RFQ_484_022626 Roundabout Alt Intersections I.pdf
PDF 353 KB Posted
- Solicitation number
- PE-48401-RFQ-2026-000000519
- Issued by
- Georgia
About this file
Summary: RFQ-484-022626 Roundabout and Alternative Intersections/Interchanges Support Services
This is a Request for Qualifications (RFQ) issued by the Georgia Department of Transportation (GDOT) seeking qualified consultant firms to provide on-call support services for the selection, planning, design, and in-service assessment of roundabouts and alternative intersection/interchange configurations. The scope of work encompasses eight intersection configuration types including mini, compact, and conventional roundabouts; median U-turns; reduced conflict intersections; jug handles; displaced left turns; green-T intersections; quadrant roadways; and diverging diamond interchanges. Required services include intersection control evaluations, traffic engineering studies, concept report preparation, plan development compliant with NEPA and GDOT procedures, in-service safety audits, staff mentoring, public outreach support, and training delivery. Statements of Qualifications are due February 26, 2026, at 2:00 PM, with a question submission deadline of February 10, 2026. The resulting on-call Indefinite Delivery/Indefinite Quantity (IDIQ) contract will be awarded to one firm for a maximum term of five years with a minimum contract value of $25,000 and maximum value of $8,000,000. Payment may be structured as lump sum, cost plus fixed fee, cost per unit of work, or specific rate of compensation.
Evaluation occurs in two phases: Phase I assesses statements of qualifications based on project manager and key team leader experience (30% weight), additional resources and approach to challenges (20% weight), and prime consultant past performance (10% weight); at least three finalists will advance to Phase II, where technical approach (40% weight) and potential presentation/interview are evaluated. The prime consultant must maintain GDOT prequalification in all required Area Classes, which span environmental documentation, traffic studies, roadway design, surveying, utility engineering, and erosion control disciplines. All respondents must submit signed addenda, completed certification forms, Georgia Security and Immigration Compliance Affidavits, organizational charts, and Project Evaluation Forms for relevant past projects. GDOT reserves the right to reject any proposals, waive technicalities, and award to the highest-ranked firm meeting all Area Class requirements, with contract negotiations to follow award announcement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| LAP Evaluation Form.xlsx | XLSX spreadsheet | |
| Legacy Evaluation Form_.xlsx | XLSX spreadsheet | |
| Finalist (Shortlist) Announcement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date Posted: 1/27/2026
Request for Qualifications
To Provide
Roundabouts and Alternative Intersections/Interchanges Support Services
RFQ-484-022626
Qualifications Due: February 26, 2026
Georgia Department of Transportation
One Georgia Center 600 West Peachtree Street, NW
Atlanta, Georgia 30308
v. 7-2025 IDIQ
I. General Project Information
A. Overview
The Georgia Department of Transportation (GDOT) is soliciting Statements of Qualifications (SOQs) from a qualified firm(s) to provide Consultant Services for the projects listed in the Exhibit.
This Request for Qualifications (RFQ) seeks to identify potential providers for the Scope of Services for the project/contract listed in the Exhibit. Firms that respond to this RFQ and are determined by GDOT to be sufficiently qualified may be deemed eligible and invited to offer a technical approach and/or possibly present and/or interview for these services. All respondents to this RFQ are subject to the instructions communicated in this document and are cautioned to completely review the entire RFQ and follow instructions carefully.
GDOT reserves the right to reject any or all Statements of Qualifications and Technical Approach, and to waive technicalities and informalities at the discretion of GDOT.
B. Restriction of Communications
From the date of advertisement of this solicitation until the successful respondents are selected and the award is officially announced, all firms are strictly prohibited from communicating in any way regarding this solicitation or the associated scope of work with any GDOT staff, including the Commissioner and GDOT Board Members. This restriction applies to all potential respondents and will be strictly enforced.
The only exception to this restriction is for the purpose of obtaining a Consultant Evaluation Form to support a project being included in the SOQ submittal.
All questions or requests for clarification regarding any aspect of this RFQ must be submitted in writing via email to:
Temekia Arnold tearnold@dot.ga.gov
Deadlines for the submission of questions are listed in the Schedule of Events section of this RFQ.
Method of Communication
All general communication regarding this solicitation, including updates, clarifications, and official announcements, will be posted to the Georgia Procurement Registry (GPR) under this RFQ. It is the responsibility of all interested firms to monitor the GPR regularly for such information.
GDOT reserves the right to communicate directly via electronic mail with the primary contact listed in the submitted Statement of Qualifications (SOQ). Additional communications may be conducted as specified elsewhere in this RFQ.
C. Contract Term and Type
GDOT anticipates. one (1) On-Call Indefinite Delivery, Indefinite Quantity Contract to be awarded to one (1) firm, for the project/contract identified in the Exhibit. GDOT anticipates that the Payment Type may be Lump Sum, Cost Plus Fixed Fee, Cost per Unit of Work, or Specific Rate of Compensation. As an On-Call Indefinite Delivery, Indefinite Quantity contract, the Agreements will remain in effect for up to a maximum of five (5) years.
mailto:tearnold@dot.ga.gov
D. Contract Amount
The On-Call, Indefinite Delivery, Indefinite Quantity contract will have a minimum dollar amount of Twenty-five thousand ($25,000.00) and a maximum dollar amount of Eight Million ($8,000,000.00).
