ADDENDUM #1 SUMMARY
This is Addendum #1 to RFP #27-20, issued by Roswell Park Comprehensive Cancer Center for the Community Outreach and Engagement Center – Phase II project located at 907 Michigan Avenue, Buffalo, New York. The addendum, dated September 2, 2026, modifies the original contract documents and must be acknowledged by bidders in their bid submissions. The bid submittal deadline is September 11, 2026, at 2:00 PM EST. The addendum introduces significant technical modifications including the addition of Section 019113 (General Commissioning Requirements), replacement of Section 230710 (Insulation), and revisions to multiple mechanical and electrical drawings (M001, M001.1, M401, M401.1, M601, P001, P002, P003, P500, E001, E002, E600) and sketches (CSK-001, ASK-001, ASK-002, ASK-003). Key mechanical changes include the addition of exhaust fan EF-102 for refrigerant exhaust, relocation of wall louvers away from exterior doors, and updates to VRF (Variable Refrigerant Flow) system schedules and ductwork configurations. The addendum also includes revised insulation specifications for refrigeration piping and ductwork, with specific thickness requirements ranging from 0.5 to 2 inches depending on application and service type.
The commissioning section establishes comprehensive requirements for system verification, including pre-functional checklists and functional performance testing for HVAC systems (VRF split systems, distribution pumps, ductwork, testing and balancing), plumbing systems, electrical distribution, and building management systems. The Commissioning Authority, reporting to the Owner, will oversee all commissioning activities with support from the Contractor, Architect, and Engineer of Record. The Contractor is responsible for providing all testing equipment, skilled technicians, Operations and Maintenance documentation, and owner training at a 9th-grade comprehension level. Commissioning must be completed before substantial completion, with deferred testing permitted for seasonal conditions. The addendum includes a complete table of contents reflecting all contract document sections across 33 divisions, covering everything from bidding requirements through utilities, and appends detailed HVAC plans, mechanical schedules, plumbing diagrams, and natural gas piping details for the standby generator installation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP 27-20 - Specifications.pdf | ||
| RFP 27-20 - Drawings.pdf | ||
| RFP 27-20 Addendum 2_9.9.26.pdf | ||
| RFP 27-20 Addendum 3_9.16.26.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Roswell Park Comprehensive Cancer Center ADDENDUM #1 Community Outreach and Engagement Center – Phase II (RFP #27-20) Page 1 of 2 #15-24-001 Young + Wright Architects
ADDENDUM #1
Date of Addendum: 9/2/2026
NOTICE TO ALL BIDDERS AND PLANHOLDERS
The Contract Documents for the above-referenced Project are modified as set forth in this Addendum. The original Contract Documents and any previously issued addenda remain in full force and effect, except as modified by this Addendum, which is hereby made part of the Contract Documents. Bidder shall take this Addendum into consideration when preparing and submitting a bid, and shall acknowledge receipt of this Addendum in the space provided on the Bid Form.
BID SUBMITTAL DEADLINE
The bid submittal deadline is September 11, 2026 at 02:00 PM EST.
1.0 – SPECIFICATIONS
Item Section No. Description of Change
1.1 TOC UPDATE:
Add Section 019113 with Issue Date “09/02/2026”.
Add Revision Date “08/28/2026” to Section 230710.
1.2 019113 ADD:
Entire Specification Section “019113 – GENERAL COMMISSIONING
REQUIREMENTS”
1.3 230710 REPLACE:
Entire Specification Section “230710 – INSULATION”
2.0 – DRAWINGS
Item Drawing No. Description of Change
2.1 AS001 ADD:
Entire drawing AS001
2.2 M001 REPLACE:
Entire Drawing. Adding EF-102 for refrigerant exhaust. Shifted wall louver from EF-211 north away from exterior door.
2.3 M001.1 REPLACE:
Entire Drawing. Shifting wall louver from EF-211 north away from exterior door.
2.4 M401 REPLACE:
Entire Drawing. Adding EF-102 exhaust duct location from BCCTRL-101.
2.5 M401.1 REPLACE:
Entire Drawing. Adding EF-102 for refrigerant exhaust and added EF-211 exhaust duct location from BCCTRL-101.
2.6 M601 REPLACE:
Entire Drawing. Adding fan requirements for EF-102, adding drawing note 2 to the VRF schedule, and adding louver L-102.
2.7 P001 REPLACE:
Entire Drawing. Clarifying name of standby generator and referenced drawing number in drawing note 5.
Roswell Park Comprehensive Cancer Center ADDENDUM #1 Community Outreach and Engagement Center – Phase II (RFP #27-20) Page 2 of 2 #15-24-001 Young + Wright Architects
2.8 P002 REPLACE:
Entire Drawing. Clarifying referenced drawing number in drawing note 9.
2.9 P003 REPLACE:
Entire Drawing. Clarifying referenced drawing number in drawing note 8.
2.10 P500 REPLACE:
Entire Drawing. Clarifying name of standby generator on detail 6.
2.11 E001 REPLACE:
Entire Drawing. Adding an engraved label at emergency generator shutdown station and clarifying labeling on the standby generator.
2.12 E002 REPLACE:
Entire Drawing. Clarifying what circuit the existing corridor lighting should be connected to in drawing note 1.
2.13 E600 REPLACE:
Entire Drawing. Adding the electrical connection for EF-102, clarifying name of standby generator and adding specifications for the existing service disconnect switch.
3.0 - SKETCHES
Item Sketch No. Description of Change
3.1 CSK-001 REVISE:
Staging Area Layout
3.2 ASK-001 REPLACE:
Detail 9 on sheet A501 with Detail 9 on ASK-001.
3.3 ASK-002 REPLACE:
Detail 11 on sheet A502 with Detail 11 on ASK-002.
3.4 ASK-003 REPLACE:
Detail 5, H2 on sheet A601 with Detail 5, H2 on ASK-003.
4.0 – QUESTIONS AND ANSWERS
The following questions and answers are provided as a matter of information to clarify issues raised about the Contract Documents. To the extent that changes to the Contract Documents are required based on the questions received, the Contract Documents have been modified as noted above in the Specifications and Drawings sections of this Addendum.
Item Questions and Answers
4.1 N/A
5.0 – INFORMATION
The following information is provided to all bidders and plan holders and will modify and become a part of the Contract Documents.
Item Description
5.1 Pre-Bid Meeting Sign-In Sheet.
5.2 Pre-Bid Meeting Agenda.
END OF ADDENDUM
September 2, 2026 Addendum 1
Roswell Park Comprehensive Cancer Center TABLE OF CONTENTS - Community Outreach and Engagement Center – Phase 2 VOLUME 1
TOC - 1
ROSWELL PARK COMPREHENSIVE CANCER CENTER
COMMUNITY OUTREACH AND ENGAGEMENT CENTER – PHASE 2
TABLE OF CONTENTS
DIVISION 00 BIDDING AND CONTRACT REQUIREMENTS
SECTION DESCRIPTION ISSUE REVISION
001113 ADVERTISEMENT FOR BIDS 8/14/2026
002113 INSTRUCTION TO BIDDERS 8/14/2026
002213B SUPPLEMENTAL INSTRUCTION TO BIDDERS –
MWBE/EEO/SDVOB 8/14/2026
004100 BID FORM 8/14/2026
005000 AGREEMENT 8/14/2026
005000A APPENDIX A – STANDARD CLAUSES 8/14/2026
005000B APPENDIX B – ACCESS TO PREMISES 8/14/2026
005000C APPENDIX C – MWBE CONTRACT FORMS 8/14/2026
005000D APPENDIX D – CONTRACT FORMS 8/14/2026
007213 GENERAL CONDITIONS 8/14/2026
009000A ENUMERATION OF CONTRACT DOCUMENTS 8/14/2026
009500 CONTRACT SCOPE 8/14/2026
009500A SITE LOGISTICS PLAN 8/14/2026
DIVISION 01 GENERAL REQUIREMENT
SECTION DESCRIPTION ISSUE REVISION
011000 SUMMARY OF WORK 8/14/2026
012020 PROGRESS MEETINGS 8/14/2026
012300 ALTERNATES 8/14/2026
012500 SUBSTITUTION PROCEDURES 8/14/2026
012519 SUBSTITUTION FORM 8/14/2026
012600 MODIFICATION PROCEDURES 8/14/2026
012900 PAYMENT PROCEDURES 8/14/2026
013100 PROJECT MANAGEMENT AND COORDINATION 8/14/2026
013200 CONSTRUCTION PROGRESS DOCUMENTATION 8/14/2026
013300 SUBMITTALS 8/14/2026
013350 COMPUTER AIDED DESIGN COORDINATION
DRAWINGS 8/14/2026
014000 QUALITY REQUIREMENTS 8/14/2026
014000A DASNY NYS STATEMENT OF SPECIAL
INSPECTIONS 8/14/2026
014200 REGULATORY REQUIREMENTS 8/14/2026
015000 CONSTRUCTION FACILITIES AND TEMPORARY
CONTROLS 8/14/2026
015123 CONSTRUCTION HEAT AND TEMPORARY HEAT 8/14/2026
015526 TRAFFIC MAINTENANCE AND PROTECTION 8/14/2026
015600 CONSTRUCTION AREA SECURITY 8/14/2026
Roswell Park Comprehensive Cancer Center TABLE OF CONTENTS - Community Outreach and Engagement Center – Phase 2 VOLUME 1
TOC - 2
015700 ENVIRONMENTAL CONTROL 8/14/2026
016000 PRODUCT REQUIREMENTS 8/14/2026
016500 MATERIALS AND EQUIPMENT 8/14/2026
017300 EXECUTION 8/14/2026
017329 CUTTING AND PATCHING 8/14/2026
017400 MOLD AND MOISTURE INTRUSION 8/14/2026
017700 CLOSEOUT PROCEDURES 8/14/2026
017823 OPERATION AND MAINTENANCE DATA 8/14/2026
017839 PROJECT RECORD DOCUMENTS 8/14/2026
019113 GENERAL COMMISSIONING REQUIREMENTS 9/02/2026
DIVISION 02 EXISTING CONDITIONS
SECTION DESCRIPTION
024119 SELECTIVE DEMOLITION 8/14/2026
DIVISION 03 CONCRETE
031000 CONCRETE FORMING AND ACCESSORIES 8/14/2026
032000 CONCRETE REINFORCING 8/14/2026
033000 CAST-IN-PLACE CONCRETE 8/14/2026
DIVISION 05 METALS
051200 STRUCTURAL STEEL FRAMING 8/14/2026
053100 STEEL DECKING 8/14/2026
054000 COLD-FORMED METAL FRAMING 8/14/2026
054400 COLD-FORMED METAL TRUSSES 8/14/2026
DIVISION 06 WOOD, PLASTICS AND COMPOSITES
061000 ROUGH CARPENTRY 8/14/2026
061600 SHEATHING 8/14/2026
062013 EXTERIOR FINISH CARPENTRY 8/14/2026
064116 PLASTIC-LAMINATE-FACED ARCHITECTURAL
CABINETS 8/14/2026
064300 INTERIOR WOOD CARPENTRY 8/14/2026
DIVISION 07 THERMAL AND MOISTURE PROTECTION
SECTION DESCRIPTION
070150.19 PREPARATION FOR REROOFING 8/14/2026
071113 BITUMINOUS DAMPPROOFING 8/14/2026
072100 THERMAL INSULATION 8/14/2026
Roswell Park Comprehensive Cancer Center TABLE OF CONTENTS - Community Outreach and Engagement Center – Phase 2 VOLUME 1
TOC - 3
072715 NONBITUMINOUS SELF-ADHERING SHEET AIR
BARRIERS 8/14/2026
073113 ASPHALT SHINGLES 8/14/2026
074113.16 STANDING-SEAM METAL ROOF PANELS 8/14/2026
074213.23 METAL COMPOSITE MATERIAL WALL PANELS 8/14/2026
074646 FIBER-CEMENT SIDING 8/14/2026
075323 ETHYLENE-PROPYLENE-DIENE-MONOMER (EPDM)
ROOFING 8/14/2026
076200 SHEET METAL FLASHING AND TRIM 8/14/2026
077100 ROOF SPECIALTIES 8/14/2026
077129 MANUFACTURED ROOF EXPANSION JOINTS 8/14/2026
077253 SNOW GUARDS 8/14/2026
078400 FIRESTOPPING 8/14/2026
079200 JOINT SEALANTS 8/14/2026
079219 ACOUSTICAL JOINT SEALANTS 8/14/2026
079513.13 INTERIOR EXPANSION JOINT COVER ASSEMBLIES 8/14/2026
079513.16 EXTERIOR EXPANSION JOINT COVER ASSEMBLIES 8/14/2026
DIVISION 08 OPENINGS
080671 DOOR HARDWARE SCHEDULE 8/14/2026
081113 HOLLOW METAL DOORS AND FRAMES 8/14/2026
081416 FLUSH WOOD DOORS 8/14/2026
081433 STILE AND RAIL WOOD DOORS 8/14/2026
084113 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS 8/14/2026
084413 GLAZED ALUMINUM CURTAIN WALLS 8/14/2026
087100 DOOR HARDWARE 8/14/2026
088000 GLAZING 8/14/2026
DIVISION 09 FINISHES
092216 NON-STRUCTURAL METAL FRAMING 8/14/2026
092900 GYPSUM BOARD 8/14/2026
093013 CERAMIC TILING 8/14/2026
095113 ACOUSTICAL PANEL CEILINGS 8/14/2026
095423 LINEAR METAL CEILINGS 8/14/2026
096513 RESILIENT BASE AND ACCESSORIES 8/14/2026
096519 RESILIENT TILE AND PLANK FLOORING 8/14/2026
096723 RESINOUS FLOORING 8/14/2026
096813 TILE CARPETING 8/14/2026
097200 WALL COVERINGS 8/14/2026
097710 FRAMED DECORATIVE PANEL SYSTEMS 8/14/2026
098433 SOUND-ABSORBING WALL UNITS 8/14/2026
099123 INTERIOR PAINTING 8/14/2026
099300 STAINING AND TRANSPARENT FINISHING 8/14/2026
Roswell Park Comprehensive Cancer Center TABLE OF CONTENTS - Community Outreach and Engagement Center – Phase 2 VOLUME 1
TOC - 4
DIVISION 10 SPECIALTIES
SECTION DESCRIPTION
101423 PANEL SIGNAGE 8/14/2026
102600 WALL PROTECTION 8/14/2026
102800 TOILET, BATH, AND LAUNDRY ACCESSORIES 8/14/2026
104413 FIRE PROTECTION CABINETS 8/14/2026
104416 FIRE EXTINGUISHERS 8/14/2026
DIVISION 12 FURNISHINGS
122413 ROLLER WINDOW SHADES 8/14/2026
123623.13 PLASTIC-LAMINATE-CLAD COUNTERTOPS 8/14/2026
123661.16 SOLID SURFACE COUNTERTOPS 8/14/2026
DIVISION 21 FIRE SUPPRESSION
210500 BASIC FIRE SUPPRESSION REQUIREMENTS 8/14/2026
210523 VALVES 8/14/2026
210553 FIRE PROTECTION IDENTIFICATION 8/14/2026
210554 PAINTING 8/14/2026
211010 PIPING SYSTEMS AND ACCESSORIES 8/14/2026
211020 UNDERGROUND PIPING SYSTEMS AND
ACCESSORIES 8/14/2026
211100 WATER SUPPLY 8/14/2026
211300 FIRE SUPPRESSION SPRINKLER SYSTEM 8/14/2026
DIVISION 22 PLUMBING
220500 BASIC PLUMBING REQUIREMENTS 8/14/2026
220523 VALVES 8/14/2026
220553 PLUMBING IDENTIFICATION 8/14/2026
220580 EXCAVATION AND BACKFILL 8/14/2026
220700 INSULATION 8/14/2026
221010 PIPING SYSTEMS AND ACCESSORIES 8/14/2026
221020 UNDERGROUND PIPING AND ACCESSORIES 8/14/2026
221300 SANITARY WASTE AND STORM DRAINAGE
SYSTEMS 8/14/2026
223010 EQUIPMENT 8/14/2026
223400 WATER HEATERS 8/14/2026
224000 PLUMBING FIXTURES AND TRIM 8/14/2026
227010 NATURAL GAS SYSTEMS 8/14/2026
DIVISION 23 HEATING, VENTILATION AND AIR CONDITIONING
230500 BASIC MECHANICAL REQUIREMENTS 8/14/2026
Roswell Park Comprehensive Cancer Center TABLE OF CONTENTS - Community Outreach and Engagement Center – Phase 2 VOLUME 1
TOC - 5
230504 ELECTRIC WIRING 8/14/2026
230530 ROOF CURBS 8/14/2026
230550 WIND RESTRAINT FOR HVAC SYSTEMS 8/14/2026
230553 MECHANICAL IDENTIFICATION 8/14/2026
230593 TESTING, ADJUSTING AND BALANCING 8/14/2026
230710 INSULATION 8/14/2026 8/28/2026
230923 BUILDING MANAGEMENT SYSTEM - DDC LOGIC 8/14/2026
232010 PIPING SYSTEMS AND ACCESSORIES 8/14/2026
233100 SHEET METAL AND DUCTWORK ACCESSORIES
CONSTRUCTION 8/14/2026
233400 FANS 8/14/2026
233713 REGISTERS AND DIFFUSERS 8/14/2026
233723.16 LOUVERS AND PENTHOUSES 8/14/2026
238129 VARIABLE REFRIGERANT FLOW HVAC SYSTEMS 8/14/2026
238216.10 DUCT COILS ELECTRIC 8/14/2026
238237 ELECTRIC BASEBOARD HEATERS 8/14/2026
238237.10 ELECTRIC RADIANT CEILING PANELS 8/14/2026
238239 UNIT HEATERS AND CABINET UNIT HEATERS -
ELECTRIC 8/14/2026
DIVISION 26 ELECTRICAL
260500 BASIC ELECTRICAL REQUIREMENTS 8/14/2026
260501 BASIC MATERIALS AND METHODS 8/14/2026
260526 GROUNDING 8/14/2026
262000 ELECTRIC DISTRIBUTION 8/14/2026
263213.16 GAS ENGINE DRIVEN GENERATOR SETS 8/14/2026
263600 TRANSFER SWITCHES 8/14/2026
265000 LIGHTING 8/14/2026
265500 LIGHTING CONTROL 8/14/2026
DIVISION 27 COMMUNICATIONS
271500 RACEWAY ROUGH-IN FOR SECURITY SYSTEMS 8/14/2026
272100 LOCAL AREA NETWORK SYSTEM 8/14/2026
DIVISION 28 ELECTRONIC SAFETY AND SECURITY
283102 ANALOG ADDRESSABLE FIRE ALARM SYSTEMS 8/14/2026
DIVISION 31 EARTHWORK
311000 SITE CLEARING 8/14/2026
312000 EARTH MOVING 8/14/2026
312100 EARTH MOVING WITHIN BUILDING 8/14/2026
312500 TEMPORARY EROSION AND SEDIMENT CONTROL 8/14/2026
Roswell Park Comprehensive Cancer Center TABLE OF CONTENTS - Community Outreach and Engagement Center – Phase 2 VOLUME 1
TOC - 6
DIVISION 32 EXTERIOR IMPROVEMENTS
321216 ASPHALT PAVING 8/14/2026
321313 CONCRETE PAVING 8/14/2026
329200 TURF AND GRASSES 8/14/2026
329300 PLANTS 8/14/2026
DIVISION 33 UTILITIES
331415 SITE WATER DISTRIBUTION PIPING 8/14/2026
333115 SITE SANITARY SEWERAGE PIPING 8/14/2026
334200 STORMWATER CONVEYANCE 8/14/2026
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 1
SECTION 019113 - GENERAL COMMISSIONING REQUIREMENTS
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the Contractor, Commissioning Agent, and Owner responsibilities during the commissioning process. Commissioning requires the participation of the Commissioning Team to ensure that all systems are operating in a manner consistent with the intention of the Contract Documents.
B. The commissioning process integrates the traditionally separate functions of system documentation, equipment startup, performance testing and training. Commissioning during the construction phase is intended to achieve the following specific objectives in accordance with the Contract Documents:
1. Verify and document that equipment and systems are installed according to the manufacturer’s recommendations, contract requirements, and industry standards, and that comprehensive operational checkout is conducted by the Contractor;
2. Verify and document correct and adequate performance of equipment and systems;
3. Verify and document that O&M documentation is suitable for long-term ownership of the systems and equipment, and complete;
4. Verify and document that the Owner was trained to operate, maintain, and troubleshoot the installed equipment and systems.
C. The systems and equipment for commissioning are listed in Section 1.02. The Contractor general commissioning requirements and coordination are detailed in Section 1.03. Specific requirements for commissioning each system or piece of equipment are detailed in the associated specification section of the Contract Documents or, in its short form, in Section 1.02 of this document when contract documents do not specify.
D. The commissioning process does not reduce the responsibility of the Contractor to independently provide finished and fully functional systems and equipment.
1.02 SYSTEMS TO BE COMMISSIONED
A. HVAC
1. Variable Refrigerant Flow Split Systems (VRF)
i) Visual and mechanical inspection
(1) Check that all indoor and outdoor units, branch selector boxes, and F-gas logbooks are correctly installed
ii) Pressure test:
(1) Pressurize the system with nitrogen up to manufacturer specifications and hold for 24 hours while adjusting for ambient temperature changes
iii) Deep Evacuation:
(1) Evacuate the system using an appropriately sized vacuum pump to target 250 microns or below to completely remove moisture and air.
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 2
iv) Weigh in extra charge:
(1) Calculate and weigh in any additional liquid refrigerant required based on the liquid line diameter and total pipe length.
v) Open service valves:
(1) Fully open the liquid, gas, and oil-balancing stop valves after charging.
vi) Compressor preheating:
(1) Turn on the main power supply for a minimum of 8 to 12 hours prior to startup to heat the compressor crankcase oil.
vii) Set dip switches:
(1) Configure master and slave outdoor units, communication resistors, and pipe types using the designated DIP switches on the printed circuit board (PCB).
viii) Initiate auto-addressing:
(1) Power on the system and use the push buttons on the outdoor unit main board to launch the automatic commissioning and indoor unit count sequence.
ix) Test run:
(1) Allow the system to run through its automatic cooling and heating test cycles to confirm sensor accuracy, operating frequencies, and error-free communication.
2. Distribution Pumps
i) Pump discharge pressure measured and documented across operating range;
ii) Pump distribution flow measured and documented across operating range;
iii) Pump and motor characteristics measured and documented across intended operating range;
3. Ductwork Distribution System
i) Leakage rate measured and documented across operating range;
ii) Ducts not supporting other components;
iii) Duct labeling;
4. Testing, Adjusting and Balancing (TAB)
i) See Sections A.1 through 8 for TAB items;
ii) TAB report is comprehensive and complete and includes pressure relationship diagram, final balance values within tolerance; floor plan with values overlaid, where practical;
iii) Completion of TAB reports and evidence of approval by Engineer of Record;
5. Building Management System
i) Graphical user interface (GUI) graphics screens are updated to reflect new conditions including fire and smoke response;
ii) GUI graphics and “tree” reflect that BMS recognizes new conditions and updates fields as conditions change;
iii) GUI graphics are consistent with current practice;
iv) Field-reported (sensor) values are sensible and accurate;
v) Sequence of operation correctly reflects operational needs of space;
(1) Failure position of equipment;
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 3
(2) Recovery after power failure;
(3) Emergency power transfer and restoration continuity of operation;
(4) Smoke control system correctly operates within zone and relative to adjoining zones;
(5) Air handling and exhaust equipment responds correctly to fire condition both “in” and “out” of zone;
(6) Air handling and exhaust equipment correctly operates in economizer mode;
(7) Air handling and exhaust equipment responds correctly to loss of steam;
(8) Alarms have been prioritized and are received/distributed;
6. Plumbing
i) Potable Hot Water (PHW) System
(1) Device and piping labeling;
ii) Potable Cold Water (PCW) System
(1) Piping labeling;
iii) Sanitary Waster System
(1) Sanitary waste pipe pressure and leak test report;
(2) Piping labeling;
7. Electrical
i) Electrical Distribution
(1) Exit lighting operation verified and documented;
(2) Emergency lighting operation verified and documented;
(3) Panel directories verified and documented;
(4) Ground Fault Circuit Interrupter Circuits on critical power verified and documented;
(5) Receptacle tension, voltage, polarity, grounding verified and documented critical power verified and documented;
ii) General Electrical
(1) Device labeling
iii) Variable Speed Drives
8. Quantities and Spot-Checking
i) Rooms without a required pressure relationship
(1) Spot-check TAB;
(2) 25% direct observation of sequence of operation through normal and failure modes;
ii) Distribution Pumps
(1) Each.
iii) Exhaust Fans
(1) Each.
iv) Ductwork Distribution
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 4
(1) Spot-check, no less than 25% of total installed length.
v) Heating Hot Water Piping
(1) Spot-check, no less than 25% of total installed length.
(2) Directly observe loop water balance at main balance valve.
vi) Building Management System
(1) Air handling unit screens;
(2) Exhaust fan screens.
vii) Electrical Distribution
(1) All.
viii) Lighting
(1) 25% occupancy sensors.
ix) Labeling
(1) 25% labeled devices.
B. Example Commissioning Documents: Example Pre-Functional Checklists and Functional Test Procedures are provided following the specification sections of equipment and systems that require commissioning. These documents are included to provide the Contractor examples of the type of documentation that will be required as part of the commissioning process.
Equipment and system specific Pre-Functional Checklists and Functional Test procedures shall developed by the Commissioning Authority based on approved submittals, and then will be provided to the Contractor.
1.03 DEFINITIONS
A. Acceptance Phase: Phase of construction after startup and initial checkout when functional performance tests, O&M documentation collection and review, and training occurs.
B. Approval: Acceptance that a piece of equipment or system has been properly installed and is functioning in the tested modes in accordance with the Contract Documents.
C. Commissioning Authority (CA): An independent agent, reporting to the Owner, responsible for the direction, coordination, and documentation of the commissioning activities.
D. Commissioning Plan (CP): The overall plan comprising finite commissioning tasks that defines the structure, tasks, schedule, and coordination planning for the commissioning process. The CP provides guidance for the execution of the commissioning process. Following the initial commissioning scoping meeting the CA will update the plan which is then considered the “final” plan, although it may be revised as the project progresses.
E. Commissioning Team (CT): The Commissioning Team comprises the Owner, CA, Contractor, and the Architect and Engineer of Record. The Owner is the final authority on matters relating to the commissioning process.
F. Communication Plan: The plan developed by CT outlining the methods, modes, and routes of communications for transmitting CP information among the CT.
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 5
G Deferred Functional Tests: Functional tests that are performed after substantial completion, due to partial occupancy, seasonal requirements, design, or other site conditions that prevent the test from being performed prior to substantial completion.
H. Deficiency: A condition of installation, manufacture, or function of a component, piece of equipment, or system that is not in compliance with the Contract Documents or CP; An observable or measured difference between specified and observed performance.
I. Factory Testing: Testing and verification of equipment performance on-site or at the factory by or under the direction of factory personnel.
J. Functional Performance Test (FT): Test of the dynamic function and full operation of equipment and systems using manual (direct observation) or monitoring methods. Systems are tested under various modes including, but not limited to, low cooling or heating loads, peak load, component failure, unoccupied, varying outside air temperatures, fire alarm, power failure, etc. The CA develops the functional test procedures in sequential written form. The CA coordinates, oversees and documents the actual testing. The Contractor performs the functional tests. FTs are performed after prefunctional checklists and startup are complete.
K. Manufacturer’s Representative: The factory-authorized representative that is licensed or otherwise certified by the equipment manufacturer to direct installation, start-up, troubleshoot equipment issues, and represent the equipment or component manufacturer on operational or warranty matters.
L. Operations and Maintenance Documentation (O&M): Electronic and/or bound documentation that explicitly states or illustrates detailed information relating to the specific system, equipment, or component capacity, installation, start-up, factory and field check-out, operation, maintenance, troubleshooting, spare parts, warranty, Manufacturer’s Representative contact, sequence of operation, and other information pertinent to the safe and correct operation and maintenance of installed systems.
M. Owner: Roswell Park Cancer Institute and its authorized representatives.
N. Phased Commissioning: Commissioning that is completed in phases because of project schedule or size, or Owner operational requirements. Commissioning shall be provided for each phase according to the schedule for that phase. Some repetition and/or remobilization may be required.
O. Prefunctional Checklist (PC): A list of items to inspect and component tests to conduct to verify proper installation of equipment prior to initiating functional testing.
P. Startup: The initial starting or activating of dynamic equipment including executing prefunctional checklists.
Q. Turnover: The state of equipment and systems at which the operation and maintenance, exclusive or warranty claims, is committed to Owner. This state is achieved after CA has determined that the equipment and systems are compliant with the CP.
1.04 COORDINATION
A. The CT develops the Communication Plan and the CA is responsible to direct and coordinate the CP. Coordination includes the determination, availability, and final scheduling of
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 6 commissioning and training activities and participants of the CT. All members of the commissioning team shall work together to fulfill their contractual responsibilities and meet the objectives of the Contract Documents.
B. The CA shall communicate the Commissioning Plan to CT, according to the Communication
Plan, to schedule the commissioning activities. The Contractor shall integrate all commissioning activities into the approved progress schedule. All parties will address scheduling problems and make necessary notifications and changes in a timely manner in order to expedite the commissioning process and maintain the approved progress schedule.
1.05 COMMISSIONING PROCESS
A. Commissioning Process. The following narrative provides an overview of the typical commissioning tasks during construction and the general order in which they occur. A more detailed description of the commissioning process can be found in the Appendix.
1. Scoping meeting conducted by the CA wherein the commissioning process and schedule is initially developed with the CT.
2. Routine commissioning meetings will be scheduled, when possible, to begin at the end of some number of construction meetings.
3. O&M is submitted to the CA, according to the Communication Plan, during the submittal process.
4. Startup and activity lists and startup documentation is developed by the CT. The CA provides prefunctional checklists to be completed by the Contractor during the startup process. Checkout and performance verification proceeds from simple to complex;
from component level to equipment to systems and intersystem levels. In each case prefunctional checklists are completed, submitted, and approved before functional testing begins.
6. CA documents that the checklists and startup were completed according to the approved plans and refers deficiencies for correction according to the Communication Plan.
7. CA develops specific equipment and system functional performance test procedures.
Contractor reviews the procedures and submits suggestions or comments. Procedures are finalized by the CA.
8. Functional Performance Tests are performed by the Contractor, under the direction of the CA.
9. Identified deficiencies of material, workmanship, installation are documented by CA and corrected and retested at Contractor expense. Contractor is responsible for providing all resources, manpower, and materials necessary to rectify deficiencies as per requirements of the approved schedule.
10. The O&M documentation prepared by the Contractor is reviewed for completeness by the CA.
11. Commissioning is completed before Substantial Completion.
12. Formally declares Turnover.
13. The CA reviews, pre-approves and coordinates the training provided by the Contractor and verifies completion of same.
14. Deferred testing is conducted as specified or required.
1.06 CONTRACTOR’S RESPONSIBILITIES
A. Contractor commissioning responsibilities are as follows (all references apply to commissioned systems and equipment only):
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 7
1. Construction and Acceptance Phase:
a. Attend the commissioning scoping meeting and other meetings scheduled by the CA in support of the CP.
b. Facilitate and abide the CP activities and schedule.
c. Submit OEM to the CA. The CA may request additional documentation necessary in support of the commissioning process.
d. Ensure that all subcontractors conform to the OEM submittal requirements and
CP requirements.
e. Assist with writing commissioning test procedures.
g. Review test procedures to ensure feasibility, safety, and equipment protection, and provide necessary written alarm limits to be used during the tests.
h. Develop a full start-up and testing plan using manufacturer’s start-up procedures and the prefunctional checklists from the CA for all commissioned equipment. Submit to the CA for review and approval prior to startup.
i. During the startup and initial checkout process, execute all portions of the prefunctional checklists for all commissioned systems and equipment. Verify that system installation includes all ports, gages, thermometers, access doors, valves, etc., required for specified functional performance testing.
j. Provide all special (peculiar to the equipment manufacturer) tools and instruments required to achieve CP results.
k. Perform, document, and communicate all completed startup and system operational checkout procedures, to the satisfaction of the CA.
l. Complete Work of the Contract on equipment or system before functional performance testing.
m. Provide skilled technicians in accordance with the needs of the CP.
n. Correct Deficiencies.
o. Prepare O&M manuals according to the Contract Documents. Provide a copy of the O&M manuals and submittals of commissioned equipment to the CA for review and approval including clarifying and updating the original sequences of operation to as-built conditions.
p. Provide training as specified.
q. Facilitates transition to Turnover.
r. Conducts deferred testing.
2. Warranty Period:
a. Correct deficiencies and make necessary adjustments to O&M manuals and as-built drawings for applicable issues identified in any deferred testing.
PART 2 - PRODUCTS
2.01 TEST EQUIPMENT
A. All standard testing equipment required to perform startup and initial checkout and required functional performance testing shall be provided by the Contractor.
B. Special equipment, tools and instruments (only available from vendor, specific to a piece of equipment) required for testing equipment shall be provided by the Contractor and relinquished to Owner at Turnover.
C. Data logging equipment and software required to test equipment shall be provided by the
Contractor but shall not become the property of the Owner’s Representative.
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 8
D. All testing equipment shall be of sufficient quality and accuracy to test and/or measure system performance within the tolerances specified in the Specifications. All equipment shall be calibrated according to the manufacturer’s recommended intervals. Calibration tags shall be affixed or certificates readily available for inspection.
PART 3 - EXECUTION
3.01 MEETINGS
A. Scoping Meeting. Prior to the commencement of construction, the CA will schedule, plan and conduct a commissioning scoping meeting with the Commissioning Team.
B. Miscellaneous Meetings. Other meetings will be planned and conducted by the CA as construction progresses. The scope of these meetings include coordination, deficiency resolution, and planning issues with the Contractor, sub-contractors, suppliers, and Owner.
3.02 START-UP, PREFUNCTIONAL CHECKLISTS, AND INITIAL CHECKOUT
A. Prefunctional checklists and initial checkout shall ensure that the equipment and systems are installed and operational. Each system identified in 1.02 A.1. receives full prefunctional checkout. No sampling strategies are used. The prefunctional testing for a given system must be successfully completed prior to formal functional performance testing of systems or equipment.
B. Start-up and Initial Checkout Plan. The CA shall assist the commissioning team members responsible for startup of any equipment in developing detailed start-up plans for all equipment.
The primary role of the CA in this process is to ensure that there is written documentation that each of the manufacturer’s recommended procedures have been completed.
C. Execution of Prefunctional Checklists and Startup.
1. Expected at least four (4) weeks prior to startup; the CA shall coordinate startup and checkout with the Owner.
2. The Contractor shall execute startup and provide the CA with a signed and dated copy of the completed start-up and prefunctional tests and checklists.
3.03 FUNCTIONAL PERFORMANCE TESTING
A. Development of Test Procedures. Using the requirements in the specifications and recommended industry practiced as approved by Owner, the CA shall develop specific test procedures and forms to verify and document proper operation of each piece of equipment and system. The Contractor shall provide assistance to the CA in developing the procedures. Prior to testing, the CA shall provide a copy of the test procedures to the Contractor who shall review the tests for feasibility, safety, equipment and warranty protection.
B. Functional performance testing shall document that each system is operating in accordance with the Contract Documents and manufacturer’s requirements. During the testing process, Deficiencies shall be identified and documented. Deficiencies shall be corrected by the Contractor and functional testing shall be re-scheduled. The Contractor shall be responsible for all costs associated with re-testing for functional performance.
C. Each system shall be operated through all modes of operation. Responses reflective of correct operation that preserves and protects life and limb, safety and security, and space and plant
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 9 integrity are considered proper and acceptable. Proper responses to modes and conditions such as power failure, freezing, high/low/no flow, component or equipment failure, damper position, fire alarm, etc. shall also be tested.
D. Test Methods. Each functional test shall be performed under real or simulated conditions. The
Contractor shall execute the test and shall provide all necessary materials, system modifications, etc. to produce the necessary flows, pressures, temperatures, etc. necessary to execute the test according to the specified conditions. At the completion of the test, the Contractor shall return all building equipment and systems affected by these temporary modifications a condition specified by the CA.
3.04 OPERATION AND MAINTENANCE MANUALS
A. The specific content and format requirements for the standard O&M manuals are detailed in Section 017823.
B. The CA shall compile and prepare commissioning documentation for all equipment and systems and transmit according to the Communication Plan for inclusion in the O&M manuals.
C. Warranty documentation shall be compiled and transmitted according to the Communication
Plan separately from the other training requirements.
D. Recommended spare parts list shall be compiled and transmitted according to the
Communication Plan separately from the other training requirements.
3.05 TRAINING
A. The Contractor is responsible to:
1. Develop an overall training plan that includes a basic curriculum and schedule of training events.
2. Training events shall be scheduled with Owner two weeks in advance of each training event.
3. Training events comprise a “classroom” session and a site visit to each piece of equipment.
4. Provide training to a 9th grade understanding of the systems and the operation and maintenance of each piece of equipment. The training events shall follow the outline in the Table of Contents of the O&M when possible.
a. Use the printed installation, operation, and maintenance instruction material included in the O&M manuals emphasizing;
i). safe, proper operation;
ii) preventative maintenance;
iii) required tools;
iv) start-up, operation, shut-down, and emergency procedures;
v) relevant health and safety issues and concerns.
vi) common troubleshooting problems and solutions;
vii) discussion of any peculiarities of equipment installation or operation.
3.06 DEFERRED TESTING
A. Unforeseen Deferred Tests. If any check or test cannot be completed due to project conditions, Owner requirement, or other deficiency, execution of checklists and functional testing may be
Roswell Park Comprehensive Cancer Center GENERAL COMMISSIONING Community Outreach and Engagement Center – Phase II REQUIREMENTS 019113 - 10 delayed upon approval of the Owner. These tests will be conducted in the same manner as the seasonal tests as soon as possible.
B. Seasonal Testing. Seasonal testing (tests delayed until weather conditions are closer to the system design conditions) shall be completed as part of this contract. Make any final adjustments to the O&M manuals and as-builts resulting from information gained during testing.
END OF SECTION 019113
INSULATION
230710 - 1
SECTION 230710 - INSULATION
PART 1 - GENERAL
1.1 WORK INCLUDED
A. Provide labor, materials, equipment and services to perform operations required for the complete installation and related Work as required in Contract Documents.
1.2 SUBMITTAL
A. Submit product data, product description, manufacturer's installation instructions.
B. Submit schedule of types and thicknesses for each application, and location of materials.
1.3 RELATED WORK SPECIFIED ELSEWHERE
A. Section 232010 - Piping Systems and Accessories.
B. Section 233100 - Sheet Metal and Ductwork Accessories Construction.
PART 2 - PRODUCTS
2.1 GENERAL
A. See Exhibits at the end of this section for where insulating materials shall be applied, thickness, jacketing and remarks.
B. Provide work in compliance with the following Codes and Standards based on the current edition in effect at project location:
1. Energy Conservation Code of New York State.
C. Insulation, jackets, adhesive, and coatings shall comply with the following:
1. Products shall not contain asbestos, lead, mercury, or mercury compounds.
2. Insulation, including jackets, finishes and adhesives on the exterior surfaces of ducts, pipes, and equipment, shall have a flame spread rating of 25 or less and a smoke developed rating of 50 or less, when tested in accordance with ASTM E84 or UL 723.
a. Plenums: Insulation materials shall be noncombustible or listed and labeled per ASTM E84 or UL 723.
b. Treatment of jackets or facing for flame and smoke safety must be permanent. Water-soluble treatments are not permitted.
3. All adhesives, coatings and sealants used for insulation in the interior of the building shall comply with the maximum Volatile Organic Compound (VOC) limits as called for in the current version of U.S. Green Building Council LEED
Credits EQ 4.1 and EQ 4.2.
Roswell Park Comprehensive Cancer Center Community Outreach & Engagement Center - Phase II
August 28, 2026 Addendum 1 dated 9/2/26
230710 - 2
4. Provide materials which are the standard products of manufacturers regularly engaged in the manufacture of such products and that essentially duplicate items that have been in satisfactory use for at least two (2) years prior to bid opening.
Provide insulation systems in accordance with the approved MICA or NAIMA
Insulation Standards.
5. Insulation shall be clearly marked with manufacturer's name, identification of installed thermal resistance (R) value, out-of-package R value, flame spread and smoke developed indexes in accordance with Energy Code requirements.
6. Products that come into contact with stainless steel shall have a leachable chloride content of less than 50 ppm when tested in accordance with ASTM C
871.
7. Insulation materials for use on austenitic stainless steel shall be qualified as acceptable in accordance with ASTM C 795.
2.2 ACCEPTABLE MANUFACTURERS
A. Flexible Elastomeric: Armacell AP ArmaFlex/FS (Indoor: AP ArmaFlex up to 1”, FS 1-
1/2” to 2”; Outdoor: All sizes), Aeroflex (Indoors/Outdoors: All sizes), K-Flex Insul-
Lock (Indoors: All sizes), or approved equal.
B. Fiberglass: Johns Manville, Knauf/Manson, Owen-Corning, or approved equal.
C. Jacketing: Johns Manville (PVC, Aluminum), Polyguard Pro (Alumaguard), or approved equal.
D. Adhesives, Coatings, Mastics, Sealants: Childers, Foster, or approved equal.
2.2 FLEXIBLE ELASTOMERIC
A. Closed-cellular, sponge or expanded-rubber with integral vapor barrier.
B. Tube and Sheet:
1. Product meeting ASTM C 534, Type I/II Grade 1.
2. 'K' Value at 75°F mean temperature
a. 0.245 BTU-in/ft2 hr. °F (up to 1 in. wall thickness).
b. 0.28 BTU-in/ft2 hr. °F (1-1/2 in. to 2 in. wall thickness).
C. Sheet:
1. Density: As required to meet specified R-value in Exhibit, unless otherwise noted.
2.3 FLEXIBLE FIBERGLASS
A. Glass fibers bonded with a resin.
Roswell Park Comprehensive Cancer Center Community Outreach & Engagement Center - Phase II
230710 - 3
B. Blanket:
1. Product meeting ASTM C 553 Types I, II and III, and ASTM C 1290;
Greenguard compliant.
2. 'K' Value: 0.27 BTU-in/ft2 hr. °F at 75°F mean temperature.
3. Maximum Service Temperature (Faced): 250°F.
4. Vapor Retarder Jacket: FSK conforming to ASTM C 1136 Type II. Vapor retarder having a maximum permeance of 0.05 perm or aluminum foil having a minimum thickness of 2 mils. Joints and seams shall be sealed to maintain the continuity of the vapor retarder.
5. Density: As required to meet specified R-value in Exhibit, unless otherwise noted.
2.4 RIGID FIBERGLASS
A. Pre-formed glass fibers bonded with a thermosetting resin.
B. Board:
1. Product meeting ASTM C 612 Type IA and IB. Maximum Service Temperature:
450º F.
2. 'K' Value: 0.24 BTU-in/ft2 hr. °F at 75°F mean temperature.
3. Vapor Retarder Jacket:
a. ASJ conforming to ASTM C 1136 Type I
b. FSK or PSK conforming to ASTM C 1136 Type II.
4. Density: As required to meet specified R-value in Exhibit, unless otherwise noted.
2.5 FIELD APPLIED JACKETS
A. PVC: High-impact UV resistant PVC; roll stock ready for shop or field cutting and forming.
1. Thickness: 30 mil.
2. PVC Jacket Color: White.
2.6 ADHESIVES, COATINGS, MASTICS, SEALANTS
A. Provide per manufacturer product requirements for associated system and application/installation location.
Roswell Park Comprehensive Cancer Center Community Outreach & Engagement Center - Phase II
230710 - 4
B. Tapes and mastics used to seal metallic and flexible air ducts and flexible air connectors shall comply with UL 181B and shall be marked “181 B-FX” for pressure sensitive tape, or “181 B-M” for mastic.
PART 3 - EXECUTION
3.1 GENERAL REQUIREMENTS
A. All materials shall be installed by skilled labor regularly engaged in this type of work and installed in strict accordance with manufacturer's recommendations, building codes, and industry standards. Install insulation materials, forms, vapor barriers or retarders, jackets, and of thicknesses required for each item of pipe system per manufacturer requirements.
Apply adhesives, mastics, and sealants at manufacturer's recommended coverage rate and wet and dry film thicknesses.
B. Locate insulation and cover seams in the least visible location. All surface finishes shall be extended in such a manner as to protect all raw edges, ends and surfaces of insulation.
No glass fibers shall be exposed to the air. Install insulation with longitudinal seams at top and bottom of horizontal runs. Install multiple layers of insulation with longitudinal and end seams staggered and with the least number of joints possible.
C. All pipe and duct insulation shall be continuous through hangers.
D. Provide thermal insulation on clean, dry surfaces and after piping, ductwork and equipment (as applicable) have been tested. Do not cover pipe joints with insulation until required tests are completed.
E. All cold surfaces that may "sweat" must be insulated. Vapor barrier must be maintained;
insulation shall be applied with a continuous, unbroken moisture and vapor seal. All hangers, supports, anchors, or other projections that are secured to cold surfaces shall be insulated and vapor sealed to prevent condensation.
F. Items such as boiler manholes, handholds, clean-outs, ASME stamp, and manufacturers' nameplates, may be left uninsulated unless omitting insulation would cause a condensation problem. When such is the case, appropriate tagging shall be provided to identify the presence of these items. Provide neatly beveled edges at interruptions of insulation.
G. Provide protective insulation as required to prevent personnel injury: Piping from zero to seven feet above all floors and access platforms including hot (above 140°F) piping and any other related hot surface.
H. If any insulation material has become wet because of transit or job site exposure to moisture or water, the contractor shall not install such material, and shall remove it from the job site.
I. Do not weld brackets, clips, or other attachment devices to piping, fittings, and specialties.
Roswell Park Comprehensive Cancer Center Community Outreach & Engagement Center - Phase II
230710 - 5
J. Finish installation with systems at operating conditions. Repair joint separations and cracking due to thermal movement. Repair damaged insulation facings by applying same facing material over damaged areas. Extend patches at least 4 inches beyond damaged areas. Adhere, staple, and seal patches in similar fashion to butt joints.
K. For above-ambient services, do not install insulation to the following:
1. Vibration-control devices.
2. Testing agency labels and stamps.
3. Nameplates and data plates.
3.2 PENETRATIONS
A. Aboveground Exterior Wall and Roof Penetrations: Install insulation continuously through penetrations.
1. Seal penetrations with flashing sealant.
2. For applications requiring only indoor insulation, terminate insulation above through surface and seal with joint sealant. For applications requiring indoor and outdoor insulation, install insulation for outdoor applications tightly joined to indoor insulation ends. Seal joint with joint sealant.
3. Extend jacket of outdoor insulation outside wall/roof flashing at least 2-in.
beyond flashing. Seal jacket to flashing with flashing sealant per roofing manufacturer requirements.
B. Underground Exterior Wall Penetrations: Terminate insulation flush with sleeve seal.
Seal terminations with flashing sealant.
C. Interior Floor, Wall and Partition Penetrations (That Are Not Fire Rated): Install insulation continuously through walls and partitions.
D. Fire-Rated Floor, Wall and Partition Penetrations: Install insulation continuously through penetrations of fire-rated walls and partitions.
1. Comply with requirements in Section 078413 "Penetration Firestopping" for firestopping and fire-resistive joint sealers.
3.3 PIPE INSULATION
A. All pipes shall be individually insulated. Cover valves, fittings and similar items in each piping system with insulation as applied to adjoining pipe run. Extra care must be taken on piping appurtenances to insure a tight fit to the piping system.
B. Piping insulation is allowed to be reduced in thickness only when a specific UL assembly detail for piping passing thru a rated wall indicates a maximum insulation thickness that is less than this specification section calls for. In this case reduce the insulation thickness just for the rated wall penetration. The reduction of insulation thickness shall be limited to the length of the penetration only.
Roswell Park Comprehensive Cancer Center Community Outreach & Engagement Center - Phase II
230710 - 6
C. Coordinate insulation installation requirements for heat tracing that may apply.
3.4 DUCTWORK INSULATION
A. Provide external thermal insulation for ductwork. Not required where ducts have internal acoustical insulation. Make special provisions at dampers, damper motors, thermometers, instruments, and access doors.
B. Provide factory ASJ jacket for ductwork required to be insulated and to be painted.
3.5 EQUIPMENT INSULATION
A. Apply insulation with joints firmly butted as close as possible to the equipment surface.
3.6 EXISTING INSULATION
A. Patch existing insulation damaged during the course of the work.
B. Insulate existing piping, ductwork, and equipment as called for.
Roswell Park Comprehensive Cancer Center Community Outreach & Engagement Center - Phase II
230710 - 7
EXHIBIT "I”
SERVICE INSULATION
MATERIAL
THICKNESS REMARKS
Refrigeration
Liquid Line
Piping (Heating or cooling mode;
temperature up to
140°F)
Flexible Elastomeric 1-1/2 in. and Larger: 1-1/2 in.
1-1/4 in. and Smaller: 1 in.
Concealed AC unit condensate drains
Flexible Elastomeric All Sizes: 1/2 in.
NOTES FOR EXHIBIT "I":
NOTE 1: For refrigeration piping services smaller than 1-1/2 in. and located in wall partitions within conditioned spaces, reduction of these thicknesses by 1 in. shall be permitted but not to a thickness less than 1 in.
NOTE 2: Piping in exterior walls, spaces, overhangs, attics, or where subject to freezing shall be insulated with double the thickness called for the associated service.
NOTE 3: All interior exposed piping, valves, fittings, and specialties less than 8'-0" above finished floor in mechanical/electrical rooms, penthouses, and services aisles/pipe chases shall be jacketed with PVC.
NOTE 4: All exterior piping shall be jacketed with PVC.
Roswell Park Comprehensive Cancer Center Community Outreach & Engagement Center - Phase II
230710 - 8
EXHIBIT "II" - DUCT INSULATION MATERIALS
SERVICE INSULATION
MATERIAL
THICKNESS REMARKS
Supply (concealed) Flexible Fiberglass 2 in. Min. installed
R value of 6
Supply (within mechanical rooms or exposed at 8'-0" or less above finished floor)
Rigid Fiberglass 1-1/2 in. Min. installed
R value of 6
Supply (exposed within the conditioned space served)
Not insulated Not insulated Does not include the associated supply ductwork within the
Mechanical Room or supply duct to the conditioned space.
Outside air ducts Rigid Fiberglass 2 in. Min. installed
R value of 8 12.
Return and exhaust within heated building envelope
Not insulated Not insulated
Exhaust, relief or vent ducts and plenums (concealed)
Flexible Fiberglass 2 in. Min. installed
R value of 6
Insulate ducts 15 ft.
from exterior opening and plenums.
END OF SECTION 230710
Roswell Park Comprehensive Cancer Center Community Outreach & Engagement Center - Phase II
SCALE: 1/4" = 1'-0"1 IRRIGATION SCOPE PLAN
EXPIRATION DATE:
BUFFALO OFFICE
50 ELK ST. STE 200
BUFFALO, NY 14210
FAX: 716.842.1807
ROCHESTER OFFICE
85 ALLEN ST. STE 310
ROCHESTER,NY 14608
FAX: 585.461.4771
PHONE: 716.842.1800
WWW.YOUNGAN…