RFP 22-028 Low-No DW Charging Infrastructure Construction - Addendum 2 with Exhibits - Final.pdf

PDF 15 MB Posted

Attached to
RFP 22-028 Low-No Del Webb Charging Infrastructure Construction
Solicitation number
S-KS2410-00004084
Issued by
Marion County, Oregon

About this file

This document is an Addendum to Request for Proposal (RFP) 22-028 issued by the Salem Area Mass Transit District (SAMTD) for the construction of Low-No Del Webb Charging Infrastructure. The addendum provides additional information and clarification regarding the scope of work, which includes the installation of new electrical service, BEB charging equipment, underground electrical infrastructure, demolition, excavation, concrete work, site testing, and commissioning support. The RFP solicits proposals for these construction services to support SAMTD's Battery Electric Bus (BEB) program. The RFP closing date is October 31, 2022, and the anticipated award date is November 30, 2022.

The addendum also includes exhibits that provide further details on the project, such as site plans and electrical one-line diagrams. Pricing terms, set-asides, and funding information are not explicitly stated in the provided documents. However, the RFP indicates that this project is funded through the Federal Transit Administration's Low or No Emission Vehicle Program, which provides funding for the acquisition or leasing of zero-emission and low-emission transit buses, including the requisite charging infrastructure.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 22-028 – Addendum #2

SALEM AREA MASS TRANSIT DISTRICT

REQUEST FOR PROPOSALS

RFP 22-028

LOW-NO DEL WEBB CHARGING INFRASTRUCTURE

CONSTRUCTION

ADDENDUM #2

Salem Area Mass Transit District is providing information and making changes / additions / modifications / revisions as an Addendum to RFP 22-028.

The following changes, clarifications and SAMTD responses to questions posed to date are hereby provided to all proposers:

1. Question: Please provide the specifications & instructions to install of the ChargePoint Charging Station and Power Block. This information will be very helpful for value engineering of the project.

Response: Attached to this Addendum #2 please find Exhibit D – ChargePoint Data Sheet, Exhibit E – ChargePoint Installation Guide, and Exhibit F – ChargePoint Site Design Guide.

2. Question: Is the charging equipment already purchased? In other words, is this bid for construction only? Or will the contractor be responsible for furnishing the charging stations as well?

Response: The charging equipment has already been placed on order under a separate procurement. The current solicitation identifies the scope of services to be performed in Part 2 of the solicitation instructions for the installation and construction services.

3. Question: Does the submittal of the proposal have to be by sealed envelope and electronic, both?

Response: No, it can be either form. We will accept PDF, or Word format; however, if you deliver hard copies of your proposal, also submit a thumb drive with all electronic files available.

4. Question: The Solicitation requests a 2 year audited financial statement; will you accept a compiled CPA statement?

Response: Yes, we will accept a compiled CPA statement; we will not accept a stand-alone tax return. We’re looking for financial ability for the successful proposer to be able to complete performance of a resulting contract.

5. Question: The Statement of Work indicates 12 charging stations, and then sub out to power block 7; are you forecasting installation of more transformers?

Response: No. The current chargers can handle approx. up to 30 buses, in varying states of charging. We are also looking into supplemental software to support future efforts and needs.

6. Question: Can we get a copy of the spec sheet for the ChargePoint chargers?

Response: Yes, please see Exhibit D to this Addendum.

7. Question: Is it OK to use cones and construction tape around the excavation area for safety purposes?

Response: The surrounding space available where the construction will be has adequate space for safety. It is expected that the proposer will cordon off the site under construction.

Cones and construction tape are acceptable.

8. Question: Is this OregonBuys on-line bid form obsolete?

Response: The page printed from the OregonBuys site is not the solicitation price sheet.

Please see Exhibit 13 Price Proposal Form as it is identified as the formal price form for the solicitation.

9. Question: What is the depth and size of the sewage drain?

Response: Please see Exhibit C for photos and depth measurements of the drains.

10. Question: On the construction drawing (C.30), it’s indicated to demolish the southern curb, and part of the concrete, drawing designed as is – contractor states it’s likely not necessary to do so. Is the design to move the concrete sidewalk? Do we have to price as per proposed?

Response: When the drawing was drafted there was a callout to remove the curb; however, if it’s salvageable, that may be an option Cherriots would elect. Please price it as identified in the drawing. Proposers may provide an alternate option if proposer believes that is a viable option.

11. Question: Please confirm…Phase-wise, the plan is to complete underground preparation, and the contractor won’t do anything until the gear has arrived? Is it safe/ secure to bring wire on site until the switchgear arrives?

Response: The plan would be to start construction after contract award for the charging gear prior to its arrival, and then continue labor after the switchgear arrives to complete the construction. SAMTD has 24 hour security on a fenced lot where the work is to be performed.

The equipment can be stored on site, however SAMTD will not be liable for any loss or damage.

Worksite safety and security is the responsibility of the Contractor.

12. The Agenda for Pre-Proposal Conference that was held on 8/29/2022 is attached as Exhibit A to this Addendum.

13. The Attendance Sheet for the Pre-Proposal Conference that was held on 8/29/2022 is attached as Exhibit B to this Addendum.

All other specifications and terms and conditions remain unchanged.

By: Daniel M. Knauss Procurement & Contracts Manager

Salem Area Mass Transit District 555 Court Street NE, Suite 5230 Salem, Oregon 97301 September 8, 2022

LOW-NO DEL WEBB CHARGING INFRASTRUCTURE CONSTRUCTION

PRE-PROPOSAL MEETING AGENDA

SAMTD RFP No. 22-028 Project Name: Low-No Del Webb Charging Infrastructure Construction

Monday August 29, 2022 at 1:00 PM SAMTD Administrative Offices, 555 Court Street NE, Salem, OR 97301

A. WELCOME

1. Sign-in sheet

2. Introductions

a. Procurement Contact: Dan Knauss, Procurement & Contracts Manager

b. Project Manager: Gregg Thompson, Maintenance Manager

B. PROJECT DESCRIPTION, DELIVERY METHOD & SCHEDULE

1. Description: SAMTD is requesting Proposals for construction services for infrastructure to support its Battery Electric Bus (BEB) program. The scope of this solicitation includes installation of new electrical service to support the charging infrastructure; installation of BEB charging equipment; installation of underground electrical infrastructure; demolition, excavation, and concrete work; site testing; and commissioning support, and all work as identified in PART 2 of this solicitation.

• Successful proposer shall be licensed by the State of Oregon to do the work required under the resultant contract.

• All items or services to be furnished under the solicitation and resultant contract shall meet all applicable state and federal requirements of the Occupational Safety and Health Standard.

• Successful proposer shall obtain and maintain in current status all applicable permits and licenses.

2. Delivery Method—Project will be performed under a single Prime Contract.

3. Project Schedule and Completion Time:

a. Notice of Intent To Award: October 15, 2022 (Estimate)

b. Notice Proceed: November 1, 2022 (Estimate)

c. Service completion:

• Substantial Contract Completion on or February 28, 2023 (Estimate)

• Final Completion on or before April 1, 2023 (Estimate)

C. PROPOSAL PROCESS AND PROPOSER INSTRUCTIONS

1. Request for Proposal, Plans, Specifications, Addenda, and other related documents for this project are available on the procurement page of the State of Oregon OregonBuys website.

www.oregonbuys.gov Notice #S-KS2410-00004084

2. Important Dates:

a. Submit Questions Deadline: September 1, 2022: 4:00PM PDT

b. Issue Addendum Response to Questions: September 8, 2022: 5:00PM PDT

c. Solicitation Closes: September 20, 2022: 4:00PM PDT

d. Issue Notice Of Intent To Award: October 15, 2022: (Estimate)

e. Contract Award and Notice To Proceed: November 1, 2022: (Estimate)

3. Required Proposal Submittals — See required items on Salem Area Mass Transit District “Instructions For Proposers” and “Exhibits” included in the Request For Proposal.

SALEM AREA MASS TRANSIT DISTRICT

Low-No Del Webb Charging Infrastructure Construction

RFP 22-028

Addendum #2EXHIBIT A http://www.oregonbuys.gov/

PRE-PROPOSAL MEETING AGENDA

SAMTD RFP No.: 22-028 Low-No Del Webb Charging Infrastructure Construction Monday August 29, 2022 @ 1:00 PM SAMTD Administrative Offices, 555 Court Street NE, Salem, OR 97301

D. SAFETY AND SECURITY

1. Safety Requirements—Job Site Conditions

• The successful proposer shall take all necessary precautions for the safety of all personnel on the job site, and shall comply with the Contract Documents and all applicable provisions of federal, state and municipal safety laws and building codes to prevent accidents or injury to persons on, about or adjacent to the premises where the Work is being performed. The Owner's Authorized Representative has no responsibility for Work site safety. Work site safety is the responsibility of the successful proposer.

2. Site Visitation & Viewing

• Proposers may view the site areas where work is to be performed.

• Proposers may submit requests to view the site where work is to be performed. Viewing may take place between the hours of 9:00AM – 3:00PM, Monday – Friday. Proposer must have an appointment scheduled in advance. If a Proposer arrives to view the site without a prior appointment, SAMTD may not accommodate the request. To schedule an appointment to view the site please contact:

Gregg Thompson, Maintenance Manager ……………….………… 503-361-7562

E. INSURANCE

Requirements as identified in RFP 22-028 Exhibit B - Sample Contract, Special Contract Conditions, Section SP.7 “Insurance”.

F. BONDING

Requirements as identified in RFP 22-028 PART 1, Section 3 “Instructions For Proposer”, and Exhibit B - Sample Contract, Exhibit C, Section G, G.2.

1. Proposal Bond

2. Performance Bond

3. Payment Bond

G. SPECIAL CONSIDERATIONS

1. Compliance with local requirements for the Jurisdiction where work is performed.

2. Coordination with SAMTD Security and Business Operations. SAMTD Project Manager will be liaison with these SAMTD organizations.

H. SAMTD SUPPLEMENTARY CONDITIONS & SUPPLEMENTARY INSTRUCTIONS

Please review all solicitation documents thoroughly to ensure complete understanding of all supplementary conditions and instructions.

1. Please review Part 1, Section 3, Subsection 2 (A-F) regarding preparation of proposals.

I. TOUR OF AREA WHERE WORK IS TO BE PERFORMED

There will be no tours associated with the Conference today.

J. SCOPE OVERVIEW BY SAMTD PROJECT MANAGER

K. QUESTION & ANSWER PERIOD

SALEM AREA MASS TRANSIT DISTRICT

lLow-No Del Webb Infrastructure Construction

Addendum #2EXHIBIT B

EXHIBIT C

Addendum #2

Express Plus Express Plus Specifications Power Module Power Module Output

Power Module Specifications

Power Block Power Block Input

Power Block Output

* Subject to site configuration and installed stations

Max Output Power 200 kW

Output Voltage, Charging 200V – 1000V

Max Current per Output 200A, 250A, 300A, 350A, 500A*

Number of Stations Served One Power Block can serve up to 2 Power Link stations. Additional Power Blocks can be added to serve more stations

Max Power Modules per Power Block 5

Input Rating 3-phase, 400-480Y VAC, 300-250 A 50/60Hz

Wiring L1, L2, L3, Earth

Short Circuit Current Rating 65 kA

Power Module Dimensions 430 mm (H) x 130 mm (W) x 760 mm (L) (1’5” x 5” x 2’6”)

Power Module Weight 45 kg (98.5 lb)

Power Module Cooling Liquid Cooled Technology

Harmonics iTHD < 5% (Complies with IEEE 519)

Max Output Power 40 kW

Max Output Current 100 A

Power Conversion Efficiency Up to 96%

Power Factor 0.99 at full load

SALEM AREA MASS TRANSIT DISTRICT

Low-No Del Webb Charging Infrastructure Construction

Addendum #2EXHIBIT D

ChargePoint Express Plus Data Sheet

Power Block Specifications

Station Station Output

**Availability may vary

Station Specifications

Functional Interfaces

ChargePoint, Inc. reserves the right to alter product offerings and specifications at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document

ChargePoint, Inc. | Copyright © 2021 2 of 4

LCD Display Optional Full-color 200 mm (8”) LCD display for driver interaction

Authentication

RFID: ISO 15693, ISO 14443, NEMA EVSE 1.2-2015 (UR)

Tap to Charge (NFC on Apple & Android) 15118-2 (EIM) Remote: Mobile and in vehicle (if supported by vehicle)

Station Dimensions 2400mm (H) x 720mm (W) x 280mm (D) (7’11” x 2'5" x 11")

Station Footprint 965mm (W) x 635mm (D) (3'2" x 2'1") with Cable Management

Station Weight 250 kg (550 lbs)

Number of Connectors Up to 2 connectors per station

Supported Connector Types CHAdeMO, CCS1 (SAE J1772™ Combo), CCS2 (IEC 61851-23)

Cable Length Standard 4.5 m (15') with Cable Management Kit (CMK) Longer cables with cable management optional

Station Enclosure Rating Type 3R, IP56

Locking Holster Yes

Mounting Type Ground, Wall, Overhead

Max Output Power 200kW, 250kW, 300kW, 350kW with Power Blocks

Output Voltage, Charging 200V – 1000V

CCS1 Max Output Current** Option 1: 200A continuous with Power Blocks Option 2: 375A peak, 350A continuous with Power Blocks

CCS2 Max Output Current** Option 1: 250A continuous with Power Blocks Option 2: 375A peak, 300A continuous with Power Blocks

CHAdeMO Max Output Current**

Option 1: NA & EU: 200A continuous with Power Blocks Option 2: NA: 140A, EU: 125A continuous with Power Blocks

Power Block Dimensions 2200 mm (H) x 1000 mm (W) x 1250 mm (L) (7’3” x 3’3” x 4’1”)

Power Block Weight 409 kg (900 lbs) without Power Modules

Power Block Enclosure Rating Type 3R, IP56

Connectivity Features

Safety and Operational Ratings

Generic Specifications

Energy Management Features

ChargePoint, Inc. reserves the right to alter product offerings and specifications at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document

ChargePoint, Inc. | Copyright © 2021 3 of 4

Dynamic Power Management

Allows a fixed maximum power output per station or lets the system dynamically manage the power distribution per station

Remote Energy Management

Manage output power via the ChargePoint Admin Portal, API, and Open ADR 2.0b VEN

Operational Altitude <3,000 m (<9,800 ft)

Operating Temperature -40°C to 50°C (-40°F to 122°F)

Storage Temperature -40°C to 70°C (-40°F to 158°F)

Operating Humidity Up to 95% @ 50°C (122°F) non-condensing

Vehicle Safety Communication

CHAdeMO – JEVS G104 over CAN, CCS1 – SAE J1772 over PLC and CCS2 — IEC 61851-23

Plug-In Detection Power terminated per JEVS G104 (CHAdeMO), SAE J2931 (CCS1) and IEC 61851-23 (CCS2)

Safety Compliance

UL and cUL listed: complies with UL 2202, UL 2231-1, UL 2231-2, CSA 107.1

CE marking: complies with IEC 61851

Surge Protection

Tested to IEC 6100-4-5, Level 5 (6 kV @ 3,000A). In geographic areas subject to frequent thunderstorms, supplemental surge protection at the service panel is recommended.

EMC Compliance U.S and Canada: FCC 15 subpart A Class A; EU: EN55011, EN55022 and IEC61000-6-3 Class B

Local Area Network 2.4 GHz and 5 GHz WiFi (802.11 b/g/n)

Wide Area Network 4G LTE

Supported Communication Protocols

OCPP 2.0

Service and Maintenance Remote system monitoring, diagnostic, and proactive maintenance

ChargePoint, Inc.

240 East Hacienda Avenue Campbell, CA 95008-6617 USA +1.408.841.4500 or +1.877.370.3802 US and Canada toll-free chargepoint.com

Contact Us Visit chargepoint.com Call +1.408.705.1992 Email sales@chargepoint.com

Copyright © 2021 ChargePoint, Inc. All rights reserved. CHARGEPOINT is a U.S. registered trademark/service mark, and an EU registered logo mark of ChargePoint, Inc. All other products or services mentioned are the trademarks, service marks, registered trademarks or registered service marks of their respective owners. February 2021. V.2021.04.001

ChargePoint, Inc. reserves the right to alter product offerings and specifications at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document

ChargePoint, Inc. | Copyright © 2021 4 of 4 mailto:sales@chargepoint.com

DC Fast Charging Solution

Installation Guide

TEMPORARY O

R PRELIM

IN

ARY

EXHIBIT E

RFP 22-028

Addendum #2

SALEM AREA MASS TRANSIT DISTRICT

Low-No Charging Infrastructure Construction ii

IMPORTANT SAFETY INSTRUCTIONS:

SAVE THESE INSTRUCTIONS

Product Disposal

To comply with Directive 2012/19/EU of the European Parliament and of the Council of 4 July 2012 on waste electrical and electronic equipment (WEEE), devices marked with this symbol may not be disposed of as part of unsorted domestic waste inside the European Union. Enquire with local authorities regarding proper disposal. Product materials are recyclable as marked.

WARNING:

1. Read and follow all warnings and instructions before installing and operating the ChargePoint® Charging Station. Install and operate only as instructed. Failure to do so may lead to death, injury, or property damage, and will void the Limited Warranty.

2. Only use licensed professionals to install your ChargePoint charging station and adhere to all national and local building codes and standards. Before installing the ChargePoint® charging station, consult with a licensed contractor, such as a licensed electrician, and use a trained installation expert to ensure compliance with local building and electrical codes and standards, climate conditions, safety standards, and all applicable codes and ordinances. Inspect the charging station for proper installation before use.

3. Always ground the ChargePoint charging station. Failure to ground the charging station can lead to risk of electrocution or fire. The charging station must be connected to a grounded, metal, permanent wiring system, or an equipment grounding conductor shall be run with circuit conductors and connected to the equipment grounding terminal or lead on the Electric Vehicle Supply Equipment (EVSE). Connections to the EVSE shall comply with all applicable codes and ordinances.

4. Install the ChargePoint charging station on a concrete pad using a ChargePoint approved method. Failure to install on a surface that can support the full weight of the charging station can result in death, personal injury, or property damage. Inspect the charging station for proper installation before use.

5. This charging station is not suitable for use in or around hazardous locations, such as near flammable, explosive, or combustible materials.

6. Do not use this product if the enclosure, EV cable, or the EV connector is broken, cracked, open, or shows any other indication of damage.

7. Do not put fingers into the electric vehicle connector.

8.This device should be supervised when used around children.

9. Use 90°C wire copper or aluminum conductors only.

10. Do not use the charging station if any signs of flood damage are detected.

Important: Under no circumstances will compliance with the information in this manual relieve the user of his/her responsibility to comply with all applicable codes or safety standards. This document describes the most commonly-used installation and mounting scenarios. If situations arise in which it is not possible to perform an installation following the procedures provided in this document, contact ChargePoint, Inc. ChargePoint, Inc. is not responsible for any damages that may result from custom installations that are not described in this document or for any failure to adhere to installation recommendations. TEMPORARY O

R PRELIM

IN

ARY

iii

No Accuracy Guarantee

Commercially reasonable efforts were made to ensure that the specifications and other information in this manual are accurate and complete at the time of its publication. However, the specifications and other information in this manual are subject to change at any time without prior notice.

Copyright and Trademarks

©2013-2020 ChargePoint, Inc. All rights reserved. This material is protected by the copyright laws of the United States and other countries. It may not be modified, reproduced or distributed without the prior, express written consent of ChargePoint, Inc. CHARGEPOINT is a U.S. and European Union registered trademark and service mark of ChargePoint, Inc. and cannot be used without the prior written consent of ChargePoint.

Symbols Used in This Document This guide and product use the following symbols:

DANGER: Risk of electric shock.

WARNING: Risk of personal harm or death.

CAUTION: Risk of equipment or property damage.

Important: Crucial step for installation success.

Read the manual for instructions.

Ground/protective earth.

TEMPORARY O

R PRELIM

iv

TEMPORARY O

R PRELIM

v

Contents

1 Prepare for Installation Check Site Readiness Check Express Plus Shipping Crates Bring Tools and Materials

2 Install the Power Block Prepare the Power Block for Mounting Mount and Secure the Power Block Pedestal Install the Power Block Enclosure Connect the Power Block Wiring Install the Wet Box Install the Racks and Power Modules Install the Power Module Cover Panels

3 Install the Power Link Prepare the Power Link for Mounting: Pedestal Only Mount and Secure the Power Link: Pedestal Mount Mount and Secure the Power Link: Vertical Mount

TEMPORARY O

R PRELIM

vi

R PRELIM

1Prepare for Installation

This document describes how to install the components of the ChargePoint® Express Plus DC fast charging solution.

The Express Plus product family is a modular solution for scalable fast charging of electric vehicles.

Power Link charging stations are powered by Power Block AC/DC converters, and the entire system communicates with ChargePoint using the cellular network. This connectivity is required for diagnostics and reporting, as well as communication with the online dashboard that allows the station owner to control its settings and commands.

Access ChargePoint documents online for each phase of the project:

Important: You must be a licensed electrician and complete online training to become a ChargePoint certified installer. If you do not complete installation training, you cannot access the ChargePoint Network to complete pinpointing and station setup.

To complete online training and become a certified installer, refer to ChargePoint University at: chargepoint.com/installers or chargepoint.com/eu/installers

Document Content Audiences

Express Plus Data Sheet Full station specifications Site designer, installer, and station owner

Express Plus Site Design Guide Civil, mechanical, and electrical guidelines to scope and construct the site

Site designer or engineer of record

DC Universal Concrete Mounting Template Guide

Instructions to install the Power Link CMT with anchor bolts and conduit placement

Site construction contractor

Power Block Concrete Mounting Template Guide

Instructions to install the Power Block CMT with anchor bolts and conduit placement

Site construction contractor

This document Anchoring, wiring, and powering on Installer

Express Plus Operations and Maintenance Guide

Operation and preventative maintenance Station owner or facility manager

Full set of Field Replacement Guides

Component replacement procedures Station owner or third party servicer

TEMPORARY O

R PRELIM

IN

ARY

https://ChargePoint.com/installers http://www.chargepoint.com/eu/installers

Note: For all charging station specifications other than dimensions and weights, refer to the Express Plus Data Sheet found online at chargepoint.com/guides or chargepoint.com/eu/guides.

For assistance, go to chargepoint.com/support and find your region’s technical support number.

Installing the Express Plus solution requires two people.

Check Site Readiness The Power Block and Power Link can be installed on either a newly poured pad or an existing concrete surface. Power Blocks and Power Links also support wiring run above ground, for locations where no underground wiring access exists (parking garages, etc.) or where underground junction boxes are not permitted. The mounting surface must be smooth and cannot exceed a slope of 6.35 mm per 304.8 mm (0.25 inches per foot).

Before beginning work, check that the site meets these civil and mechanical requirements outlined below, as illustrated in the following images. Measurements are in mm.

• All concrete pads are ready and the concrete is fully cured and level.

• Each Power Block concrete pad either has a site drawing approved by a structural engineer for this specific site, OR existing concrete has been approved by a structural engineer for the Power Block’s dimensions and weight.

• Each Power Link pad conforms to the design requirements listed in the Express Plus Site Design Guide.

• Walls, fences, or slopes do not prevent water from draining from the pad.

CAUTION: Do not install the charging station in inclement weather. If you must complete the installation in rain or wind, you must use a weather-proof shelter that covers all boxes and components.

CAUTION: Do not use power tools during installation or servicing. Over-torquing can damage the equipment.

Important: Always ensure that the installation complies with all applicable codes.