E. Scope of Services
Under the terms of the resulting Agreements, the selected consultants will perform the anticipated scope of work for the project outlined in the accompanying Exhibit referenced herein.
F. Schedule of Events
The following Schedule of Events represents GDOT’s best estimate of the Schedule that will be followed. All times indicated are prevailing times in Atlanta, Georgia. GDOT reserves the right to adjust the Schedule as GDOT deems necessary.
PHASE I DATE TIME
a. GDOT issues a public advertisement for this RFQ. 01/27/2026 --------
b. Deadline for submission of written questions and requests for clarification
02/10/2026 2:00 PM
c. Deadline for submission of SOQs
02/26/2026 2:00 PM
II. Selection Method
A. Phase I - Selection of Finalists
Based on the SOQs submitted in response to the projects/contracts listed in the Exhibit below, individual Selection Committee members will evaluate all firms individually based on the Phase I selection criteria and weights listed in the solicitation. All firms will be discussed and evaluated by the selection committee as a group and assigned a group rating for each of the Phase I evaluation criteria and weights, resulting in a group score for Phase I, and the final rankings of the top submittals will be determined. From the group scores of the top submittals, at least three (3) or more of the most highly qualified consultants will be shortlisted for additional evaluation.
B. Finalist Notification
Each finalist firm shall be notified by email to participate in Phase II of the evaluation process and informed of all due dates, additional details, and requirements beyond those provided in the solicitation.
C. Phase II – Evaluation of Final Selection
Based on the Phase II response from the finalist firms, the selection committee members will evaluate and discuss each finalist firm's submittal based on the Phase II selection criteria and weights listed in the solicitation and assign a group rating resulting in a group score for Phase II.
D. Final Selection
The Final selection will be determined by carrying the selection committee group scores from Phase I forward and adding them to the results for Phase II selection committee group scores, together for a total score. The finalists will be ranked in order of preference. At least three firms will be identified as the most highly qualified to perform the services listed in the Exhibit. Note that there may be separate Selection Committees for each project/contract listed in the Exhibit.
Upon completion of the evaluation process, GDOT will formally award the contract to the top-ranked firm(s). Following the award, GDOT will initiate negotiations to finalize the terms and conditions of the contract(s), including the scope, compensation, and fees to be paid.
If a satisfactory agreement cannot be reached with the highest-ranked firm, GDOT will formally terminate negotiations and may initiate discussions with the next highest-ranked firm, continuing in order of ranking until a mutual agreement is established and the contract is executed.
III. Selection Criteria and Weights
A. Phase I – The following criteria and weights will be utilized in the evaluation and scoring of Phase I SOQs to determine which firms are shortlisted:
1. Project Manager, Key Team Leader(s), and Key Team Member – Experience and
Qualifications Weight: 30% - Evaluation will be based on the relevant experience, professional qualifications, and technical expertise of the proposed Project Manager, Key Team Leader(s), and Key Team member for the identified scope of work.
2. Additional Resources and Challenges Weight: 20% - This criterion considers the firm on its
Additional Resources and Approach to address scope challenges.
3. Prime Consultant Experience and Past Performance Weight: 10% - Past performance will be assessed using the evaluation forms submitted by the firm and any relevant experience or project knowledge held by members of the Selection Committee, particularly regarding similar or related GDOT projects.
B. Phase II – The following criteria and weights will be utilized in the evaluation and scoring of the shortlisted firms (finalists): Technical Approach.
1. Technical Approach Weight: 40% - This criterion evaluates the firm’s proposed methodology, understanding of the project requirements, approach to managing key tasks, anticipated challenges, and strategies for delivering a successful project outcome.
2. Presentation/Interview GDOT reserves the right to request a presentation/interview on any project/contract as determined in its best interests; however, this additional requirement shall typically be reserved for the most complex projects.
IV. Instructions for Content and Preparation of Statement of Qualifications – Phase I Response
The SOQs submittal must be submitted per the instructions provided below and be organized, categorized using the same headings (in red), numbered and lettered exactly as outlined below, and responsive to all requested information. For the sections in which page number limits are stated, each section with a stated limit must begin on a new page and end on the last page allowed for the section.
New sections shall not begin on a page allowed for a previous section, if applicable. This will enable the Department to ensure compliance with the page limitations.
Restrictions on Inclusion of GDOT Employees and Personnel Disclosure
Respondents shall not list, reference, or otherwise include any current Georgia Department of Transportation (GDOT) employee in their Statement of Qualifications (SOQ), including but not limited to resumes, organizational charts, narratives, or proposed team roles. The inclusion of any current GDOT employee in any capacity shall render the SOQ non-responsive.
Respondents must also ensure that all individuals identified in the SOQ have been informed of, and have agreed to, their inclusion on the proposed team. Respondents shall not list employees of other firms—including potential sub-consultants or unaffiliated entities—without those individuals’ knowledge and the concurrence of their current employer.
To ensure transparency and avoid conflicts of interest, Respondents must clearly identify the current employer of all individuals proposed in the SOQ, including the Project Manager, Key Team Leaders, Key Team Members, all individuals shown on the organizational chart, and any individual referenced in the SOQ narrative or resumes. Failure to comply with these requirements shall result in a determination of non-responsiveness.
Cover page – Each project/contract submittal must have a separate cover page for each copy of each Phase I submittal and must indicate the response is for Phase I, and each project/contract must list the RFQ#, RFQ Title, proposing firm’s full legal name, and the specific project contract being submitted on to include the Project Numbers, PI Numbers, County(ies), and Description.
