RFI_M67400-26-RFI-0002_ISTF Site Location Map.pdf
PDF 284 KB Posted
- Attached to
- ISTF Aggregate Material Ie Shima
- Solicitation number
- M67400-26-RFI-0002
- Issued by
-
United States Marine Corps
About this file
This document is a Site Location Map detailing specifications for a storage area. The potential storage area is 9,960 m2 (107k SF), indicated by a red-hatched area with a blue border. Key instructions include selecting the flattest surface for aggregate storage, constructing access from adjacent streets using available aggregates, and compacting a 6-inch (150 mm) layer to serve as a floor/slab for stockpiles.
The map provides additional guidance for storage area configuration, such as storing fine material at the northern end and constructing walls or dividers as recommended in an attached sketch. The storage area walls should include a mesh cover with overlapped edges (approximately 0.5m) and, if using a two-layer mesh, a heavy rope layer on top. The document includes multiple satellite/aerial images showing the proposed storage location from different perspectives and zoom levels.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOO_M67400-26-RFI-0002_ISTF Aggregate Material Organization.pdf | ||
| RFI_M67400-26-RFI-0002_ISTF Aggregate Material Organization.pdf | ||
| M67400-26-RFI-0002_QA_Form_.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Location Map:
• Potential Storage Area = 9,960 m2 (107k SF) as shown in “red hatch with blue border” area
• Select the appropriate area(s) with the flattest surface to store expected aggregate volumes
• Construct access from adjacent street(s) by using available aggregates
• Compact 6-inches (150 mm) layer using available aggregates to be used as floor/slab for stockpiles
• Store fine material at the Northend of storage area
• Walls /dividers of the storage areas can be built as the recommended sketch attached.
o Install mesh cover with overlapped edges (˜ 0.5m) o heavy rope layer on top if 2-layer mesh is used