RFI - Draft Statement of Work (693JJ924RQ000149) (11-28-23).pdf
PDF 197 KB Posted
- Attached to
- Resurface SATF Asphalt Traction Test Pad
- Solicitation number
- 693JJ924RQ000149
About this file
This document outlines requirements for a federal contract to resurface an asphalt traction test pad surface at the San Angelo Test Facility in Texas. The National Highway Traffic Safety Administration requires removing the existing asphalt surface that was last resurfaced in 2013 and installing a new overlay designed to achieve a wet traction coefficient of 0.55 to 0.62. The successful bidder must complete test strips to validate the mix design meets friction requirements, remove any existing cracks or debris, install 100-foot ramps, and repaint lane lines matching previous dimensions. The performance period is 24 months from award. Key deliverables and milestones include a kickoff meeting within two weeks, placing and evaluating test strips within three months, gaining base access for contractor personnel, and providing final documentation within three weeks of government acceptance of the completed test pad.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
693JJ924RQ000149
Resurface SATF Asphalt Traction Test Pad
DRAFT STATEMENT OF WORK
C.1 BACKGROUND
The National Highway Traffic Safety Administration (NHTSA) has a need to resurface the asphalt test surface portion of the Traction Grading Test Track used to perform testing in accordance with the Uniform Tire Quality Grading System (UTQGS) at the Office of Vehicle Safety Compliance’s (OVSC’s) San Angelo Test Facility (SATF) located on the grounds of Goodfellow Air Force Base (GAFB) in San Angelo, Texas (TX). The asphalt test surface was last resurfaced in September 2013. The test surface is used by OVSC to perform traction testing for enforcement of the UTQG consumer information program. The test surface is also used by outside entities to perform traction testing.
The UTQG traction test measures the slide friction coefficient of tires using a tire traction skid trailer at a test speed of 40 miles per hour (MPH). The allowable surface coefficient range per 49 C.F.R. § 575.104 is 0.50 ± 0.10. This value is measured using the American Society for Testing and Materials (ASTM) E 501 tire with a test load of 1,085lbs and an onboard watering system with an output of approximately 4.0 GPM per wetted inch of nozzle width.
C.2 CONTRACT OBJECTIVES
The objective of this contract is to replace the asphalt UTQG traction test surface located at the SATF located on GAFB in San Angelo, TX with a durable surface that meets the tire test surfaces specified in 49 C.F.R. § 575.104.
This may include, but is not limited to, identifying a suitable replacement asphalt mix with test strips, removing the existing surface, placing a new asphalt surface, and re-painting the required lines.
C.3 GENERAL REQUIREMENTS
Phase One (1) Test Strip Surface Application
The Contractor shall schedule all work under this Contract with the Contracting Officer’s Representative (COR).
The Contractor shall identify a suitable asphalt mix design through the placement and evaluation of a test strip, removing the existing test surface (if required), replacing the test surface, and ensuring smooth transitions to and from the test surface, to include painting of the completed test surface. The Contractor shall be familiar with work requirements for GAFB and certain requirements and approvals that must be met and/or obtained prior to the start of work by the contractor.
The Contractor shall be responsible for the following:
C.3.1 The Contractor, inclusive of Contractor personnel and subcontractors supporting this project on-site at the SATF, must meet all Air Force Base (AFB) security requirements. This will include background and verification checks required prior to base access. The general requirements may be found at: https://www.goodfellow.af.mil/Home/Visitor-Control-Center- Gate-Information/
The contractor must provide a list of all personnel who will be accessing the base and all required information to include the following: (Full Name, Date of Birth, Driver’s License No.
w/State of Issuance, and Last Four (4) of SSN) to the COR for the contractor personnel to gain approval to access the base. This process can take between 2-4 weeks to complete from the time the list is submitted. This list must be provided to the COR via email within 1 month of the completion of the Kick-Off Meeting.
C.3.2 The Contractor must meet all other AFB requirements that are in effect at and during time of project, including but not limited to, obtaining environmental approval for all materials required to complete the project.
C.3.3 The Contractor shall ensure that its equipment and operations does not interfere with AFB operations at any time during project.
C.3.4 Parking on turf or base roads is not permitted without prior approval from the COR.
C.3.5 All equipment, (e.g., vehicles) shall pass through an inspection station when accessing the AFB or whenever entering the AFB located at:
4368 S Chadbourne St.
San Angelo, TX 76905
Note: The inspection station is located at the south gate, near the visitor’s center entrance to the base.
C.3.6 Upon completion of the project the Contractor shall perform cleanup of debris from all work areas. The Contractor shall collect all trash, debris, refuse, garbage, etc., that is generated, and place it in appropriate containers or vehicles as directed by the COR. The Contractor shall haul materials from the site by appropriate means as needed. The Contractor shall ensure proper disposal of materials outside the limits of Government property. The Contractor shall ensure that disposal by recycling, sanitary landfill or other approved methods conforms to all local, state, and federal guidelines, criteria, and regulations. Upon completion of the work, the Contractor shall leave the work site and any storage area(s) in a clean, neat, and orderly condition as determined by the COR. The COR will inspect the work site, prior to the Contractor’s final departure from the site, to confirm that the work site is in a satisfactory condition.
