, [ ] does not provide covered telecommunications equipment or services as part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ] does, [ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.
(end of provision)
AC4533 REQUEST FOR MODIFICATION OF CONTRACT TERMS AND CONDITIONS (JAN 1997)
Offeror’s are hereby notified that the terms and conditions of this SIR shall be changed only through formal amendment(s) issued by the Contracting Officer. If an offeror takes issue with the terms and conditions contained herein, the offeror shall submit a Request for Modification of Terms and Conditions under separate attachment to their proposal. This request should be in offeror’s format, on offeror’s letterhead, signed by an officer of the company with authority to bind the offeror. The request must include documentation that fully highlights the offeror’s proposed changes and must be specific as to the exact term(s) or condition (s) to which the exception(s) are being taken. These changes shall not be binding on the FAA until fully agreed to by both the FAA and the offeror and incorporated into the document prior to contract award.
Instructions for Preparation and Submission of Quotes Because several quotes are anticipated, uniformity of the quotes are essential to assure a fair and accurate assessment of each offer. All quotes must be submitted in accordance with the information provided below and must conform to all the terms and conditions of the RFQ. Failure to conform to all requirements expressed may be cause for rejection without further evaluation or discussion.
1) On page 2 of this Solicitation, Offer and Award, fill in Blocks 14 through 20c with Offerors information.
All Offerors are required to provide an acknowledgement of any Amendment(s) on page 2 or provide a signed copy of any Amendment(s) within their bid submission. If any amendment(s) is not acknowledged or signed, the RFQ will be considered non-responsive.
2) On page 3 of this Solicitation, Offer and Award, list the Offerors' bid amount under Amount (F) column.
3) The FAA will be using the approved Offerors completed Section K, Representations, Certifications, and other Statements of Bidders that the Offeror completed on the QVL Solicitation, 6973GH-20-R-00040.
4) The contractor must fill out the appropriate items in clauses/provisions 3.6.4-22, 3.6.4-24, 3.3.1-41, & 3.6.4-18 in this RFQ.
The remainder of this page has been intentionally left blank.