Exhibit I Submittal Requirements
View the file
Other files
Show 40 more
Latest 50 of 54 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit I Attachment B for EP (Rev. 0.1, 2-17-15) Subcontractor Submittal Requirements Summary Revision 2 Dated 3/20/2019
Subcontract No. PR#0000297 Page 1 of 4
Subcontractor Submittal Requirements Summary
NOTICE
Failure to submit required submittals as delineated on this form may result in withholding of payment in accordance with subcontract terms and conditions.
Submit To: Overnight Delivery Address: Regular Mailing Address:
SUBMITTAL SCHEDULE
A Per Subcontract Schedule S Prior to Shipment Z When Required SANN Semi Annual B Prior to Balance of Payment U Prior to Use ANN Annually WKLY Weekly F Prior to Fabrication W Prior to Commencing Work DAY Daily WRR Implemented at work release level on Blanket Agreements
M Prior to Mobilization X Prior to Purchase MON Monthly BI-
WKLY
Every 2 weeks
N Prior to Notice to Proceed Y Prior to Progress Payment for Each Specific Task
QRTLY Quarterly
SUBMITTAL TYPE REQUIRED
D Drawings ED Electrical Diagrams P Prints /photocopies SD Shop Drawings
EM Electronic media II Installation InFETLuctions PD Performance Data - Curves SP Spare Parts and Maintenance Materials
CA Calculations ML Materials/Parts List/Design Mixes
PH Photographs TR Test Reports
CD Catalog Data OM Operations & Maintenance Data
RD Project Record Documents WA Warranties
CT Certifications OT Other S Sample (2) (*) indicates quantity R Report O Original SC Samples/Colors SPEC
REVIEWER DESIGNATION (For N3B Use Only)
CA Contract AdminiFETLator IT Information Technology RM Regulatory Manager
CFO Chief Financial Office LR Labor Relations SA Safety
CON Construction LTS Long Term Stewardship SBM Small Business Office Manager
DC Derivative Classifier NFS Nuclear/Facility Safety SCM FETL Manager
EC Environmental Compliance NMC Nuclear Materials & Accountability SEC Security
ES&H Environmental Safety & Health OCI Office of Counterintelligence SST Secondary SCC
ERM Emergency Management PCE Project Controls FETL Field Execution Technical Lead
FM Facility Manager PHS Physical Security TA Transportation
FP Fire Protection PM Project Manager TL Technical Lead
HR Human Resources PS Personnel Security TRN Training
HRE HR Employee Concern QA Quality Assurance VC Visitor Control
HRS HR Secondary RAD RADCON WGS Waste Generator Services
IH InduFETLial Hygiene RM/L Risk Manager/Legal (*) Denotes Lead Reviewer
Submittal No./ Submittal Description
Reference
Submittal Schedule
Submittal Type
N3B Response Needed?
N3B Reviewer (For N3B Use Only)
Commercial Document Requirements (CDR)
3.0 Exhibit D Scope of Work and Technical Requirements
3.8 Field Data
3.8.1 Summary of IH Sampling Results Exhibit D 1.3.4, 2.4.11
Z RD N FETL/ES&H
3.8.2
NMED Notifications
Exhibit D 1.3.4 15 working days prior to beginning work requiring notification
RD Y FETL/TL
3.8.3
Sample Collection Logs and Chain of Custody records
Exhibit D 1.3.4 Within 24 hours of sample collection
P N FETL/TL
Subcontract No. PR#0000297 Page 2 of 4
Submittal Type
N3B Response Needed?