A. Addendum(s) - Signed cover page (Only) of any Addendum(s) issued.
B. Basic Company Information
The following general information is required for each submittal. This information will not be scored but may be used by the Department to determine eligibility for selection. Firms must submit only the requested information. Providing additional or unsolicited information may result in disqualification from this solicitation.
1. Company Name: Provide the full legal name of the company.
2. Company Headquarters Address: Include the complete address of the company’s headquarters.
3. Primary Contact Information: Provide the name, telephone number(s), and email address of the individual who will serve as the main point of contact for this solicitation. This individual will receive all communications from the Department.
4. Company Website: Include the company’s website URL, if available.
5. Georgia Office Locations: Identify all office locations within the State of Georgia, including full addresses.
6. Staffing in Georgia Offices: List the number of staff members employed at each Georgia office and specify their disciplines.
7. Ownership Structure: Indicate the form of ownership (e.g., sole proprietorship, partnership, corporation, limited liability company, or other structure). Include the state of residency or incorporation and the number of years the firm has been in business.
This information is (Excluded from the page count).
C. Experience and Qualifications
1. Project Manager - The following information must be provided for the proposed Project Manager.
This section is critical for evaluating qualifications and project relevance. Resumes and supporting documentation must be clearly labeled and organized.
a. Current Employment:
1) State the name of the firm where the Project Manager is currently employed.
2) Indicate the number of years the Project Manager has been with the firm.
3) Provide the total number of years of experience serving in the role of a Project Manager, to distinguish between overall career length and actual leadership experience directly relevant to the position.
b. Education: List relevant degrees or academic credentials.
c. Registration: Provide details of applicable licenses or registrations required, if applicable and necessary for the position.
d. Relevant Project Management Experience: Provide a combination of narrative and listing of specific experience managing on-call contracts or multiple projects of similar complexity, size, scope, and function, and experience managing internal and sub-consultant resources to staff projects on an as-needed basis.
e. GDOT-Specific Standards Experience: Describe experience utilizing GDOT-specific procedures, policies, and guidance such as the Plan Development Process (PDP), Design Policy Manual, Environmental Procedures Manual, etc. If any listed projects did not follow
GDOT processes, clearly identify the alternative processes, manuals, or guidance used and provide a comparison where appropriate.
This information is limited to two (2) pages maximum.
2. Key Team Leaders are defined as individuals who oversee project areas deemed critical to each specific project (see Section 6 of the Project Description in the Exhibit below for the required Key Team Leader roles per project). For each Key Team Leader identified, the following information must be provided:
a. Current Employment and Experience:
1) State the name of the firm where the Key Team Leader is currently employed.
2) Indicate the number of years with the firm.
3) Provide the total years of experience serving in a leadership role within their discipline, to distinguish between overall career length and actual leadership experience directly relevant to the position.
b. Education: List relevant degrees or academic credentials.
c. Registration: Provide details of applicable licenses or registrations required for the Key Team
Leader’s area of responsibility (e.g., PE, RLA, PG), if necessary and applicable.
d. Relevant Resource Area Experience: Describe the Key Team Leader’s relevant experience in their specific resource area, highlighting involvement in projects of comparable complexity, size, scope, and function.
e. GDOT-Specific Standards Experience: Describe the experience detailing the Key Team Leader’s use of GDOT-specific processes, manuals, and guidance relevant to their discipline (e.g., PDP, Design Policy Manual, Environmental Procedures Manual, etc.) For any projects that did not follow GDOT processes, list the alternative processes, manuals, or standards used and explain their comparability.
The information required for each Key Team Leader, as identified in Exhibit Section 6, is limited to one (1) page maximum per individual.
Respondents submitting more than one (1) page for any Key Team Leader will be subject to disqualification. Additionally, respondents must provide only the Key Team Leaders specified in the Project Exhibit. Submitting more Key Team Leaders than required will be considered non-compliant and may result in disqualification, as it provides an unfair advantage over firms that followed the stated requirements. Conversely, failure to submit all required Key Team Leaders will render the proposal nonresponsive, and the respondent’s team will be deemed unqualified for the award. It is the respondent’s responsibility to carefully review Section 6 of the relevant Exhibit and ensure strict compliance with both the number and content of Key Team Leader submittals.
3. Key Team Member is defined as an individual team member not included as the Project
Manager or a Key Team Leader, whose qualifications the Prime firm would like to highlight as essential in the delivery of the proposed project/contract. For the Key Team Member identified, the following information must be provided:
a. Current Employment and Experience:
1) State the name of the firm where the Key Team Member is currently employed.
2) Indicate the number of years with the firm.
3) Provide the total years of experience serving in a leadership role within their discipline, to distinguish between overall career length and actual leadership experience directly relevant to the position.
b. Education: List relevant degrees or academic credentials.
c. Registration: Provide details of applicable licenses or registrations required for the Key
Member area of responsibility (e.g., PE, RLA, PG), if necessary and applicable.
d. Relevant Resource Area Experience: Describe the Key Team Member's relevant experience in their specific resource area, highlighting involvement in projects of comparable complexity, size, scope, and function.
e. Narrative: Discuss why the inclusion of the Key Team Member is important in the overall delivery of the project/Contract.
f. GDOT-Specific Standards Experience: Describe the Key Team Member's use of GDOT-specific processes, manuals, and guidance relevant to their discipline (e.g., PDP, Design Policy Manual, Environmental Procedures Manual, etc.) For any projects that did not follow GDOT processes, list the alternative processes, manuals, or standards used and explain their comparability.
