About this file

Exhibit C Form D Subcontract Schedule

View the file

Other files

File Type Posted
Exhibit_C_FORM_H_Resume_of_Key_Personnel.doc DOC document
RFP-0000297_Amendment_3.docx DOCX document
1._N3B-P101-21_Chronic_Beryllium_Disease_Prevention_Program_DRAFT.pdf PDF
RFP-0000297_Amendment_2.docx DOCX document
4._N3B-Form-2120_Beryllium_Release_Fillable_Form__DRAFT.pdf PDF
3._N3B-Form-2119__Regulated_Beryllium_Area_Entry_Log_Form__DRAFT.pdf PDF
5._N3B-Form-2175_Beryllium_Inventory_Update_Form__DRAFT.pdf PDF
2._N3B-Form-2061_Beryllium_Hazard_Assessment_Form__DRAFT.pdf PDF
RFP-0000297_Amendment_1.docx DOCX document
2_TA-33_Overview.jpg JPG image
5_TA-33_Chaquehui_South_Site.jpg JPG image
3_TA-33_South_Ancho_East_Site.jpg JPG image
1_N3B_Task_Specific_Briefing_Form.doc DOC document
4_TA-33_Chaquehui_Main_Site_Area_6.jpg JPG image
Exhibit_D_Appendix_D-3_IWP_for_Lower_Water.pdf PDF
Exhibit_D_Appendix_D-9_Training_Matrix_Chaquehui_South_Ancho_Lower_Water.pdf PDF
Exhibit_D_Appendix_D-16_NMED_SSG.pdf PDF
Exhibit_D_Appendix_D-5_CCAA_Analytical_Table_Figures_Coordinates_Lithlog.pdf PDF
Exhibit_D_Appendix_D-11_NMED_Consent_Order.pdf PDF
Exhibit_D_Appendix_D-4_SA_Analytical_Table_Figures_Coordinates.pdf PDF
Exhibit_D_Appendix_D-7_CGP.pdf PDF
Exhibit_C_FORM_M_Work_In_Progress.doc DOC document
Exhibit_D_Appendix_D-1_IWP_for_SACAA.pdf PDF
Exhibit_C_FORM_B_Construction_Plant_Equipment_List.doc DOC document
VMF_with_NTTC.pdf PDF
Exhibit_D_Rev_0_Chaquehui_South_Ancho_Lower_Water_CAAs.pdf PDF
Exhibit_I_Attachment_B.pdf PDF
Exhibit_D_Appendix_D-18_N3B_Subcontractor_Submittal_Form.pdf PDF
Exhibit_D_Appendix_D-14_SDDR_Form_2178.pdf PDF
RFP-0000297_Chaquehui_South_Ancho_Water_Canyons_FINAL.pdf PDF
Exhibit_C_FORM_N_Experience_Statement.doc DOC document
Exhibit_B_RFP-0000297_-_N3B_General_Conditions_for_Fixed_Price_Subcontracts.pdf PDF
Exhibit_D_Appendix_D-13_N3B_Request_for_Information_Form.pdf PDF
Exhibit_D_Appendix_D-15_PRPP_for_Chaquehui_and_South_Ancho.pdf PDF
Form_9100_-_Subcontract_Long_Form_Rev._0_RFP-0000297.pdf PDF
Exhibit_D_Appendix_D-2_IWP_for_CCAA.pdf PDF
Exhibit_D_Appendix_D-6_Lower_Water_Analytical_Table_Figures_Coordinates.pdf PDF
Exhibit_H_Quality.pdf PDF
Exhibit_G_Signed_South_Ancho_Canyon_and_Chaquehi_Canyon_1-24-2019.pdf PDF
Exhibit_D_Appendix_D-12_Threemile_SIR.pdf PDF
Certificate_of_Current_Cost_or_Pricing_Data.pdf PDF
Exhibit_F_Chaquehui_South_Ancho_Water_Canyon_w_DRAFT_CBDPP.pdf PDF
Exhibit_D_Appendix_D-10_N3B_SOPs_Procedures.pdf PDF
Exhibit_D_Appendix_D-8_WCSF_Chaq_Cyn_Agg_Area_022519.pdf PDF
Exhibit_F_Form_F3-2.docx DOCX document
Exhibit_C_FORM_A_Scheudle_of_Quantities_and_Prices.docx DOCX document
Exhibit_A_RFP-0000297_-_Prime_Contract_Flow_Down_Clauses_N3B_Form_9055.pdf PDF
Exhibit_C_FORM_F_Project_Organization_and_Workplan.doc DOC document
Exhibit_C_FORM_C-1_Lower_Tier_Experience_Statement.doc DOC document
WD_15_5463_Effective_1_1_19.pdf PDF
Show 40 more

Latest 50 of 54 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ex C Form D (Rev. 1, 9/22/08) Exhibit C Form D – Subcontract Schedule March 20, 2019

EXHIBIT “C”

FORM D

SUBCONTRACT SCHEDULE

PN: Edit the Clause titles identified below to fit the Subcontract pro forma being used. For example, Services and Architect/Engineer proformas incorporate schedule requirements in the milestone clause.

Bidder to submit a Preliminary Subcontract Schedule addressing the Subcontract Milestone dates listed in the Task Order Schedule and the Target/Milestone dates in the table below.

Bidder is to identify at least three potential problem areas that may affect successful subcontract completion and Bidder’s proposed resolution of each problem should it occur.

Based on the successful Bidder’s Preliminary Subcontract Schedule and CONTRACTOR requirements, an agreed schedule shall be developed after award, in accordance with RFP-0000297 Section 15.0, Schedule.

*Consent Order Deliverable

Target/Milestone
Due Date
Issue RFP
March 20, 2019
Pre-bid meeting/Site Visit
April 10, 2019/April 11, 2019
Questions Due
April 12, 2019
Response to Questions Complete
April 19, 2019
Bid Due Date
April 24, 2019
Notice of Award (NOA)
June 7, 2019
Kick Off Meeting
June 14, 2019
Project Execution Plan and Beryllium Program Field Implementation Plan
June 28, 2019
Pre-Job Submittals Complete and Approved
July 26, 2019
Readiness Review Complete
July 31, 2019
Notice to Proceed (NTP)
August 2, 2019
Begin Mobilization
August 5, 2019
Chaquehui Canyon Letter Report summarizing progress due to NMED
*September 30, 2019
Chaquehui Canyon Aggregate Area 30% Draft to N3B
December 6, 2020
Chaquehui Canyon Aggregate Area 60% Draft to N3B
February 14, 2020
Chaquehui Canyon Aggregate Area 95% Draft to N3B
May 8, 2020
Chaquehui Canyon Aggregate Area Final Draft to N3B
June 5, 2020
Chaquehui Canyon Aggregate Area Investigation Report Submitted to NMED
*June 30, 2020
South Ancho Canyon Aggregate Area 30% Draft to N3B
February 7, 2020
South Ancho Canyon Aggregate Area 60% Draft to N3B
April 10, 2020
South Ancho Canyon Aggregate Area 95% Draft to N3B
June 12, 2020
South Ancho Canyon Aggregate Area Final Draft to N3B
July 10, 2020
South Ancho Canyon Aggregate Area Investigation Report Submitted to NMED
*September 30, 2020
Lower Water/Indio Canyons Aggregate Area 30% Draft to N3B
March 13, 2020
Lower Water/Indio Canyons Aggregate Area 60% Draft to N3B
May 8, 2020
Lower Water/Indio Canyons Aggregate Area 95% Draft to N3B
August 7, 2020
Lower Water/Indio Canyons Aggregate Area Final Draft to N3B
September 4, 2020
Lower Water/Indio Canyon Aggregate Area Investigation Report Submitted to NMED
*September 30, 2020
Field Summary Report for Chaquehui Canyon Aggregate Area
30 calendar days after completion of field work
Field Summary Report for South Ancho Canyon Aggregate Area
30 calendar days after completion of field work
Field Summary Report for Lower Water/Indio Canyons Aggregate Area
30 calendar days after completion of field work

NOTE: THIS FORM IS PRIMARILY FOR BID EVALUATION HOWEVER IS NOT PRECLUDED FROM BECOMING PART OF A RESULTANT SUBCONTRACT.

PR# RFP-0000297

File details come from the government source that posted it.