WARNING: If not installed correctly, the ChargePoint® charging components may pose a fall hazard, leading to death, personal injury, or property damage. Always use the provided Concrete Mounting Template, or a ChargePoint-approved surface mounting solution to install ChargePoint® charging components and install in accordance with applicable codes and standards using licensed professionals. Non-approved installation methods are performed at the risk of the contractor and void the Limited One-Year Parts Exchange Warranty.

TEMPORARY O

R PRELIM

IN

ARY

https://www.chargepoint.com/guides https://www.chargepoint.com/support https://www.chargepoint.com/support http://www.chargepoint.com/eu/guides

Prepare for Installation

Power Block Readiness

The Power Block Concrete Mounting Template (CMT) should already be embedded in the concrete pad, unless the site is using Surface Conduit Entry.

Verify the AC and DC conduits are positioned correctly and cut to 914 mm (24 in) above grade for the Power Block.

a. Power Block footprint

b. DC output options: 200, 250, 350, or 500 A; up to 102 mm (4 inch trade size) conduit each

TEMPORARY O

R PRELIM

c. M16 anchor bolts (x4)

d. Surface Conduit Entry anchor positions (optional: x2 left, x2 rear, or x2 right)

e. DC auxiliary input (optional): 102 mm (4 inch trade size) conduit

f. AC input: 89 mm (3.5 inch trade size) conduit

g. Low voltage DC and Ethernet options, (1 inch trade size) conduit (x4):

• Shunt trip: always present (x1)

• 1 Ethernet, 1 LV out: (x1)

• 2 Ethernet, 1 or 2 LV out: (x2)

• 3 Ethernet, 1 or 2 LV out: (x3)

h. Front of enclosure (top view)

Note: For maximum wire and ground sizes and their minimum conduit sizes, see the Express Plus Site Design Guide.

The Power Block requires minimum site and service clearances as listed below.

a. Rear: 457 mm (18 in) required, 610 mm (24 in) recommended

b. Front: 1000 mm (39.3 in)

c. Sides: 51 mm (2 in)

TEMPORARY O

R PRELIM

Power Link Readiness

If the Power Link is pedestal-mounted and using stub-up wiring, the Power Link Concrete Mounting Template (CMT) should already be embedded in the concrete pad.

a. DC conductors

b. 48 VDC and Ethernet

c. Power Link anchor bolt locations

The Power Link requires minimum site and service clearances as listed below.

* Side clearance is measured from top corner to top corner

** Side clearance can be shared between two Power Links

Note: All operation and service for the Power Link is performed from the front. No rear clearance is required.

Front Clearance 610 mm (24 in) minimum open space

Side Clearance* 711 mm (28 in) required; 864 mm (34 in) recommended**

Top Clearance 305 mm (12 in)

TEMPORARY O

R PRELIM

The arrows below indicate door swing and service clearances. Measurements are shown in millimeters (inches).

If the site does not meet these basic requirements, contact ChargePoint before continuing.

• Enough space is available around the installation pad to use a forklift and other lifting equipment, unpack crates, remove packing materials, and allow two people to freely move throughout the area.

Also ensure these electrical requirements are in place:

• The appropriate circuit protection and metering is in place at the installation site.

• A grounding conductor that complies with local codes is properly grounded to earth at the service equipment or, when supplied by a separate system, at the supply transformer.

A correctly rated, dedicated breaker is installed for each Power Block:

1 Adds 5% to current at low line conditions 2 The overload setting for North America is fixed at 125% of continuous rated current

• Breakers have shunt trip capability to each Power Block.

• All necessary electrical infrastructure has been completed per local codes and ChargePoint specifications for 3-phase power plus ground, with properly sized wire at the station. (Neutral is not required for system operation.)

Important: Remove any concrete that is not level with the rest of the surface, or you cannot level the components. Use a grinder or a hammer and chisel to remove any bumps in the concrete.

Nominal Voltage Input Current Rating Recommended Overload Protection Breaker Size

400 V (EU) 315 A 370 A1 400 A

480 V (N. America) 260 A 325 A2 400 A

(28)

(24)

(28)

(28.7)

TEMPORARY O

R PRELIM

• A consistently strong cellular signal is needed before installers can activate the station. Do not rely on cell phone applications to measure cellular signals when conducting site surveys. Ensure the signal at the installation site is consistently strong. If RSRQ is measured at -10 dB or better, then RSRP can be -90 dBm or better. If RSRQ cannot be measured or is not adequate, RSRP must be -85 dBm or better. Note that these numbers are all negative, so -70 dBm is stronger than -85 dBm, and -90 dBm is weaker. Use a cellular signal detection device (such as a Snyper or equivalent) to take signal strength readings at the exact proposed charging station locations.

If the signal is below -85 dBm, take cellular readings at the location where a cellular signal booster antennas will be installed, to ensure enough signal exists to be boosted. Install repeaters to boost the strength of the cellular signals. Repeaters are often required when installing charging stations in an underground garage or enclosed parking structure.

For any questions about site specifications, refer to the Express Plus Data Sheet and Express Plus Site Design Guide.

Check Express Plus Shipping Crates Each Express Plus solution ships in multiple crates. Ensure you have all crates at the installation site.

• Power Block pedestal and gland plates

• Power Block enclosure (dry box plus wet box)

• Power Block doors and cover panels

• Power Block dry box heat exchanger

• Power Link(s)

• Power Modules (up to 5 per Power Block)

• Installation kit:

• Duct seal compound

• Propylene glycol coolant (the coolant label references its Safety Data Sheet if needed)

• T25 Torx security driver

Important: The Power Link is tested to IEC 61000-4-5, Level 5 (6 kV @ 3000 A) standards.

In geographic areas that experience frequent thunderstorms, supplemental surge protection must be installed at the service panel.

CAUTION: Always transport and store the charging components in their original packaging.

Use appropriate lifting equipment (forklift, crane and lifting straps, etc.). Ensure the load rating of all lifting equipment is adequate for the weight of the crated components as shown above.

Important: Leave components in the shipping crate until needed. When removing, protect them from damage (such as scratches) by placing them flat on a blanket or tarp, face up.

Do not stand up cover panels, as they may be knocked or blown over. Cover charging connectors to prevent damage or ingress.

TEMPORARY O

R PRELIM

• T30 Torx driver

• Coolant funnel

• Printed Installation Guide

Bring Tools and Materials In addition to the tools and materials provided by ChargePoint in product crates, an approved installer needs:

• Lifting equipment (forklift or crane)

• Lock out/tag out equipment

• Step ladder

• Cut-resistant gloves

• Hard hat

• Safety glasses

• Head-mounted flashlight

• Torque wrenches capable of 4 to 95 Nm (3 to 70 ft-lbs)

• 15 mm (9/16 in) wrench

• 18 mm (11/16 in) wrench

• #2 Phillips screwdriver with long handle

• Flathead screwdriver

• Cellular signal detection device, such as a Snyper or similar (to detect both strength and quality)

• Standard electrical equipment such as wire cutter, wire stripper, and cable ties

• Level

• Isopropyl wipes

• Wire brush

• If not already installed, AC and ground conductors per site drawings

• If not already installed, DC conductors per site drawings

• If not already installed, shunt trip wiring

• If not already installed, Ethernet wiring

• Cable puller or fish tape (if not already completed)

• AC and DC lugs: plated copper compression lugs, M12 (1/2 in) hole size, 44 mm (1.75 in) hole spacing (2-hole specified for North America), maximum tongue width of 50 mm (2 in) (NOTE: check site drawings for quantity of lugs)

CAUTION: Always rest a Power Module flat on the ground until it is being installed. Power Modules are not stable in any other position. Images of Power Modules standing with the handles on top are only to illustrate the proper installation position.

TEMPORARY O

R PRELIM

• Lug crimper and die that are compatible with lug size and brand (NOTE: The lug die and crimp tool must match the lug manufacturer. Always review the lug manufacturer’s instructions for compatibility)

• Multimeter, such as Fluke 117 or similar

• Ethernet tester such as a Klein Tools VDV526-052 VDV LAN Scout Jr. Tester or similar

• Permanent marker

• Torque paint pen

• Two padlocks provided by station owner (to secure panels on Power Block)

TEMPORARY O

R PRELIM

R PRELIM

2Install the Power Block

This section describes how to anchor, wire, and install all components on a Power Block.

The Power Block pedestal (a) and dry box (b) each have built-in forklift pockets. The Power Block dry box has four M10 threaded mounting points in the upper corners that can accept crane lifting shackles if a spreader bar is used AND if the wet box (c) is first removed.

The dry box and wet zone usually ship already assembled, unless the site has height constraints for installation, such as inside a parking garage.

Prepare the Power Block for Mounting

1. Ensure all AC and DC conduit stub-ups (if applicable) are trimmed to a minimum of 610 mm (24

in) from the ground. If the site is using armored cable, strip the outer jacket to within the same height.

2. Remove the plastic caps from all mounting bolts on the concrete installation pad.

3. Use a wire brush to clean out threads if any concrete is on the bolts.

4. Place one washer, then one nut, all the way to the bottom of each anchor bolt, against the concrete.

5. Place a leveling nut and washer on each of the four corner bolts.

Leave approximately 6.4 mm (1/4 in) between the bottom of the leveling nuts and the nut against the concrete. Check nut positions relative to each other with a level.

Note: If a wall is located behind the installation pad, ensure the forklift blades do not protrude far enough to hit the wall when moving the Power Block onto the pad.

TEMPORARY O

R PRELIM

Mount and Secure the Power Block Pedestal

1. Position the forks of the forklift to fit between the conduit stub-ups.

2. Use a forklift (or two installers) to lift the Power Block pedestal over the mounting bolts on the installation pad, ensuring the bolts align with the corresponding holes in the bottom of the Power Block. Move the service wiring out of the way to ensure it is not pinched or trapped.

3. Lower the Power Block pedestal onto the anchor bolts.

4. Using a level on all four sides, adjust three of the bottom corner leveling nuts as needed to ensure that the Power Block is both horizontally and vertically level.

5. Measure the height of the conduit stub-ups. Mark each conduit at the height of the pedestal top surface.

6. Remove the pedestal and set it aside.

7. Cut each conduit stub-up to height.

8. Replace the pedestal onto the anchor bolts.

9. Install a washer and nut onto each of the four corner mounting bolts to secure the Power Block.

For easier leveling, leave a 6.4 mm (1/4 in) gap between the bottom of these top nuts and the baseplate of the frame.

10. Recheck leveling nuts. When level, tighten leveling top nuts by hand. Then raise the remaining (non-leveling) lower nut by hand-turning until flush against the frame.

11. Torque all top nuts to 94.9 Nm (70 ft-lbs).

12. Use the two pins on one long edge of each gland plate to locate the plate against the edge of the pedestal.

13. Use a marker to mark the exact locations of each conduit stub-up against the bottom of each gland plate.

Remove the plates.

14. Aligning with each existing pilot point on the gland plate, drill out the required holes according to the size of each conduit.

15. Pull all wires.

TEMPORARY O

R PRELIM

Install the Power Block

16. Thread all wires through the gland plates according to the Power Block layout shown in Power Block Readiness (page 3).

Note: For maximum wire and ground sizes and their minimum conduit sizes, see the Express Plus Site Design Guide.

17. Install an approved sealing method to seal each conduit stub-up to the gland plate. Tighten all glands on the wiring.

18. Measure the DC output wiring (b) on the left side of the Power Block. Trim all conductors to approximately 940 mm (37 in) above grade.

Note: This round of cutting conductors is rough and allows extra room for more precise measurement later.

19. Measure the Ethernet wiring (g) coming from the center of the pad through the right enclosure opening. Trim all wires to approximately 1397 mm (55 in) above grade.

20. Measure the low voltage (48 V and shunt trip, also g) wiring coming from the center of the pad through the right enclosure opening. Trim all wires to approximately 1880 mm (74 in) above grade.

21. Measure the AC input wiring (f) and DC input if applicable (e). Trim all conductors to approximately 1092 mm (43 in) above grade.

Install the Power Block Enclosure

1. Transport the Power Block enclosure crate close to the installation site.

2. If the crate is horizontal, carefully tilt the crate up until vertical. Use lifting straps to stabilize the crate and prevent it from tipping.

3. Using either a forklift or crane, remove the Power Block enclosure from its crate. Move it to its mounting location and keep it elevated.

4. Lift the Power Block enclosure over the pedestal. Move the service wiring through the bottom openings to ensure it is not pinched or trapped.

5. Lower the Power Block enclosure onto the pedestal, being careful to keep service wiring from damaging internal components:

WARNING: THE CRATE IS HEAVY AND CAN CAUSE INJURY OR

DEATH IF DROPPED. DO NOT STAND OR MOVE BENEATH THE

CRATE AS IT IS BEING TILTED. TAKE PRECAUTIONS AGAINST THE

CRATE TIPPING OR SLIDING.

WARNING: The Power Block has a high center of gravity. Take care to prevent tipping when moving the Power Block.TEMPORARY O

R PRELIM

• Right/left movement is aligned by the center pedestal beam fitting between the two enclosure forklift tunnels.

• Forward/back movement is aligned by the small slanted alignment blocks on the front and rear edges.

6. Pre-install the empty lugs for all bus bars (DC output, AC input, and DC input if applicable), using the provided bolts, washers, and nuts. Only hand-tighten all fasteners at this step.

7. Measure the actual length of each DC output, AC input, and DC input conductor. Mark the height of each compared to its lug.

8. Remove the Power Block enclosure. Trim all large conductors to size.

Note: Removing and replacing the Power Block enclosure is recommended, but not required, if the installers have adequate room to trim and crimp all conductors.

9. Replace the Power Block enclosure, being careful to keep service wiring from damaging internal components. Keep the enclosure slightly lifted as installers visually inspect and adjust the last quarter-inch or so of fine alignment for fastener holes.

10. Use a 15 mm wrench and seven M10 screws to secure each of the two gland plates and the enclosure to the pedestal (screws shown in red, enclosure not shown).

TEMPORARY O

R PRELIM

Connect the Power Block Wiring

1. Follow standard practice and local code to de-energize the applicable circuit and lock out/tag out the disconnect before proceeding. Use a multimeter to test that power is off.

2. Identify the DC fuse kit for this site’s Power Block(s). Install the DC fuses and associated ratings label.

3. Remove the empty DC output lugs from the bus bars. Using the manufacturer’s crimp tool and die, strip and crimp a lug onto each conductor.

4. Use dielectric grease and an 18 mm socket to install the lugs onto the bus bar with M12 bolts. Torque to 21 Nm (185.9 in-lbs).

5. Remove the empty AC input lugs from the bus bars. Using the manufacturer’s crimp tool and die, strip and crimp a lug onto each conductor.

6. Use dielectric grease and an 18 mm socket to install the lugs onto the bus bar with M12 bolts. Torque to 21 Nm (185.9 in-lbs). The L1 bus bar is the one closest to the front, L2 is behind it, etc.

DANGER: RISK OF SHOCK. Before performing this procedure, disconnect the power to the Power Block at the service panel. Keep power off for this circuit until all cover panels are correctly reinstalled and the work scope is completed. FAILURE TO FOLLOW THESE

INSTRUCTIONS CAN RESULT IN SERIOUS INJURY OR LOSS OF LIFE.

CAUTION: Ensure a grounding conductor that complies with local codes is properly grounded to earth at service equipment or, when supplied by a separate system, at the supply transformer.

Important: If any DC or AC lug is single-hole, the lug must be installed within +/- 10 degrees from vertical to avoid interference.

TEMPORARY O

R PRELIM

7. If applicable, remove the empty DC input lugs from the bus bars. Using the manufacturer’s crimp tool and die, strip and crimp a lug onto each conductor.

8. Use dielectric grease and a 18 mm socket to install the lugs onto the bus bar with M12 bolts. Torque to 21 Nm (185.9 in-lbs).

9. Strip the LV (a) and shunt trip (b) wires 20 mm each. Use a screwdriver to loosen each terminal’s tab and seat the wire. Tighten the screw hand-tight and perform a push-pull test to ensure each wire is seated.

Important: If the AC input wiring is using only one 750 kcmil conductor, it must be installed on the bus bar in the position farther from the enclosure wall (toward the center) to avoid interference.

Important: Ensure the L1, L2, and L3 cables are installed in the correct order. Incorrect installation creates a phase rotation error later in the process. Phase rotation must be counter-clockwise.

TEMPORARY O

R PRELIM

10. Connect each Ethernet connector into an available Ethernet port on the lower right side of the enclosure.

11. Crimp a 13 mm (0.5 in) single-hole lug onto the ground wire. Connect the GND (protective earth) service wiring to the enclosure stud in the bottom front right corner of the enclosure.

12. Use the provided cable routing clips along the right front edge of the enclosure to route the Ethernet, LV, and shunt trip wires down the side.

13. Pull any extra Ethernet wire loops down into the pedestal, to prevent pinching in cover panels.

14. Use the supplied duct seal compound to completely seal all wiring openings against pest ingress.

Important: The conduit opening must be sealed to protect the wiring from the environment.

TEMPORARY O

R PRELIM

If the wet box and its components are already installed on the dry box, skip to the section Install the Racks and Power Modules (page 21). If not, continue with Install the Wet Box (page 18).

Install the Wet Box If the wet box is not already installed on top of the dry box, follow these steps before installing Power Modules.

1. Using a forklift or two installers, lift the wet box enclosure on top of the dry box so that the deeper opening (behind the dividing panel) is in back.

2. Align the wet box so that the small guide pins on the dry box tabs fit into the wet box dividing panel (a).

3. Use a T30 Torx to fasten the wet box to the dry box with one M6 screw and captive washer in each front edge (b) and two screws in each rear edge.

4. Use a T30 Torx to fasten four M6 screws to install the power supply plenum in the back of the wet box, so that the shelf faces out.TEMPORARY O

R PRELIM

5. Use four washers and screws to install the auxiliary power supply in the back of the wet box.

6. Plug in the power supply harness:

• Three connectors under the power supply’s right edge

• Three ground straps on the right to the provided ground stud

• Three connectors under the power supply’s left edge

• One connector to the top of the dry box enclosure on the left

• One ground strap that connects the Aux PS enclosure to the dry box frame

Connectors can only be installed one way. Drape the rest of the cable across the back, not top, of the power supply.TEMPORARY O

R PRELIM

7. Fasten the ground wire to the tab on the wet box enclosure at the front left corner.

8. Using two people, angle the heat exchanger into the front of the wet box, starting with the bottom edge. Let the alignment pegs at the bottom of the exchanger slide down the angled tabs on the dry box until it rests flush against the bottom.

9. If not already installed, slide each of the three fan trays down onto the securing tabs.

TEMPORARY O

R PRELIM

10. Connect the three fan power cords to the three matching connectors in the top left of the dry box, through the enclosure slots.

11. Connect the pump, level sensor, and RTD wiring on the right side.

12. Connect the two coolant hoses at the front of the heat exchanger to the matching quick disconnect valves in the front top edge of the dry box.

Install the Racks and Power Modules If the Power Module racks were not installed during shipment, or were removed for better access to wiring, this section describes how to install them.

A Power Block can contain up to five Power Modules (modular power converters). Power Modules ship in separate pallets.

WARNING: Power Modules and the dry box heat exchanger are heavy. Two people are needed to install any of these modules.

TEMPORARY O

R PRELIM

1. Lift each of the two empty racks into the center of the enclosure with the rack mounts facing inward. Slide each one along its bottom rail between the guidance tabs (a). The rack with the latches (b) goes on the left side.

2. Use a 15 mm wrench to fasten four M10 screws on each side (2 top, 2 bottom) that secure the Power Module rack to the enclosure.

3. Identify the auxiliary heat exchanger (c). Using two people, slide it into the top position in the Power Module rack.

Firmly push the heat exchanger into place against the back plane connections until it latches.

TEMPORARY O

R PRELIM

4. Plug the multi-pin round connector from the top edge of the dry box into the front of the auxiliary heat exchanger.

5. Remove the coolant port caps from each Power Module’s connectors.

6. Use two people to install Power Modules in the other five positions in the rack (d), with the connectors at the back and the handles facing to the left.

Firmly push each one into place against the back plane connections until it latches.

7. Using a step ladder if needed, unscrew the captive screw on the coolant reservoir in the wet box. Rotate the reservoir out and to the right to access the cap.

8. Unscrew the reservoir cap. Use the funnel to fill the reservoir to the marked Max line with coolant.

9. Replace the reservoir cap. Rotate the reservoir back into place and tighten the captive screw.

Note: Always fill the coolant reservoir after installing the Power Modules, which are part of the coolant path. Filling the reservoir first does not allow full station coolant levels.

TEMPORARY O

R PRELIM

Install the Power Module Cover Panels

1. Install all four pedestal panels by hooking each one onto the frame (a) and sliding it down to touch the ground.

2. Use a T30 Torx driver to fasten two M6 screws (b) for each panel.

3. Insert the front dry box door into the bottom lip of the enclosure (c) and tip it up into place.

4. Check that the door switch and its actuator line up, and adjust if needed.

5. Fasten the two latches at the top (d).

TEMPORARY O

R PRELIM

6. Fasten two side panels in place on each side (e). The top and bottom side panels are interchangeable.

7. Slide the bottom and middle rear cover panels into place (f). The middle and bottom side panels are interchangeable.

8. Slide the bottom and middle front cover panels into place (g). The middle and bottom side panels are interchangeable.

9. Slide the top rear cover panel into place (h). Check that the door switch and its actuator line up, and adjust if needed.

Lift the small insert door to apply a padlock. Close the insert door.

10. Slide the top front cover panel into place. Check that the door switch and its actuator line up, and adjust if needed. Lift the small insert door (i).

Fold the security tab (j) across the Ethernet port and apply a padlock.

Close the insert door.

TEMPORARY O

R PRELIM

R PRELIM

3Install the Power Link

This section describes how to anchor and wire each Power Link.

Prepare the Power Link for Mounting: Pedestal Only If the Power Link will be pedestal mounted, follow this procedure to check and prepare the site.

Otherwise, skip to Mount and Secure the Power Link: Vertical Mount on page 28.

Note: The Power Link is equipped with lift points for moving and mounting. Lifting straps, supplied with the crate, can be used for either configuration.

1. Ensure all DC and LV/Ethernet conduit stub-ups (if applicable) are trimmed to a minimum of 60 mm (2.4 in) from the ground, maximum 160 mm (6.3 in). If the site is using armored cable, strip the outer jacket to within the same height.

2. Ensure no bell ends are left on any conduit after all wires are pulled. Bell ends can interfere with station placement.

3. Remove the plastic caps from all mounting bolts on the concrete installation pad.

4. Use a wire brush to clean out threads if any concrete is on the bolts.

Important: To protect the charging cables from damage, keep them wrapped throughout the installation process.

TEMPORARY O

R PRELIM

5. Place a leveling nut and washer on each of the four corner bolts.

6. Leave approximately 6.4 mm (1/4 in) between the bottom of the leveling nuts and the concrete. Check nut positions relative to each other with a level.

7. Transport the crate close to the installation site.

8. Using either a forklift or crane, remove the Power Link from its crate. Move it to its mounting location and keep it elevated.

Mount and Secure the Power Link: Pedestal Mount This information is in development.

Note: The bottom of the Power Link (not including the bottom cap) must sit 640 mm (25.2 in) above ground to comply with ADA regulations, both when wall mounting and when mounting on a pedestal. It must always sit 457 mm (18 in) above grade to comply with flood regulations.

Mount and Secure the Power Link: Vertical Mount

1. If not already done, pull service wiring through the wall or conduit as described in the Express

Plus Site Design Guide.

2. Use a multimeter to test each DC conductor for continuity.

3. Measure the…