This is a Request for Proposal (RFP) for dockside repairs to the United States Coast Guard Cutter (USCGC) MIDGETT, solicitation number 70Z08525RLREP0009, issued by the U.S. Coast Guard Surface Forces Logistics Center. The contract is a total small business set-aside with a NAICS code of 336611 and size standard of 1,300 employees. The ordering period will run from the date of award through 17 March 2026, with the first task order's performance period from 28 October 2025 through 17 January 2026, located at the cutter's homeport in Honolulu, Hawaii.

The solicitation requires contractors to perform comprehensive ship maintenance, repair, and associated support work as specified in task orders. Proposals are due by 25 July 2025 at 3:30 p.m. Pacific Time, with a 90-day acceptance period. The government will evaluate offers based on a best value trade-off approach, considering price, technical capability (which is significantly more important than price), and past performance. Technical capability will be assessed on the offeror's project planning, schedule management, risk mitigation, and understanding of work requirements. Contractors must submit detailed planning documents, pricing schedules, past performance information, and additional required documentation to be considered for award.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

2. CONTRACT NO.

3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER

5. SOLICITATION NUMBER

70Z08525RLREP0009

6. SOLICITATION

ISSUE DATE

25 June 2025

7. FOR SOLICITATION INFORMATION CALL:
a. NAME

Andrew Jacobs

b. TELEPHONE NUMBER (no collect calls)

(510) 316-4544

8. OFFER DUE DATE/ LOCAL TIME

25 July 2025, 3:30 p.m. Pacific Time

9. ISSUED BY CODE 75174

USCG Surface Forces Logistics Center U.S. Coast Guard Island, Building 55 Alameda CA 94501

10. THIS ACQUISITION IS UNRESTRICTED OR|_| SET ASIDE: 100 %FOR:
|X|SMALL BUSINESS|_| WOMEN-OWNED SMALL
BUSINESS (WOSB)
|_|HUBZONE SMALLNAICS:
BUSINESS|_| ECONOMICALLY DISADVANTAGED336611
WOMEN-OWNED SMALL (EDWOSB)
|_|SERVICE-DISABLED
VETERAN-OWNEDSIZE STANDARD:
SMALL BUSINESS|_| 8(A)1300 employees

11. DELIVERY FOR FOB DESTINATION UNLESS BLOCK IS MARKED

|_| SEE SCHEDULE

12. DISCOUNT

TERMS

|_|13a. THIS CONTRACT IS A RATED ORDER UNDER DPAS (15 CFR 700)
13b. RATING

14. METHOD OF SOLICITATION

|X| RFQ |_| IFB |_| RFP

15. DELIVER TO CODE

See Description of Supplies/Services

16. ADMINISTERED BY CODE

Same as block 9

17a. CONTRACTOR/ CAGE CODE FACILITY

OFFEROR CODE

DUNS No.

TELEPHONE NO:

FAX NO:

18a. PAYMENT WILL BE MADE BY CODE

Commanding Officer USCG Finance Center 1430A Kristina Way Chesapeake, VA 23326

(800) 565-5504

|_| 17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED |X| SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

The Contractor shall perform Dry dock Repairs to the United States Coast Guard Cutter (USCGC) MIDGETT in accordance with this solicitation, specification and with each issued Task Order under the resulting requirements contract. Scope of work shall include all ship maintenance, repair, and associated support work as required to repair CGC MIDGETT, to be specified via task order. Ordering period of this contract will be from date of award through 17 March 2026. First task order’s period of performance is from 28 October 2025 through 17 January 2026. Place of performance will be at the cutter’s homeport.

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (FOR GOVT USE ONLY)

|X| 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 & 52.212-5 ARE ATTACHED. ADDENDA |X| ARE |_| NOT ATTACHED.

|_| 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4, FAR 52.212-5 IS ATTACHED. ADDENDA |_| ARE |_| ARE NOT ATTACHED.

|X| 28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 1COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.
|_| 29. AWARD OF CONTRACT: REFERENCE _____

OFFER DATED___. YOUR OFFER ON SOLICITATION (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR

31a. UNITED STATES OF AMERICA (SINGATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER

30c. DATE SIGNED

31b. NAME OF CONTRACTING OFFICER

31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (Rev. 2/2012) PREVIOUS EDITION IS NOT USABLE Prescribed by GSA – FAR (48 CFR) 53.212

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

Funds will be awarded with each task order and will be awarded subject to the availability of funds. See Attachment 2 Price Schedule.

32a. QUANTITY IN COLUMN 21 HAS BEEN

|_| RECEIVED |_| INSPECTED |_| ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

33. SHIP NUMBER

34. VOUCHER NUMBER

35. AMOUNT VERIFIED CORRECT FOR

36. PAYMENT

|_| COMPLETE|_| PARTIAL|_| FINAL
37. CHECK NUMBER

|_| PARTIAL |_| FINAL

38. S/R ACCOUNT NUMBER

39. S/R VOUCHER NUMBER

40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

42 a. RECEIVED BY (Print)

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER
41c. DATE

42b. RECEIVED AT (Location)

42c. DATE REC’D (YY/MM/DD)

42d. TOTAL CONTAINERS

TABLE OF CONTENTS:

