This is a project manual for RFB 2026-24, a Public Safety Building Corridor Renovation project in New York. The document outlines the scope of work for comprehensive corridor renovations within the Public Safety Building, including demolition, structural repairs, flooring installation, wall finishes, painting, lighting upgrades, HVAC modifications, and plumbing work. The project encompasses multiple corridor sections throughout the facility with detailed specifications for materials, installation methods, and quality standards. The manual establishes the framework for bidders to understand project requirements, site conditions, and technical specifications necessary to prepare accurate proposals. Specific response dates, due dates, site visit schedules, and bidder's conference information should be referenced in the primary RFB document, as this manual serves as the technical attachment detailing work scope and performance standards rather than administrative timeline details.
The project manual provides detailed specifications for materials, labor, and construction methods required to complete the corridor renovation work to code compliance standards. Pricing terms, contract duration, set-asides, and funding sources are contained within the main RFB 2026-24 document rather than this technical attachment. The manual indicates no business enterprises have been awarded identical or substantially similar procurement contracts within the past five years, establishing this as a new procurement. Bidders should review all associated RFB documents concurrently with this project manual to obtain complete information regarding submission requirements, evaluation criteria, pricing structure, and contract terms.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
FOR THE CONSTRUCTION OF
PUBLIC SAFETY BUILDING
CORRIDOR RENOVATION
COUNTY OF MADISON
138 NORTH COURT STREET
BUILDING 7
WAMPSVILLE, NEW YORK 13163
June 5, 2026
NO ALTERATION PERMITTED HEREIN EXCEPT AS PROVIDED UNDER .SECTION 7209
SUBDIVISION 2 OF THE NEW YORK STATE EDUCATION LAW
TABLE OF CONTENTS 1 of 1
Technical Specifications
DIVISION 01 – GENERAL REQUIREMENTS
011000 ........... Summary
012100 ........... Allowances
012300 ........... Alternates
012500 ........... Substitution Procedures
012600 ........... Contract Modification Procedures
012900 ........... Payment Procedures
013100 ........... Project Management and Coordination
013200 ........... Construction Progress Documentation
013300 ........... Submittal Procedures
014000 ........... Quality Requirements
014200 ........... References
015000 ........... Temporary Facilities and Controls
016000 ........... Product Requirements
017300 ........... Execution
017419 ........... Construction Waste Management and Disposal
017700 ........... Closeout Procedures
DIVISION 04 – Masonry
042000 ........... Unit Masonry
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
079200 ........... Joint Sealants
DIVISION 08 – OPENINGS
083463.13 ...... Detention Security Hollow Metal Doors and Frames
088853 ........... Security Glazing
DIVISION 09 – FINISHES
092216 ........... Non-Structural Metal Framing
092900 ........... Gypsum Board
096723 ........... Resinous Flooring
099123 ........... Interior Painting
DIVISION 11 – EQUIPMENT
119814 ........... Detention Door Hardware
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work performed by Owner.
4. Owner-furnished/Owner-installed (OFOI) products.
5. Contractor-furnished/Owner-installed (CFOI) products.
6. Contractor's use of site and premises.
7. Coordination with occupants.
8. Work restrictions.
9. Specification and Drawing conventions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
2. Section 017300 "Execution" for coordination of Owner-installed products.
1.3 DEFINITIONS
A. Work Package: A group of specifications, drawings, and schedules prepared by the design team to describe a portion of the Project Work for pricing, permitting, and construction.
1.4 PROJECT INFORMATION
A. Project Identification: Madison County – Public Safety Building Door Relocation.
1. Project Location: 138 North Court Street, Building 7, Wampsville, New York 13163.
B. Owner: County of Madison.
1. Owner's Representative: John Regan, Director of Public Facilities.
C. Architect: C&S Architects, Engineers, and Landscape Architect, PLLC / C&S Engineers, Inc. 499 colonel Eileen Collins Boulevard, Syracuse, New York, 13212.
SUMMARY 011000 - 2
1. Architect's Representative: Adam Bruce, Project Architect.
D. Web-Based Project Software: Project software will be used for purposes of managing communication and documents during the construction stage.
