Ex C Form D (Rev. 1, 9/22/08) Exhibit C Form D – Subcontract Schedule March 20, 2019
EXHIBIT “C”
FORM D
SUBCONTRACT SCHEDULE
PN: Edit the Clause titles identified below to fit the Subcontract pro forma being used. For example, Services and Architect/Engineer proformas incorporate schedule requirements in the milestone clause.
Bidder to submit a Preliminary Subcontract Schedule addressing the Subcontract Milestone dates listed in the Task Order Schedule and the Target/Milestone dates in the table below.
Bidder is to identify at least three potential problem areas that may affect successful subcontract completion and Bidder’s proposed resolution of each problem should it occur.
Based on the successful Bidder’s Preliminary Subcontract Schedule and CONTRACTOR requirements, an agreed schedule shall be developed after award, in accordance with RFP-0000297 Section 15.0, Schedule.
*Consent Order Deliverable
| Target/Milestone |
| Due Date |
| Pre-bid meeting/Site Visit |
| April 10, 2019/April 11, 2019 |
| Questions Due |
| April 12, 2019 |
| Response to Questions Complete |
| April 19, 2019 |
| Bid Due Date |
| April 24, 2019 |
| Notice of Award (NOA) |
| June 7, 2019 |
| Kick Off Meeting |
| June 14, 2019 |
| Project Execution Plan and Beryllium Program Field Implementation Plan |
| June 28, 2019 |
| Pre-Job Submittals Complete and Approved |
| July 26, 2019 |
| Readiness Review Complete |
| July 31, 2019 |
| Notice to Proceed (NTP) |
| August 2, 2019 |
| Begin Mobilization |
| August 5, 2019 |
| Chaquehui Canyon Letter Report summarizing progress due to NMED |
| *September 30, 2019 |
| Chaquehui Canyon Aggregate Area 30% Draft to N3B |
| December 6, 2020 |
| Chaquehui Canyon Aggregate Area 60% Draft to N3B |
| February 14, 2020 |
| Chaquehui Canyon Aggregate Area 95% Draft to N3B |
| May 8, 2020 |
| Chaquehui Canyon Aggregate Area Final Draft to N3B |
| June 5, 2020 |
| Chaquehui Canyon Aggregate Area Investigation Report Submitted to NMED |
| *June 30, 2020 |
| South Ancho Canyon Aggregate Area 30% Draft to N3B |
| February 7, 2020 |
| South Ancho Canyon Aggregate Area 60% Draft to N3B |
| April 10, 2020 |
| South Ancho Canyon Aggregate Area 95% Draft to N3B |
| June 12, 2020 |
| South Ancho Canyon Aggregate Area Final Draft to N3B |
| July 10, 2020 |
| South Ancho Canyon Aggregate Area Investigation Report Submitted to NMED |
| *September 30, 2020 |
| Lower Water/Indio Canyons Aggregate Area 30% Draft to N3B |
| March 13, 2020 |
| Lower Water/Indio Canyons Aggregate Area 60% Draft to N3B |
| May 8, 2020 |
| Lower Water/Indio Canyons Aggregate Area 95% Draft to N3B |
| August 7, 2020 |
| Lower Water/Indio Canyons Aggregate Area Final Draft to N3B |
| September 4, 2020 |
| Lower Water/Indio Canyon Aggregate Area Investigation Report Submitted to NMED |
| *September 30, 2020 |
| Field Summary Report for Chaquehui Canyon Aggregate Area |
| 30 calendar days after completion of field work |
| Field Summary Report for South Ancho Canyon Aggregate Area |
| 30 calendar days after completion of field work |
| Field Summary Report for Lower Water/Indio Canyons Aggregate Area |
| 30 calendar days after completion of field work |
NOTE: THIS FORM IS PRIMARILY FOR BID EVALUATION HOWEVER IS NOT PRECLUDED FROM BECOMING PART OF A RESULTANT SUBCONTRACT.