Listing of Incorporated Purchase Requisitions4
Section B - Supplies or Services and Prices/Costs4
Section C - Description/Specifications/Work Statement6
Section D - Packaging and Marking6
Section E - Time and Place of Performance6
Section F8
Section G - Contract Administration Data8
Section H - Special Contract Requirements17
Section I - Contract Clauses19
Section J - List of Documents, Exhibits, and other Attachments46
Section K - Representations, Certifications, and Other Statements of Offerors.46
Section L - Instructions, Conditions and Notices to Offerors.72
Section M - Evaluation Factors for Award74

1. Listing of Incorporated Purchase Requisitions

Incorporated Purchase Requisition Numbers:

2. Section B - Supplies or Services and Prices/Costs

Item Number
Base Item

Number Supplies/Services

CGC MIDGETT FY26 Dockside Repair

Description:

Purchase Requisitions

CONTINUATION OF SF 1449- BLOCKS 17a-25

Block 17a: Offeror shall include company's name, address and Unique Entity ID number.

Block 17b: REMITTANCE ADDRESS: Payment will be made to the Financial Institution listed in System for Award Management (SAM). To receive award Offeror must be registered in SAM (copy and paste www.sam.gov into search engine).

Block 19 through 24: SEE ATTACHMENT 2, PRICE SCHEDULES

Block 20: SCHEDULE OF SUPPLY / SERVICES: The Contractor shall perform Dock-Side Repairs to the United States Coast Guard Cutter (USCGC) MIDGETT in accordance with this solicitation, specification and with each issued Task Order under the resulting requirements contract. Scope of work shall include all ship maintenance, repair, and associated support work as required to repair CGC MIDGETT, to be specified via task order. Ordering period of this contract will be from date of award through 17 March 2026. First task order's period of performance is from 28 October 2025 – 17 January 2026. Place of performance will be at the cutter's homeport Honolulu HI.

Funds will be awarded with each task order and will be awarded subject to the availability of funds. See Attachment 2 Price Schedule.

Block 25: ACCOUNTING AND APPROPRIATION DATA: To be included per task order.

(1) OFFEROR IS RESPONSIBLE FOR VERIFYING THE RECEIPT OF THEIR PROPOSAL.

This Solicitation incorporates provisions and clauses in effect through Federal Acquisition Circular 2025-03, dated January 17, 2025. The NAICS code applicable to this requirement is 336611.

3. Section C - Description/Specifications/Work Statement

See: ATTACHMENT 1 MIDGETT SPECIFICATION

4. Section D - Packaging and Marking

N/A

5. Section E - TIME AND PLACE OF PERFORMANCE

TIME AND PLACE OF PERFORMANCE

TIME OF PERFORMANCE

USCGC MIDGETT will be available for performance of the work under the first task order during the period of 28 October 2025 – 17 January 2026.

PLACE OF PERFORMANCE

a. All work under this contract will be performed at the cutter's homeport Honolulu HI. This requirement is a total small business set aside.

b. The work to be performed on the cutter shall not be performed at any other location unless the Contracting officer approves a change in location in writing, in advance.

This requirement is a total small business set aside.

INSPECTION OF CUTTER PRIOR TO SUBMISSION OF PROPOSALS:

This Request for Proposal (RFP) is for the Dock-Side (DS) Repairs of the USCGC MIDGETT hereinafter referred to as "vessel". The DS Repairs are to be awarded via Task Orders under this contract. The vessel's home pier is in Honolulu, HI.

USCGC MIDGETT: will be available for a site visit: Monday - Friday 0645 – 1300; 25 June – 12 July 2025.

Cutter availability is subject to change without notice. Request must be submitted 24-48 hour prior to visit.

Contact the following to schedule a ship check: USCGC MIDGETT Port Engineer: LT Blake Knox.: (571) 608-1148 E.: walter.b.knox@uscg.mil. mailto:Contacting this person by email is preferred and when doing so, please CC: andrew.g.jacobs@uscg.mil and jaime.diaz3@uscg.mil.mailto:The objective of a ship check is to provide prospective offerors the opportunity to physically witness and make inquiries about the CGC MIDGETT before submitting a proposal. All prospective offerors are encouraged to visit and visually inspect each item of work and to be acquainted with general and local conditions, locations of items and fixtures, removals, replacements, interference and the nature of work to be performed that may affect the cost of contract performance, to the extent that the information is reasonably obtainable.

Interested vendors requesting a ship check must meet facility access requirements for the cutter's home port. Required to have 2 forms of government ID (birth certificate, SS, Driver's License, etc) and a CG sponsor to walk them through.

Failure to inspect the cutter will not relieve the offeror from responsibility of properly estimating the difficulty or cost of successfully performing the work. In no event shall failure to inspect the cutter constitute grounds for a claim after contract award.

The Government assumes no responsibility for any representations concerning conditions made by any of its officers, agents, or employees before execution of the contract unless included in the solicitation, documents incorporated therein or amendments thereto.

RESPONSIBILITY

1. The Government reserves the right to perform Pre-award surveys for the purpose of further confirming the capabilities of the Offerors.

2. The Offerors must be determined responsible in accordance with the standards of Federal Acquisition Regulation (FAR) Subpart 9.1 to be eligible for award.

NOTICE OF PREAWARD SURVEY

1. Offerors are advised that the Government may contact potential Contractors to ascertain their capabilities to perform the work specified in this solicitation. In addition to financial statements and credit rating checks, the Government may visit a prospective Contractor's facility(s). Areas of interest on this survey may include, but are not limited to the following:

(a) Performance plans

(b) Quality assurance and control plans

(c) Personnel recruitment and training plans

(d) Workload factor for manpower utilization

(e) Management plan for handling peak workloads

(f) Production capability.

a. Plant facilities and equipment

b. Purchasing and subcontracting

c. Labor resources

d. Performance record

e. Ability to meet delivery schedules

(g) Environmental/energy considerations

(h) Plant safety

(i) Technical and/or professional abilities

(j) Accounting systems

(k) Security clearance

(l) Government property control

INSPECTIONS

Except as specified elsewhere (e.g., Specifications, Drawings, etc.), the U.S. Coast Guard shall rely on the Contractor to accomplish all inspection and testing needed to ensure that the work conforms to contract quality requirements. Records of all inspection work by the Contractor shall be kept complete and available to the Government during the term of this contract and for such longer period as may be specified elsewhere in this contract. The name and telephone number of the U.S. Coast Guard Inspector will be provided after the award of a contract resulting from this solicitation.

6. Section F

None

Article Number
Reference Text
52.242-15
52.242-15 STOP-WORK ORDER (AUG 1989)

7. Section G - Contract Administration Data

Requesting Office Address

52000 SFLC LRE PL

SURFACE FORCES LOGISTICS CENTER USCG

2401 HAWKINS POINT RD

BALTIMORE MD 21226-5000

Phone:808/352-5336
Fax:

Contact Details:

SCHILLER, BRANDEE MALIA

Brandee.M.Schiller@uscg.mil

Property Administration Office Address

52000 PROP SFLC COMMAND STAFF

SURFACE FORCES LOGISTICS CENTER USCG

2401 HAWKINS POINT RD

BALTIMORE MD 21226-5000

Phone:571/608-3650
Fax:

Contact Details:

WARNER, DALE D.

Dale.D.Warner@uscg.mil

COR Office Address

52000 COR SFLC LRE PL

2401 HAWKINS POINT RD

BALTIMORE MD 21226-5000

Phone:808/754-1742
Fax:

Contact Details:

YUG, FRANCO F

Franco.F.Yug@uscg.mil

Issuing Office Address

70Z085 CPD 2 - Oakland, CA

Commander

USCG-SFLC-CPD 2

1301 Clay Street, Suite 800N

Oakland CA 94612

Phone:
Fax:

Contact Details:

JACOBS, Mr. ANDREW G

ANDREW.G.JACOBS@USCG.MIL

Payment Office Address

USCG FINANCE CENTER

FINANCE CENTER USCG

1430A KRISTINA WAY

CHESAPEAKE VA 23326-1000

Phone:
Fax:

Contact Details:

SILVA, MARCUS QUEIROGA

Marcus.Q.Silva@uscg.mil

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

The Contractor shall be required to (a) commence work under each order under this contract within 1 calendar day after the date the Contractor receives the notice to proceed by email, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 17 January 2026, the end of the performance period for the first task order. *The time stated for completion shall include final cleanup of the premises.

ASSOCIATE CONTRACTOR AGREEMENT (ACA):

(1) This clause is intended to ensure that there will be appropriate integration of work by the USCGC MIDGETT's associate contractors to maximize coordination and prevent delay or additional costs. Currently there are no known associate contractors.

(2) For purposes of this clause, the Associate Contractor, known at this time, is defined as: None known at this time.

(3) Any Associate Contractors shall work and maintain close liaison with each other. In order to assure accomplishment of this objective, the Associate Contractors shall enter into a written ACA with each other.

(4) The ACA shall provide for a complete and unbiased exchange of scheduling information to include work locations. The following shall be included in the ACA:

(a) Identification of the information to be furnished between the Associate Contractors. This shall, at a minimum, include the schedule and locations of work to be performed.

(b) Services to be provided by one Associate Contractor to another [if applicable]

(c) The materials to be provided between the Associate Contractors during performance. [if applicable]

(d) In accordance with Specification General Requirements, the Prime Contractor shall hold a weekly progress meeting, and also daily production meetings. At the daily production meetings, Associate Contractors shall attend and participate to resolve any potential conflicts in the work schedule for that day, so as to minimize delay, disruption or overlapping work.

(i) At the daily production meetings, Associate Contractors shall attend and participate to resolve any potential conflicts in the work schedule for that day, so as to minimize delay, disruption or overlapping work.

(ii) At the weekly progress meetings, the Associate Contractors shall provide an integrated and de- conflicted master planning document for review by the USCG COR. Associate Contractors shall meet together prior to the weekly progress meeting to develop this master planning document.

(iii) The Associate Contractors are responsible to resolve all planning conflicts. However, the USCG COR reserves the right to serve as final decision authority when needed to ensure timely schedule completion and/or that Operational Commander's priorities are met.

(e) The ACA may also address treatment of any proprietary or confidential information. [if applicable]

(5) Following execution by both Associate Contractors, the ACA may be made an attachment to this contract. The ACA is for information purposes only and shall not be subject to or governed by this contract. In the event of a conflict between the terms of this contract and terms of the ACA, the terms of this contract shall control.

(6) Where the Associate Contractors fail to agree upon action to be taken in connection with their respective responsibilities, each of them shall promptly notify the COR responsible for their respective contract and furnish their recommendations for a solution. The Associate Contractors shall not be relieved of its obligations to make timely deliveries or be entitled to any other adjustment because of their failure to: (a) resolve ACAs disputes; (b) promptly refer matters to the COR assigned to their respective contract; or (c) to implement any direction given by the COR assigned to their respective contract.

