RFP Addendum #2- Fort Wilkins Water-Sewer System Upgrades - 19152.pdf
PDF 79 KB Posted
- Solicitation number
- RFQ-171-190000000325-3
- Issued by
- Houghton County, Michigan
About this file
This document is a Request for Proposal (RFP) Addendum No. 2 issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division, for the Fort Wilkins State Park Water/Sewer System Upgrades project. The addendum, dated 3/25/2019, provides clarifications to potential proposers regarding two specific questions about the project scope. The proposal due date is 4/4/2019, and the project file number is 751/19152.RAA, with Robert A. Adams serving as the Project Director.
The addendum addresses two key questions from potential bidders: first, confirming that the stockade sprinkler and hydrant water system drawing from Lake Fanny Hooe is not part of the project scope; and second, clarifying the status of the Manager's Residence, Crew Quarters, and Assistant Manager's Residence in relation to the sewer disposal system. Bidders are instructed to assume that these buildings are not connected to the sewer system and are still utilizing standalone drain fields. No specific budget or funding details are provided in this addendum, which serves primarily to provide additional context and clarification for the proposed water and sewer system upgrades at Fort Wilkins State Park.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 RFP (Rev 6/16)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
REQUEST FOR PROPOSAL ADDENDUM NO. 2
This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals. Addenda will be numbered by the Project Director and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL PROPOSERS
DATE ISSUED
3/25/2019
PROJECT NAME
Fort Wilkins State Park Water/Sewer System Upgrades.
FILE NUMBER
751/19152.RAA
PROJECT DIRECTOR
Robert A. Adams
PROPOSAL DUE DATE:
4/4/2019
ADDENDUM ITEMS:
Question #1: Do we need to plan for replacement of the separate stockade sprinkler and hydrant water system that draws water out of Lake Fanny Hooe? This system is shown on plan U-1 sheet 1 of 4. Answer: No. The stockade sprinkler and hydrant water system is not in scope and has a separate source.
Question #2: Have the Managers Residence, Crew Quarters, and Assistant Managers Residence been connected to Chamber No. 5 Flushing/Connection Chamber indicated on sheet 5 of 10 of the Roberts, Bartow & Associates, Inc plan set from 1991? If so, how many grinder pumps and electrical panels have been installed as part of this connection to the force main? If the connection has not been completed are the above mentioned building still being serviced by the septic tanks and drain fields indicated in the provided drawings? Answer: Assume that the Manager’s residence, Crew Quarters, and assistant manager’s residence is not connected to the sewer disposal system and is on a standalone drain field.
APPROVED BY:
DATE:
http://www.michigan.gov/SIGMAVSS