N3B Reviewer (For N3B Use Only)
3.8.4 Field log and note books (PIC logbooks, Health & Safety logbooks and documents, field photographs, daily field reports, samples taken table, waste inventory, field forms and inspections)
Exhibit D 1.3.4 Z RD N FETL
3.8.5 Digital photography and associated
electronic files
Exhibit D 1.3.4 Z R,EM N FETL
3.8.6 Field Data tables/Samples Taken Tables Exhibit D 1.3.4 Z RD N FETL/TL
3.8.7 Daily Field Reports and Tailgate Safety
Meeting Exhibit D 1.3.4 DAY RD Y FETL/TL
3.8.9 Turnover Punch List Exhibit D 2.6 Z R Y FETL
3.9 Mapping
3.9.1 Arc GIS .shp files Exhibit D 1.4.6 Z RD N FETL/TL
3.9.2
Sample Location Coordinates Exhibit D 1.3.4, 1.3.6, 2.4.37
Z RD N FETL/TL
3.14 Readiness
3.14.1 Schedules Exhibit D 2.4.5 MON, Z OT Y FETL/PM
3.14.2 Readiness Assessments, including
training audit verification sheets Exhibit D 2.4.9 A EM Y FETL/PM
3.14.3 Project Execution Plan Exhibit D 2.4.10 M, 15 working
days after mobilization
R Y FETL/PM
3.14.4 Beryllium Program Field Implementation
Plan
Exhibit D 2.4.11 Exhibit F 53.0
M, 15 working days after mobilization
R Y FETL/ES&H
3.14.5 Kick off meeting minutes Exhibit 2.4.4 M, 2 days
after meeting date
RD Y FETL
3.15 Reports
3.15.1 Data Action Summary Reports for
Chaquehui Canyon Aggregate Area Exhibit D 1.4.1 Z EM,R Y FETL/ TL
3.15.2 30% Draft Investigation Report for Chaquehui Canyon Aggregate Area
Exhibit D 1.4.3 ZA EM,R Y FETL/ TL
3.15.3 60% Draft Investigation Report for Chaquehui Canyon Aggregate Area
Exhibit D 1.4.3 ZA EM,R Y FETL/ TL
3.15.4 95% Draft Investigation Report for Chaquehui Canyon Aggregate Area
Exhibit D 1.4.3 ZA EM,R Y FETL/ TL
3.15.5 Final Investigative Report for Chaquehui
Canyon Aggregate Area
Exhibit D 1.4.6 ZA EM,R Y FETL/ TL
3.15.6 Approved NMED Investigation Report for
Chaquehui Canyon Aggregate Area
Exhibit D 1.4.7 ZA EM,R,CT Y FETL/ TL
3.15.7 Field Summary Report for Chaquehui
Canyon Aggregate Area
Exhibit D 2.4.33 ZA EM,R Y FETL/ TL
3.15.8 Data Action Summary Reports for South
Ancho Canyon Aggregate Area
Exhibit D 1.4.1 Z EM,R Y FETL/ TL
3.15.9 30% Draft Investigation Report for South Ancho Canyon Aggregate Area
Exhibit D 1.4.4 ZA EM,R Y FETL/ TL
3.15.10 60% Draft Investigation Report for South Ancho Canyon Aggregate Area
Exhibit D 1.4.4 ZA EM,R Y FETL/ TL
3.15.11 95% Draft Investigation Report for South Ancho Canyon Aggregate Area
Exhibit D 1.4.4 ZA EM,R Y FETL/ TL
3.15.12 Final Investigation Report for South Ancho
Canyon Aggregate Area
Exhibit D 1.4.6 ZA EM,R Y FETL/ TL
3.15.13 Approved NMED Investigation Report for
South Ancho Canyon Aggregate Area
Exhibit D 1.4.7 ZA EM,R,CT Y FETL/ TL
3.15.14 Field Summary Report for South Ancho
Canyon Aggregate Area
Exhibit D 2.4.33 ZA EM,R Y FETL/ TL
3.15.15 Data Action Summary Reports for Lower
Water/Indio Canyons Aggregate Area
Exhibit D 1.4.1 Z EM,R Y FETL/ TL
3.15.16 30% Draft Investigation Report for Lower Water/Indio Canyons Aggregate Area
Exhibit D 1.4.4 ZA EM,R Y FETL/ TL
3.15.17 60% Draft Investigation Report for Lower Water/Indio Canyons Aggregate Area
Exhibit D 1.4.4 ZA EM,R Y FETL/ TL
3.15.18 95% Draft Investigation Report for Lower Water/Indio Canyons Aggregate Area
Exhibit D 1.4.4 ZA EM,R Y FETL/ TL
3.15.19 Final Investigation Report for Lower
Water/Indio Canyons Aggregate Area
Exhibit D 1.4.6 ZA EM,R Y FETL/ TL
3.15.20 Approved NMED Investigation Report for
Lower Water/Indio Canyons Aggregate Area
Exhibit D 1.4.7 ZA EM,R,CT Y FETL/ TL
3.15.21 Field Summary Report for Lower
Water/Indio Canyons Aggregate Area
Exhibit D 2.4.33 ZA EM,R Y FETL/ TL
3.15.22 Daily Activity Report Exhibit D 2.4.32 DAY RD Y FETL
Subcontract No. PR#0000297 Page 3 of 4
Submittal Type
N3B Response Needed?