PROGRESS PAYMENTS:

A. The Contractor may invoice requesting progress payments without discount, other than any prompt payment discount offered, not more frequently than every two weeks.

B. The invoice amount should reflect the percentage and dollar amount of completion established by the cutter's appropriate weekly progress report. Payments shall be derived from the accomplished percentage of completion as determined by the Contracting Officer.

C. All material and work paid for by progress payments shall there by become the sole property of the Government, but this provision shall not relieve the contractor from the obligation to complete the requirements of the contract.

D. The Contractor shall be paid the remaining amount due upon completion and acceptance of all work under this contract.

METHOD OF PAYMENT AND INVOICING INSTRUCTIONS INVOICE SUBMISSION PROCESS:

A request for payment is proper if it includes the items required by the clause at FAR 52.232-25, Prompt Payment [(a)(3)(i) through (a)(3)(x)] and those items are accurate. If a request for payment does not include all the items required by the clause at FAR 52.232-25, Prompt Payment, or any information is inaccurate, then the request is not proper and shall be returned to the contractor with a statement of the reason(s) it is not proper.

(a) WHEN TO SUBMIT: The contractor must first:

(1) Receive a fully executed purchase order, contract, delivery order or task order

(2) Provide the requirements, and

(3) Have ACTIVE status in the System for Award Management (SAM) at https://www.sam.gov

(b) INVOICE CONTENT: Each invoice must contain the following information:

(1) Invoice Date

(2) Invoice Number

(3) Purchase Order Number or Contract Number or Contract and Delivery/Task Order Number

(4) Contractor's Name

(5) Contractor's Address

(6) Contractor's UEI

(7) Contracting Officer's Name

(8) Contracting Officer's Representative's (COR's) Name (if applicable)

(9) Invoice Routing Code (IRC) assigned by the Coast Guard as follows: SFLC-2

(10) Period of Performance for Work Invoiced

(11) Contract Line Item Number(s) (CLIN(s)) and Description (if applicable)

(12) CLIN units for the period (if applicable), CLIN rate (if applicable), CLIN Total (if applicable)

(13) For Travel: Components in accordance with FAR 31.205-46

(14) Invoice Total

(15) Discount Offerings

(16) Status as a Small Business (if applicable) for accelerated payment

(17) The last invoice submitted for this award must be clearly labeled with "FINAL INVOICE."

(18) NOTE: A request for payment is proper if it includes the items required by the clause at FAR 52.232-25, Prompt Payment [(a)(3)(i) through (a)(3)(ix), with common items captured in the list above] and those items are accurate. If a request for payment does not include all the items required by the clause at FAR 52.232-25, Prompt Payment, or any information is inaccurate, then the request is not proper and will be returned to the contractor with a statement of the reason(s) it is not proper.

(c) HOW TO SUBMIT:

Contractor must submit proper invoices electronically using the Invoice Processing Platform (IPP) at https://www.ipp.gov/. Information regarding IPP, including IPP Customer Support contact information, is available at that same link. IPP is a secure web-based electronic invoicing system provided by the U.S. Department of the Treasury's Bureau of the Fiscal Service in partnership with the Federal Reserve Bank of St. Louis. IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency. You will be required to enroll if you are not yet enrolled. If your company is already registered to use IPP, you will not be required to re-register and you do not need to contact IPP.

If you are NOT already enrolled in IPP:

The point of contact you provided in your SAM.gov registration will receive two emails from ipp.noreply@mail.eroc.twai.gov. Please note that emails from this email address may filter into your spam or junk folder:

1. The first email will have the IPP Logon ID and a link to the IPP application.

2. A second email, which will be sent within 24 hours of the first email, contains a temporary password.

Once your contact receives these emails, please ensure they log into IPP and complete the registration process.

Once registered to use IPP, your company may submit invoices electronically, receive e-mail notifications when requests are paid, view payment history, and access remittance downloads. The e-mail notification of payment is sent when a payment is distributed to your bank account and may include the following payment information: Date of payment, dollar amount, invoice number, paying agency, payee name, and ACH trace number.

Vendor training materials, including a first-time login tutorial, are available on the https://www.ipp.gov/ website. Once you have logged in to the IPP application, you will have access to user guides that provide step-by-step instructions for all IPP capabilities, ranging from creating and submitting an invoice to setting up email notifications. Live webinars are held monthly and provide a great opportunity to learn the basic of the system and to call in and ask the IPP team questions about the IPP application.

IPP Customer Support is available to assist users of the system and can answer your questions related to accessing IPP or completing the registration process.

· Toll-free number: 866-973-3131

· Email address: IPPCustomerSupport@fiscal.treasury.gov

· Hours of operation: Monday through Friday (excluding bank holidays) from 8:00 am - 6:00 pm ET

(d) PROMPT PAYMENT INFORMATION: In accordance with the Prompt Payment Act, for the purposes of determining a payment due date and the date on which interest will begin to accrue if a payment is late, a proper invoice date is:

(1) On the later of:

(i) For invoices that are mailed, the date a proper invoice is actually received by the designated billing office and annotates the invoice with date of receipt at the time of receipt.

(ii) For invoices electronically transmitted by the contractor via web based submission, the date a transmission is received by the designated billing office, and receipt confirmation is provided to the designated recipient; or

(ii) The seventh day after the date on which the property is actually delivered or performance of the services is actually completed; unless—

a) The agency has actually accepted the property or services before the seventh day in which case the acceptance date must substitute for the seventh day after the delivery date; or

b) A longer acceptance period is specified in the contract, in which case the date of actual acceptance or the date on which such longer acceptance period ends must substitute for the seventh day after the delivery date;

(2) On the date placed on the invoice by the contractor, when the agency fails to annotate the invoice with date of receipt of the invoice at the time of receipt (such invoice must be a proper invoice); or

(3) On the date of delivery, when the contract specifies that the delivery ticket may serve as an invoice.

(4) Web-based submission by the contractor and receipt confirmation does not reflect Government review or acceptance of the invoice.

(5) Payment inquiries and status may be obtained at the following website: https://www.uscg.mil/fincen/electron/

(e) Failure to follow any of these instructions will result in invoice rejection.

CONTRACTOR PERFORMANCE EVALUATION

(a) The U.S. Coast Guard Surface Forces Logistic Center (SFLC) will monitor and evaluate the successful offeror's past performance of task orders under this contract and prepare a Contractor Performance Assessment Report (CPAR) in accordance with FAR Part 42.15. All information contained in this assessment may be used, within the limitations of FAR 42.15, by the government for future source selections and in accordance with FAR 15.304, when past performance is an evaluation factor for award.

(b) NOTIFICATION: Upon completion of the task order under this contract, the contractor will be notified of the assessment. The contractor will be allowed 60 days to respond to the SLFC's assessment of its performance entered into CPARS. The contractor's response, if any, will be made part of the CPAR system at https://www.cpars.csd.disa.mil.

(c) INFORMATION: Information included in the CPAR may include, but is not limited to, the contractor's record of conforming to contract requirements and to standards of good workmanship; the contractor's record of forecasting and controlling costs; the contractor's adherence to contract schedules, including the administrative aspects of performance; the contractor's history of reasonable and cooperative behavior and commitment to customer satisfaction; the contractor's record of integrity and business ethics, and generally, the contractor's business-like concern for the interest of the customer.

(d) RELEASE OF DATA: Contractor Performance Assessment Report (CPAR) information is considered business sensitive and will not be released except: (1) to other Federal procurement activities which request it; (2) when SFLC must release pursuant to a Freedom of Information Act (FOIA) request; or (3) when prior written consent is requested and obtained from the contractor.

POSSIBLE ADDITIONAL WORK

(a) All work required in the specification (Attachment 1) will be captured in the initial task order and this first task order will be awarded at the time of award of the requirements contract. The Contracting Officer reserves the right to contract for additional work via issuance of a new task order or modification of an existing task order, on the basis of a firm-fixed-price negotiated Task Order when it is in the best interest of the Government.

(b) Upon request, the Contractor shall furnish a price breakdown directly to the Contracting Officer, itemized as required by the Contracting Officer, of any quote submitted for additional work. Unless otherwise directed, the breakdown shall be submitted on an SFLC 002 quote form provided at the arrival conference permitting an analysis of all materials, labor, equipment, subcontract, overhead costs, and profit covering all work involved in the change/modification whether such work was deleted, added or changed. Any amount claimed for subcontracts shall be supported by a separate, similar price breakdown. If the quote includes a request for a time extension, justification shall be furnished with the quote.

(c) This instruction is to be used in conjunction with the following instruction, COMPOSITE LABOR RATE. The

Contractor is required to have and/or furnish all tools and equipment incidental to each bench trade. All supplies necessary to accomplish the Work Items, such as wiping rags, hacksaw blades, sandpaper, welding wire, helium, etc., shall be included in the composite labor rate. Other materials are to be charged at regular rates and prices currently in effect and negotiated and agreed to by the Contracting Officer. Material shall be best commercial quality available, where a precise specification is indicated, in which case the specification shall apply, e.g., MILSPEC, FEDERAL SPEC.

COMPOSITE LABOR RATE:

The composite labor rate offered shall be the sole labor hour rate used to price the Prime Contractor's direct labor hours for additional work. The Contractor shall not receive any compensation in addition to this rate for the Prime Contractor's direct labor associated with such Task Orders under this contract.

(a) The composite labor hour rate shall represent total compensation for the following:

(1) Direct labor wages and salaries;

(2) All employee benefits including, but not limited to, paid leave, supplemental pay, insurance, retirement, savings, and legally required benefits;

(3) Other direct costs associated with transit time, delay, disruption, expendable supplies, and equipment;

(4) All indirect costs such as overhead and general and administrative expense;

(5) Any port or association fees, rents, or other levies;

(6) profit (fee); and

(6) All direct and indirect costs and profit associated with the following support functions:

Supervision and ManagementPlanning Material HandlingHousekeeping
EngineeringTransportation/Drivers
Quality AssuranceContract Administration
Security GuardTesting
Worker Transit TimeEstimating Surveyors

(b) The composite labor hour rate will be applied to production labor hours only. Production labor hours include only those hours necessary and reasonable to perform direct production functions and do not include the hours expended on the support functions listed above. This exclusion of direct labor charges for support function hours applies whether such support functions are normally charged directly or indirectly by the Contractor's accounting system. These support functions are to be priced into the composite labor rate quoted and shall not be separately compensated.

