This document is a cost proposal worksheet (RFP 510573 Attachment D) submitted by TRC Companies for environmental consulting services. The worksheet is structured as an Excel-based pricing template that includes multiple tabs for different service categories, hourly rates, classifications, and cost calculations. TRC has provided detailed pricing for various environmental assessment and inspection services, with staff classifications ranging from Contract Managers to Field Technicians, Administrative Support, and specialized roles like Asbestos Inspectors.

The contract covers a comprehensive range of environmental services including asbestos and bat inspections for bridge structures (priced from $500-$1,500 per structure depending on complexity and quantity), fueling system removal, Phase 2 site assessments, construction dewatering, pre-acquisition site assessments, and residential lead sampling. Bridge inspection services are offered on a tiered pricing structure with volume discounts, while other services are billed at hourly rates ranging from $24.36 for Administrative Support to $71.81 for Contract Managers, plus a 172.25% overhead rate and 7% profit margin. The market basket totals show significant contract values: $1.9 million for environmental assessments, $44,744 for residential lead sampling, $31,150 for program management assistance, and $601,100 for asbestos inspections, culminating in a total contract value of approximately $2.58 million. Direct expenses include standard government rates for mileage ($0.51/mile), meals, and lodging, with subcontractor costs passed through at actual cost with no markup.

View the file

Other files

File Type Posted
6_Cost_Proposal_Attachment_D_Cost_table_AECOM.xlsx XLSX spreadsheet
RFP_510573_Attachment_D_Cost_table_Ramboll.xlsx XLSX spreadsheet
RFP_510573_Attachment_D_Cost_table_Terracon.xlsx XLSX spreadsheet
GEI__Attachment_D_Cost_table_510573.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Contract Cost Worksheets RFP 510573 Attachment E
INSTRUCTIONS Return as Excel Spreadsheet! Do not reformat.
Fill in only those cells highlighted in blue. Cells in green are calculated.
Tab 1 Hourly Rates and CostsCell #
1. Fill in firm nameB2
2. Fill in asbestos inspection costs per bridge structure, cellsB5, C5, D5, E5
3. Fill in combined bat and asbestos inspection cost per bridge structure, cellsB6, C6, D6, E6
4. Fill in confined space combined bat and asbestos inspection cost per bridge structure, cellsB7 C7 D7 E7
5. Fill in standalone bat inspections cost per bridge structure, cellsB8, C8, D8, E8
6. Fill in confined space standalone bat inspection cost per bridge structure, cellsB9, C9, D9, E9
7. Fill in proposed overhead rateB42
8. Fill in proposed profit percentage as a whole number, field is formatted as a percentageB45
Tab 2 Classifications in titlesCell #
1. Please fit each of your current employee classifications into one of the Twenty Eight contract Rate titlesB4 through AC13
2. Put no more than ten classifications into each rate category.
3. Leave unused cells blank
Tab 3 Average Wage Rate CalcCell #
1. Enter the direct hourly wage rate (without overhead or profit) for each classification entered in Tab 2Columns D,F,H,J,L,N,P,R,T,V, Cells 4 through 31
2. Put a zero in any unused cell in column D
3. Leave all other unused cells blank
Tab 4 Fueling System Removal
1. Enter the number of hours for each classification for each task in columns C through F GColumns C, D, E, F, G rows 4 through 31
2. Enter direct expenses in columns J K through M NColumns J K, L, M, N rows 4 through 31
3. Enter subcontract costs in columns P Q through R SColumns P, Q, R S rows 4 through 31
Tab 5 Phase 2 Site Assessment
1. Enter the tasks from the project scope document in Cells C3 through J3Columns C, D, E, F, G, H, I, J row 3
2. Enter the number of hours for each classification for each task in Columns C through JColumns C, D, E, F, G, H, I, J rows 4-31
3. Enter the direct expenses in columns N through QColumns N, O, P, Q, rows 4-31
5. Enter the subcontract costs in columns T through VColumns T, U, V rows 4-31
Tab 6 Construction Dewatering
1. Enter the tasks from the project scope document in Cells C3 through J3
2. Enter the number of hours for each classification for each task in Columns C through J
3. Enter the direct expenses in columns N through Q
5. Enter the subcontract costs in columns T through V
Tab 7 Pre-Acquisition Site Assessment
1. Enter the tasks from the project scope document in Cells C3 through J3
2. Enter the number of hours for each classification for each task in Columns C through J
3. Enter the direct expenses in columns N through Q
5. Enter the subcontract costs in columns T through V
Tab 8 Residential Lead Sampling
1. Fill in the price per sample in Column B
2.Fill in the price per expedited sample in Column C

