This document is a Questions and Answers (Q&A) file related to a Request for Information (RFI) for a federal contract opportunity.
The RFI is for a new requirement from the Air Force Life Cycle Management Center (AFLCMC) Enterprise IT & Cyber Infrastructure Division (HNI) to explore, analyze, and adapt the current use and management of personnel resources within HNI. The purpose is to assist the division's leadership in defining the most efficient and effective support to meet current and future portfolio requirements. Respondents are expected to use proven workforce planning and organizational assessment approaches, as well as industry best practices, to identify opportunities for workforce and organizational design improvements within HNI.
The Q&As provide details on the new requirement, indicating it is not an incumbent contract. The agency is open to placing the requirement in the 8(a) program and considering a small business set-aside. The RFP is expected to be released within 30-60 days of the RFI closing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI_HNI Resource Management Study_16 May 24.docx | DOCX document | |
| Definition for the White Paper_15 May 2024.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Per the instructions of FA8772-24-R-0001, the Requiring Agency is asking for White Papers as a response to this RFI. For additional details, please review the “Definition for the White Paper” attachment.
Request for Information (RFI) For Air Force Life Cycle Management Center (AFLCMC) Enterprise IT & Cyber Infrastructure Division (HNI) HNI Resource Management Study
Questions and Answers (Q&As) Updated a/o 30 May 2024
FA8772-24-R-0001 Q&As
| No. |
| Questions |
| Answers |
| 1 |
| “Is this” a new requirement or is there a contractor presently performing the same or similar work (incumbent contract). If that’s the case, can you kindly provide me the contract number and name of the vendor? |
| This is a new requirement. |
| 2 |
| Who is the current incumbent (if any) related to the sources sought? |
| Please see the response to question #1. |
| 3 |
| What is the incumbent's current project/job/contract number? |
| Please see the response to question #1. |
| 4 |
| Is the agency open to placing the prospective requirement into the 8(a) program? |
| We are open to placing the prospective requirement into the 8(a) program. |
| 5 |
| Would you kindly confirm if this is an entirely new effort or is there an incumbent currently providing these services? If so, would you please provide the incumbent contract details? |
| Please see the response to question #1. |
| 6 |
| What will be the contract value for this opportunity? |
| We do not have a contract value at this time as this is a new requirement. |
| 7 |
| Are there any set-aside consideration? |
| We are open to a small business set-aside. |
| 8 |
| Would you please provide an approximate timeline for the RFP release? |
| Approximately 30-60 Days from the closing of this RFI |