1. See Section 013100 "Project Management and Coordination." for requirements for using web-based Project software.
1.5 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:
1. The project consists of renovations to the Public Safety Building including the relocation of a door and glazing assembly.
2. Other Work indicated in the Contract Documents.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.6 WORK PERFORMED BY OWNER
A. Cooperate fully with Owner, so work may be carried out smoothly, without interfering with or delaying Work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.
B. Concurrent Work: Owner will perform the following construction operations at Project site. Those operations will be conducted simultaneously with Work under this Contract.
1. Installation of access control door hardware and low voltage wiring.
C. Subsequent Work: Owner will perform the following additional work at site after Substantial Completion.
Completion of that work will depend on successful completion of preparatory Work under this Contract.
1. Installation of Fixtures, Furniture, and Equipment.
1.7 CONTRACTOR'S USE OF SITE AND PREMISES
A. Rules for Contractors
1. Employees of contractors must have proper photo identification on your person, at all times, while on property.
2. No weapons, chemical agents, alcoholic beverages or drugs are allowed on anyone's person or in any vehicles., Cell phones/digital cameras are not allowed, however, arrangements can be put into place to allow contractor supervisor(s) to possess a cell phone for project purposes. Those arrangements must be made in writing, and in advance of project start.
3. All vehicles shall be secured and locked when unattended in designated parking area.
4. Keys must be removed from all vehicles and equipment when not in use.
SUMMARY 011000 - 3
5. Tools shall be secured and locked-up when not in use. Take only the tools needed on the job into the work site. Count and know how many and what type of tools are being used. Immediately report any lost keys or tools to security staff. Daily tool inventory log will be maintained and verified by contractor representative and is subject to review by owner/owner representative. Ladders will not be left unattended at any time.
6. Employees of contractors shall proceed directly to the work site upon reporting for work and leave property immediately at the end of the workday. Contractor employees will sign in and out in a designated "Contractor Logbook" each time the employee enters and departs the facility. There will be no sight-seeing allowed at any time.
7. Nothing shall be given to, or taken from any inmate, nor shall any contractor employee fraternize with inmates in any way.
8. All scrap or waste materials, including but not limited to wood, glass, metal and wire, are considered dangerous. These materials and wrappings must be removed from the work site each day to include the use of magnetic devices to ensure metal objects/debris is cleared.
9. Smoking - smoking is only authorized in a permitted area that will be identified by the owner.
Smoking items will be stored in locked vehicles when employee(s) are not on break.
10. Other security issues or rules specific to the work site or the work itself may apply and will be discussed prior to the work starting.
11. When situations arise which are not covered by specific instructions, contact one of the following people immediately:
I. Captain Neal Schneider 315-366-2436 Duty hours 0800-1600 II. Lieutenant Mike Currier 315-366-2435 Duty hours 0800-1600
III. Lieutenant Ryan Collins 315-366-2323 Duty hours 0800-1600
B. Owner Occupancy
1. Owner will occupy premises during entire period of project/construction, for the conduct of normal operations. Cooperate with Owner to minimize conflict, and to facilitate Owner's operations.
C. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
D. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
SUMMARY 011000 - 4
1.8 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work to between 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging for temporary utility services according to requirements indicated:
1. Notify Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner’s written permission before proceeding with disruptive operations.
E. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances on Project site is not permitted.
1.9 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:)
is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.
C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
SUMMARY 011000 - 5
D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings and published as part of the U.S. National CAD Standard.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
ALLOWANCES 012100 - 1
SECTION 012100 - ALLOWANCES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
B. Types of allowances include the following:
1. Contingency Allowances
1.3 ACTION SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders.
1.4 INFORMATIONAL SUBMITTALS
A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.5 COORDINATION
A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.
1.6 CONTINGENCY ALLOWANCES
A. Use the contingency allowance only as directed by Architect for Owner's purposes and only by Change Orders that indicate amounts to be charged to the allowance.
ALLOWANCES 012100 - 2
B. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, insurance, equipment rental, and similar costs.
C. Change Orders authorizing use of funds from the contingency allowance will include Contractor's related costs and overhead and profit margin of 15%.
D. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES
A. Allowance No. ALG-1: General Contract Contingency Allowance: Include a contingency allowance of $5,000.00 for use according to Owner's written instructions.
END OF SECTION 012100
ALTERNATES
012300 - 1
SECTION 012300 - ALTERNATES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for alternates.
1.2 DEFINITIONS
A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if the Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.
1. Alternates described in this Section are part of the Work only if enumerated in the Agreement.
2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternates into the Work. No other adjustments are made to the Contract Sum.
1.3 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.
1. Include, as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation, whether or not indicated as part of alternate.
B. Execute accepted alternates under the same conditions as other Work of the Contract.
C. Schedule: A Part 3 "Schedule of Alternates" Article is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.
ALTERNATES
012300 - 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF ALTERNATES
A. Alternate No. 1: “ADD-ALT-1”
1. Base Bid: All work as indicated on Drawings and as specified, not otherwise described in an Alternate.
2. Alternate: Resinous flooring in rooms “CORRIDOR 165” and “CORRIDOR 301” as indicated on Drawing A-701 and as specified in Section 096723 “Resinous Flooring.”
END OF SECTION 012300
SUBSTITUTION PROCEDURES 012500 - 1
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including clauses for General Requirements and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Division 01 Section "Allowances" for products selected under an allowance.
2. Division 01 Section "Product Requirements" for requirements for submitting comparable product submittals.
3. Divisions 02 through 34 Sections for specific requirements and limitations for substitutions.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.
SUBSTITUTION PROCEDURES 012500 - 2
b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.
Significant qualities may include, but not limited to, attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified for each contract involved in the project.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. List of similar installations for completed projects with project names and addresses and names and addresses of Engineers and owners.
h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for Project.
j. Detailed comparison of the combined Contractor's construction schedule (including the work of all contracts) using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
2. Engineer's Action: If necessary, Engineer will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.
Engineer will notify Contractor through Construction Manager of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or Engineer's Supplemental Instructions for minor changes in the Work.
b. Use product specified if Engineer does not issue a decision on use of a proposed substitution within time allocated.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
SUBSTITUTION PROCEDURES 012500 - 3
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Engineer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Not allowed.
C. When the Engineer approves an equivalent substitution proposed by the Contractor, and when such proposed substitution requires a revision or redesign of any part of the work of this Contract or any other separate Contract, all excess costs occasioned by redesign, revision or extra work which is required by this or other Contractors shall be the cost and expense of the Contractor proposing the substitution.
D. The Contractor shall have and make no claim for an extension of time or for damages by reason of the time taken by the Owner and/or Engineer in considering a substitution proposed by the Contractor or because the Owner and/or Engineer disapprove such proposed substitution.
E. By making requests for substitutions based on Clause above, the Contractor:
1. Represents that he has personally investigated the proposed substitute product and determined that it is equal or superior in all respects to that specified.
2. Represents that he will provide the same warranty for the substitution that he would for that specified.
3. Certifies that the cost data presented is complete and includes all related costs under this
Contract but excludes costs under separate contracts, and excludes the Engineer’s redesign
SUBSTITUTION PROCEDURES 012500 - 4
costs and waives all claims for additional costs related to the substitution which subsequently became apparent.
4. Will coordinate the installation of the accepted substitute. Making such changes as may be required for the work to be complete in all respects.
END OF SECTION 012500
CONTRACT MODIFICATION PROCEDURES 012600 - 1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
B. Related Requirements:
1. Division 01 Section "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Engineer will issue through Resident Engineer supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Resident Engineer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Resident Engineer are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request or 10 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish
CONTRACT MODIFICATION PROCEDURES 012600 - 2
times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
e. Cost proposal to be in accordance with Section 200-09 of the contract documents regarding allowable costs and mark ups for change order work
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Resident Engineer.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Division 01 Section "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Cost proposal to be in accordance with Section 200-09 of the contract documents regarding allowable costs and mark ups for change order work.
1.5 ADMINISTRATIVE CHANGE ORDERS
A. Allowance Adjustment: See Division 01 Section "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.
1.6 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Change Proposal Request, Resident Engineer will issue a Change Order for signatures of Engineer, Contractor and Owner.