Tab 1 Hourly Rates and Costs

Contract Cost Package 2024Fill in only those cells highlighted in blue. Cells in green are calculated.
FIRM NAME:TRC
Asbestos Inspections - BridgesTerms: Lump Sum
Cost per single structureTwo to four structures, cost per structureFive to nine structures, cost per structureTen or more structures, cost per structure
Asbestos inspection, per bridge structure (Terms: Lump Sum)$ 650.00$ 625.00$ 600.00$ 575.00
Combined Bat and Asbestos inspection, per bridge structure (Terms:Lump Sum)$ 1,000.00$ 950.00$ 900.00$ 850.00
Asbestos and Bat inspection - Confined Space or Two Person project (for traffic control, water entry or other safety considerations)# Terms: Lump Sum$ 1,500.00$ 1,400.00$ 1,300.00$ 1,200.00# The determination of need for confined space entry, or two person team for traffic control, water entry, or other safety considerations will be made by the consultant.
Bat inspection of bridges without asbestos inspection (Terms: lump sum)$ 575.00$ 550.00$ 525.00$ 500.00
Bat inspection of bridges without asbestos inspection - Confined space # (Terms: lump sum)$ 1,100.00$ 1,000.00$ 950.00$ 900.00
NOTE: Structures requrested at the same time in the same spreadsheet constitute a single request, number of structures for pricing is determined by number of structures in request, not number of project IDs. Prices for long, multiple-section structures such as the Hoan Bridge, Wisconsin River bridges, St Croix river bridges, and Mississippi River bridges, will be negotiated separately at the time of request.
Asbestos inspection, buildings, bridge tender houses, other structuresTerms: average direct hourly rate*
Asbestos abatementTerms: average direct hourly rate*
Project StaffTerms: average direct hourly rate**the average direct hourly rate for each classification shall be the rate charged for the contract
Contract Manager$71.81Average Hourly Rate
Project Supervisor I$56.48Average Hourly Rate
Project Supervisor II$63.57Average Hourly Rate
Engineer I$35.95Average Hourly Rate
Engineer II$0.00Average Hourly Rate
Engineer III$0.00Average Hourly Rate
Hydrogeologist I$42.32Average Hourly Rate
Hydrogeologist II$50.85Average Hourly Rate
Hydrogeologist III$0.00Average Hourly Rate
Scientist I$31.73Average Hourly Rate
Scientist II$0.00Average Hourly Rate
Scientist III$0.00Average Hourly Rate
Field Technician I$29.39Average Hourly Rate
Field Technician II$0.00Average Hourly Rate
Field Technician III$0.00Average Hourly Rate
CADD/GIS I$34.66Average Hourly Rate
CADD/GIS II$45.93Average Hourly Rate
Accounting I$0.00Average Hourly Rate
Accounting II$0.00Average Hourly Rate
Administrative Support I$24.36Average Hourly Rate
Administrative Support II$34.05Average Hourly Rate
Asbestos Inspector$34.20Average Hourly Rate
Exterior Abatement Worker$0.00Average Hourly Rate
Exterior Asbestos Supervisor$0.00Average Hourly Rate
Asbestos Worker$0.00Average Hourly Rate
Asbestos Supervisor$0.00Average Hourly Rate
Asbestos Project Designer$0.00Average Hourly Rate
Asbestos Management Planner$0.00Average Hourly Rate
Equipment and suppliesTerms: direct expense, no markup
Subcontractor CostsTerms: actual cost, no markup
MileageTerms: current state reimbursement rate
Per mile, personal vehicle rate$0.51/mile
MealsTerms: current state reimbursement rate
Breakfast$ 10.00
Lunch$ 12.00
Dinner$ 23.00
LodgingTerms: current state reimbursement rate, excluding taxes
Per night$98.00
Per night, Milwaukee, Racine and Kenosha counties$103.00
Asbestos inspection, buildings, bridge tender houses, other structuresTerms: average direct hourly rate*
Overhead
Proposed rate172.250%Percentage of Direct Labor
ProfitTerms: percentage of labor and overhead, no profit on subcontractors or direct expenses
Proposed Rate7%Percentage of Direct Labor + Labor Overhead, NO PROFIT ON SUBCONTRACTORS OR DIRECT EXPENSES

Tab 2 Classifications in Titles

Classifications included in average wage rate: (list each classification on a separate line, do not insert or delete rows, do not leave blank rows between classifications.)
TRCPlease fill in the actual titles of your staff. Limit 10 titles per classification
Rate Title:Contract ManagerProject Supervisor IProject Supervisor IIEngineer IEngineer IIEngineer IIIHydrogeologist IHydrogeologist IIHydrogeologist IIIScientist IScientist IIScientist IIIField Technician IField Technician IIField Technician IIICADD/GIS ICADD/GIS IIAccounting IAccounting IIAdministrative Support IAdministrative Support IIAsbestos InspectorExterior Abatement WorkerExterior Asbestos SupervisorAsbestos WorkerAsbestos SupervisorAsbestos Project DesignerAsbestos Management Planner
Classifications included in Rate Titles:Contract Manager 1Project Supervisor I-1Project Supervisor II-1Engineer I-1ell1elll1Hydrogeologist I-1Hydrogeologist II-1hIII1Scientist I-1sII1sIII1Field Technician I-1ftII1ftIII1CADD/GIS I-1CADD/GIS II-1accI1accII1Administrative Support I-1Administrative Support II-1Asbestos Inspector-1eaw1eas1aw1as1apd1amp1
Contract Manager 2Project Supervisor I-2Project Supervisor II-2Engineer I-2ell2elll2Hydrogeologist I-2Hydrogeologist II-2hIII2Scientist I-2sII2sIII2Field Technician I-2ftII2ftIII2CADD/GIS I-2cadII2accI2accII2Administrative Support I-2Administrative Support II-2Asbestos Inspector-2eaw2eas2aw2as2apd2amp2
Contract Manager 3Project Supervisor 1-3Project Supervisor II-3Engineer I-3ell3elll3Hydrogeologist I-3hll3hIII3Scientist I-3sII3sIII3Field Technician I-3ftII3ftIII3CADD/GIS I-3cadII3accI3accII3admI3Administrative Support II-3Asbestos Inspector-3eaw3eas3aw3as3apd3amp3
Contract Manager 4psI4Project Supervisor II-4Engineer I-4eII4eIII4hI4hII4hIII4Scientist I-4sII4sIII4ftI4ftII4ftIII4cadI4cadII4accI4accII4admI4Administrative Support II-4Asbestos Inspector-4eaw4eas4aw4as4apd4amp4
cm5psI5psII5Engineer I-5eII5eIII5hI5hII5hIII5Scientist I-5sII5sIII5ftI5ftII5ftIII5cadI5cadII5accI5accII5admI5admII5ai5eaw5eas5aw5as5apd5amp5
cm6psI6psII6Engineer I-6eII6eIII6hI6hII6hIII6Scientist I-6sII6sIII6ftI6ftII6ftIII6cadI6cadII6accI6accII6admI6admII6ai6eaw6eas6aw6as6apd6amp6
cm7psI7psII7eI7eII7eIII7hI7hII7hIII7sI7sII7sIII7ftI7ftII7ftIII7cadI7cadII7accI7accII7admI7admII7ai7eaw7eas7aw7as7apd7amp7
cm8psI8psII8eI8eII8eIII8hI8hII8hIII8sI8sII8sIII8ftI8ftII8ftIII8cadI8cadII8accI8accII8admI8admII8ai8eaw8eas8aw8as8apd8amp8
cm9psI9psII9eI9eII9eIII9hI9hII9hIII9sI9sII9sIII9ftI9ftII9ftIII9cadI9cadII9accI9accII9admI9admII9ai9eaw9eas9aw9as9apd9amp9
cm10psI10psII10eI10eII10eIII10hI10hII10hIII10sI10sII10sIII10ftI10ftII10ftIII10cadI10cadII10accI10accII10admI10admII10ai10eaw10eas10aw10as10apd10amp10
EXAMPLE:0
Rate Title: Scientist I
Classifications included in title: Staff scientist 1
Arborist
Geologist 1
Geologist 2
Senior Project Technical 1
Senior Project Technical 2