(c) The Quantity of Composite Labor hours indicated in the Schedule of Supplies/Services, is only an estimate pursuant to this solicitation. The inclusion of this item does not obligate the Government to exercise the item nor entitle the Contractor to compensation if not exercised.

PROCEDURES FOR TASK ORDERS, DISCOVERIES, AND CHANGES TO CONTRACT:

After Contract award, individual task orders will be issued as necessary to support Contract requirements. Following mutual agreement on the additional work, a Task Order or modification will be sent from the Contracting Officer and the Contractor will commence work. The Contractor shall provide notice of acceptance of the Task Order or modification by signing the Standard Form (SF-30 or SF-1449) and returning it to the Contracting Officer, or by starting work when the Contracting Officer issues a Task Order.

The Contractor shall not perform any type of additional work without the Contracting Officer's authorization. No oral or written statement of any person other than the Contracting Officer will in any manner or degree modify or otherwise affect the terms of this contract. The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and an adjustment may not be made in the contract price to cover any increase in cost incurred as a result thereof.

The Contracting Officer reserves the right to add additional work via Task Orders or modifications for Additional Work, on the basis of a firm-fixed-price, negotiated Task Order or modification when it is in the best interest of the Government.

Change Request Process (for changes to existing task order and additional work items):

1. Condition Found Report – Generated by the Contractor and provided to Contracting Officer's Representative (COR) in accordance with SFLC Standard Specification 0000.

2. Condition Found Report Reply – Generated by the COR and provide to Contractor.

3. Change Request (CR) – CR is generated by the COR and the COR will assign the CR number.

4. COR provides copy of CR to the Contractor.

5. Contract Specialist/Contracting Officer/COR shall send a Request for Quote (RFQ) with the Work Item Specification.

6. Contractor's quote – provided to the Contract Specialist (KS)/Contracting Officer (KO) within 72 hours of receipt of the Change Request. The Contractor shall furnish a price breakdown, itemized as required by the KS/KO. Rates in the proposal shall be in accordance with the rates specified in the Price Schedule. Any amount claimed for subcontracts shall be supported by separate, similar price breakdown. If the proposal includes a request for a time extension, justification shall be furnished with the proposal. The Contractor shall furnish a price breakdown, itemized as required by the Contract Specialist/Contracting Officer. The breakdown shall permit an analysis of all materials, labor, equipment and subcontract costs, covering all work involved in the new Task Order or Additional Work CLIN, whether such work was deleted, added or changed. Rates in the proposal shall use the Composite Labor Hour Rate, or other rates specified in the contract for changes.

7. Negotiations- If needed, the Contract Specialist/Contracting Officer may negotiate to establish pricing subject to Contracting Officer approval.

8. The Contracting Officer shall offer a new Task Order, or a modification of an existing Task Order based on the negotiated CR, which the contractor must accept before the contracting officer incorporates and implements all changes into the contract.

CONTRACTING OFFICER'S AUTHORITY

No oral or written statement of any person other than the Contracting Officer will in any manner or degree modify or otherwise affect the terms of this contract. The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract, and, notwithstanding any provisions contained elsewhere in this contract, said authority remains solely with the Contracting Officer. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in cost incurred as a result thereof.

MAINTAINING, REPORTING, AND DISPOSING OF GOVERNMENT PROPERTY IN THE PERFORMANCE OF A SHIP REPAIR CONTRACT

1. FAR 52.245-1. Government Property (SEP 2021) is incorporated by reference.

2. The Contractor shall sign for all government-furnished-property (GFP) using either a DD Form 1149, entitled, "Requisition and Invoice/Shipping Document" or a DD Form 1348-1A, entitled, "Issue Release/Receipt Document". A copy of the DD 1149 or DD 1348-1A must be sent within 48 hours of receipt of property, to the designated Government Property Administrator. The name of the individual assigned as Property Administrator will be furnished to the Contractor at time of award. The Contractor shall not take receipt of property that is not listed in the specification, has not been previously identified as becoming part of the contract (via contract modification) or which otherwise cannot be identified. Such irregularities shall be immediately reported to the Property Administrator.

3. The Contractor shall complete the report provided herein, entitled, "Government Property Report". This report is intended as a living document whereby relevant fields shall be filled in, maintained and kept current at all times. At contract completion the Contractor and the Property Administrator shall ensure that all fields are appropriately completed. The Government Property Report shall clearly delineate the complete track that all Government property took over the course of the contract. This completed report must accompany the Contractor's final invoice. Final payment may be delayed, without penalty of interest, until such time as the report is received. A separate copy of the completed report and any final DD 1149s or DD 1348-1As executed, as a result of carrying out disposition instructions shall be provided to the Property Administrator.

4. Pursuant to the Government Property Clause the authority to render disposition instructions of Government property associated with this contract is delegated to the Property Administrator. The Contractor shall comply with all instructions in the contract for the return of government property to the Coast Guard. This includes government property taken off the vessel (shafts, propellers, etc.), government property returned to the vessel (special tools, etc.) or surplus government property not used during performance of the contract.

DHS NOTICE TO OFFERORS

It is DHS policy that pricing for competitive negotiations should be based on adequate price competition. However, in the event only one responsible offer is obtained as a result of this solicitation, that offeror may be required to submit Data Other Than Certified Cost or Pricing Data (FAR 15-403-3) to support price negotiations.