1.7 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Resident Engineer may issue a Construction Change Directive on AIA G714 form titled “Construction Change Directive”. A Construction Change Directive instructs the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
CONTRACT MODIFICATION PROCEDURES 012600 - 3
B. Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012600
Ref. No.:
Qty Unit @ Unit Price = Cost
@ = 0.00
@ = 0.00
@ = 0.00
Note: Copies of Sub-Quote
Overhead & Profit @ 5% = $ $0.00
Qty Unit @ Unit Price = Cost
@ = 0.00 @ = 0.00
@ = 0.00 Note: Copies of Invoices Required
Overhead & Profit @ 15% = $ $0.00
Mnhrs Class @ Mnhr Ttl Rate ** = Cost
@ = 0.00
@ = 0.00
@ = 0.00
@ = 0.00
** Rate Break-Down to be provided. Overhead & Profit @ 15% = $ $0.00
$0.00 $0.00 $0.00
Reviewed & Recomended by _________________________________Date: __________________
C&S Companies
Total RFC Value……………………….…………………………….
(description of added scope of work or "NONE")
0.00
Total adjustment to Contractor's Contract…………………………
Total Labor Costs:
0.00
Sub-Total Labor costs…………………… $
Total Subcontractor Costs:
0.00
0.00 Break-Downs Required.
Additional A/E Fees:
Total Material/ Equipment Costs:
Labor Costs: Description
Sub-Total Material costs………………… $
Subcontract Work: Name
Sub-Total Material costs………………… $ 0.00 0.00
RFC#:
Date:
Proj.No.:
Reviewed and
Approved by:
Project:
Contractor:
Contract No.:
Scope:
DESCRIPTION:
Mat'l / Eqpmnt Costs: description
Request for Change (RFC)
To be Completed by C&S C.O. Number:
Modification
Number:
Subject:
V-18A 5/04
PAYMENT PROCEDURES 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including Clauses for General Requirements
Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process
Applications for Payment.
B. Related Requirements:
1. Division 01 Section "Allowances" for procedural requirements governing the handling and processing of allowances.
2. Division 01 Section "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
3. Division 01 Section “Allowances” for administrative and procedural requirements governing allowances.
1.3 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for
Payment.
1.4 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following:
a. Application for Payment forms with continuation sheets.
b. Submittal schedule.
c. Items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the schedule of values to Engineer through Resident Engineer at earliest possible date, but no later than seven days before the date scheduled for submittal of initial
Applications for Payment.
PAYMENT PROCEDURES 012900 - 2
3. Subschedules for Phased Work: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values coordinated with each phase of payment.
4. Subschedules for Separate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work, provide subschedules showing values coordinated with each element.
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.
1. Identification: Include the following Project identification on the schedule of values:
a. Project name and location.
b. Name of Engineer.
c. Engineer's project number.
d. Contractor's name and address.
e. Date of submittal.
2. Arrange schedule of values consistent with format of AIA Document G703.
3. Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:
a. Related Specification Section or Division.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers) that affect value.
g. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.
1) Labor.
2) Materials.
3) Equipment.
4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project
Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.
5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
6. Provide a separate line item in the schedule of values for each part of the Work where
Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance.
7. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
PAYMENT PROCEDURES 012900 - 3
8. Allowances: Provide a separate line item in the schedule of values for each allowance.
Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.
9. Each item in the schedule of values and Applications for Payment shall be complete.
Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.
10. Schedule Updating: Update and resubmit the schedule of values before the next
Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Engineer and Resident Engineer and paid for by Owner.
1. Initial Application for Payment, Application for Payment at time of Substantial
Completion, and final Application for Payment involve additional requirements.
B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.
C. Payment Application Times: Submit Application for Payment to Engineer by the 25 of the month.
The period covered by each Application for Payment is one month, ending on the day of the month.
1. Submit draft copy of Application for Payment seven days prior to due date for review by
Engineer.
D. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.
1. Calculate retainage at the rate of 5% of the value of the Total Completed and Stored to
Date.