C.3.7 The Contractor shall comply with all Occupational Safety and Health Administration (OSHA) regulations while executing Contract activities.
C.3.8 The Contractor shall comply and ensure that all subcontractors, if any, comply with all applicable federal, state, and local laws, regulations, ordinances, and standards related to any environmental matters. The Contractor shall also comply and ensure that all subcontractors, if any, comply with all specific instructions or directions provided to the Contractor by Goodfellow AFB regarding any environmental or safety matters.
C.3.9 The Contractor shall execute the work for this project in the best and most competent manner, by qualified and efficient Contractor personnel, skilled in their respective trades. The Contractor shall coordinate and perform all operations in a manner that will result in a professional and expeditiously completed project. The Contractor shall conduct the work in strict accordance with prevailing industry standards and manufacturer’s instructions. The Contractor shall ensure that the work and materials comply with industry best practices for quality and technical/performance requirements for this project as described herein and (the resultant Contract award) for all applicable criteria, regulations, guidelines, and codes, all of which are made a part thereof.
C.3.10 Normal working hours for SATF personnel are Monday through Friday between the hours of 7:00 a.m. and 4:00 p.m. excluding Saturdays, Sundays, and Federal holidays. If noncontractor personnel (e.g. federal or NHTSA contractor personnel) are reasonably available, the Contracting Officer may authorize the Contractor to perform work during periods other than the normal tour of duty for work hours/days.
C.4 TEST SURFACE SPECIFIC REQUIREMENTS
C.4.1 KICK-OFF MEETING
Within two (2) weeks of the effective date of the contract, the Contractor shall participate in a Kick-Off meeting with the Contracting Officer’s Representative (COR), Contracting Officer (CO), and other NHTSA staff. The Kickoff meeting will take place via teleconference and will be approximately two hours in length. The Contractor shall make a brief presentation of their understanding of the contract requirements. After the presentation, the parties shall discuss basic contract requirements, including the schedule for evaluations and operational procedures.
Washington, DC, based NHTSA staff may join via teleconference for these discussions.
C.4.2 The Contractor shall clean and remove all grass, weeds, debris, and soil from cracks in the asphalt test surface prior to beginning paving.
C.4.3 If the contractor deems it necessary to meet the requirements of this solicitation, the Contractor shall remove the existing surface as needed; or subject to COR approval repair the existing asphalt test surface with a suitable asphalt crack sealant.
C.4.4 The Contractor shall prepare and install an asphalt and aggregate seal coat overlay on the entire test surface and shoulders, 1000 feet long and 104 feet wide, that will serve in part as a moisture barrier.
C.4.5 The Contractor shall provide an initial asphalt mix design that meets the required performance characteristics using the test methods detailed in Section C.4.6 prior to applying the first test strip. The government will provide historical mix design documentation as reference material for the contractor if desired.
a. The Contractor shall prepare and install an initial test strip before installing the full asphalt test surface. The Contractor shall ensure the test strip is 10 feet wide and 150 feet long in the shoulder area of the asphalt test surface. The purpose of the test strip is to validate that the mix design will provide the required wet traction coefficient of friction as stated in C.4.6 below. The validation process will be:
1) Once the surface has cured (approximately 2 weeks depending on weather) the government will burnish and test the surface for wet traction coefficient of friction. This process may take as much as 3 weeks.
2) The government will discuss the results of the testing with the contractor.
b . If an additional test strip is required; the following procedure will be followed:
1) The Contractor shall then adjust the asphalt mix design as required to meet the friction coefficient requirements and install another complete asphalt test strip in the same general area as the previous one; as described in paragraph (C.4.5.a, above). The contract requires successful paving of at least one test strip that meets the required wet traction coefficient of friction prior to receipt of approval to move onto Phase 2 for paving of the full asphalt test surface.
2) Once the government determines that the test strip meets skid coefficient requirements, the contractor will be notified by the COR that it may proceed to the task detailed at C.4.6 below.
Phase Two (2) Full Asphalt Test Surface Application
C.4.6 The Contractor and government shall work together to achieve a wet slide coefficient of friction within the acceptable range of 0.55µ to 0.62µ after curing and the government has burnished the surface. The coefficient of friction will be measured by the government using the UTQG traction test procedure and an ASTM E 501 tire. The timeline between test strip approval and final test surface application shall be no longer than 1 month with exceptions for weather delays and hot mix asphalt plant availability.