The information is limited to one (1) page Maximum.
4. NOTE: Key Personnel Changes
If, after the RFQ submission deadline, a Project Manager or Key Team Leader listed in the SOQ is no longer employed with the firm, a replacement may be submitted if the firm is shortlisted.
The replacement must be selected from within the same firm and included as part of the Phase II Technical Approach submittal. All required information for the replacement personnel must be provided, and the submittal must comply with the original page limitations. During the Phase II evaluation meeting, the evaluation team will revisit and adjust the Phase I score to reflect the experience and qualifications of the replacement personnel.
D. Additional Resources and Challenges
Overall Resources - Provide information regarding the overall resources dedicated to delivering the specific project, including:
1. Organizational Chart - Provide an organizational chart that identifies the Project Manager, Prime Consultant, Key Team Leaders, support personnel, and reporting structure. This chart is (Excluded from the page count) and may be submitted in portrait or landscape orientation on (8.5” X 11”) or (11” x 17”) paper, particularly when the Chart requires a large consultant team.
2. Primary Office - Identify and discuss the primary office responsible for managing the specific project. Include the number and types of staff within that office and describe how this office will benefit the project and promote efficiency. This information must be included on one (1) page, combined with the Narrative on Additional Resource Areas and Abilities described in Section D.3.
3. Narrative on Additional Resource Areas and Ability – Provide a narrative describing any additional resource areas important to the project. Discuss how the key areas will integrate and work together, and include any pertinent information relevant to these areas. The narrative should also explain how the team’s organization—including the Project Manager, Key Team Leaders, and Key Team Member — will support project delivery on schedule, given their current workload capacity. GDOT acknowledges that some individuals may meet schedule requirements while managing heavier workloads. Respondents may highlight the strengths and advantages of their team and explain how the team’s capabilities will help meet the proposed schedule outlined in the applicable Exhibit. If no schedule is provided, discuss how the team’s composition will support the project moving forward as expeditiously as possible. Note:
Respondents submitting more than one (1) page combined for Sections D.2 and D.3 will be subject to disqualification.
4. Identify Additional Resources – Respondents are allowed one (1) page to provide information on additional resources, outside of the Project Manager, Key Team Leaders, and Key Team Member, providing a brief description of the resource and describing how the additional resources identified will help address scope challenges. Respondents submitting more than one (1) page will be subject to disqualification.
E. Prime Consultant Experience and Past Performance
Provide detailed descriptions of the Prime Consultant’s past performance on task order-based or Indefinite Delivery/Indefinite Quantity (IDIQ) contracts that demonstrate the firm’s ability to manage and deliver a variety of assignments that differ in scope, schedule, and complexity. Emphasize experience that highlights the ability to manage multiple concurrent task orders, respond quickly to evolving priorities, coordinate effectively across teams, and consistently meet quality, budget, and schedule requirements.
1. Similar Project Experience - Provide information on the prime consultant’s experience and ability to deliver effective services for projects of similar complexity, size, scope, and function, demonstrating the firm's qualifications to perform services for GDOT. For each project listed, include the following details:
a. Project: Provide the project name (use GDOT GeoPI description, if applicable), GDOT PI number (if applicable), and project location.
b. Client: State the name of the client.
c. Date: Indicate the start and end dates of service. If the project is ongoing, please note that accordingly.
d. Description: Provide a brief description of the overall project and clearly define the services your firm performed.
e. Client Contact: Provide current contact information for the client, including contact name(s), telephone number(s), and e-mail address(es).
f. Team Involvement: Specify the involvement of the Project Manager and Key Team Leaders identified in your SOQ on each project listed.
g. Similarity: Explain why this project is similar to the project(s) for which the firm is submitting a proposal.
h. If applicable. If performance ratings are not available, provide a brief explanation.
2. Similar Project Experience Summary Write-up For the similar projects listed above, provide a summary write-up detailing the firm’s experience utilizing GDOT-specific processes, manuals, or guidance, such as the Plan Development Process (PDP), Design Policy Manual, Environmental Procedures Manual, and other applicable resources. If any projects did not follow GDOT processes, clearly identify the alternative processes, manuals, or guidance that were used and explain their comparability to GDOT standards.
This information is limited to four (4) pages maximum.
F. Prime Consultant Evaluation Forms –
Respondents must submit a completed Project Evaluation Form for each project referenced in the Similar Project Experience. The form must be the most current version of the Contract Management Information System (CMIS) Evaluation Form, printed directly from CMIS for the respective project, and included in the SOQ submittal.
If the pursuing prime firm served as a sub-consultant on a project, the Legacy Evaluation Form may be submitted in lieu of the CMIS form.
If neither a CMIS nor a Locally Administered Project (LAP) Evaluation Form is available, respondents must complete and include the Legacy Evaluation Form provided with the RFQ on the Georgia Procurement Registry.
Note: GDOT will no longer issue reference requests via email or Microsoft Forms. It is the sole responsibility of the respondent to obtain and include all required evaluation forms with the SOQ submittal.
The Project Evaluation Form assesses the consultant’s performance on a specific project, focusing on key performance indicators such as:
a. Project Quality
b. Timeliness
c. Cost management
d. Communication
e. Overall client satisfaction
These evaluations serve as a record of the consultant’s effectiveness, professionalism, and ability to meet project objectives and deadlines. The Department reserves the right to randomly validate any submitted project evaluations by contacting the evaluators listed on the forms.
This information is excluded from the page count.
G. Area Class Prequalification Requirements:
1. Summary Table.
2. Notice of Professional Consultant Qualifications.
Respondents must complete a table indicating the firm (Prime Consultant or Subconsultant) that meets each required GDOT Area Class for the project/ Exhibit. The applicable Area Classes are listed in Exhibit Section 4.
3. Definitions:
a. Prime Consultant: The firm submitting the Statement of Qualifications (SOQ) and the entity with whom GDOT will contract.
b. Team: The Prime Consultant and any Subconsultants and/or joint venture partners included in the SOQ. The Team (either the Prime Consultant or one or more of their Subconsultant team members) must be prequalified by GDOT in all Area Classes required for the project/Exhibit.
c. The Area Class Summary Table is an administrative procedure that ensures respondents meet the Area Class requirements. It does not designate which firm on the team—Prime or Sub—is responsible for delivering that portion of the work.
4. Instructions for completing the Summary Table:
a. Place an “X” in the appropriate column to identify whether the Prime Consultant or a Subconsultant holds each required Area Class.
b. Only include Area Classes that apply to the specific project.
c. Highlight all Area Classes required for the Prime Consultant, as specified in Exhibit
Section 4.
d. Ensure that the Prequalification Expiration Date is valid and current at the time of submission.
e. Only one firm should be listed per Area Class to demonstrate compliance
f. Refer to an example of the required Area Class Summary Table below:
Failure to demonstrate valid prequalification for all required Area Classes will result in disqualification.
Primes and Subconsultants
Certificate Expires
.0
(a
.0
(b
.0
(c
.0
(d
.0
(e
.0
(f
.0
(g
.0
.1
Firm Name(s) (Prime) MM/DD/YYYY X X X X X
(Insert Sub Name) MM/DD/YYYY X
(Insert Sub Name) MM/DD/YYYY X X
(Insert Sub Name) MM/DD/YYYY X
5. The proposed project team must meet the Area Class requirements listed in the Exhibit (for each project at the time SOQs are due. GDOT will conduct a pre-screening of all potential shortlisted teams to verify that the proposed team meets the required Area Class(es). If the required Area Class(es) are not met, the team will be disqualified from further consideration.
6. If a team member’s prequalification is scheduled to expire before the SOQ due date, the respondent must provide documentation confirming that a renewal application has been submitted before the SOQ due date. It is the consultant’s responsibility to maintain current prequalification certifications in accordance with the GDOT Prequalification Manual throughout the procurement process to remain eligible for award.
7. If the highest-ranking firm does not meet the required Area Class(es), the Department reserves the right to award the contract to the next highest-ranking firm that meets all Area Class requirements.
8. The Area Class Summary Table (Excluded from the page count) may be submitted in portrait or landscape orientation on (8.5” X 11”) or (11” x 17”) paper, particularly when the Area Class Table requires an extensive list of area classes or a large consultant team.
V. Instructions for Preparing Technical Approach – Phase II Response
The following information will only be requested of the shortlisted firms. The Selection Committee will evaluate the shortlisted firms using the information provided as requested below (NOTE: Scores from Phase I will be carried forward to Phase II):
The Phase II response must be submitted following the instructions provided below and must be organized, categorized using the same headings (in red), numbered and lettered exactly as outlined below, and responsive to all requested information. For the sections in which page number limits are stated, each section with a stated limit must begin on a new page and end on the last page allowed for the section. It is not allowed to begin new sections on a page allowed for a previous section, if applicable. This will enable the Department to ensure compliance with the page limitations.
Phase II Cover page – Each submittal must have a separate cover page for each copy of each Phase II submittal, and each must indicate the response is for Phase II, list the RFQ#, RFQ Title, proposing firm’s full legal name, and the specific project contract being submitted on to include the Project Numbers, PI Numbers, County(ies), and Description.
A. Administrative Requirements
Each submittal will require a certification to allow the Department to analyze risks in determining if any Firm should be ineligible for the award. The certification shall cover a wide variety of information. Any firm that responds in any potentially concerning manner must provide additional information as directed herein for consideration by GDOT to determine if the Firm is eligible for an award.
1. Certification Form - Complete the Certification Form and provide a notarized original within the firm’s Statement of Qualifications. This is to be submitted for Prime ONLY.
2. Georgia Security and Immigration Compliance Act Affidavit – Complete the form and provide a notarized original within the firm’s Statement of Qualifications. This is to be submitted for Prime
ONLY.
3. Addendum(s) - Signed cover page of any Addenda issued to shortlisted firms. This is to be submitted for the Prime ONLY.
B. Technical Approach
1. Technical approach to managing on-call contracts.
2. Technical approach to assigning and managing services performed by sub-consultants.
3. Technical approach to managing uncertain workload and staffing needs.
4. Provide any unique challenges of the project/contract and how your firm intends to mitigate these challenges, including quality control, quality assurance procedures.
5. Provide any specific qualifications, skills, or knowledge that your firm has that could benefit the contract and subsequent projects.
