This document is an addendum to Request for Proposal (RFP) 25-19 issued by the Massachusetts Bay Transportation Authority (MBTA) for the procurement of Wheel Scanning Measurement Devices. The addendum provides clarifications and revisions to the RFP and technical specifications, including the deletion of the requirement to detect flat spots and the change to the schedule of payment for maintenance and warranty work. The RFP calendar is also updated, with the deadline for submission of proposer questions moved to March 6, 2018, and the date for publishing official answers moved to March 11, 2018. The response due date remains March 14, 2018, with estimated dates for in-person presentations, contract execution, and service start.

The addendum also notes that the liquidated damages section has been deleted in its entirety. The MBTA is seeking to procure two Wheel Measurement Systems to be installed at its maintenance facility yards, which will enable rail vehicle maintenance to monitor and schedule wheel sets for wheel trueing and replacement.

View the file

Other files

File Type Posted
Prompt Payment Discount Form - Wheel Scanner Measurement System.doc DOC document
25-19 Addendum No. 2.dotx DOTX file
RFP No. 25-19 - Figure 3.jpg JPG image
Figure 3.JPG JPG image
RFP No. 25-19 Work Scope Attachment 1B.pdf PDF
RFP No. 25-19 Wheel Scanner II.doc.docx DOCX document
RFP No. 25-19 Figure 4.jpg JPG image
Addendum No. 3 - Scanner.dotx DOTX file
RFP No. 25-19 Work Scope Attachment 1A.pdf PDF
RFP 25-19 Addendum No. 5.docx DOCX document
RFP No. 25-19 Work Scope Attachment 1C.pdf PDF
RFP No. 25-19 Work Scope EEQA897.docx DOCX document
25-19 W-9 Request for Taxpayer ID number and Certification.pdf PDF
RFP 25-19 Addendum No. 6.docx DOCX document
RFP No. 25-19 - Addendum No. 1 02-15-19.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MBTA Logo, Charles D. Baker, Governor, Karyn E. Polito, Lieutenant Governor, Stephanie Pollack, MassDOT Secretary & CEO, Luis Manuel Ramírez, General Manager & CEO, MassDOT logo

March 8, 2019

SUBJECT: RFP 25-19 Procurement for Wheel Scanning Measurement Devices

Addendum No. 4

Dear Bidders:

Please be advised that the above has been amended and/or clarified as shown on the attached that is made a part of herein.

Acknowledgment of this Addendum must be so noted on your proposal submittal.

ALL ELSE REMAINS AS PREVIOUSLY STATED.

Sincerely,

Joe Flynn
Sourcing Executive

Attachments

CLARIFICATIONS AND REVISIONS TO RFP & SPECIFICATIONS

Scope of Work – Technical Specification EE&QA-897 Section 3.1 General Requirements, bullet j, page 5 To further clarify from Addendum No. 3, Wheel Profile systems do not measure weight of passing vehicles; please delete this this requirement.

In the Scope of Works Page 5 Section 3.1 General Requirements bullet (j) there is a requirement for detecting imperfections and flat spots. Please delete the requirement for detecting flat spots from the specification, as our understanding is that detecting flat spots requires a separate system and we are looking for the wheel profile.

Section 6.1.3, Schedule of Payment, page 14

For the last item on the Schedule of Payment, the cumulative amount of 10% for Maintenance/Warranty work and support, will be broken down into 4 equal, separate, sequential payments, in a chronological manner, for the remainder of the contract on an annual basis instead of cumulatively at the end of the fifth year of the Contract. It shall read as follows:

“2.5% Maintenance/Warranty
2.5% Maintenance/Warranty
2.5% Maintenance/Warranty
2.5%Maintenance/Warranty

Cumulative 100% Total for milestones”

RFP 25-19

Section 3.2.3 Project Schedule, page 7

Please change the date in the row that reads “Official Answers for Bid Q&A published by MBTA on COMMBUYS” to the date listed in the Table below.

TABLE: RFP CALENDAR

Procurement Activity
Date
Time
RFP issued
2/12/2019
Pre-bid conference
2/19/201911:00 a.m.

Site Visit – Upon Request

Deadline for submission of Proposer questions via COMMBUYS
3/6/20184:00 p.m.
Official Answers for Bid Q&A published by MBTA on COMMBUYS
3/11/20184:00 p.m.
Response Due Date
3/14/20182:00 p.m.
In-person presentations at MBTA (estimated)
3/21/2018
Contract Execution (estimated)
3/29/2018
Service Start Date (estimated)
4/5/2018

Section 8.1.18.3, Liquidated Damages Please delete this section in its entirety.

All Else Remains as Previously Stated