8. Section H - Special Contract Requirements

Clauses incorporated by full text

HAZARDOUS WASTE

Contractors performing dry dock and dockside ship repair work at Government facilities are required to comply with FAR 52.223-3, Hazardous Material Identification and Material Safety Data (FEB 2021) Alt I, the U.S. Coast Guard shipboard hazardous waste policy, as prescribed in COMDINST M16478.1B, and SFLC standard specifications. Disposal of all hazardous wastes shall be performed by the Contractor and the Contractor shall meet all federal and state requirements. The Contractor is also required to submit an acceptable hazardous waste management plan to the Port Engineer at the Arrival Conference. The plan will be reviewed by the facility hazardous waste manager. An acceptable plan must address, at a minimum, the following requirements:

(a) EPA and local authority hazardous waste generator ID numbers or registration of the Contractors, his transporters, and disposal facilities (TSDFs);

(b) An inventory of all hazardous chemicals, compounds and other agents brought aboard the facility accompanied by their respective Material Safety Data Sheets;

(c) A list of all anticipated hazardous wastes to be generated and a federal/state/local regulation cross reference list for those wastes;

(d) Waste collection and containment procedures;

(e) A hazardous material spill and cleanup plan including tools and materials that will be on hand and readily available to facility containment and cleanup; and

(f) Training certification for the Contractor's hazardous waste manager.

The Contractor shall note the local environmental regulations in the place of performance. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with, the local and state regulations.

The Contractor shall notify the Contracting Officer's Representative (COR) 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

CONTRACT DEFICIENCY REPORT

The Contracting Officer or Contracting Officer's Representative (COR) may issue a Contract Deficiency Report (CDR), SFLC Form 005. The Contractor shall respond in writing within 24 hours of receipt, unless otherwise approved by the Contracting Officer, to the COR. The COR will comment on the Contractor's response and will forward the Deficiency Report and comments to the Contracting Officer, with a copy to the Contractor and Availability Program Manager. The

Contracting Officer will render a final determination and provide it to the Contractor and COR in writing.

INSURANCE – WORK ON A GOVERNMENT INSTALLATION

a. The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required by this Clause as follows: TYPE AMOUNT

70Z08525RLREP0009

Page 1 | 1

1) Workman's Compensation and Employer's Liability (including Federal Longshoremen .and Harbor Worker's Insurance)

As legally required by the State wherein the work is being performed.

2) Comprehensive General Liability Insurance Personal Injury Liability:

$1 million per person $1 million per occurrence

Property Damage (may be included in general aggregate limits or combined single unit coverage)

3) Automobile Liability Personal Injury Liability:

$1 million per person $1 million per occurrence

Property Damage (may be included in general aggregate limits or combined single unit coverage):

4) a. If single general aggregate limits or combined single unit coverage is obtained for General Liability and/or Automobile Liability coverage, minimum amounts shall be the sum of the personal injury and property damage coverage required above. Umbrella Form Excess Liability insurance coverage shall be added to general liability and automobile liability coverage to determine if minimum insurance limits are met.

b. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe, or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.

c. As evidence that it has obtained the insurance specified in paragraph (a) of this clause, the contractor shall furnish the Contracting Officer with a certificate, or certificates executed by an agent of the insurer authorized to execute such certificates. Such certificates shall be furnished prior to commencement of the work. Each certificate shall state that (name of insurer) has insured (name of contractor) awarded contract number (to be determined at time of award) for repair/alteration of applicable USCG ship in accordance with the Liability and Insurance clause and the Insurance Requirements clause contained herein.

d. The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proof of required insurance, and shall make copies available to the Contracting Officer upon request.

e. "Government Installation" for this clause includes government vessels.

VOLATILE ORGANIC COMPOUNDS (VOC) REGULATIONS

(a) Contractors are required to comply with federal, state and local VOC compliance laws and regulations. Among other requirements, certain Contractors may also be required to operate pursuant to a Title V permit. The need for such a permit will depend on the provisions of the applicable state's "State Implementation Plan" (SIP) and the type/quantity of the Contractor's regulated emissions, including VOCs. Certain SIPs may also mandate certain Contractors to operate under the terms of a compliance plan intended to reduce VOC emissions.

(b) Contractors, therefore, must submit the following to the designated Port Engineer not later than two weeks after contract award:

1) Copies of any federal, state or local permits required and applicable to the use or application of VOCs at Contractor's facility or offsite workplaces; and

2) Copies of any compliance plans required and applicable to the use or application of VOCs at Contractor's facility or offsite workplaces.

(c) If no federal, state or local permits or compliance plans are required and applicable to the use or application of VOCs at Contractor's facility or offsite workplaces, then Contractor shall submit to the designated Port Engineer a letter, notarized under oath, that such documents are not required.

(d) Contractors will submit the following to the designated Port Engineer not later than two weeks after contract award: Data Sheets (MSDS) documents, certificates, specifications or any other manufacturing data verifying the VOC ratings of paints to be applied to the Cutter in accordance with Standard SFLC Specifications.

Information Related to System for Award Management System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Additional examples include 52.212-5, Contract Terms and Conditions Required To Implement Statutes or Executive Orders—Commercial Products and Commercial Services, and 52.213-4, Terms and Conditions—Simplified Acquisitions (Other Than Commercial Products and Commercial Services).

