This document is a Request for Information (RFI) Sheet for Solicitation # 36C24223B0019 to replace the roof of Building 76 at the Bath VA Medical Center. The RFI includes questions and answers related to the project, covering topics such as asbestos removal requirements, substrate materials, roof access, power sources, and work schedule restrictions.
The solicitation is for construction services to remove the existing natural slate shingles and replace them with an approved synthetic slate product, as well as install a new electrical ice melt system. The building is a historical six-story structure constructed in 1938, with a total roof area of approximately 31,000 square feet. The work will involve the removal and disposal of asbestos and lead-containing materials. The contractor will be responsible for providing all materials, labor, and supervision to complete the project in accordance with the contract drawings and specifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24224B0028 0003.docx | DOCX document | |
| S04 - Site Visit Conference Agenda - 36C24224B0028 REPLACE ROOF BUILDING 76.pdf | ||
| S04 - PRE BID CONFERENCE ATTENDEES 2 - 36C24223B0019 REPLACE ROOF BUILDING 76.pdf | ||
| 36C24224B0028 0002.docx | DOCX document | |
| 36C24224B0028 0001.docx | DOCX document | |
| S02 - Revised Specs - 528A6-19-605 REPLACE ROOF BUILDING 76.pdf | ||
| P01- Drawings - 528A6-19-605 REPLACE ROOF BUILDING 76.pdf | ||
| 36C24224B0028_1.docx | DOCX document | |
| P01- Specifications - 528A6-19-605 REPLACE ROOF BUILDING 76.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI SHEET
Solicitation # 36C24223B0019
REPLACE ROOF BUILDING 76 - Bath VA Medical Center
RFI # 1
1.) Question - In the bid documents, it says that the VA will only choose a contractor who is certified for asbestos removal in NY. Will the VA allow us to sub the asbestos removal OR can they change the language so that the contractor has time to get certified before the notice to proceed?
Answer – A new specs document has been uploaded that has an amended Section 1.2 - General
Intention - A.
RFI # 2
2.) Question – Will plywood need to be installed as a substrate over the existing tongue and groove deck?
Answer - Tongue and groove decking is an acceptable substrate and there is no warranty requirement for the installation of plywood over the existing T&G
RFI # 3
3.) Question - Is there current Sheathing on the building?
Answer – Yes, the existing sheathing is 1x6 T&G (see attached photo on last page).
4.) Question - Are there security fence areas?
Answer - No
5.) Question - Scaffolding Areas for stair towers
Answer - Limited
6.) Question - Laydown area(s) for dumpsters, forklift, job trailer, material trailer, parking, and additional materials
Answer - The area will away from the immediate construction site. There isn’t much room around the main hospital building.
7.) Question - Are there other projects going on at the building and adjacent areas?
Answer - Yes. There will be 3 projects at this building.
8.) Question - Where can we hook up power to the job trailer from the power source?
Answer - There is power available near the designated job trailer site.
9.) Question - Are there roof access areas from inside the building?
Answer – Yes, there is an existing roof access hatch located in the elevator penthouse.
10.) Question - Patient and staff access points
Answer – All four sides of the building.
11.) Question - Could we have weekend work authorization (bring up weather limitations due to the time of the project)?
Answer - No. Normal work hours only.
12.) Question - Plan for slate removed (VA retains or do we need to dispose of it)
Answer – The removed existing slate shall be disposed of by the contractor.
RFI # 4
13.) Is the IMPS and IMPN new panels? Are they provided by us?
Answer – NEW, PROVIDED BY CONTRACTOR. SEE RESPONSE IN RFI#5, DRAWINGS AND SPECS
FOR ADDITIONAL INFORMATION.
14.) Is the measurements on the heat trace just the roof or is it the length of the heat trace including the zig zag?
Answer – LENGTHS INDICATED ARE THE LENGTH OF THE SPECIFICED DESIGN MAKE HEAT TRACE
THAT IS ON THE ROOF, FROM THE HOMERUN POWER WIRING JUNTION TO THE END OF THE
RUN.
RFI # 5
15.) Contractor is inquiring to get information on the electric panels (IMPS - IMPN) that will be installed on the 7th floor based on the drawing EP-102. Need size of panel, qty of breakers. This is not covered on dwgs or in specs.
Answer –
IMPS: 480/277V; 225A MCB; 30 CKT. PROVIDE (12) ACTIVE SINGLE POLE 30A BREAKERS AND (8)
SPARE. (10) SPACE.
IMPN: 480/277V; 225A MCB; 30 CKT. PROVIDE (7) ACTIVE SINGLE POLE 30A BREAKERS AND (13)
SPARE. (10) SPACE.
16.) There is a discrepancy in the IM control panels. This may vary between vendors but they are saying the IMP requires a single pole 277v-30a breakers - not dbl pole 20a.
Answer – ALL BREAKERS SHALL BE SINGLE POLE 30A 277V.