This information will be limited to a maximum of three (3) pages.
C. Key Personnel Changes (if applicable)
If, after the RFQ submission deadline, a Project Manager or Key Team Leader listed in the SOQ is no longer employed with the firm, a replacement may be submitted if the firm is shortlisted. The replacement must be selected from within the same firm. All required information for the replacement personnel must be provided and must comply with the original page limitations. During the Phase II evaluation meeting, the evaluation team will revisit and adjust the Phase I score to reflect the experience and qualifications of the replacement personnel.
D. Presentation/Interview
GDOT reserves the right to request a presentation/interview on any project/contract as determined in its best interests; however, this additional requirement shall typically be reserved for the most complex projects.
VI. Instructions for Submittal for Phase I and Phase II Response
A. There is one (1) electronic version submittal required. The Submittal must follow the format and meet the content requirements identified in Section IV for Phase I and Section V for Phase II Responses. Phase II Responses are intended solely for those firms identified and notified as finalists.
Submittals must be typed in portrait orientation on standard (8½” x 11”) paper. However, the Organization Chart (11” x 17” allowed) and the Area Class Summary Table may be submitted in landscape orientation. Pages should be numbered, but compliance with page limits will be determined by counting pages within each section. The page count will be based on pages containing printed content rather than the total number of sheets. Responses must follow the specified page limits in each section, using a minimum font size of 11. Each submittal should be prepared simply and economically, focusing on completeness, relevance, and clarity. Colored displays and promotional materials are not required or desired.
NOTE: Additional pages other than what has been specified above in each section should not be included and will be grounds for disqualification. Submittals are limited to the information requested in each Section. Hyperlinks or embedded videos are not allowed.
B. The submittals must be a PDF document for each project/contract. Each PDF document must follow the naming convention for electronic records as follows: the proposing firm’s full legal name, RFQ#, RFQ Title, and the specific project contract being submitted.
To submit your Phase I, Statement of Qualification, and Phase II, Technical Approach, click the following Link: https://solicitation.dot.ga.gov/
NOTE: Solicitation Submittal Manual To review the manual for solicitation Submittal, click the following Link:
https://dotauthoring.dot.ga.gov/GDOT/Pages/SolicitationTraining.aspx.
If a firm is responding to multiple projects or contracts, a separate submittal must be uploaded for each response. Each submittal must comply with the required electronic records naming convention and be submitted using the designated submission link provided. Upon successful submission, the system will generate an email confirmation to the sender. If a confirmation email is not received within one (1) hour of submission, the firm must promptly contact the Negotiator listed in Section B: Restrictions on Communications.
Statements of Qualifications (SOQs) must be received by GDOT no later than the deadline specified in Section F: Schedule of Events. Technical Approach submittals must be received by the deadline indicated in the Remaining Schedule as referenced in the Notice to Selected Finalists.
Late submittals will not be accepted under any circumstances unless the deadline is formally revised through an official amendment issued by GDOT.
All costs associated with the preparation and submission of responses are solely the responsibility of the submitting party. GDOT is under no obligation to reimburse any such expenses. All submittals become the property of GDOT upon receipt. Designating any part of a submittal as “proprietary,” “confidential,” or with any other restriction will not prevent disclosure under the Georgia Open Records Act. The contents of all submittals will remain confidential only until the final contract award is made.
GDOT reserves the right, at its sole discretion, to waive any technicalities or informalities associated with the submittal process when such action is determined to be in the best interest of the State.
GDOT Terms and Conditions
A. Statement of Agreement
With the submission of an SOQ, the respondent agrees that he/she has carefully examined the Request for Qualifications and agrees that it is the respondent’s responsibility to request clarification on any issues in any section of the Request for Qualifications with which the respondent disagrees or needs to be clarified. The respondent also understands that failure to mention these items during the question period or in the SOQ will be interpreted to mean that the respondent is in full agreement with the terms, conditions, specifications, and requirements therein. With the submission of an SOQ, the respondent hereby certifies: (a) that this SOQ is genuine and is not made in the interest or on behalf of any undisclosed person, firm, or corporation; (b) that respondent has not directly or indirectly included or solicited any other respondent to put in a false or insincere SOQ; (c) that respondent has not solicited or induced any person, firm, or corporation to refrain from sending an SOQ.
https://solicitation.dot.ga.gov/ https://dotauthoring.dot.ga.gov/GDOT/Pages/SolicitationTraining.aspx
The respondent also understands that failure to provide the required information may result in disqualification. Failure to provide administrative information may not result in disqualification. At the Department’s discretion, the Department may notify the respondent that administrative information is not provided or that there was an error in the information provided, and the Department will allow the respondent to provide an update to the administrative information.
However, the exception to this is the provision of the required GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT, which, by Georgia Law, requires the disqualification of the response. The above changes mentioned to administrative information would be considered allowable, as these would be limited to changes that do not affect the information that the evaluators use to score the respondents. Failure of a respondent to provide the specific administrative information as required in the notice will result in disqualification. Any respondent who provides changes in addition to the information requested in the notice shall be subject to disqualification. Failure of a respondent’s SOQ to provide any information about a respondent and its team's qualifications, of any type, will subject the SOQ to disqualification. The Department will not allow updates to qualifications to be provided to avoid disqualification, as this would allow a respondent to modify its SOQ and alter the information that evaluators would score. The above changes related to qualifications would not be allowable, as these would allow changes that affect the information that the evaluators use to score the respondent's SOQ.