C.4.7 Additional Construction Requirements
a. The test procedure requires a traction testing apparatus consisting of a pickup truck and instrumented trailer to travel at a steady speed of 40 MPH. The Contractor shall construct the new asphalt test surface in a way that allows for a very smooth transition from the oval track road to the test surface with no perceptible impact to the driver and enough distance for the vertical loads to settle out of the suspension prior to reaching the first test location. The Contractor shall ensure the exit ramp of the test surface meets the same requirements. The Contractor shall ensure that the surface transition is smooth from both directions if traffic flow needs to be reversed.
b. The Contractor shall ensure that the final test surface is smooth and free of bumps, divots, or any other surface disturbances. These things will cause transient disturbances in traction testing data which will increase test variability and produce bad data.
c. The Contractor shall ensure that there are no foreign objects purposefully or accidentally left in the test surface. The Contractor shall ensure that the surface is a smooth, finished, homogenous, asphalt surface.
d. The Contractor shall ensure that there are no longitudinal or horizontal cracks in the final test surface. The Contractor shall ensure that the construction seams between asphalt lays are minimal with no vertical difference between lays.
e. The Contractor shall determine the recommended overlay thickness and the final density such that the surface can support the static and dynamic loads of the trailer traction testing apparatus for the extent of the test surface life (8 years) without rutting or significant cracking.
1. The trailer traction test vehicle is a Ford F350 pickup truck with test equipment installed. The fully loaded vehicle weight is approximately 13,500 lbs. and the test surface will experience an annual average daily traffic (AADT) of approximately 40.
C.4.8 At transition areas between the test surface and the non-test surface, the Contractor must provide:
a. Butt joints to transition to and from asphalt test areas to ensure structural integrity and smooth transition to the asphalt roadway surface.
b. Provide a smooth transition between the test surface and the non-test surface, such that, the driver of an instrumented skid trailer driving over the transition area will not feel a bump and the data acquisition system will not be affected as the various axles pass over the transition area.
c. Two full-width, ramp-like surface grades of 100 feet length each. The Contractor shall ensure that each grading has a gradual height transition from the original non-test asphalt surface with overlay to the existing concrete test surface.
C.4.9 The Contractor shall paint new lane stripes on the new test surface that duplicate the color, width and length of the old lane stripes, i.e., alternating yellow and white stripes, 10 feet long, beginning 10 feet prior to entering skid pad test surface from both directions and a lateral midpoint stripe.
C.4.10 The government will evaluate the completed test surface and provide final acceptance to the contractor. The government will provide final acceptance within two (2) months of the completion of the lane stripes being completed.
C.4.11 The Contractor shall provide all quality assurance or quality control data and documentation for any of the materials and test surface along with the final mix design to the COR. These documents must be provided within 3 weeks of the government’s final acceptance of the completed test surface.
(i) Delivery date, acceptance (f.o.b. destination)
D. Delivery Performance
1) Date of Delivery
The period of performance for this Contract shall be twenty-four (24) months from date of award. (dates TBD)
2) Place of Delivery
Department of Transportation National Highway Traffic Safety Administration Office of Vehicle Safety (NEF-220) 131 Comanche Trail Building 3527 Goodfellow AFB, Texas 76908
3) Contracting Officer’s Representative (COR) – TBD
4) Alternate Contracting Officer’s Representative (ACOR) – TBD
5) Performance Milestones and Deliverables:
DELIVERABLES/MILESTONES
The following milestones and deliverables apply to this contract and are considered critical to the successful completion of the project.
Item No. Section Deliverable (D) /Milestone (M) Estimated Timeline
1 C.4.1 (Phase 1) Kickoff Meeting (M)
Within Two (2) weeks After Contract Award
(ACA)
2 C.3.1 Contractor submits personnel list with required information for base security checks (D)
Within one (1) month of Item 1
3 C.3.1 Personnel List is approved (M) Typically 2-4 Weeks from Item 2 Completion
4 C.4.5 Contractor and COR determine test strip start date (M) TBD
5 C.4.5 Contractor Places Test Strip (D) TBD
6 C.4.5.a.1 SATF Completes Evaluation of Test Strip (M)
Within 2 months of Item 5 Completion
7 C.4.5.a.2 SATF Discusses Test Strip Results with Contractor (M)
Within 1 week of Item 6 Completion
Item No. Section Deliverable (D) /Milestone (M) Estimated Timeline
8 C.4.5.b.1 (Retest; if required) Contractor Places Additional Test Strip (D)
TBD
9 C.4.5.a.1 (Retest; if required) SATF Completes Evaluation of Additional Test Strip (M)
Within 2 months of Item 8 Completion
10 C.4.5.b.2 SATF Approves Mix Design (M) Within One (1) week of identifying a test strip that meets the performance criteria
11 C.4.6 (Phase 2 Begins) Upon Approval Contractor Places Full Test Surface (D) TBD
12 C.4.9 Contractor Paints Test Surface (D) TBD
13 C.4.10 SATF Accepts Final Test Surface (M) Within two (2) months of Item 12 Completion
14 C.4.11 Contractor provides SATF with all QA/QC data and final mix design (D)
Within three (3) weeks of Item 13 Completion