RFP QA_v1.xlsx
XLSX spreadsheet 10 KB Posted
- Attached to
- NRL Building 101 Room 140 Mezzanine Demolition
- Solicitation number
- N0017323RRS02
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP QA_v3.xlsx | XLSX spreadsheet | |
| Amend 0002.pdf | ||
| RFP QA_v2.xlsx | XLSX spreadsheet | |
| Amend 0001.pdf | ||
| Attachment A_SOW.pdf | ||
| RFP_v1.pdf | ||
| Attachment D_Davis-Bacon Act WD DCDC20230002.pdf | ||
| Attachment C_SECNAV_ 5512_Fillable.pdf | ||
| Attachment E_Requirements for On-Site Contractors.docx | DOCX document | |
| Attachment F_NRL Visitor Access Request List.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFP N0017323RRS02 Q&A | ||
| Question | Government Response | |
| 1 | The SOW states “ Determine if lead based paint exists on surface of steel before demolition work. If lead based paint exists, the contractor shall submit a written plan for treatment of lead based paint for review and approval”. Can you clarify if this means we should include the cost of a lead based pint survey is to be included in the base price? Also, does this mean that any lead abatement will be a change order? It is hard to estimate the cost without the results of a survey. | Initial proposed pricing should account for a lead based paint survey. In the event that a written treatment plan is required, the Government will issue a change order to account for a fair and reasonable price increase. |
| 2 | Will a site visit be allowed? | Site Visit information/instructions are provided on page 19 of the solicitation. |
File details come from the government source that posted it. Updated .