E. In addition to the requirements listed above, the following additional information must be provided with each monthly Application for Payment in order for e the Application for Payment to be considered for processing:
1. Certified Payrolls for Prime and Subcontractor(s) for the period the Application for
Payment covers.
2. Monthly record of weekly safety meetings.
3. Monthly “CPM Activity Status” Report, reference Section 013200.
PAYMENT PROCEDURES 012900 - 4
4. Monthly as-built drawing progress sets.
5. Monthly DBE Reports
F. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Resident Engineer will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule.
Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of
Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.
G. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.
1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment, for stored materials.
2. Provide supporting documentation that verifies amount requested, such as paid invoices.
Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.
3. Provide summary documentation for stored materials indicating the following:
a. Value of materials previously stored and remaining stored as of date of previous
Applications for Payment.
b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.
c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.
H. Transmittal: Submit four signed and notarized original copies of each Application for Payment to Resident Engineer by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
I. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.
1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit conditional final or full waivers.
3. Owner reserves the right to designate which entities involved in the Work must submit waivers.
PAYMENT PROCEDURES 012900 - 5
4. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.
J. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of values.
3. Combined Contractor's construction schedule (90 day) incorporating Work of multiple contracts, with indication of acceptance of schedule by each Contractor.
4. Products list (preliminary if not final).
5. Schedule of unit prices.
6. Submittal schedule (preliminary if not final).
7. List of Contractor's staff assignments.
8. List of Contractor's principal consultants.
9. Copies of building permits.
10. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
11. Initial progress report.
K. Application for Payment at Substantial Completion: After Engineer issues the Certificate of
Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for
Owner occupancy of designated portions of the Work.
L. Final Payment Application: After completing Project closeout requirements, submit final
Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Certificates of Release: From authorities having jurisdiction.
3. Certificate of Insurance: For continuing coverage.
4. Field Report: For pest control inspection.
5. Written guarantee on the Contractor’s letterhead of all work as called for in this Contract.
6. Contractor’s Affidavit of Payment of Debts and Claims, AIA Document G706.
7. Contractor’s Affidavit of Release of Liens, AIA Document G706A, for the Contractor.
8. Contractor’s Affidavit of Release Of Liens, AIA Document G706A , for each
Subcontractor.
9. Consent of Surety Form, AIA Document G707.
PAYMENT PROCEDURES 012900 - 6
10. Record Product Data and Shop Drawing: Provide one set in three ring binder and drawings bound together with index sheet where too large to fit in book.
11. Application and Certificate for Payment: Provide fully executed AIA Document G702 and
G703.
12. Fire Underwriter’s Certificate: Provide New York State Board of Fire Underwriter’s
Certificate of Approval of Electrical Wiring, or equivalent City Electric Inspector’s
Approval.
13. Labor Affidavits (Prime and Subcontractor’s Certifications).
14. DBE Final Utilization Reports.
15. Any other closeout documents requested by the Owner.
16. Evidence that claims have been settled.
17. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.
18. Final liquidated damages settlement statement.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012900
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. Requests for Information (RFIs).
4. Digital project management procedures.
5. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
C. Related Requirements:
1. Division 01 Section "Project Schedule" for preparing and submitting Contractor's construction schedule.
2. Division 01 Section "Execution" for procedures for coordinating general installation and field-architecting services, including establishment of benchmarks and control points.
3. Division 01 Section "Closeout Procedures" for coordinating closeout of the Contract.
1.3 DEFINITIONS
A. RFI: Request from Resident Architect, Architect, or Contractor seeking information required by, or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
B. Key Personnel Names: Within 15 working days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in project meeting room, in temporary field office, and by each temporary telephone. Keep list current at all times.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work.
Each contractor shall coordinate his operations with operations included in different Sections, that that are dependent on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.
1.6 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applicable Drawings as a basis for preparation of coordination drawings.
Prepare sections, elevations, and details as needed to describe relationship of various systems and components.
b. Coordinate the addition of trade-specific information to the coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of Architectural, structural, civil, mechanical, and electrical systems.
d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
f. Indicate required installation sequences.
g. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show Architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings, where required to adequately represent the Work.
2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical…
This is the start of the file's text. The full file is on GovTribe.