B. Joint-Venture Proposals, Sub-Consultants, and Vendors
GDOT does not generally desire to enter “joint venture” agreements with multiple firms. In the event two or more firms desire to “joint venture”, it is strongly recommended that one incorporated firm propose and maintain status as the Program Management firm, with the remaining firms participating as major firms. Any joint venture, proposed and established as a separate business entity, should have its own set of books and supporting documentation sufficient for an audit trail.
Transactions should be recorded consistently with the joint-venture agreement, and care must be taken to ensure that the joint-venture bears its equitable share of the costs. Therefore, “unpopulated joint ventures” would not have an adequate accounting system suitable for cost-reimbursement contracts.
However, more traditional “populated joint ventures” are welcomed. A populated joint venture is where an alliance is brought to life by infusing it with working capital, employees, and control systems. The alliance implements all necessary business systems, including payroll processing, purchasing, property control, etc. The alliance will develop its indirect rate structure and calculate its indirect cost rates, based on the direct and indirect costs it incurs.
Sub-consultants shall generally be considered any team member who is performing any service that typically requires prequalification, which is subject to the Audit and Accounting System Requirements, and whose services are billed as costs. Sub-Consultant Team Members must be written into the resulting Agreement and are subject to all terms and conditions in the Agreement.
Vendors shall be considered any team member who is performing any service that typically does not require prequalification, which is not subject to the Audit and Accounting System Requirements, and whose services are billed as direct expenses. Vendors may not be written into the resulting Agreement and may not be subject to all terms and conditions in the Agreement.
Phone: (404) 631-1972.
C. Audit and Accounting System Requirements
GDOT reserves the right to reject any proposal from firms that do not meet the following requirements:
1. Firm(s) should have an accounting system in place to meet the requirements of 48 CFR Part
31 and, in the case of non-profit organizations, OMB Circular A-122.
2. Any firm that currently has an aggregate contract amount exceeding $250,000 should have submitted its yearly CPA overhead audit.
3. The firm (s) should have no significant outstanding deficient audit findings from previous contracts with GDOT that have not been resolved.
4. The prime is responsible for being reasonably assured that all sub-consultants (s) presented as part of the proposed team are similarly in compliance with the above requirements.
D. Submittal Costs and Confidentiality
All expenses for preparing and submitting responses are the sole cost of the respondent submitting the response. The Department is not obligated to reimburse any respondent to reimburse such expenses. All submittals upon receipt become the property of the Department. Labeling information provided in submittals as “proprietary,” “confidential,” or any other designation of restricted use will not protect the information from public view. Subject to the provisions of the Open Records Act, the details of the proposal documents will remain confidential until a final award.
E. Award Conditions
This request is not an offer to contract or a solicitation of bids. This request and any proposal submitted in response, regardless of whether the proposal is determined to be the best proposal, are not binding upon the Department and do not obligate the Department to procure or contract for any services. Neither the Department nor any respondent submitting a response will be bound unless and until a written contract mutually accepted by both parties is negotiated as to its terms and conditions and is signed by the Department and a respondent containing such terms and conditions as are negotiated between those parties. The Department reserves the right to waive non-compliance with any requirements of this Request for Qualifications and to reject any or all proposals submitted in response. Upon review of responses, the Department will determine the respondent's proposal that, in the sole judgment of the Department, is in the best interest of the Department (if any is so determined), concerning the evaluation criteria stated herein. The Department then intends to conduct negotiations with such respondent(s) to determine if an acceptable contract may be reached.
F. Debriefings
In place of Pre-Award and Post-Award debriefings, it shall be the Department’s policy to provide the “Selection Package” at the time of the Selection Announcement (also referred to as the Announcement of Entering into Negotiations). The “Selection Package” will include the scores and comments of the phases for all firms that responded and will typically be provided as a PDF file and emailed. Previously, pre-award debriefings only provided the scores and comments of the firm.
It shall be the policy of the Department that all debriefings will typically be conducted in writing.
G. Right to Cancel or Change RFQ
GDOT reserves the right to cancel any Request for Qualifications where it is determined to be in the best interest of the Department to do so. GDOT reserves the right to increase, reduce, add to, or delete any item in this solicitation as deemed necessary.
It is the responsibility of all firms interested in submitting Statement of Qualifications (SOQs) for this advertisement to routinely check the posting on the Georgia Procurement Registry for any revisions to this RFQ.
H. GDOT Code of Conduct Pertaining to Conflict of Interest in the Award and Administration of
Contracts
Under GDOT Policy 3A-17, any GDOT employee who leaves the employment of the Department and subsequently becomes employed with a consultant firm and whose duties while employed with the Department included the direct involvement with the negotiation, administration, or management of a contract in which the firm is either the primary consultant or a sub-consultant SHALL NOT be authorized to work on that contract as an employee of that firm for one (1) year after their employment ends.
Additionally, on July 1st of each year, any consulting firm that is under contract with the Department as a prime or sub-consultant shall provide to the Department's Chief Procurement Officer (CPO) a current list of all former Department employees employed by the firm and a document that certifies the responsibilities of those employees as it relates to the current contracts with the Department.
