This amendment modifies a request for proposals for construction services at the National Renewable Energy Laboratory's Field Test Laboratory Microbial Energetic Laboratory. The amendment extends the proposal submission deadline to October 30th, 2023 in response to questions from prospective offerors. It provides responses to clarifying questions about required resumes, schedules, bid guarantees, and the possibility of duplicating project examples between different criteria sections. No other significant changes are made to the solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION

Solicitation No. RFP-2023-23076 Amendment No. 2 Date: 9/29/2023

ISSUED BY:

NREL

Attn: Darcy Montgomery 15013 Denver West Parkway Golden, CO 80401 Email: Darcy.Montgomery@nrel.gov

PROJECT NAME & LOCATION:

Field Test Laboratory Microbial Energetic Laboratory FTLB – NREL South Table Mountain

The above numbered solicitation is amended as set forth below.

The date specified for receipt of offers [ ] remain unchanged. [ X ] is extended to Monday October 30, 2023.

FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN ACCORDANCE WITH THE INSTRUCTIONS

TO OFFERORS MAY RESULT IN REJECTION OF YOUR OFFEROR. EXCEPT AS PROVIDED

HEREIN, ALL TERMS AND CONDITIONS OF THE SOLICITATION DOCUMENT REMAIN

UNCHANGED AND IN FULL FORCE AND EFFECT.

Description: The purpose of this Amendment No. 2 is to

A. Amend the solicitation schedule as follows:

SITE WALK SCHEDULED: OCTOBER 6, 2023@ 10:00 a.m. – NREL SOUTH TABLE MOUNTAIN

CAMPUS – MEET @ FIELD TEST LABORATORY BUILDING (FTLB)

TECHNICAL QUESTIONS DEADLINE: OCTOBER 16, 2023

PROPOSAL SUBMISSION DEADLINE: OCTOBER 30, 2023

B. Respond to questions received to date below:

1. In section 2 Project Overview Selection Details for Technical Requirements IV 4.2.3 it states that you are requesting Superintendents and Craft Professionals resumes. Is this for the subcontractor's superintendent resumes, I see you are requesting superintendents' resumes again in section 4.3.3. Not sure if that is a duplicate request for our team superintendents or not. Please clarify.

RESPONSE: One resume for the subcontractor’s superintendent is acceptable to be included in the proposal submission and will satisfy both requirements. Examples of resumes we are seeking include the subcontractor’s project management team generally employed on a construction project i.e. -superintendent, safety professional, and project manager. Lower tier project management resumes are mailto:Darcy.Montgomery@nrel.gov not required for proposal submission.

2. In section 2 Project Overview Selection Details for Technical Requirements it states #2 schedule.

Are you requesting a project schedule for proposal submission, or is this just for information? I saw it but didn’t have a submission requirements box. I just want to make sure. Please clarify if a project schedule is required for submission.

RESPONSE: Please provide a schedule based on your best forecast which includes your trade partnership’s ability to meet material and services requirements needed to meet the project objectives.

3. Is there a Bid Guarantee (Bid Bond) Required for proposal submission?

RESPONSE: No.

4. Section 4.1.4 and 4.1.6 look like they may be requesting the same thing. Would it be ok to submit the same projects in section 4.1.4 and 4.1.6?

RESPONSE: Yes. Please provide information that accurately reflects your organization’s ability to perform the work requirement, which will satisfy each of the best value criteria listed above.