Amendment 1 to RFP-19-PHX-03, SF30,
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_RFP-19-PHX-03_Amend-2_8-12.pdf | ||
| Amend_1_Attachment_E_-_SOW_Temp_Mobile_CT_Trailer.pdf | ||
| Amend-1_Combined_Syn-Sol_RFP-19-PHX-03.docx | DOCX document | |
| Amend-1_Attachment_B_Scope_of_Work_CT_and_Injector.pdf | ||
| Amend-1_Attachment_A_-_Price_Schedule.xlsx | XLSX spreadsheet | |
| Amend-1_Scope_of_Work_CT_Project.doc | DOC document | |
| Scope_of_Work_CT_Project.doc | DOC document | |
| Attachment_E_-_SOW_Temp_Mobile_CT_Trailer.doc | DOC document | |
| Attachment_B_-_Scope_of_Work_CT_and_Injector_R2.docx | DOCX document | |
| Attachment_D_-_Scope_of_Work_PM_and__Repair_R1.doc | DOC document | |
| Combined_Synop-Solicit_RFP-03.docx | DOCX document | |
| Attachment_G_-_CT_Mobile_Trailer_Location.pdf | ||
| Attachment_I_-_2019_Tax_Exempt_Letter.pdf | ||
| Attachment_A_-_Price_Schedule.xlsx | XLSX spreadsheet | |
| Attachment_F_-_CT_Buidling_Floor_Plan.pdf | ||
| Attachment_H_-_Clause_Admin_Data.docx | DOCX document | |
| Attachment_C_-_VistA_Imaging_DICOM.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RPF-19-PHX-03
7 11/2019
08/06/2019000001
AMENDMENT 000001:
Purpose of this amendment is to change the NAICS code, change Attachment E - Statement of Work, Attachment A - Price Schedule, and Attachment B Scope of Work CT and Injector.
1. Changes to Combined Synopsis Solicitation: See attachment Amend-1 Combination Synopsis-Solicitation RFP-19-PHX-03 and changes are highlighted and underline in blue.
1.a. Paragraph (iv), change NAICS from 330112 to 334517 and size standard is 1,000 employees.
1.b. Paragraph (ix), Sub-Paragraph A. Technically Acceptable, sub-section (i), change from Lateral table slide to Lateral Table Slide or equivalent.
1.c. Change proposal due date for the following paragraphs.
(viii) Addendum to FAR 52.212-1 and (xv) Proposals are due:
Change from August 11, 2019 to August 14, 2019.
2. Change to Scope of Work CT Project, see attachment Amend-1 Scope of Work CT Project. Amendments are highlighted in blue and underlined.
Paragraph D, Scope of Services, sub-paragraph 3.a. Add " 10 days after award or sooner".
3. Change to Attachment A - Price Schedule. Change item number 13 and 14 and changes are highlighted in blue and underlined. See attachment Amend-1 Attachment A - Price Schedule.
4. Change to Attachment B - Scope of Work CT and Injector.
Amendments are highlighted in blue and underlined.
Paragraph 2., INSTALLATION. See attachment Amend-1 Attachment B - Scope of Work CT and Injector.
5. Change to Attachment E - Scope of Work Temporary Mobile Trailer. Amendments are highlighted in blue and underlined.
5.a.Change paragraph sequence from r. to ac.
5.b.Change Paragraph r. and Paragraph s.
5.c. Paragraph X is BLANK.
5.d. Paragraph Ai. REPORTING REQUIREMENTS, remove Report #4 5.e. Paragraph Aj. PERFORMANCE WORK OBJECTIVES/STANDARDS, Remove PRS#2.
5.f. Add paragraph AK PROTOLS.