This certification document shall attest to the fact that over the last year, no former Department employee who is employed by their firm has worked on a contract between the Department and their firm where that employee, when employed by the Department, had direct involvement with the selection, award, and/or administration of the consultant contract. Any consultant firm entering a contract with the Department for the first time as a prime or sub-consultant shall provide the initial required list of former Department employees and certification before the contract's effective date.
If the Department's CPO determines at any point during a contract that an actual conflict exists as it relates to the above paragraph, then the CPO shall have the authority to issue a stop-work order on that contract.
[REMAINDER OF PAGE INTENTIONALLY LEFT BLANK]
EXHIBIT I-1
1. Contract Type: IDIQ
2. County(ies): All
3. Description: Roundabouts and Alternative Intersections/Interchanges Support Services
4. Required Area Classes: This table identifies all GDOT Area Classes relevant to the scope of services. It indicates whether the Prime Consultant and/or any Team Members (Subconsultants) must be prequalified by GDOT in each listed Area Class.
Area Class No.
Area Class Description Prime
Required Team
Required
1.06(a) Documentation x
1.06(b) History x
1.06(c) Air Studies x
1.06(d) Noise Studies x
1.06(e) Ecology x
1.06(f) Archaeology x
1.06(g) Freshwater Aquatic Survey x
1.07 Attitude, Opinion & Community Value Studies x
1.10 Traffic Studies x
1.13 Non-Motorized Transportation Planning x
3.01 Two-lane or Multi-lane Rural Roadway Design x
3.02 Two-lane or Multi-lane Urban Roadway Design x
3.03 Multi-lane Urban Roadway Widening or Reconstruction Design in heavily developed commercial, industrial or residential areas x
3.04 Multi-lane Rural Interstate Highway Design x
3.05 Multi-lane Urban Interstate Highway Design x
3.06 Traffic Operations Studies x
3.07 Traffic Operations Design x
3.08 Landscape Architecture x
3.09 Traffic Control Systems Analysis, Design & Implementation x
3.13 Bicycle and Pedestrian Facility Design x
3.15 Highway Lighting x
5.01 Land Surveying x
5.02 Engineering Surveying x
5.08 Overhead-Subsurface Utility Engineering (SUE) x
6.01(a) Soil Survey Studies x
9.01 Erosion, Sedimentation, and Pollution Control and Plan Preparation x
5. Scope:
The Consultant shall provide on-call/as-requested support services for the selection, planning, design, and in-service assessment of Roundabouts and Alternative Intersections/Interchanges.
The Consultant shall provide:
A. Intersection/interchange configurations to include the following:
1) Roundabouts: mini, compact, conventional single lane and multilane/hybrid configurations.
2) Median U-Turn (MUT).
3) Reduced Conflict Intersection (RCI) /Superstreet.
4) Jug Handle.
5) Displaced Left Turn (DLT).
6) Green-T – signalized and unsignalized.
7) Quadrant Roadway.
8) Diverging Diamond Interchange (DDI).
B. Proposed alternative Intersection designs will follow best practices as established by GDOT.
Design refinement will be identified to maximize the operational and safety performance of the alternative intersections while considering project-specific constraints. Tasks to be performed include:
1) Provide Monthly Progress Reports that track, record, and summarize all activities.
2) Intersection Control Evaluation (ICE), which will include the roundabout and other alternatives, such as innovative intersections.
3) Preparation of Traffic Engineering Studies, including operational analysis, safety performance prediction, benefit/cost comparison, and cursory environmental impact assessment.
4) Preparation and/or review of Concept Reports.
5) Concept Validation Reviews.
6) Review of Plans Submittals – Preliminary and Final.
7) Preparation of plans applying adhering to NEPA requirements and GDOT Project Development
Process and Plan Preparation Guide provisions.
8) Research of alterative intersection design operations safety and design elements.
9) Policy and guidelines formulation, review, and development.
10) Develop and deliver planning and design training in-person and virtual.
11) Assist with public outreach and Public Information Open House meetings – meeting content displays and presentation.
12) Support and coordination with Safety and Operations contracts.
13) Traffic Forecasts in accordance with the Office of Planning content and documentation requirements.
14) In-service, pre/post-construction safety and operations audits.
15) Incremental review and mentoring of GDOT staff and consultants on all aspects of planning, design, and construction plan preparation.
16) On-call Support – phone calls, web conferences, and/or other meetings outside of the project’s formal peer review.
17) Prepare and give presentations.
18) Executive-Level Briefings.
C. Technical sub-tasks include:
1) Intersection Control Evaluation spreadsheet input of traffic data, selection of crash modification factors, cost data, social and environmental factors, and submit for review.
2) Perform/review benefit cost (B/C) ratio for comparison of alternatives, including quantity estimation and project costing.
3) Documentation of project background and site conditions – description of the corridor, vicinity map, aerial photo for Time Extension Transportation Enhancement Traffic Engineering (TE) studies.
4) Safety assessment (planning or in-service):
a. Retrieve and/or review crash data.
b. Prepare/review crash diagram.
c. Field review of operations, traffic conflicts, and human factors.
d. Countermeasure development.
e. Economic assessment.
f. Report documentation.
5) Alternative sketches which will include the roundabout and other alternatives such as innovative intersections, stop control, and signal control.
6) Traffic Forecasting:
a. 12-Hour Turning Movement Counts.
b. Truck percentages.
c. Traffic growth trend analysis.
d. Traffic Diagrams.
e. Operational Analysis using GDOT tools and…
This is the start of the file's text. The full file is on GovTribe.