Tab 3 Average Wage Rate Calc

TRCFill in only those cells highlighted in blue. Cells in green are calculated.Do not alter or change the formulas.
Enter the hourly rate for each classification shown
TitleAverage Hourly RateClassification 1Hourly rate 1Classification 2Hourly Rate 2Classification 3Hourly Rate 3Classification 4Hourly Rate 4Classification 5Hourly Rate 5Classification 6Hourly Rate 6Classification 7Hourly Rate 7Classification 8Hourly Rate 8Classification 9Hourly Rate 9Classification 10Hourly Rate 10
Contract Manager$71.81Contract Manager 1$ 69.63Contract Manager 2$ 64.46Contract Manager 3$ 66.61Contract Manager 4$ 86.54cm5cm6cm7cm8cm9cm10
Project Supervisor I$56.48Project Supervisor I-1$ 53.21Project Supervisor I-2$ 57.73Project Supervisor 1-3$ 58.49psI4psI5psI6psI7psI8psI9psI10
Project Supervisor II$63.57Project Supervisor II-1$ 60.05Project Supervisor II-2$ 65.88Project Supervisor II-3$ 62.34Project Supervisor II-4$ 65.99psII5psII6psII7psII8psII9psII10
Engineer I$35.95Engineer I-1$ 35.79Engineer I-2$ 34.89Engineer I-3$ 35.98Engineer I-4$ 37.56Engineer I-5$ 34.32Engineer I-6$ 37.14eI7eI8eI9eI10
Engineer II$0.00ell1$ - 0ell2ell3eII4eII5eII6eII7eII8eII9eII10
Engineer III$0.00elll1$ - 0elll2elll3eIII4eIII5eIII6eIII7eIII8eIII9eIII10
Hydrogeologist I$42.32Hydrogeologist I-1$ 43.58Hydrogeologist I-2$ 43.30Hydrogeologist I-3$ 40.07hI4hI5hI6hI7hI8hI9hI10
Hydrogeologist II$50.85Hydrogeologist II-1$ 48.40Hydrogeologist II-2$ 53.30hll3hII4hII5hII6hII7hII8hII9hII10
Hydrogeologist III$0.00hIII1$ - 0hIII2hIII3hIII4hIII5hIII6hIII7hIII8hIII9hIII10
Scientist I$31.73Scientist I-1$ 33.68Scientist I-2$ 30.26Scientist I-3$ 32.19Scientist I-4$ 30.77Scientist I-5$ 32.70Scientist I-6$ 30.77sI7sI8sI9sI10
Scientist II$0.00sII1$ - 0sII2sII3sII4sII5sII6sII7sII8sII9sII10
Scientist III$0.00sIII1$ - 0sIII2sIII3sIII4sIII5sIII6sIII7sIII8sIII9sIII10