9. Section I - Contract Clauses

Clauses incorporated by reference

Article Number
Reference Text
3052.205-70
3052.205-70 ADVERTISEMENTS, PUBLICIZING AWARDS, AND RELEASES (SEP 2012)
3052.211-70
3052.211-70 INDEX FOR SPECIFICATIONS (DEC 2003)
3052.217-93
3052.217-93 SUBCONTRACTS (DEC 2003)
3052.217-95
3052.217-95 LIABILITY AND INSURANCE (DEC 2003)
3052.217-96
3052.217-96 TITLE (DEC 2003)
3052.217-97
3052.217-97 DISCHARGE OF LIENS (DEC 2003)
3052.217-98
3052.217-98 DELAYS (DEC 2003)
3052.217-99
3052.217-99 DEPARTMENT OF LABOR SAFETY AND HEALTH REGULATIONS FOR SHIP REPAIR (DEC 2003)
3052.222-70
3052.222-70 STRIKES OR PICKETING AFFECTING TIMELY COMPLETION OF THE

CONTRACT WORK (DEC 2003)

3052.222-71
3052.222-71 STRIKES OR PICKETING AFFECTING ACCESS TO A DHS FACILITY (DEC

2003)

3052.223-90
3052.223-90 ACCIDENT AND FIRE REPORTING (DEC 2003)
3052.228-70
3052.228-70 INSURANCE (DEC 2003)
3052.242-72
3052.242-72 CONTRACTING OFFICER'S TECHNICAL REPRESENTATIVE (DEC 2003)
52.203-12
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN 2020)
52.203-13
52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (NOV 2021)
52.203-19
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS (JAN 2017)
52.203-6
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN

2020)

52.204-10
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (JUN 2020)
52.204-15
52.204-15 SERVICE CONTRACT REPORTING REQUIREMENTS FOR INDEFINITE- DELIVERY CONTRACTS (OCT 2016)
52.204-16
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (AUG 2020)
52.204-23
52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES(NOV 2021)
52.204-25
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
52.204-7
52.204-7 SYSTEM FOR AWARD MANAGEMENT (NOV 2024)
52.209-10
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)
52.209-2
52.209-2 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS-REPRESENTATION (NOV 2015)
52.209-6
52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, PROPOSED FOR DEBARMENT, OR VOLUNTARILY EXCLUDED (JAN 2025)
52.209-9
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
52.212-4
52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)
52.215-20
52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OR INFORMATION OTHER THAN CERTIFIED COST OR PRICING DATA (NOV 2021)
52.215-21
52.215-21 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA

OTHER THAN CERTIFIED COST OR PRICING DATA-MODIFICATIONS (NOV 2021)

52.219-14
52.219-14 Limitations on Subcontracting (OCT 2022)
52.219-28
52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REPRESENTATION (JAN 2025)
52.219-6
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)
52.219-8
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (JAN 2025)
52.222-19
52.222-19 CHILD LABOR-COOPERATION WITH AUTHORITIES AND REMEDIES (JAN

2025)

52.222-3
52.222-3 CONVICT LABOR (JUNE 2003)
52.222-35
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
52.222-36
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
52.222-37
52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUN 2020)
52.222-50
52.222-50 COMBATING TRAFFICKING IN PERSONS (NOV 2021)
52.222-54
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (JAN 2025)
52.223-11
52.223-11 OZONE-DEPLETING SUBSTANCES AND HIGH GLOBAL WARMING POTENTIAL HYDROFLUOROCARBONS (MAY 2024)
52.223-12
52.223-12 MAINTENANCE, SERVICE, REPAIR, OR DISPOSAL OF REFRIGERATION EQUIPMENT AND AIR CONDITIONERS (MAY 2024)
52.223-20
52.223-20 AEROSOLS (MAY 2024)
52.223-21
52.223-21 FOAMS (MAY 2024)
52.223-3
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (FEB

2021)

52.223-10
Waste Reduction Program (MAY 2024) (Deviation FEB 2025)
52.224-3
52.224-3 PRIVACY TRAINING (JAN 2017)
52.225-1
52.225-1 Buy American-Supplies (OCT 2022)
52.225-13
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021)
52.225-25
52.225-25 PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN CERTAIN ACTIVITIES OR TRANSACTIONS RELATING TO IRAN-REPRESENTATION AND CERTIFICATIONS (JUN 2020)
52.229-3
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.232-18
52.232-18 AVAILABILITY OF FUNDS (APR 1984)
52.232-23
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-33
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER-SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.232-39
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (MAR 2023)

52.233-1

52.233-1 DISPUTES (MAY 2014)

52.233-3
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.242-15
52.242-15 STOP-WORK ORDER (AUG 1989)
52.242-2
52.242-2 PRODUCTION PROGRESS REPORTS (APR 1991)
52.245-1
52.245-1 GOVERNMENT PROPERTY (SEP 2021)
52.245-9
52.245-9 USE AND CHARGES (APR 2012)
52.247-55
52.247-55 F.O.B. POINT FOR DELIVERY OF GOVERNMENT-FURNISHED PROPERTY (JUNE 2003)

Clauses incorporated by full text 3052.225-70 REQUIREMENT FOR USE OF CERTAIN DOMESTIC COMMODITIES (MAR 2013) (DEVIATION 13-01)

(a) Definitions. As used in this clause-

(1) "Commercial," as applied to an item described in subsection (b) of this clause, means an item of supply, whether an end product or component, that meets the definition of "commercial item" set forth in (FAR) 48 CFR 2.101.

(2) "Component" means any item supplied to the Government as part of an end product or of another…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .