SMBA Phase A Industry Day With Question Topics.pdf
PDF 1 MB Posted
- Attached to
- LEOS Sounder Request for Information Federal contract opportunity
- Solicitation number
- RFI-LEOS-Sounder2022
About this file
This document outlines a request for information for a Low Earth Orbit Earth Observation System Sounder for Microwave Brightness and Analysis Phase A study. The National Aeronautics and Space Administration Goddard Space Flight Center is seeking feedback on a draft statement of work, performance specification document, and instrument mission assurance requirements for a microwave sounding instrument to fly on the National Oceanic and Atmospheric Administration's Low Earth Orbit Earth Observation System satellites beginning in 2031. Interested vendors should provide comments on the feasibility of the study scope and clarity of requirements, as well as input to risk reduction and technology development efforts, by November 8, 2022. The agency intends to award up to four $5 million fixed-price contracts for 12-month definition-phase studies, with final reports due one year after award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SMBA Industry Day Response_Architecture.pdf | ||
| AMS Panelv2.pdf | ||
| LEO NEON and SMBA Organization.pdf | ||
| Grycenkov et al_disag_v4.pdf | ||
| LEOS SMBA Questions and Answers (20230124).pdf | ||
| Inherited_Items_Process_2.pdf | ||
| Industry Day Questions and Responses.pdf | ||
| Industry Day - Agenda.pdf | ||
| Industry Day - Early Notice (20221121).pdf | ||
| Interested Vendors List (20221117).pdf | ||
| LEOS SMBA Questions and Answers (20221117).pdf | ||
| 470-MWS-00434 SMBA Phase A SOW_RFI Release_V0.pdf | ||
| 470-MWS-00435 SMBA Instrument PSD_RFI Release_V0.pdf | ||
| 470-00436 SMBA IMAR_RFI Release_V0.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1LEO Earth Observation System Program
Sounder for Microwave Brightness and Analysis (SMBA)
Phase A Study Industry Day Jessica Knizhnik
Bruce Tsai Ken Yienger Negar Ehsan
Brooke Greybeck Ed Kim
Tim Walsh
JPSS Reviewed – Not Subject to Export Control
2LEO Earth Observation System Program
Welcome/Introduction/Logistics
3LEO Earth Observation System Program
Ground Rules
• The NOAA/NASA team cannot have any technical discussions with vendors outside of full group discussions and official one on ones
• Information provided to one vendor must be provided to all vendors
– Company questions will be anonymous
• The final chart deck from today will be posted on SAM.gov
4LEO Earth Observation System Program
Welcome to SMBA Phase A Industry Day
• We are using today to
– Elaborate on the government’s thinking behind the documents that were released with the SMBA Phase A Study Request for Information
– Answer questions vendors might have
– Foster discussion on the LEOS program and the SMBA instrument
The Phase A Study Statement of Work (SOW), Performance Specification Document (PSD), and Instrument Mission Assurance Requirements (IMAR) as well as other information included in the Request for Information are available on SAM.gov at the following link:
https://sam.gov/opp/6efaeb75571e46529e3fd9681e9d2aab/view
Anything in the final SMBA Phase A Study Request for Proposal (RFP) will supersede the information provided as part of Industry Day.
https://sam.gov/opp/6efaeb75571e46529e3fd9681e9d2aab/view
5LEO Earth Observation System Program
Who’s Here SMBA Team
• Jessica Knizhnik – SMBA Instrument Manager
• Bruce Tsai – SMBA Contracting Officer
• Eric Newman – LEOS Procurement Manager
• Quinton Nabors – SMBA Financial Manager
• Ed Kim – Acting SMBA Instrument Scientist
• Negar Ehsan – SMBA Senior Microwave
Engineer
• Ken Yienger – LEOS Chief Engineer
• Brooke Greybeck – SMBA Chief Safety and
Mission Assurance Officer
• David Bogart – LEOS Program Chief Safety and
Mission Assurance Officer
• Tim Walsh – LEOS Program Manager
• Support service contractor team
Vendors
• Ball
• L3Harris
• Northrop Grumman
• Orbital Micro Systems
• Raytheon
• Spire Global
6LEO Earth Observation System Program
Agenda
7LEO Earth Observation System Program
Other Logistics
• Food
– Snack café in the lobby
– Goddard main campus cafeterias in buildings 1, 21, 33, and 34
– Nearby restaurants – Chevy’s, Osaka, Subway
• Wifi
– Network: Guest-CNE
– Login Page Sponsoring Organization: 470
8LEO Earth Observation System Program
LEOS Program Overview
9LEO Earth Observation System Program
Serving NOAA NESDIS User Needs From Low-Earth Orbit (LEO)
Nearly every product category across the thematic areas in the NESDIS Level Requirements relies on LEO observational measurements
IR/MW/RO
Soundings
MW Imagery
AltimetryRADAR Imagery
LIDAR
UV Imagery LEO Program Level Objectives NESDIS-REQ-4400.1
VIS/NIR/IR Imagery
Scatterometry
10LEO Earth Observation System Program
Evolving LEO Satellite Technology to Improve Forecast Accuracy
1960 1980 2000 2020 2040 TIROS-1 launch in
April 1960. 48° inclination
Nimbus-1 launch in Aug. 1964. First infrared sensor
TIROS-9 launch in 1965. “Cartwheel configuration.”
First polar orbit
TIROS-N launch in October 1978. First
AVHRR
First microwave sounder—increase in forecast accuracy due to ability to see through clouds
NOAA-15,16, 17.
More microwave channels
NOAA + EUMETSAT
IJPS agreement
NPOESS/JPSS
development
Collaboration with DoD on the Defense Meteorological Satellite Program and WINDSAT Coriolis
First hyperspectral infrared sounders
JPSS series operational
METOP-SG
Jason-2/3
COSMIC-2 GNSS RO
GOSAT3 / AMSR3
Next-gen sounder development
Increased national and international partnerships
Enterprise ground system
Capitalize on cutting-edge technology
Information integration
11LEO Earth Observation System Program
Exploiting the Trends: Leveraging Advancements
• In FY 2022, NOAA began conceptualizing a Low Earth Orbit (LEO) Weather Satellites (LWS) Program, to set the stage for managing future polar and other low earth and medium earth orbit satellite observations as loosely coupled programs.
• Make use of industry’s significant investment of funding, expertise, and innovation to date.
• Put capabilities where and when we want them, enabled by shorter development timelines and more frequent launches.
• Provide more capability at a better price, leveraging smaller and more capable instruments and satellites.
• Achieve greater agility to incorporate continuous advancement, using new business models.
12LEO Earth Observation System Program
Improved Microwave (MW) and Infrared (IR) Sounding Measurements
• LEO Soundings (MW and IR) have the highest impact on NWP forecast skills.
– 80% of data that feeds Numerical Weather Prediction (NWP) models comes from existing LEO sats
• With Existing Partner, LEOS Program achieves 4-hour global refresh (+3 Improvement)
– METOP (0930), JPSS/LEOS (1330), and LEOS(1730)
– LEOS Missions Provide MW/IR Soundings in BOTH 1330 (existing) and 1730 (proposed) LTAN’s
• Partnering with EUMETSAT EPS-Sterna proposed MW constellation, we can achieve 2-hour global refresh (+5 Improvement)
– Sterna Satellites Planned for 1130, 1530 and 1930 LTANs (with reduced MW channels)
Adding Sounders to current two orbits significantly Improves forecast skill
Metop
(0930 LTAN)
NOAA JPSS/LEOS
(1330 LTAN)
NOAA LEOS
(1730 LTAN)
Proposed Future MW Constellation
Proposed Future IR Constellation
Sterna (1130, 1530, and 1930 LTANs)
Metop
(0930 LTAN)
JPSS/LEOS
(1330 LTAN)
NOAA
LEOS
(1730 LTAN)
Government Reference Mission
13LEO Earth Observation System Program
SMBA Overview
14LEO Earth Observation System Program
Next Generation Backbone Microwave Sounder
• As the requirements reflect, SMBA will serve as the backbone microwave sounder for the LEOS program.
• Planning to include:
– All ATMS channels plus 118GHz and 229GHz channels
– Radio Frequency Interference (RFI) detection and hyperspectral capabilities
– Intercalibration performance
• Capabilities driven by the science community’s needs as described in the following reports
– Systems performance Assessment Team (SAT), Boukabara, S.(chair), Gallagher, F.(co-chair). [Scientific Guidance for potential study and design of Microwave Sounder (for SounderSat and GEO-XO)]. Retrieved from NOAA/NESDIS Center for Satellite Applications and Research.
September 17, 2020.
– NOAA workshop on MW sounders: https://doi.org/10.25923/wkgd-pw75 https://doi.org/10.25923/wkgd-pw75
15LEO Earth Observation System Program
From NOAA Products to Channel Choices & Prioritizations (1/5)
Climate channel needs
NWP channel needs
Other NOAA product channel needs (hurricane 4casts, MIRS, etc)
16LEO Earth Observation System Program
Prioritizations (2/5)
• NWP needs: T & q profiles can be generated from a variety of channel choices once the bands are set
• Climate needs: long-term trend analyses benefit strongly from channel choices consistent w/previous channel choices
• Other product needs: algorithms often have specific channel needs
17LEO Earth Observation System Program
Prioritizations (3/5)
NWP channel choices
• T & q sounding are the SMBA’s top priority products, respectively, hence T & q sounding bands & channels are priorities 1,2, respectively, in PSD Table 4.0-1.
• There is flexibility regarding exact frequencies for both sounding & window channels for T & q profile generation.
• The number, exact center frequency, and width of channels are chosen to achieve performance targets for NEDT, vertical resolution, etc.
• Certain other channels (window & quality control channels) are needed to maintain & improve the quality of T & q soundings.
Hence these channels are priority 3.
• Priorities I,II,III,IV in Table 4.1-1 map to priorities 1,2,3,11 in Table 4.0-1.
• Hyperspectral & RFI considerations may modify the tradespace.
18LEO Earth Observation System Program
Prioritizations (4/5)
Climate needs:
• Long-term trend analyses benefit strongly from channel choices consistent w/previous channel choices (AMSU & MSU)
• Climate applications are lower priority than NWP for SMBA, hence channel continuity is lower priority in PSD Table 4.0-1
• Mixing some ‘continuity’ channels with some new channels may be an option
• Hyperspectral & RFI considerations may modify the tradespace
19LEO Earth Observation System Program
Prioritizations (5/5)
Other performance parameters in Table 4.0-1 have prioritization also based on the importance of T & q profiles as well as other considerations.
20LEO Earth Observation System Program
SMBA Performance Capabilities Prioritization Priority# Performance Factor Baseline Aspirational Target
1 Channels for direct Temperature Sounding
*13 Channels around 50-60 GHz and 7 channels around 118GHz line
*More than 20 channels around 50-60 GHz and 118GHz line
2 Channels for direct Moisture sounding
*5 Channels or more around 183 GHz
*10 Channels or more around 183 GHz
Window channels; channels for cloud, precip, ice detection for direct all-sky assimilation and NWP QC
Channels at 23.8, 31.4, 88.2. One channel at 165.5 (TBR) and/or 229 (TBR) GHz channels Other channel combinations will be considered. Such as: at least 4 channels at low frequencies (priority order) (i.e. 22-23 GHz(a), 31-37 GHz(b), 89 GHz(c) and 18 GHz (d)) if possible, channels for TPW integration, cloud/precip detection and surface signal distinction
4 Spatial coverage (daily)
100% Global Coverage 100% Global Coverage
5 Noise Level (NEDT) for Temperature sounding channels
See Table 4.1-2 See Table 4.1-2
6 Noise level (NEDT) for Moisture sounding channels
See Table 4.1-2 See Table 4.1-2
7 Spatial horizontal resolution As-good as ATMS Smaller (better) than ATMS 8 Spatial sampling Contiguous footprints (or better) Oversampling (Spatial Nyquist sampling at a minimum) to enable higher spatial resolution 9 Scan geometry Cross track or conical Cross track or conical 10 Polarization Single linear polarization Baseline, and dual-polarization (vertical and horizontal) for window channels below 50 GHz 11 ATMS Channels Continuity Yes, for similar channels Yes, for similar channels 12 Calibration accuracy See Table 4.1-2 Less than values in Table 4.1-2
23LEO Earth Observation System Program
Radio Frequency Interference Some relevant presentations, reports:
• IGARSS 2022, FARS session
• “Recent RFI-related Developments from a
NOAA LEO Perspective” E.Kim. (contains an overview of many topics)
• RFI 2019 & 2022 workshops
• http://www.rfi2019.org/
• https://events.ecmwf.int/event/258/
• ECMWF RFI workshop https://www.ecmwf.int/en/elibrary/19026-radio-frequency-interference-rfi-workshop-final-report
• NOAA workshop on MW sounders
• https://doi.org/10.25923/wkgd-pw75 http://www.rfi2019.org/ https://events.ecmwf.int/event/258/ https://doi.org/10.25923/wkgd-pw75
24LEO Earth Observation System Program
Phase A Study Goals
• Refine requirements and mature technology
• Balance the need for a backbone instrument with the desire to be flexible on tailoring requirements and to realize significant cost and schedule savings
– We are very open to and interested in feedback.
– SOW, PSD, and IMAR reflect NOAA/NASA team’s initial expectations. We are open to suggestions on these expectations.
• Move instrument to at least SRR/SDR
– Desire to move instrument to PDR or CDR
25LEO Earth Observation System Program
Phase A Study SOW Guiding Assumptions (1/2) The Flight hardware development cost and schedule estimates shall be based on the following assumptions:
• 1 Engineering Test Unit (ETU), to be completed and tested NLT CDR, that can make calibrated radiometric measurements. This ETU will be fabricated using the same manufacturing processes as the flight instruments.
• 4 Flight Units plus parts for 5 more flight models to be procured concurrently, with contractual options to build units 5, 6, 7, 8, and 9. Deliveries will be as shown in the following schedule (all dates are for the Government Fiscal Year):
MILESTONE DATE (assume 1st day of quarter) Flight Contract Award Q1 FY25 Flight Model 1 Pre-Ship Review (PSR1) Q1 FY30 Launch 1 Readiness Date Q1 FY31 Flight Models 2, 3, and 4 PSR (PSR234) Q1 FY32 Launch 2 Readiness Date Q1 FY34 Launch 3 Readiness Date Q1 FY37 Launch 4 Readiness Date Q1 FY40
These assumptions are for study planning purposes.
We expect to revise them during the Phase A studies.
26LEO Earth Observation System Program
• 1 year is needed between Pre-Ship Review (PSR) for each flight model and the Launch Readiness Date for that flight model.
• No Government Furnished Equipment (GFE) will be provided. If there is specific Government owned equipment which the contractor is proposing to utilize, then this equipment shall be specifically identified, along with the benefit and verification of availability.
• Instrument Class: C (as defined in NPR 8705.4)
• Mission durations: 5 year on-orbit mission life after 10 year on-ground storage after instrument delivery
• The following instrument-level reviews will be held for the first flight build: SRR, IBR, PDR, CDR, PER, PSR. Subsequent flight builds will hold a PER and PSR. Review pre-requisites, content, and success criteria are documented in NPR 7123.1.
Phase A Study SOW Guiding Assumptions (2/2) The Flight hardware development cost and schedule estimates shall be based on the following assumptions:
These assumptions are for study planning purposes.
We expect to revise them during the Phase A studies.
27LEO Earth Observation System Program
Follow On Options
• Suggested long term schedule requirement
– Starts, instrument delivery, and material procurement milestones
– The nominal launch readiness dates (LRD) and instrument no-later-than need dates are as follows:
• Note: The options for an additional 5 instruments led to the 10 year on ground storage life.
Mission Instrument Need Date (NLT, Gov. FY) LRD (Gov. FY)
F5 Q1 FY33 Q3 FY38
F6 Q1 FY33 Q1 FY40
F7 Q1 FY33 Q3 FY41
F8 Q1 FY33 Q1 FY43
F9 Q1 FY33 Q3 FY44
28LEO Earth Observation System Program
RFI FAQs and Other Q&A
29LEO Earth Observation System Program
Procurement Questions
30LEO Earth Observation System Program
Procurement Timeline
What is the procurement timeline?
• RFP Release – Late February 2023
• RFP Responses Due – Late March 2023 (one month response time)
• Contract Award – October 2023
• Final Study Review – October 2024
Note: The above are notional schedule dates. Please continue to monitor http://www.sam.gov and official correspondences related to this solicitation for official dates and updates to the schedule.
31LEO Earth Observation System Program
One on Ones
How often can vendors speak with the government team?
• Vendors may request as many one on ones with the government team as they like until the RFP is released. The government will grant these as schedule permits. Vendors may also email any further questions/clarifications during the run up to the RFP release. All questions answered will be posted to SAM.gov in an anonymous fashion.
32LEO Earth Observation System Program
Who Can Compete
Can my team include a Federally Funded Research and Development Center
(FFRDC)?
• The authorized usage of each FFRDC should be defined in their sponsoring agreement and each FFRDC should know their restrictions the best.
Can my team include international vendors or partners?
• The usage of international vendors or partners should be compliant with the contract clauses and governing laws at the time of the Request for Proposal (RFP). It is anticipated that there will be several clauses in the RFP that pertain to foreign vendors including 52.225-1 Buy American- Supplies.
33LEO Earth Observation System Program
SOW Questions
34LEO Earth Observation System Program
Instrument Level Reviews
When are instrument-level reviews (SRR, IBR, PDR, CDR, etc.) planned for?
• Instrument level reviews have not been specified on purpose. The government would like the Phase A study vendors to suggest their own dates for the instrument level reviews. We are interested in understanding how soon each vendor believes these reviews are technically feasible. A Pre-Ship Review date and Launch Readiness Date have been specified in the Phase A SOW.
35LEO Earth Observation System Program
Design Fidelity at the End of the Study
What is the required fidelity of instrument design upon conclusion of the Phase A study?
• Required fidelity at the end of the study is at a minimum SRR/SDR level, however, preference will likely be given to those vendors that can further advance their instrument designs to PDR, CDR, and beyond.
36LEO Earth Observation System Program
Instrument Design Deliverable
What data products are needed to fulfill the Instrument Design CDRL?
• In addition to the items previously listed in SMBA Phase A SOW item 2.2.1, the following will be requested:
– A concept of operations
– A block diagram
– A visual depiction of top-level geometry choices
– Identification of technical risk
• Consider referencing the review content recommended from GSFC-STD- 1001 Reviews for a Systems Requirement Review / System Design Review
(SRR/SDR)
37LEO Earth Observation System Program
ETU Testing and Verification
Is the SMBA ETU expected to be tested and verified before CDR?
• Our baseline preference is to have the ETU tested and verified before CDR in order to buy down technical risk before manufacturing. We realize this may be difficult to do while also meeting an aggressive schedule. We are open to discussing which testing and verification can be pushed to after CDR as part of the Phase A studies.
38LEO Earth Observation System Program
PSD Questions
39LEO Earth Observation System Program
Instrument Capabilities and Channel Set Are the SMBA capabilities and channel set negotiable?
• A more general study has already occurred on which capabilities and channels to include (NWP report on slide 11). These capabilities are for the backbone sensor that our customers, the NOAA science community, have specifically requested.
• Vendors may suggest alternative channels to the ones listed. These channels must still meet our needed Baseline capabilities in PSD table 4.0-1.
Priority # Performance Factor Baseline Aspirational Target
1 Channels for direct Temperature Sounding
*13 Channels around 50-60 GHz and 7 channels around 118GHz line
*More than 20 channels around 50-60 GHz and 118GHz line
2 Channels for direct Moisture sounding
*5 Channels or more around 183 GHz
*10 Channels or more around 183 GHz
Window channels;
channels for cloud, precip, ice detection for direct all-sky assimilation and NWP
QC
Channels at 23.8, 31.4, 88.2. One channel at 165.5 (TBR) and/or 229
(TBR) GHz channels
Other channel combinations will be considered. Such as: at least 4 channels at low frequencies (priority order) (i.e. 22-23 GHz(a), 31-37 GHz(b), 89 GHz(c) and 18 GHz (d)) if possible, channels for TPW integration, cloud/precip detection and surface signal distinction
4 Spatial coverage (daily) 100% Global Coverage 100% Global Coverage
Noise Level (NEDT) for Temperature sounding channels See Table 4.1-2 See Table 4.1-2
Noise level (NEDT) for
Moisture sounding channels
See Table 4.1-2 See Table 4.1-2
7 Spatial horizontal resolution As-good as ATMS Smaller (better) than ATMS 8 Spatial sampling
Contiguous footprints (or better) Oversampling (Spatial Nyquist sampling at a minimum) to enable higher spatial resolution
9 Scan geometry Cross track or conical Cross track or conical 10 Polarization
Single linear polarization Baseline, and dual-polarization (vertical and horizontal) for window channels below 50 GHz
11 ATMS Channels Continuity Yes, for similar channels Yes, for similar channels 12 Calibration accuracy See Table 4.1-2 Less than values in Table 4.1-2
40LEO Earth Observation System Program
Spacecraft Interfaces and Environments
What are the expected spacecraft interfaces and environments?
• While we have specified initial instrument accommodation assumptions in PSD Section 5.1, we will be flexible in the allocations to extent needed to accommodate the instrument’s needs.
– Vendors are encouraged to use industry-standard solutions (mechanical, electrical, communication, and data format) for interface needs.
• During Phase A study, we will work with potential vendors to refine the enveloping accommodation requirements as well as to define expected spacecraft mechanical environments.
41LEO Earth Observation System Program
IMAR Questions
42LEO Earth Observation System Program
Risk Class
Can vendors use a Class D approach instead of a Class C approach if they have design heritage and believe that a higher tolerance risk class will save cost and schedule?
• No, this will be NASA Class C per NPR 8705.4, as directed. However, NASA is open to, and encourages, IMAR requirements tailoring.
– Expect to allow vendors to follow their internal processes where they meet the intent of NASA's higher-level requirements.
– During tailoring discussions NASA would like to see cost, schedule, and technical risk analyses.
– For vendors with heritage hardware or software, it may be possible to use GSFC’s inherited items process (see next slide) to develop alternative approaches to meet requirements.
43LEO Earth Observation System Program
Inherited Items Process
• Inherited Items: Items that are currently built, COTS, or to be built-to-print, and otherwise will not be changed
• Purpose: Many items are built to non-NASA standards and/or level of oversight
• The reason for NASA’s traditional requirements:
– Based on one-of-a-kind developments
– Where there was no historical basis for reliability, reliability was assured as a by-product of quality measures, piece-part controls, and reliability tools
Predicted outcome and use:
Inherited items are based on the principle that a manufacturer whose products have proven reliability can be trusted to deliver standard products without outside interference in their processes. A reduction in government process requirements on vendors who show reliability of an item through inheritance may, in some cases, reduce project risk.
• GSFC Safety and Mission Assurance Chief Engineer has offered to give any vendor interested a presentation on this process.
44LEO Earth Observation System Program
One on Ones
45LEO Earth Observation System Program
Agenda
46LEO Earth Observation System Program
Final FAQs and Other Q&A
47LEO Earth Observation System Program
Common Question Topics
• Possible schedule acceleration goal
• Aspirational requirements optional
• Inherited items process is encouraged
• Program architecture forthcoming, hopefully in January 2023
• Spacecraft accommodations: assume volume allowed 1mx1mx1m
• Partnering
• Negotiating Priorities
48LEO Earth Observation System Program
Thank You!
• RFP Release – Late February 2023
• RFP Responses Due – Late March 2023 (one month response time)
• Contract Award – October 2023
• Final Study Review – October 2024
Note: The above are notional schedule dates. Please continue to monitor http://www.sam.gov and official correspondences related to this solicitation for official dates and updates to the schedule.
| Sounder for Microwave Brightness and Analysis (SMBA) Phase A Study Industry Day |
| Welcome/Introduction/Logistics |
| Ground Rules |
| Welcome to SMBA Phase A Industry Day |
| Who’s Here |
| Agenda |
| Other Logistics |
| LEOS Program Overview |
| Serving NOAA NESDIS User Needs From Low-Earth Orbit (LEO) |
| Evolving LEO Satellite Technology to Improve Forecast Accuracy |
| Exploiting the Trends: Leveraging Advancements |
| Improved Microwave (MW) and Infrared (IR) Sounding Measurements |
| SMBA Overview |
| Next Generation Backbone Microwave Sounder |
| From NOAA Products to Channel Choices & Prioritizations (1/5) |
| From NOAA Products to Channel Choices & Prioritizations (2/5) |
| From NOAA Products to Channel Choices & Prioritizations (3/5) |
| From NOAA Products to Channel Choices & Prioritizations (4/5) |
| From NOAA Products to Channel Choices & Prioritizations (5/5) |
| SMBA Performance Capabilities Prioritization |
| Radio Frequency Interference |
| Phase A Study Goals |
| Phase A Study SOW Guiding Assumptions (1/2)�The Flight hardware development cost and schedule estimates shall be based on the following assumptions: |
| Phase A Study SOW Guiding Assumptions (2/2)�The Flight hardware development cost and schedule estimates shall be based on the following assumptions: |
| Follow On Options |
| RFI FAQs and Other Q&A |
| Procurement Questions |
| Procurement Timeline |
| One on Ones |
| Who Can Compete |
| SOW Questions |
| Instrument Level Reviews |
| Design Fidelity at the End of the Study |
| Instrument Design Deliverable |
| ETU Testing and Verification |
| PSD Questions |
| Instrument Capabilities and Channel Set |
| Spacecraft Interfaces and Environments |
| IMAR Questions |
| Risk Class |
| Inherited Items Process |
| One on Ones |
| Agenda |
| Final FAQs and Other Q&A |
| Common Question Topics |
| Thank You! |
File details come from the government source that posted it. Updated .