This document is a Request for Offers (RFO) for a Design-Build Underground Utilities Replacement and Parking Lot Refurbishment project at the Denver Air Route Traffic Control Center (ARTCC) in Longmont, Colorado. The Federal Aviation Administration (FAA) is seeking qualified small business contractors to perform utility investigation, engineering design, and construction to replace underground utilities and refurbish the facility's parking areas.

The project is estimated to cost between $5,000,000 and $10,000,000 and is set aside for small businesses under NAICS code 237110 - Water and Sewer Line and Related Structures Construction. Key dates include a site visit during the week of May 20, 2024, with questions due by June 5, 2024 and offers due by June 24, 2024. The contract will be funded through the Bipartisan Infrastructure Law and includes additional reporting requirements. Contractors must provide performance and payment bonds, and meet insurance and security access requirements. The work includes replacing underground gas, storm, sanitary, domestic water, manholes, fire water loop and hydrants, as well as refurbishing facility parking areas and sidewalks.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Transportation Federal Aviation Administration

Request for Offers (RFO) Cover Letter

Solicitation Package

Project Name: Denver ARTCC Underground Utilities Replacement and Parking Lot Refurbishment Project

Location: Longmont, CO

Solicitation No.: 697DCK-24-R-00361

Issue Date: May 7, 2024

Submit Offers to: cindi.tjelde@faa.gov

Submit Offers by: Monday, June 24, 2024, 5:00 PM (Mountain time)

Special Instructions:

1) Bipartisan Infrastructure Law (BIL) Funded Project – This contract is being funding with BIL funds. See Contract Clause 3.18-1 Bipartisan Infrastructure Law – Reporting Requirements (October 2022) and Attachment 3 – Uniform BIL Data Report, for special contract reporting requirements.

2) Insurance is required (See Contract Clause 3.4.1-12 Insurance (Jul 1996) for required coverage limits).

3) Payment and Performance Bonds Required (See Contract Clauses 3.4.1-5 Payment Bond Requirements and 3.4.1-4 Performance Bond Requirements).

4) Set Aside: This procurement is being set aside for a small business.

5) NAICS Code: 237110 Water and Sewer Line & Related Structures Construction, which has a small business size standard of $45.0 Million.

6) Estimated Project Size: Between $5.0 M and $10.0 M.

7) Site Visit: A site visit for this project will be held during the week of May 20, 2024. The site visit is not mandatory, but highly encouraged, so that the offeror and potential subcontractors can verify existing conditions, quantities of materials, and amount of work required. The contractor is responsible for ensuring that their offer reflects all work and time required to accomplish this project. RSVP for the site visit by contacting Joe Crabtree at joseph.crabtree@faa.gov AND Jamie Lehmer at james.r.lehmer@faa.gov.

8) Solicitation Questions: Any questions related to the RFO, Statement of Work, or Reference Documents & Drawing, including questions resulting from the site visit, must be submitted in writing to the Contracting Officer, Cindi Tjelde at cindi.tjelde@faa.gov only. Any clarification received verbally and not incorporated into the RFO through an amendment will not be part of the resultant contract and should not be considered when submitting an offer. See Section L for additional information regarding submission of questions and deadline date for questions.

SOLICITATION, OFFER

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

A. NAME B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder"

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED BID (RFP)

WS-24-00875

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

2200 S. 216TH STREET

DES MOINES WA 98198-6547

AAQ530ANM-AFN

cindi.tjelde@faa.gov

Cynthia Tjelde 206-231-3026 x

05/07/2024 76

PURCHASE REQUEST NO.

697DCK-24-R-00361

10. THE CONTRACT AUTHORITY REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Underground Utilities Replacement & Parking Lot Refurbishment Project at Denver Air

Route Traffic Control Center located at 2211 17th Avenue, Longmont, Colorado.

11. The Contractor shall begin performance within

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award notice to proceed. The performance period is mandatory, negotiable. (See ________________________________________________ .)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and is not required.is, B. An offer guarantee

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers must be publicly opened at that time . Sealed envelopes containing offers shall be marked to show the offeror's name and address. The solicitation number, and the date and time offers are due.

D. Offers providing less than

12B. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in item 12B.)

5 730 calendar days and complete it within ________________ ________________ calendar days after receiving

06/24/2024 x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Contract Authority acceptance after the date offers are due will not be considered and will _________________ be rejected.

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Contract Authority in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13D. Failure to insert any number means the offeror accepts the minimum in item 13D.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (MUST BE FULLY COMPLETED BY OFFEROR)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Contract Authority)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Contract Authority solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE 30C. DATE 31B. CONTRACT AUTHORITY 31C. AWARD DATE

BY

2PAGE OF

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

2200 S. 216TH STREET

DES MOINES WA 98198-6547

AAQ530ANM-AFN

Cynthia A. Tjelde

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

Continued...

cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 76

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

697DCK-24-R-00361

(A) (B) (C) (D) (E) (F)

Delivery: 10/30/2026

Delivery Location Code: S698228F

S698228F

698228 DOT FAA

LONGMONT ENROUTE SSC ARTCC

2211 17TH AVE

LONGMONT CO 805019763 US

00001 ZDV Underground Utilities Replacement project

Electronic & IT: 03

Section A - Solicitation/Contract Form

A001 SOLICITATION INDEX

The Federal Aviation Administration (FAA) is soliciting competitive proposals through the use of this Request for Offers (RFO) for the award of a firm, fixed price construction contract.

This RFO consists of the following Parts / Sections:

Part I – The Schedule Section A: Solicitation / Contract Form Section B: Supplies or Services / Prices Section C: Descriptions / Specifications Section D: Packaging and Marking Section E: Inspection and Acceptance Section F: Deliveries or Performance Section G: Contract Administration Data Section H: Special Contract Requirements

Part II – Contract Clauses Section I: Contract Clauses

Part III – List of Documents, Exhibits, and Other Attachments Section J: List of Documents, Exhibits, and Other Attachments

Part IV – Representations and Instructions Section K: Representations, Certifications, and Other Statements of Bidders Section L: Instructions, Conditions, and Notice to Bidders Section M: Evaluation Factors for Award

End of Clause

Section B - Supplies or Services/Prices Section B - Schedule

Clause List

3.2.2.3-17 PREPARING OFFERS (JUL 2004)

(a) The offeror (you) should examine any drawings, specifications, schedule, and instructions. Failure to do so will be at your own risk.

(b) You must provide the information the SIR requires. Print or type your name and sign the offer. The person signing the offer must initial erasures or other changes. If an agent signs your offer, include evidence of the agent's authority unless you previously gave that evidence to the issuing office.

(c) For each item offered:

(1) Show the unit price or cost, including, unless otherwise specified, packaging, packing, and preservation; and

(2) Enter the extended price or cost for the quantity of each item offered in the 'Amount' column of the Schedule. If there is a discrepancy between a unit price or cost and an extended price or cost, the FAA (we) will assume the unit price or cost is correct, subject to your correction to the same extent and in the same manner as any other mistake.

(d) We will not consider offers for supplies or services other than those specified unless the SIR authorizes it.

(End of provision)

3.2.2.3-43 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (JUL 2004)

(a) The Contractor (you) acknowledges that you have taken reasonable steps to determine the nature and location of the work, and you have investigated and are satisfied about the general and local conditions which can affect the work or its cost, including but not limited to:

(1) Conditions bearing upon transportation, disposal, handling, and storage of materials;

(2) The availability of labor, water, electric power, and roads;

(3) Uncertainties of weather, river stages, tides, or similar physical conditions at the site;

(4) The conformation and conditions of the ground; and

(5) The character of equipment and facilities needed before and during the work.

You also acknowledge that you are satisfied as to the character, quality, and quantity of surface and subsurface materials or obstacles you might find, to the extent you can, from an inspection of the site, including all exploratory work done by FAA (we, us), as well as from the drawings and specifications that are a part of this contract. If you do not take the actions described and acknowledged in this paragraph, you will still be responsible for properly estimating the difficulty and cost of successfully performing the work, and for proceeding to successfully perform the work without additional expense to us.

(b) We are not responsible for your conclusions or interpretations of information we provided before contract award.

We are not responsible for your understanding of conditions you get from any of our officers or agents before contract award. You can rely on representations we make about conditions that we put into the contract.

(End of clause)

B001 PRICE / COST

The Contractor is required to furnish all labor, tools, materials, services, equipment, transportation, insurance, bonds, security notifications, submittals, supervision, licenses, permits, state sales taxes and fees in accordance with applicable federal, state, and local regulatory requirements, for the Underground Utilities Replacement & Parking Lot Refurbishment Project at the Denver Air Route Traffic Control Center (ARTCC) located at 2211 17th Avenue, Longmont, Colorado 80501, in accordance with the Statement of Work (SOW), contract clauses, and applicable wage rates.

LINE ITEM DESCRIPTION TOTAL

0001 1 JOB $_______________________

The offered price must include all costs related to (a) direct and indirect labor, fringe benefits, overhead, G&A expenses, profit, material, equipment, other direct costs, insurance, freight, transportation, inspections, testing, operation and maintenance manuals, warranties, payment and performance bonds, etc., (b) federal, state, and local taxes, (c) all applicable fees, permits, licenses, and (d) any miscellaneous charges.

Effective April 1, 1996, the Federal Aviation Administration (FAA) began operating under the new FAA Acquisition Management System (AMS). The 1996 DOT Appropriation Act, Public Law 104-50, mandated that the FAA rewrite its acquisition regulations and granted legislative relief from certain laws. The Federal Acquisition Regulations (FAR), Federal Acquisition Streamlining Act of 1994, Small Business Act, and Competition in Contracting Act, are four of these laws.

B002 BUY AMERICAN GUIDANCE

This project is being funded using Bipartisan Infrastructure Law (BIL) funds, which are subject to the provisions of the Buy American Act (41 U.S.C. 8301-8305) (BAA) including its associated exceptions. See Section "I" Contract Clause 3.6.4-3 Buy American Act - Construction Materials (Jan 2024) for BAA requirements. Contractor is responsible for completing and submitting data reports quarterly and at the completion of the contract to the email address indicated in the Uniform BIL Data Report. See Section "J" Attachment 8 - Uniform BIL Data Report.

B003 SECURITY CONSIDERATIONS

The contractor will be allowed a sufficient number of contractor/subcontractor workers to be badged during this project. Contractor’s badged workers must escort unbadged workers at all times. This air traffic facility is a secure facility that requires daily entry through security. Entrance into the facility requires all unbadged individuals to go through the security building and obtain a visitor pass for that day. This process may take anywhere from 15 to 30 minutes depending on the number of workers requiring entry. See Contract Clause 3.14-2 Contractor Personnel Suitability Requirements (Apr 2022) for additional information regarding security requirements.

The remainder of this page has been intentionally left blank.

cindi tjelde Highlight cindi tjelde Highlight cindi tjelde Highlight

Section C - Description/Specifications Scope of Work

Clause List

C001 SCOPE OF WORK

See Attachment 1 - Statement of Work

The remainder of this page has been intentionally left blank.

Section D - Packaging and Marking Clause List

Section E - Inspection and Acceptance Clause List

3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)

This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:

https://fast.faa.gov/contractclauses.cfm.

(End of clause)

3.10.4-10 INSPECTION OF CONSTRUCTION (SEP 2009)

3.10.4-11 INSPECTION - DISMANTLING, DEMOLITION, OR REMOVAL OF IMPROVEMENTS

(APR 1996)

Section F - Deliveries or Performance Clause List

3.10.1-11 GOVERNMENT DELAY OF WORK (APR 1996)

(a) If the performance of all or any part of the work of this contract is delayed or interrupted (1) by an act of the Contracting Officer in the administration of this contract that is not expressly or impliedly authorized by this contract, or (2) by a failure of the Contracting Officer to act within the time specified in this contract, or within a reasonable time if not specified, an adjustment (excluding profit) shall be made for any increase in the cost of performance of this contract caused by the delay or interruption and the contract shall be modified in writing accordingly. Adjustment shall also be made in the delivery or performance dates and any other contractual term or condition affected by the delay or interruption. However, no adjustment shall be made under this clause for any delay or interruption to the extent that performance would have been delayed or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an adjustment is provided or excluded under any other term or condition of this contract.

(b) A claim under this clause shall not be allowed:

(1) for any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved, and

(2) unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the delay or interruption, but not later than the day of final payment under the contract.

(End of clause)

F001 FEDERAL HOLIDAYS OBSERVED / HOLIDAY MORATORIUMS

The following federal holidays are observed by the Federal Aviation Administration. No work will take place on holidays.

-New Year’s Day -Martin Luther King, Jr.’s Birthday -Washington’s Birthday -Memorial Day -Juneteenth -Independence Day -Labor Day -Columbus Day -Veterans Day -Thanksgiving Week -Christmas Week

If a federal holiday falls on a Saturday, the holiday is observed on the preceding Friday. If the federal holiday falls on a Sunday, the holiday is observed on the following Monday.

(End of Clause)

Section G - Contract Administration Data Clause List

3.10.1-23 CONTRACTING OFFICER'S REPRESENTATIVE-CONSTRUCTION CONTRACTS (APR

2012)

(a) The Contracting Officer may appoint other Government personnel to accomplish certain contract administration matters. While there shall be various titles and divisions of duties for these individuals, generically they are known as Contracting Officer's Representatives (CORs). The Contracting Officer will provide written notice of COR appointment(s), setting forth the authorities and limitations, to the Contractor within 5 calendar days prior to the notice to proceed. COR duties may include, but are not limited to:

(1) Perform as the authorized representative of the Contracting Officer for technical matters, including interpretation of specifications and drawings, and inspection and review of work performed.

(2) Perform as the authorized representative of the Contracting Officer for administrative matters, including reviewing payments, and updated delivery schedules.

(b) These representatives are authorized to act for the Contracting Officer in all specifically delegated matters pertaining to the contract, except:

(1) contract modifications that change the contract price or cost, technical requirements or time for performance, unless delegated field change order authority;

(2) suspension or termination of the Contractor's right to proceed, either for default or for convenience;

(3) final decisions on any matters subject to appeal, e.g., disputes under the "Contract Disputes" clause; and

(4) final acceptance under the contract.

(End of clause)

G001 INVOICING INSTRUCTIONS

Contractor is to submit draft payment requests concurrently to the Contracting Officer (CO) and the Contracting Officer's Representative (COR) for review and approval prior to uploading the invoice into FAA's e-invoicing system. Once the pay app documents have been reviewed and approved, the contractor will be instructed to upload the approved invoice into the FAA's e-invoicing system for payment. A minimum of 5% of the contract price will be held at completion of the project until all closeout contractual documents are received and approved by the FAA.

Payment requests are to include:

1) Draft Invoice (including updated schedule of values)

2) Updated project schedule reflecting progress to-date

3) All payrolls through the pay application end date

4) Construction waste management report, including supporting waste receipts.

See Contract Clause 3.3.1-2 Payments Under Fixed-Price Construction Contracts (Jul 2018) and 3.31-19 Prompt Payment for Construction Contracts (Jan 2021) for additional information regarding payments.

Section H - Special Contract Requirements Clause List

3.1.9-1 ELECTRONIC COMMERCE AND SIGNATURE (JUL 2020)

(a) The Electronic Signatures in Global and National Commerce Act (E-SIGN) establishes a legal equivalence between:

(1) Contracts written on paper and contracts in electronic form;

(2) Pen-and-ink signatures and electronic signatures; and

(3) Other legally-required written records and the same information in electronic form.

(b) With the submission of an offer, the offeror acknowledges and accepts the utilization of electronic commerce as part of the requirements of this solicitation and the resultant contract.

(c) Certain documents may need to be provided or maintained in original form, such as large-scale drawings impractical to convert to electronic format or a document with a raised seal signifying authenticity. This clause does not change or affect any other requirements that a document must be in paper format to satisfy legal requirements such as for certain real estate transactions.

(d) The use of electronic signature technology is authorized under this solicitation and the resulting contract.

(e) Contractors must not digitally sign any documents with software that uses the Secure Hash Algorithm 1 (SHA- 1). All digitally signed documents and contracts sent to the FAA must use a SHA-256 or higher hash algorithm. This is based on the National Institute of Standards and Technology (NIST) Policy Statement on Hash Functions dated August 5, 2015. Further guidance on the use of SHA-256 is in NIST Special Publication (SP) 800-57 Part 1, section

5.6.2 as amended and SP 800-131A, Revision 1 dated November 6, 2015. Additional guidance on the use of SHA-3 is in NIST SP 800-185 as amended.

(f) Contractors do not have to update documents previously digitally signed using SHA-1 hash algorithms unless the document requires updating. The FAA and contractors may continue to use SHA-1 for the following applications:

Verifying old digital signatures and time stamps, generating and verifying hash-based message authentication codes (HMACs), key derivation functions (KDFs), and random bit/number generation.

(End of Clause)

3.8.2-17 KEY PERSONNEL AND FACILITIES (JUL 2019)

(a) The personnel and/or facilities as specified below are considered essential to the work being performed hereunder and may, with the consent of the contracting parties, be changed from time to time during the course of the contract.

(b) Prior to removing, replacing, or diverting any of the specified personnel and/or facilities, the Contractor must notify in writing, and receive consent from, the Contracting Officer reasonably in advance of the action and must submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on this contract.

(c) No diversion will be made by the Contractor without the written consent of the Contracting Officer.

(d) The key personnel and/or facilities under this contract are:

Project Manager [ ] Superintendent [ ] Quality Control Manager [ ] Site Safety & Health Officer [ ]

(List key personnel and/or facilities)

(End of clause)

H001 STATE REGULATION OF FEDERAL CONSTRUCTION PROJECTS

FAA contractors may encounter requests from State and local governments for the FAA’s contractors to obtain building permits, zoning approval, sanitation approval, etc. Based on the “Supremacy Clause” set forth in Article 6 of the U.S. Constitution, construction contractors are not required to obtain most permits or approvals for work done on Federal construction projects. The States do have enforcement authority for safety and environmental protection as specified by the Occupational Safety and Health Administration (OSHA), the Comprehensive Environmental Response, Compensation and Liability (Superfund) Act (CERCLA), and the Resource Conservation and Recovery Act (RCRA).

Contractors who encounter attempts by State or local government entities to assess various types of fees against a FAA construction project should be advised to inform the Contracting Officer immediately if the assessing entity attempts in any way to prevent or hinder the contractor at the job site.

(End of Clause)

H002 APPLICABLE MINIMUM HOURLY WAGE RATES

The wage determination decision of the Secretary of Labor in this contract specifies the minimum hourly rate of wages which must be paid to the laborers and mechanics employed or work at the job site. The rates have been determined by the Secretary of Labor in accordance with the provisions of the Davis Bacon Act, as amended, to be prevailing rates for the corresponding classes of laborers employed on contracts of a similar character in the locality where the work is performed.

While the wage rates given in the decision are the MINIMUM rates required to be paid during the life of the contract, it is the responsibility of offerors to inform themselves as to local labor conditions, such as the prevailing wage rates, the length of the workday and work week, overtime compensation, fringe benefits payments, available labor supply, and prospective changes or adjustments to wage rates. The contractor must abide by and conform to all applicable laws, Executive Orders, and rules, regulations, and orders of the Secretary of Labor. No increase in contract price will be allowed or authorized for the payment of wage rates in excess of those listed in the contract wage determination decision.

The wage determination decision of the Secretary of Labor in this contract is solely for the purpose of setting for the minimum hourly wage rates required to be paid during the life of the contract and is not to be accepted as a guarantee, warranty, or representation of the wage rates indicated.

NOTE: THE DAVIS BACON ACT IS APPLICABLE (SEE CONTRACT CLAUSES). REFERENCE

THE ATTACHED GENERAL WAGE DECISION NO. CO20240017, dated 02/23/2024, FOR THE STATE OF

COLORADO (SEE SECTION “J”). THE WAGE DETERMINATION IS HEREBY INCORPORATED INTO

THIS REQUEST FOR OFFERS (RFO) AND WILL BE PART OF ANY RESULTANT CONTRACT.

Section I - Contract Clauses Clause List

3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)

This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:

https://fast.faa.gov/contractclauses.cfm.

(End of clause)

3.1.7-2 ORGANIZATIONAL CONFLICTS OF INTEREST (JAN 2023)

3.1.7-5 DISCLOSURE OF CONFLICTS OF INTEREST (JUL 2018)

3.2.2.3-47 PERMITS AND RESPONSIBILITIES (JUL 2004)

3.2.2.3-48 OTHER CONTRACTS (MAR 2009)

3.2.2.3-49 PROTECTING EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS (JUL 2004)

3.2.2.3-50 PROPERTY PROTECTION (OCT 2014)

3.2.2.3-51 OPERATIONS AND STORAGE AREAS (APR 2012)

3.2.2.3-52 USE AND POSSESSION BEFORE THE PROJECT IS COMPLETE (JUL 2004)

3.2.2.3-53 CLEANING UP AND ROADWAY MAINTENANCE (JUL 2004)

3.2.2.3-54 PREVENTING ACCIDENTS (JUL 2004)

3.2.2.3-55 AVAILABILITY AND USE OF UTILITY SERVICES (JUL 2004)

3.2.2.3-58 LAYOUT OF WORK (MAR 2009)

3.2.2.3-59 ORGANIZATION AND DIRECTION OF THE WORK (JUL 2004)

3.2.2.3-61 RESPONSIBILITY OF THE ARCHITECT-ENGINEER CONTRACTOR (JUL 2004)

3.2.2.3-64 DISMANTLING AND DEMOLISHING OF PROPERTY (JUL 2004)

3.2.2.3-83 PROHIBITION AGAINST CONTRACTING WITH INVERTED DOMESTIC

CORPORATIONS (OCT 2015)

3.2.2.7-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH

CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (APR 2023)

3.2.2.7-8 DISCLOSURE OF TEAM ARRANGEMENTS (APR 2008)

3.2.4-4 FIXED-PRICE CONTRACTS WITH ECONOMIC PRICE ADJUSTMENT-LABOR AND

MATERIAL (OCT 2019)

3.2.5-1 OFFICIALS NOT TO BENEFIT (APR 2021)

3.2.5-3 GRATUITIES OR GIFTS (OCT 2019)

3.2.5-4 CONTINGENT FEES (OCT 1996)

3.2.5-5 ANTI-KICKBACK PROCEDURES (OCT 2019)

3.2.5-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE FAA (OCT 2022)

3.2.5-8 WHISTLEBLOWER PROTECTION FOR CONTRACTOR EMPLOYEES (APR 1996)

3.2.5-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (APR 2023)

3.2.5-14 DISPLAY OF HOTLINE POSTER(S) (APR 2023)

3.3.1-2 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (JUL 2018)

3.3.1-3 PAYMENTS UNDER FIXED-PRICE ARCHITECT-ENGINEER CONTRACTS (JUL 2018)

3.3.1-9 INTEREST (APR 2023)

3.3.1-15 ASSIGNMENT OF CLAIMS (JUL 2018)

3.3.1-18 PROMPT PAYMENT FOR FIXED-PRICE ARCHITECT-ENGINEER CONTRACTS (JAN

2021)

3.3.1-19 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2021)

3.3.1-20 PROVIDING ACCELERATED PAYMENT TO SMALL BUSINESS SUBCONTRACTORS

(OCT 2012)

3.3.1-34 PAYMENT BY ELECTRONIC FUNDS TRANSFER- SYSTEM FOR AWARD

MANAGEMENT (JUL 2018)

3.3.1-40 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (APR 2022)

3.3.2-1 FAA COST PRINCIPLES (OCT 2019)

3.4.1-10 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (OCT 2020)

3.4.1-12 INSURANCE (OCT 2019)

3.4.1-13 ERRORS AND OMISSIONS (JUL 1996)

3.4.2-6 TAXES - CONTRACTS PERFORMED IN U.S. POSSESSIONS OR PUERTO RICO (OCT

1996)

3.4.2-8 FEDERAL, STATE, AND LOCAL TAXES - FIXED PRICE CONTRACT (JUL 2019)

3.5-1 AUTHORIZATION AND CONSENT (APR 2023)

3.5-4 PATENT INDEMNITY - CONSTRUCTION CONTRACTS (JAN 2009)

3.5-24 UNLIMITED RIGHTS IN DATA - ARCHITECT-ENGINEER CONTRACTS (OCT 2021)

3.6.1-1 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (OCT 2019)

3.6.1-3 UTILIZATION OF SMALL, SMALL DISADVANTAGED, WOMEN-OWNED, SERVICE-

DISABLED VETERAN OWNED, AND HUBZONE SMALL BUSINESS CONCERNS (JAN 2021)

3.6.1-15 POST-AWARD SMALL BUSINESS PROGRAM RE-REPRESENTATION (JUL 2023)

3.6.2-1 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT-OVERTIME

COMPENSATION (OCT 2018)

3.6.2-2 CONVICT LABOR (APR 1996)

3.6.2-9 EQUAL OPPORTUNITY (JUL 2023)

3.6.2-12 EQUAL OPPORTUNITY FOR VETERANS (APR 2022)

3.6.2-13 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (APR 2022)

3.6.2-16 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (OCT 2018)

3.6.2-18 DAVIS BACON ACT (JUL 2023)

3.6.2-19 WITHHOLDING-LABOR VIOLATIONS (JUL 2023)

3.6.2-20 PAYROLLS AND BASIC RECORDS (JUL 2023)

3.6.2-21 APPRENTICES, TRAINEES, AND HELPERS (JUL 2023)

3.6.2-22 SUBCONTRACTS (LABOR STANDARDS) (JUL 2023)

3.6.2-23 CERTIFICATION OF ELIGIBILITY (JUL 2023)

3.6.2-31 FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS-

PRICE ADJUSTMENT (JUL 2023)

3.6.2-35 PREVENTION OF SEXUAL HARASSMENT (JUL 2023)

3.6.2-39 TRAFFICKING IN PERSONS (JUL 2023)

3.6.2-44 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS

ACT (JUL 2023)

3.6.2-46 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JUL 2023)

3.6.2-47 MINIMUM WAGES FOR CONTRACTOR WORKERS UNDER EXECUTIVE ORDER 14026

(JUL 2023)

3.6.3-13 AFFIRMATIVE PROCUREMENT OF RECYCLED CONTENT AND PRODUCTS UNDER

SERVICE AND CONSTRUCTION CONTRACTS (JAN 2020)

3.6.3-14 USE OF ENVIRONMENTALLY PREFERABLE PRODUCTS (JAN 2020)

3.6.3-17 EFFICIENCY IN ENERGY-CONSUMING PRODUCTS (JAN 2020)

3.6.3-23 DELIVERY OF ELECTRONIC AND PAPER DOCUMENTS (JAN 2020)

3.6.3-24 ASBESTOS NESHAP COMPLIANCE (OCT 2015)

3.6.3-25 AEROSOLS (OCT 2016)

3.6.3-26 FOAMS (OCT 2016)

3.6.4-8 BUY AMERICAN ACT AND FAA BUY AMERICAN PREFERENCE - USMCA

IMPLEMENTATION ACT - BALANCE OF PAYMENTS PROGRAM (JAN 2024)

3.6.4-10 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JAN 2010)

3.6.6-1 DRUG FREE WORKPLACE (APR 2023)

3.6.6-2 SEAT BELT USE BY CONTRACTOR EMPLOYEES (APR 2023)

3.6.6-3 CONTRACTOR POLICY TO BAN TEXT MESSAGING WHILE DRIVING (JUL 2023)

3.8.9-2 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND

VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (JUL 2023)

3.9.1-1 CONTRACT DISPUTES (JAN 2020)

3.9.1-2 PROTEST AFTER AWARD (AUG 1997)

3.10.1-7 BANKRUPTCY (APR 1996)

3.10.1-8 SUSPENSION OF WORK (SEP 1998)

3.10.1-12 CHANGES - FIXED-PRICE (APR 1996)

3.10.1-12 CHANGES - FIXED-PRICE (APR 1996) - ALTERNATE III (APR 1996)

3.10.1-15 CHANGES-CONSTRUCTION, DISMANTLING, DEMOLITION, OR REMOVAL OF

IMPROVEMENTS (JUL 2023)

3.10.1-20 WARRANTY-CONSTRUCTION (JUL 1996)

3.10.1-25 NOVATION AND CHANGE-OF-NAME AGREEMENTS (OCT 2007)

3.10.1-28 CHANGES REQUIRED BY AMS (JAN 2024)

3.10.2-4 SUBCONTRACTORS AND OUTSIDE ASSOCIATES AND CONSULTANTS (APR 1996)

3.10.6-1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (OCT

1996)

3.10.6-6 DEFAULT (FIXED PRICE CONSTRUCTION) (OCT 1996)

3.13-14 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT

AWARDS (OCT 2023)

3.2.2.3-33 ORDER OF PRECEDENCE (MAR 2009)

The order of precedence is:

(a) The Schedule (excluding the specifications);

(b) Representations;

(c) Contract clauses;

(d) Other documents, exhibits, and attachments;

(e) The specifications; and

(f) The drawings.

(End of clause or provision)

3.2.2.3-39 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OR DATA OTHER

THAN CERTIFIED COST OR PRICING DATA - MODIFICATIONS (JAN 2022)

(a) Request for exception from certified cost or pricing data requirements.

(1) In lieu of submitting certified cost or pricing data for modifications under this contract, on the date of the agreement on price or the date of the award, whichever is later, the Contractor may submit a written request for exception by submitting the information described in paragraphs (a)(1)(i) and (ii) of this clause. The Contracting Officer may require additional supporting information, but only to the extent necessary to determine whether an exception should be granted, and whether the price is fair and reasonable.

(i) Identification of the law or regulation establishing the price offered. If the price is controlled under law by periodic rulings, reviews, or similar actions of a governmental body, attach a copy of the controlling document, unless it was previously submitted to the contracting office.

(ii) Information on modifications of contracts or subcontracts for commercial items.

(A) If-

(1) The original contract or subcontract was granted an exception from certified cost or pricing data requirements because the price agreed upon was based on adequate price competition or prices set by law or regulation, or was a contract or subcontract for the acquisition of a commercial item; and

(2) The modification (to the contract or subcontract) is not exempted based on one of these exceptions, then the Contractor may provide information to establish that the modification would not change the contract or subcontract from a contract or subcontract for the acquisition of a commercial item to a contract or subcontract for the acquisition of an item other than a commercial item.

(B) For a commercial item exception, the Contractor must provide, at a minimum, information on prices at which the same item or similar items have previously been sold that is adequate for evaluating the reasonableness of the price of the modification. Dependent upon the commercial items being catalog items, market-priced items, or items included on an active Federal Supply Service Multiple Award Schedule contract, the Contractor must include the corresponding information pursuant to that of which is described in paragraphs (a)(1)(B)(1); (a)(1)(B)(2) or (a)(1)(B)(3) of this clause:

(1) For catalog items, a copy of or identification of the catalog and its date, or the appropriate pages for the offered items, or a statement that the catalog is on file in the buying office to which the proposal is being submitted. Provide a copy or describe current discount policies and price lists (published or unpublished), e.g., wholesale, original equipment manufacturer, or reseller. Also explain the basis of each offered price and its relationship to the established catalog price, including how the proposed price relates to the price of recent sales in quantities similar to the proposed quantities.

(2) For market-priced items, the source and date or period of the market quotation or other basis for market price, the base amount, and applicable discounts. In addition, describe the nature of the market.

(3) For items included on an active Federal Supply Service Multiple Award Schedule contract, proof that an exception has been granted for the schedule item.

(2) The Contractor grants the Contracting Officer or an authorized representative the right to examine, at any time before award, books, records, documents, or other directly pertinent records to verify any request for an exception under this clause, and the reasonableness of price. For items priced using catalog or market prices, or law or regulation, access does not extend to cost or profit information or other data relevant solely to the Contractor's determination of the prices to be offered in the catalog or marketplace.

(b) Requirements for certified cost or pricing data.

If the offeror is not granted an exception from the requirement to submit certified cost or pricing data, the following applies:

(1) The offeror must prepare and submit certified cost or pricing data, data other than certified cost or pricing data, and supporting attachments in accordance with the information contained at AMS Guidance T3.2.3.G.1 "Instructions for Submitting Certified Cost/Price Proposals for Supplies, Services, or Construction," which is incorporated by reference with the same force and effect as though it were inserted here in full text. The instructions in AMS T3.2.3.G.1 are incorporated as a mandatory format to be used in this contract.

(2) As soon as practicable after agreement on price, but before contract award (except for unpriced actions such as letter contracts), the offeror must submit a Certificate of Current Cost or Pricing Data that conforms to the instructions contained in the Appendix G1 to AMS Guidance T3.2.3, 'Cost and Price Methodology."

(End of clause)

3.2.2.3-41 PERFORMING WORK (JUL 2004)

The Contractor (you) must perform, using your own organization, work equivalent to at least 15 percent of the total amount of work under the contract on the site. The CO may modify this contract to reduce this percentage if you request a reduction and the CO determines that it would be to the Government's advantage to do so.

(End of clause)

3.2.2.3-42 DIFFERING SITE CONDITIONS (JUL 2004)

(a) Before the conditions are disturbed, the Contractor (you) must promptly notify the Contractor Officer (CO) in writing of either or both of the following conditions:

(1) Subsurface or latent physical conditions at the site which differ materially from those described in this contract.

(2) Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inherent to the type of work the contract covers.

(b) FAA (we) will investigate the site conditions promptly after receiving the notice. If the CO determines that the conditions do materially differ and cause an increase or decrease in your cost of, or the time required for, performing any part of the work under this contract, the CO will make an equitable adjustment under this clause and modify the contract accordingly in writing.

(c) The CO will not accept your request for an equitable adjustment to the contract unless you give the written notice. However, the CO may extend the time for giving written notice.

(d) The CO will not accept your request for an equitable adjustment for differing site conditions after we make final payment under this contract.

(End of clause)

3.2.2.3-44 PHYSICAL DATA (JUL 2004)

Data and information the FAA (we, us) provides or refers to below is for the Contractor's (your) information. We are not responsible for your interpretation of or conclusions based on the data or information. Further, we do not warrant construction methodology which may be included in these documents.

(a) The descriptions of physical conditions on the drawings and in the specifications are the result of site investigations by facility surveys, as-builts, reference drawings, etc. as noted in Section J as reference documents..

(b) Other relevant information N/A.

(End of clause)

3.2.2.3-45 MATERIAL AND WORKMANSHIP (JUL 2004)

(a) The Contractor (you) must incorporate equipment, material, and articles that are new and of the most suitable grade for the purpose intended to do the work this contract covers, unless the contract provides otherwise. The FAA

(we) encourages you to use recycled materials to manufacture the products. If the contract specifies equipment, material, or articles by trade name, make, or catalog number, you must use those specific items. We will not accept equivalent items unless the specification authorizes it.

(b) You must perform all work under this contract in a skillful and workmanlike manner. The Contracting Officer (CO) may require, in writing, that you remove employees whom the CO determines are incompetent, careless, or otherwise objectionable.

(End of clause)

3.2.2.3-46 SUPERVISING THE CONTRACT WORK (JUL 2004)

At all times while the Contractor (you) performs this contract, and until you complete the work and FAA accepts it, you must directly supervise the work or assign and have on the worksite a competent supervisor who the Contracting Officer (CO) is satisfied with and who has authority to act for you.

(End of clause)

3.2.2.3-56 SCHEDULES FOR CONSTRUCTION CONTRACTS (JUL 2004)

(a) The Contractor (you) must, within five days after the work on the contract starts or after another period determined by the Contracting Officer (CO), prepare and submit to the CO for approval three copies of a practicable schedule showing the order in which you propose to perform the work, and the dates you plan to start and finish the important stages of the work (including acquiring materials, plant, and equipment). The schedule must be in a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion during the contract period. If you do not submit a schedule within the time prescribed, FAA (us) may withhold payments until you submit the schedule. If you fall behind your schedule, you must send a revised schedule with your next request for payment. Provide us additional schedules as soon as practicable if the CO requests them.

(b) With each payment request, submit a copy of the last schedule you submitted, annotated to show progress to date. If at any time, in the CO's opinion, you have fallen behind the schedule to an extent which would jeopardize timely completion, you must take steps to improve progress, including those the CO may require, to enable timely completion without additional cost to us. The CO may require you to increase the number of shifts, the amount of overtime, days of work each week, or the amount of constructor plant being used. You must submit any supplementary schedules the CO deems necessary to demonstrate how you will regain the rate of progress necessary for timely completion.

(c) If you fail to comply with the CO's requirements under this clause, the CO may determine that you are not performing the work with enough diligence to ensure completing it within the time the contract requires. If the CO makes this determination, the CO may terminate this contract for default.

(End of clause)

3.2.2.3-60 SPECIFICATIONS, DRAWINGS, AND MATERIAL OFFERS (MAR 2009) - ALTERNATE

I (MAR 2009)

(a) If either the specifications or the drawings (but not both) mention tasks, the Contractor (you) must assume that the tasks are in both. If the drawings and specifications differ, the specifications govern. If there is a discrepancy in the figures, in the drawings, or in the specifications, submit the matter promptly to the Contracting Officer (CO), who will promptly determine which governs, and notify you in writing. Any adjustment you make without the CO's determination is at your own risk and expense. From time to time the CO will provide necessary detailed drawings and other information, unless otherwise provided.

(b) Wherever in the specifications or the drawings FAA (we, our) uses "directed," "required," "ordered," "designated," "prescribed," or similar words, they refer to the CO's requirements. Similarly, "approved," "acceptable," "satisfactory," or similar words refer to the CO's approval, unless otherwise expressly stated. You must have a complete set of plans and specifications on site and available for our use.

(c) Where we use "as shown," "as indicated," "as detailed," or similar words, they refer to the drawings accompanying this contract, unless stated otherwise. The word "provided" means "provided and installed."

(d) Omissions from the drawings and specifications or the erroneous description of details of work which are necessary to carry out the intent of the drawings and specifications, or which are customarily performed, does not relieve you from performing those omitted or erroneously described details of the work. You must perform them as if fully and correctly set forth and described in the drawings and specifications.

(e) You must check all drawings we provide to you before starting work and must promptly notify the CO of any discrepancies. In general you should follow figures marked on drawings, rather than scale measurements. In general, large scale drawings have precedence over small scale drawings. You must compare all drawings and verify the figures before laying out the work. If you do not verify the figures, you will be responsible for any errors you might have avoided had you verified them.

(f) "Shop drawings" means drawings, you or any subcontractor submit to us under a construction contract, showing in detail the proposed fabrication and assembly of structural elements and the installation (that is, form, fit, and attachment details) of materials or equipment. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials you provided to explain in detail specific portions of the work the contract requires.

FAA may duplicate, use, and disclose in any manner and for any purpose shop drawings you deliver under this contract.

(g) If this contract requires material offers (for example, shop drawings, catalog cuts, certificates of conformance), you must coordinate all of your offers, and review them for accuracy, completeness, and compliance with contract requirements. You must provide evidence that you approve the submittals. If you submit materials to us without this evidence, we may return them and ask you to resubmit them. The CO will indicate whether he or she approves or disapproves your offer, and if the CO does not approve it as submitted, will indicate our reasons for rejecting it. Any work done before the CO's approval is at your risk. The CO's approval does not relieve you from responsibility for any errors or omissions in the submittals, nor from responsibility for complying with the contract requirements, except as described under (h).

(h) If you submittals vary from the contract requirements, you must describe the variations in writing, separate from the submittal, when you submit them. Send this description, a copy of the offer, and a proposal to incorporate it into the contract directly to the CO. If the CO approves a variation, the CO must issue an appropriate contract modification, unless the variation is minor or does not involve a change in price or in time of performance.

(i) You must submit to the CO for approval four copies (unless otherwise indicated) of all shop drawings as called for under the various headings of these specifications. The CO will keep three sets (unless otherwise indicated) of all offers and will return one set to you.

(j) You must insert this clause, with appropriate changes in the designation of the parties, in all subcontracts.

(k) When you finish the work under this contract, you must provide (see SOW) complete reproducible sets of all shop drawings as we finally approve them. These drawings must show all changes and revisions made up to the time you finish the work and we accept it.

(End of clause)

3.2.2.3-62 PRECONSTRUCTION CONFERENCE (JUL 2004)

The successful offeror must attend a pre-construction conference at a site the Contracting Officer designates before starting the work.

(End of clause)

3.2.2.3-66 CONTRACTOR'S DAILY LOG (OCT 2014)

The Contractor (you) must submit a "Daily Log." You must complete the forms daily and deliver them to the designated FAA Contracting Officer's (CO) Representative. The forms must include, but is not limited to, workers by classification, construction equipment moved on and off the site, materials and equipment delivered to the site, inspections and tests performed, and total cumulative hours worked.

(End of clause)

3.2.2.3-68 SAFETY AND HEALTH (OCT 2014) - ALTERNATE I (JUL 2004)

(a) Before beginning work, the Contractor (you) must:

(1) Perform a hazards analysis of the work specified in this contract. Consider both the site and adjacent conditions.

Identify all significant hazards. Some of the hazards you might encounter are tripping, falling, construction equipment injuries, power tools, etc.

(2) Submit a safety plan for dealing with each specific hazard identified, whether you or FAA identified it.

(3) Meet with the CO's representatives during the preconstruction conference to discuss and to develop a mutual understanding about the content and implementation of the plan.

(4) The CO or her or his representatives may require other hazards to be added to the plan. If the CO determines that your planned hazard avoidance measures are insufficient, the CO or a designated representative may require you to revise the plan. You may not begin work involving identified hazards unless you have submitted adequate plans to the CO and the CO has reviewed them. This approval does not relieve you of your liability for safe performance.

(End of clause)

3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (OCT 2021)

The Contractor must (a) begin work under this contract within 5 calendar days after the date you receive the notice to proceed, (b) perform the work diligently, and (c) complete the entire…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .