This is an RFP Addendum No. 1 issued by the Michigan Department of Technology, Management and Budget, State Facilities Administration Design and Construction Division for HVAC repairs at the WHV Calhoun & Dickinson facilities (File Number 472/26396.SAA). The addendum, issued on October 7, 2026, modifies the original Request for Proposal by establishing three key requirements: mandatory attendance at a pre-proposal meeting, inclusion of a BASS Controls upgrade as part of the work scope, and provision of nineteen sheets of existing Mechanical and Electrical drawings for the Dickinson location. The proposal due date is October 22, 2026, with Project Director Sheryl Ananich overseeing the procurement.

The addendum does not address pricing terms, set-asides, incumbent contractors, or funding sources. Notably, Calhoun facility drawings are not currently available, which may impact proposers' ability to develop comprehensive cost estimates for that portion of the project. All proposers must comply with the mandatory pre-proposal meeting attendance requirement and incorporate the BASS Controls upgrade specifications into their proposals to be considered responsive.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 2/22)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

REQUEST FOR PROPOSAL

ADDENDUM NO. 1

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.

Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.

TO:

ALL PROPOSERS

DATE ISSUED

10/7/2026

PROJECT NAME

WHV Calhoun & Dickinson HVAC Repairs

FILE NUMBER

472/26396.SAA

PROJECT DIRECTOR

Sheryl Ananich

PROPOSAL DUE DATE:

10/22/26

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

1. See attached Mandatory Pre-Proposal Meeting Attendance

2. Include a BASS Controls upgrade as part of the required work scope.

3. See attached (19)-sheets of various existing Mechanical and Electrical drawings for Dickinson.

Calhoun drawings are not available at this time.