About this file

This document is a Request for Bidding Interpretation (RFBI) for Project Number 000000000011567, which is for the installation of electric vehicle supply equipment (EVSE) at the Bay Area District Office and Sonoma State Historic Park (SHP) located in Sonoma County, California. The project is being managed by the Executive Office of Sustainability Transportation. Bidders must submit any questions or requests for interpretation by October 21, 2024 at 5:00 p.m. The awarded contractor will receive fully permitted plan sets for the project.

The RFBI indicates that the contractor will be responsible for submitting drawings to the appropriate jurisdictions for permitting. No other pricing, funding, or contractual details are provided in this document.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESDMSTR: REV. 6.3.2021 Appendix 00 21 00.1 Project Number: 000000000011567

REQUEST FOR BIDDING INTERPRETATION (RFBI)

(Email no later than October 21, 2024, 5:00 p.m.)

OS RFBI No.: _______________ Requestor RFBI No.: ___________ Request Date:

To: Janelle Goulding, Project Director From (Bidder):

Executive Office of Sustainability Transportation Phone: 916-823-7059 Contact: __________________________

Phone: ___________________________ Fax: _____________________________

Email: janelle.goulding@dgs.ca.gov Email: ___________________________

All RFBIs received prior to deadline identified above, and responses from the State will be published on http://www.caleprocure.ca.gov. Click on “Start Search.” In the event name field, enter the project number and click search. While viewing the Event Details, click on “View Event Package” to view RFBI responses.

Project No.: 000000000011567 Project Name: Parks - Electric Vehicle Supply Equipment - Bay Area District Office and Sonoma SHP Location: Sonoma County, CA

Drawing Reference: ____________________ Project Manual Reference: ___________________________

Question:

Bidder’s Authorized Signature: ______________________________________________________ [ ] Check here if additional pages attached Page 1 of ____

The awarded contractor will receive fully permitted plan sets.

Janelle Goulding 10/15/2024

Kira Stewart

Kira Stewart Terralink Communications, Inc.

Kira Stewart 10/15/2024

Kira Stewart Kira Stewart

Kira Stewart 916-952-2242

Kira Stewart kstewart@trlink.com

Kira Stewart See below

Kira Stewart

General - Will we be issued a fully permitted sets of plans or is GC responsible for submitting drawings to jurisdictions?