Field Technician I$29.39Field Technician I-1$ 28.06Field Technician I-2$ 29.81Field Technician I-3$ 30.29ftI4ftI5ftI6ftI7ftI8ftI9ftI10
Field Technician II$0.00ftII1$ - 0ftII2ftII3ftII4ftII5ftII6ftII7ftII8ftII9ftII10
Field Technician III$0.00ftIII1$ - 0ftIII2ftIII3ftIII4ftIII5ftIII6ftIII7ftIII8ftIII9ftIII10
CADD/GIS I$34.66CADD/GIS I-1$ 33.48CADD/GIS I-2$ 36.50CADD/GIS I-3$ 33.99cadI4cadI5cadI6cadI7cadI8cadI9cadI10
CADD/GIS II$45.93CADD/GIS II-1$ 45.93cadII2cadII3cadII4cadII5cadII6cadII7cadII8cadII9cadII10
Accounting I$0.00accI1$ - 0accI2accI3accI4accI5accI6accI7accI8accI9accI10
Accounting II$0.00accII1$ - 0accII2accII3accII4accII5accII6accII7accII8accII9accII10
Administrative Support I$24.36Administrative Support I-1$ 26.01Administrative Support I-2$ 22.71admI3admI4admI5admI6admI7admI8admI9admI10
Administrative Support II$34.05Administrative Support II-1$ 34.60Administrative Support II-2$ 32.83Administrative Support II-3$ 31.77Administrative Support II-4$ 36.99admII5admII6admII7admII8admII9admII10
Asbestos Inspector$34.20Asbestos Inspector-1$ 30.26Asbestos Inspector-2$ 34.89Asbestos Inspector-3$ 28.06Asbestos Inspector-4$ 43.58ai5ai6ai7ai8ai9ai10
Exterior Abatement Worker$0.00eaw1$ - 0eaw2eaw3eaw4eaw5eaw6eaw7eaw8eaw9eaw10
Exterior Asbestos Supervisor$0.00eas1$ - 0eas2eas3eas4eas5eas6eas7eas8eas9eas10
Asbestos Worker$0.00aw1$ - 0aw2aw3aw4aw5aw6aw7aw8aw9aw10
Asbestos Supervisor$0.00as1$ - 0as2as3as4as5as6as7as8as9as10
Asbestos Project Designer$0.00apd1$ - 0apd2apd3apd4apd5apd6apd7apd8apd9apd10
Asbestos Management Planner$0.00amp1$ - 0amp2amp3amp4amp5amp6amp7amp8amp9amp10
Example:Average Hourly RateClassification 1Hourly rate 1Classification 2Hourly Rate 2Classification 3Hourly Rate 3Classification 4Hourly Rate 4Classification 5Hourly Rate 5Classification 6Hourly Rate 6
Scientist$30.57Staff Scientist 1$ 21.20Staff Scientist 2$ 23.70Staff Scientist 3$ 27.50Geologist 1$ 32.50Geologist 2$ 37.50Senior Project Technical$ 41.00

