This is Addendum A to Request for Proposals RFP-PAR02-26 issued by Orange County Department of General Services for Engineering Services for Plum Point Lane Bridge Rehabilitation. The addendum addresses twelve vendor questions regarding project timeline, funding, oversight, hazardous materials, design standards, and documentation availability. The County anticipates that the design phase will be completed, followed by a two-month interval before the project goes to bid for construction contractors, with construction commencing two months after the bidding process begins. The mandatory site visit occurred on August 19, 2026, with questions due by August 25, 2026, and proposals due September 10, 2026 at 4:00 p.m. The contract term extends through issuance of the final Certificate for Payment or ninety days after substantial completion, with County discretion to extend on identical terms. Part 1 of the scope of services shall be completed by month 2 and Part 2 by month 4, although the County will consider extending these timeframes if warranted by project complexity, agency coordination, or additional investigation requirements.
The project is funded through County capital funding sources rather than state or federal grants. NYSDOT will not administer, oversee, or provide design review and approval for any phase of the project. No hazardous materials testing has been completed; the Engineer must coordinate for such testing in accordance with industry standards. The addendum confirms that no tree removal restrictions exist within the project limits and that all available historical documentation, including 1930 record plans, 1992 record drawings, geotechnical data, and 1917 New York Central Railroad maps, have been published with the original RFP. The County provides attachments regarding CSX Transportation right-of-way information, including a Temporary Right of Way Entry Agreement, Statement of Fees, and sample Certificate of Insurance, as the bridge crosses an active CSX Transportation railway line.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Steven M. Neuhaus County Executive
September 4, 2026
RE: RFP-PAR02-26, Engineering Services for Plum Point Lane Bridge Rehabilitation Addendum A
Dear Vendor:
This amendment is to address questions for the above-mentioned RFB:
1. Q When is this project expected to go to bid for contractors and what is the expected start date for construction?
A: The County anticipates that the project will go out to bid for contractors two (2) months after completion of the deign completion and construction will start two (2) months after it goes out to bid.
2. Q What is the funding source for this project?
A: County capital funding
3. Q Will the design and/or construction phases of this project be administrated / overseen by
NYSDOT?
A: No.
4. Q Are there any hazardous or contaminated materials on the bridge, specifically the substructure?
A: No hazardous materials testing has been completed at this time. The Engineer shall coordinate for hazardous materials testing to be performed in accordance with industry standards.
5. Q Will the design be subjected to NYSDOT review and approval at any stage of project development? If so, please identify the anticipated review milestones.
A: No.
DEPARTMENT OF GENERAL SERVICES
Renee Arnold-O’Regan, M.A.
Commissioner
255-275 Main St., P.O. Box 218 Goshen, New York 10924
TEL: (845) 291-2792 FAX: (845) 378-2365
www.orangecountygov.com
6. Q 5. The RFP indicated Part 1 of the scope of services shall be completed by month 2 and Part 2 shall be completed by month 4. Will the County consider extending these timeframes if warranted by project complexity, agency coordination, or additional investigation requirements?
A: Yes.
7. Q Are there any known restrictions, limitations, or stakeholder concerns related to tree removal within the project limits? The use of overhead equipment may require tree removal or trimming.
A: No.
8. Q Are the 1930 record plans of the original construction available? If so, can you provide.
A: All available documents were published with the original RFP.
9. Q The load rating report includes only a partial set of the 1992 record drawing. Is the full set of
1992 record drawing by Lichtenstein Engineering Associates available?
A: All available documents were published with the original RFP.
10. Q Drawing B1 of the 1992 record drawing shows 5 existing soil borings, B1 to B5. Are the corresponding boring logs, geotechnical data, and/or geotechnical reports available? If so, can you provide.
A: All available documents were published with the original RFP
11. Q Is any information available regarding railroad right-of-way limits, property ownership, easements, or railroad agreements with the bridge and surrounding project area?
A: New York Central Railroad maps created in 1917 are attached. The bridge is located at the match line between the two sheets (north end on sheet 35 + south end on sheet 36).
12. Q Can the County provide any documentation or correspondence related to previous coordination with CSX Transportation? Any available information regarding CSX requirements, comments, concerns, agreements, or prior discussions associated with this bridge would be greatly appreciated.
A: The following documents are attached for reference only and without representation as to the contents of any potential agreement between CSX and the Engineer:
• CSX Temporary Right of Way Entry Agreement
• CSX Statement of Fees
• Sample COI
Regards, Commissioner of General Services