N3B Reviewer (For N3B Use Only)
3.15.23 Monthly Status Report Exhibit F 2.4.33 MON 5 days
after completion of month
RD N FETL/PM
3.15.24 Meeting Materials and Meeting Minutes Exhibit D 2.4.4, 1.4.8, 1.4.7
Z EM Y FETL
3.15.25 Schedules Exhibit D 1.3.4, 1.4.8, 2.4.5
MON, Z OT N FETL/PM
3.15.26 Accruals Exhibit D 2.4.36 MON, Z By
the 16th of each month
OT N FETL/PM
4.0 Exhibit F Environmental Safety & Health
4.1 ES&H Plan (Corporate) Exhibit F 2.0 5 days after
award
RD Y FETL/ES&H
4.2 SSESHP Exhibit F 2.1 N RD Y FETL/ES&H
4.3 Subcontractor & Lower-Tier Subs
Minimum Performance Eligibility Factors Exhibit F 3.1, F 3.2 M, 15 days prior to new lower- tier start
Y FETL/ES&H
4.4 Qualifications ES&H Professional Exhibit F 4.2 M RD Y FETL/ES&H
4.5 Qualifications Environmental Professional Exhibit F 4.10 Z RD Y FETL/ES&H
4.6 Incident Reporting Written Exhibit F 5.2 Within 24
hours of the incident
RD Y FETL/ES&H
4.7 Complete Accident/Incident Exhibit F 5.4 Within 2
working days of the incident
RD Y FETL/ES&H
4.8 Injury/Illness Recordkeeping and
Reporting
Exhibit F 6.1 Z RD Y FETL/ES&H
4.9 Weekly Productive Man-hour report Exhibit F 6.4 WKLY-
Mondays
RD N FETL/ES&H
4.10 Training Records Exhibit F 7.0 W RD Y FETL/ES&H/TL
4.11 Emergency Procedures Exhibit F 11.3 M ES&H plan RD Y FETL/ES&H
4.12 Respiratory Protection Exhibit F 13.1 M ES&H plan RD Y FETL/ES&H
4.13 Hearing Conservation Program Exhibit F 14.1 M ES&H plan RD Y FETL/ES&H
4.14 Motor Vehicle Safety Program Exhibit F 16.1 M ES&H plan RD Y FETL/ES&H
4.15 Major Equipment Declaration and
documentation of removal of uncontaminated equipment
Exhibit F 16.10 Prior to placing in service
RD Y FETL/ES&H
4.16 Hazard Communication Program Exhibit F 19.1 M ES&H plan RD Y FETL/ES&H
4.17 Material Safety Data Sheets (MSDS) Exhibit F 19.2 M, Z RD Y FETL/ES&H
4.18 Integrated Work Documents (IWDs) Exhibit F 20 Prior to start of task-specific work
RD Y FETL/ES&H
4.19 Fire Protection and Prevention Plan Exhibit F 21 M ES&H plan RD Y FETL/ES&H
4.20 Fall Prevention/Protection Plan Exhibit F 23 UM ES&H
plan
RD Y FETL/ES&H
4.21 Spark and Flame Permit F22.0
Attachment F22-1
2 working days prior to activity
RD Y FETL/ES&H
4.22 Excavation and Trenching
Potholing Plan
Exhibit F 28.3 Exhibit F 28.20
10 working days prior to activity submit Excavation/So il Disturbance Request
RD Y FETL/ES&H
4.23 Cranes & Material Handling Equipment
training, certifications, inspections, and lift plan(s)
Exhibit F32 Attachment F32-1
M ES&H plan RD Y FETL/ES&H
4.24 Gas Cylinder Use and Storage Procedure Exhibit F 35.1 M ES&H plan RD Y FETL/ES&H
4.25 Traffic Control Plan Exhibit F 37.1 M ES&H plan RD Y FETL/ES&H
4.26 Spill Prevention Control and
Countermeasure (SPCC), including spill inspection records and waste water discharge records
Exhibit F42.1 M,Z ES&H plan
RD Y FETL/ES&H
4.27 Storm Water Management Exhibit F 43 Z ES&H plan RD Y FETL/ES&H
4.28 Air Quality permits Exhibit F 44 Z ES&H plan RD Y FETL/ES&H
4.29 Biological Resources Exhibit F 45 M ES&H plan RD Y FETL/ES&H
4.30 Cultural Resources Exhibit F 46 M ES&H plan RD Y FETL/ES&H
4.31 Radioactive Sealed Sources Exhibit F 50.3 Z ES&H plan RD Y FETL/ES&H
4.32 Industrial Hygiene Program Exhibit F 52.1 M ES&H plan RD Y FETL/ES&H
4.33 Beryllium Program Exhibit F 53.0 Z ES&H plan RD Y FETL/ES&H
Subcontract No. PR#0000297 Page 4 of 4
Submittal Type
N3B Response Needed?
N3B Reviewer (For N3B Use Only)
5.0 Exhibit G Security
5.1 Vehicle Information Exhibit G4.4 M, Z RD N FETL/SEC
5.2 Badging Exhibit G6.2 M, Z RD N FETL/SEC
5.3 PED’s/Computing Devices in Limited Area Exhibit G8.2 Z RD Y FETL/SEC
6.0 Exhibit H Quality Assurance Requirements
6.1 Quality Assurance Plan (Corporate) Exhibit H 5 days after award
RD Y FETL/SEC
6.2 Project Specific Quality Assurance
Program
QC-01B 30 calendar days after award
RD Y FETL/QA
6.3 Design/Change Control for Subcontractor
Provided Design
QC-02 Z RD Y FETL/QA
6.4 Design/Change Control for Contractor
Provided Design
QC-02A Z RD Y FETL/QA / TL
6.5 Qualification and Certification of Personnel
and Staff
QC-03 M RD Y FETL/QA/ TL
6.6 Traceability - Item QC-04 Z RD Y FETL/QA
6.7 Certificate of Conformance QC-06 Z RD Y FETL/QA
6.8 Manufacturing, Inspection, Maintenance, Repair, and/or Test Procedures
QC-07 Z RD Y FETL/QA
6.9 Inspection, Examination, and Test Reports QC-08 Z RD Y FETL/QA
6.10 Engineering Evaluation / Analysis Report QC-08A Z RD Y FETL/QA
6.11 Engineering Drawings QC-11 Z RD Y FETL/QA
6.12 Certification of Calibration QC-12 Z RD Y FETL/QA
6.13 Shelf Life Certifications/Storage
Requirements QC-16 Prior to first shipment
RD N FETL/QA
6.14 Catalog Data QC-17A Z RD Y FETL/QA
6.15 Contractor’s Right of Access to
Subcontractor’s Facility
QC-22 Z RD Y FETL/QA
6.16 Design Review Prior to Production QC-24 Z RD Y FETL/QA
6.17 Nonconformance Reporting QC-25 Within 3 days
of occurrence
RD Y FETL/QA/TL/PM
6.18 Corrective Action Reports QC-26 Z RD Y FETL/QA
6.19 Suspect/Counterfeit Items QC-27 Z RD Y FETL/QA
6.20 Serialization and Marking QC-28 Z RD Y FETL/QA
6.21 Handling, Receiving, Storage, Shipping, and Packaging
QC-29 Z RD Y FETL/QA
6.22 Documents and Records QC-34 Z RD Y FETL/QA
6.23 Documents and Records: Environmental
Work
QC-34A Z RD Y FETL/QA
6.24 Certificates of Analysis QC-35A Z RD Y FETL/QA
6.25 Other QC-37 Z RD Y FETL/QA