Tab 4 Fueling System Removal

TRCFueling System Removal
STAFF HOURSDirect ExpensesSubcontract
ClassificationHourly rateTask1Task 2Task 3Task 4Task 5Total HoursTotal costItemQuantityUnit or rateRate or Unit CostTotalSubcontractorTaskTotal
Contract Manager$71.810.50.5$ 35.91Meals - Lunch1Each12$ 12.00Laboratory11 PVOCs + naphthalene$ 473.00
Project Supervisor I$56.4810.511.54$ 225.91Mileage50Mile0.51$ 25.50Tank Remover/Cleanerfueling system removal$ 8,500.00
Project Supervisor II$63.570$ - 0Misc. Field Supplies1Each25$ 25.00$ - 0
Engineer I$35.95112$ 71.89PID1Day110$ 110.00$ - 0
Engineer II$0.000$ - 0GPS1Day150$ 150.00$ - 0
Engineer III$0.000$ - 0$ - 0$ - 0
Hydrogeologist I$42.320$ - 0$ - 0$ - 0
Hydrogeologist II$50.850$ - 0$ - 0$ - 0
Hydrogeologist III$0.000$ - 0$ - 0$ - 0
Scientist I$31.734110823$ 729.75$ - 0$ - 0
Scientist II$0.000$ - 0$ - 0$ - 0
Scientist III$0.000$ - 0$ - 0$ - 0
Field Technician I$29.390$ - 0$ - 0$ - 0
Field Technician II$0.000$ - 0$ - 0$ - 0
Field Technician III$0.000$ - 0$ - 0$ - 0
CADD/GIS I$34.6644$ 138.63$ - 0$ - 0
CADD/GIS II$45.930$ - 0$ - 0$ - 0
Accounting I$0.000$ - 0$ - 0$ - 0
Accounting II$0.000$ - 0$ - 0$ - 0
Administrative Support I$24.3610.5427.5$ 182.70$ - 0$ - 0
Administrative Support II$34.050$ - 0$ - 0$ - 0
Asbestos Inspector$34.200$ - 0$ - 0$ - 0
Exterior Abatement Worker$0.000$ - 0$ - 0$ - 0
Exterior Asbestos Supervisor$0.000$ - 0$ - 0$ - 0
Asbestos Worker$0.000$ - 0$ - 0$ - 0
Asbestos Supervisor$0.000$ - 0$ - 0$ - 0
Asbestos Project Designer$0.000$ - 0$ - 0$ - 0
Asbestos Management Planner$0.000$ - 0$ - 0$ - 0

Total Staff Labor $ 1,384.78 Total Direct Expenses $ 322.50 Total Subcontracts $ 8,973.00

Tab 5 Phase 2 Site Assessment

TRCPhase 2 Site Assessment
STAFF HOURSDirect ExpensesSubcontract
ClassificationHourly rateTask 1Task 2Task 3Task 4Task 5Task 6Task 7Task 8Total HoursTotal costItemQuantityUnit or rateRate or Unit CostTotal costSubcontractorTaskTotal cost
Contract Manager$71.8111$ 71.81Meals - Lunch1Each12$ 12.00Laboratory5 VOCs, 3 PCBs, 5 metals, 3 PAHs$ 1,185.75
Project Supervisor I$56.480.50.5124$ 225.91Mileage50Mile0.51$ 25.50Geoprobe Subcontractor3 soil borings and 2 temp wells$ 1,405.00
Project Supervisor II$63.570$ - 0Misc. Field Supplies1Each25$ 25.00$ - 0
Engineer I$35.950$ - 0PID1Day110$ 110.00$ - 0
Engineer II$0.000$ - 0Misc. Field Equipment1Each100$ 100.00$ - 0
Engineer III$0.000$ - 0GPS1Day150$ 150.00$ - 0
Hydrogeologist I$42.321113$ 126.95$ - 0$ - 0
Hydrogeologist II$50.850$ - 0$ - 0$ - 0
Hydrogeologist III$0.000$ - 0$ - 0$ - 0
Scientist I$31.73189$ 285.56$ - 0$ - 0
Scientist II$0.000$ - 0$ - 0$ - 0
Scientist III$0.000$ - 0$ - 0$ - 0
Field Technician I$29.39421101119$ 558.35$ - 0$ - 0
Field Technician II$0.000$ - 0$ - 0$ - 0
Field Technician III$0.000$ - 0$ - 0$ - 0
CADD/GIS I$34.6633$ 103.97$ - 0$ - 0
CADD/GIS II$45.930$ - 0$ - 0$ - 0
Accounting I$0.000$ - 0$ - 0$ - 0
Accounting II$0.000$ - 0$ - 0$ - 0
Administrative Support I$24.36111429$ 219.24$ - 0$ - 0
Administrative Support II$34.050$ - 0$ - 0$ - 0
Asbestos Inspector$34.200$ - 0$ - 0$ - 0
Exterior Abatement Worker$0.000$ - 0$ - 0$ - 0
Exterior Asbestos Supervisor$0.000$ - 0$ - 0$ - 0
Asbestos Worker$0.000$ - 0$ - 0$ - 0
Asbestos Supervisor$0.000$ - 0$ - 0$ - 0
Asbestos Project Designer$0.000$ - 0$ - 0$ - 0
Asbestos Management Planner$0.000$ - 0$ - 0$ - 0
Total Staff Labor$ 1,591.78Total Direct Expenses$ 422.50Total Subcontracts$ 2,590.75

Tab 6 Construction Dewatering

TRCConstruction Dewatering
STAFF HOURSDirect ExpensesSubcontract
ClassificationHourly ratetask 1Task 2Task 3Task 4Task 5Task 6Task 7Task 8Total HoursTotal costItemQuantityUnit or rateRate or Unit CostTotal costSubcontractorTaskTotal cost
Contract Manager$71.8111$ 71.81Meals - Lunch2Each12$ 24.00Laboratory2 VOCs, 2 PFAS, 1 TCLP$ 1,202.00
Project Supervisor I$56.4810.50.5125$ 282.38Mileage100Mile0.51$ 51.00$ - 0
Project Supervisor II$63.570$ - 0Misc. Field Supplies1Each50$ 50.00$ - 0
Engineer I$35.9522$ 71.89PID2Day110$ 220.00$ - 0
Engineer II$0.000$ - 0GPS1Day150$ 150.00$ - 0
Engineer III$0.000$ - 0$ - 0$ - 0
Hydrogeologist I$42.320$ - 0$ - 0$ - 0
Hydrogeologist II$50.850$ - 0$ - 0$ - 0
Hydrogeologist III$0.000$ - 0$ - 0$ - 0
Scientist I$31.734142041043$ 1,364.32$ - 0$ - 0
Scientist II$0.000$ - 0$ - 0$ - 0
Scientist III$0.000$ - 0$ - 0$ - 0
Field Technician I$29.390$ - 0$ - 0$ - 0
Field Technician II$0.000$ - 0$ - 0$ - 0
Field Technician III$0.000$ - 0$ - 0$ - 0
CADD/GIS I$34.66134$ 138.63$ - 0$ - 0
CADD/GIS II$45.930$ - 0$ - 0$ - 0
Accounting I$0.000$ - 0$ - 0$ - 0
Accounting II$0.000$ - 0$ - 0$ - 0
Administrative Support I$24.3610.510.5429$ 219.24$ - 0$ - 0
Administrative Support II$34.050$ - 0$ - 0$ - 0
Asbestos Inspector$34.200$ - 0$ - 0$ - 0
Exterior Abatement Worker$0.000$ - 0$ - 0$ - 0
Exterior Asbestos Supervisor$0.000$ - 0$ - 0$ - 0
Asbestos Worker$0.000$ - 0$ - 0$ - 0
Asbestos Supervisor$0.000$ - 0$ - 0$ - 0
Asbestos Project Designer$0.000$ - 0$ - 0$ - 0
Asbestos Management Planner$0.000$ - 0$ - 0$ - 0

Total Staff Labor $ 2,148.27 Total Direct Expenses $ 495.00 Total Subcontracts $ 1,202.00

Tab 7 Pre-Acquisition Assessmen

TRCPre- Acquisition Site Assessment
STAFF HOURSDirect ExpensesSubcontract
ClassificationHourly ratetask 1Task 2Task 3Task 4Task 5Task 6Task 7Task 8Total HoursTotal costItemQuantityUnit or rateRate or Unit CostTotal costSubcontractorTaskTotal cost
Contract Manager$71.8111$ 71.81Meals - Lunch1Each12$ 12.00$ - 0
Project Supervisor I$56.4810.5225.5$ 310.62Mileage50Mile0.51$ 25.50$ - 0
Project Supervisor II$63.570$ - 0$ - 0$ - 0
Engineer I$35.950$ - 0$ - 0$ - 0
Engineer II$0.000$ - 0$ - 0$ - 0
Engineer III$0.000$ - 0$ - 0$ - 0
Hydrogeologist I$42.320$ - 0$ - 0$ - 0
Hydrogeologist II$50.850$ - 0$ - 0$ - 0
Hydrogeologist III$0.000$ - 0$ - 0$ - 0
Scientist I$31.731162028$ 888.39$ - 0$ - 0
Scientist II$0.000$ - 0$ - 0$ - 0
Scientist III$0.000$ - 0$ - 0$ - 0
Field Technician I$29.390$ - 0$ - 0$ - 0
Field Technician II$0.000$ - 0$ - 0$ - 0
Field Technician III$0.000$ - 0$ - 0$ - 0
CADD/GIS I$34.6644$ 138.63$ - 0$ - 0
CADD/GIS II$45.930$ - 0$ - 0$ - 0
Accounting I$0.000$ - 0$ - 0$ - 0
Accounting II$0.000$ - 0$ - 0$ - 0
Administrative Support I$24.3610.5225.5$ 133.98$ - 0$ - 0
Administrative Support II$34.050$ - 0$ - 0$ - 0
Asbestos Inspector$34.200$ - 0$ - 0$ - 0
Exterior Abatement Worker$0.000$ - 0$ - 0$ - 0
Exterior Asbestos Supervisor$0.000$ - 0$ - 0$ - 0
Asbestos Worker$0.000$ - 0$ - 0$ - 0
Asbestos Supervisor$0.000$ - 0$ - 0$ - 0
Asbestos Project Designer$0.000$ - 0$ - 0$ - 0
Asbestos Management Planner$0.000$ - 0$ - 0$ - 0

Total Staff Labor $ 1,543.43 Total Direct Expenses $ 37.50 Total Subcontracts $ - 0

Tab 8 Residential Lead Sampling

TRCResidential Lead Sampling
Sample TypePrice per SampleExpedited Turnaround Price per Sample
Paint chips1010.6
Bulk Lead Sampling1010.6
Wipe Sampling9.5510.55

Total Cost Score

CategoryMarket BasketTotal Cost
Environmental Assessment{(Labor + Labor*overhead)*profit +(Labor + Labor*overhead)+Direct Expenses + Subcontractor}* Market Basket
Fueling system Removal22293248.5095925
Phase 2 Site Assessment1571201084.48793488
Construction Dewatering25198876.912134375
Pre-Acquisition Assessment46208547.08130925
Total Environmental Assessment COST1901756.990971
Residential Lead SamplingMarket basket
Paint Chips5$ 50.00
Bulk Lead100$ 1,000.00
Wipe1250$ 11,937.50
Paint chips expedited0$ - 0
Bulk Lead expedited10$ 106.00
Wipe Expedited3000$ 31,650.00

Total Residential Lead Sampling Cost $ 44,743.50

Program Management AssistanceNumber of HoursStaff classificationtotal
1040Admin Support 1$ 25,334.40
40Project supervisor 2$ 2,542.60
20Contract Manager$ 1,436.20
40CADD/GIS 2$ 1,837.20
Total Program Management Assistance Cost$ 31,150.40
Market Basket
Asbestos inspection
Normal one person844$ 548,600.00
Asbestos plus bats
confined space, two people35$ 52,500.00
Total Asbestos Inspection cost$ 601,100.00

Total Cost 2578750.890971