This document provides a table of contents for construction specifications for an expansion of the mental health clinic at the Southern Arizona VA Health Care System Medical Center in Tucson, Arizona. The specifications cover requirements for various construction divisions including concrete, masonry, metals, wood, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, special construction, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, and transportation. The related federal contract opportunity is a solicitation to provide the expansion of the mental health clinic building at the Tucson medical center. The solicitation number is 36E77620B0008_0003 and provides a copy of the final technical questions tracking spreadsheet and responses for interested contractors to review as part of their response preparation.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAVAHCS VA Medical Center VA Project: #678-329 Tucson, AZ Expand Mental Health Clinic, B90
TABLE OF CONTENTS
00 01 10 - 1
REVISED-11/23/2020
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 45 00 Quality Control 01-18
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 04-18
01 57 19 Temporary Environmental Controls 01-11
01 74 19 Construction Waste Management 09-13
01 80 00 Geotechnical Reports
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 02-16
DIVISION 04 – MASONRY (Not Used)
DIVISION 05 – METALS
05 05 23 Welding, Structural
05 12 00 Structural Steel Framing 11-18
05 21 00 Steel Joist Framing 11-18
05 31 00 Steel Decking 02-16
05 40 00 Cold-Formed Metal Framing 05-16
05 50 00 Metal Fabrications 08-18
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
00 01 10 - 2
REVISED-11/23/2020
07 21 13 Thermal Insulation 10-17
07 22 00 Roof and Deck Insulation 02-16
07 32 13 Concrete Roof Tiles
07 40 00 Roofing and Siding Panels 10-15
07 52 16.11 Cold Adhesive Styrene-Butadiene-Styrene Modified Bituminous Membrane Roofing
08-16
07 60 00 Flashing and Sheet Metal 07-14
07 71 00 Roof Specialties 10-15
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
07 95 13 Expansion Joint Cover Assemblies 02-16
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08-16
08 14 00 Interior Wood Doors 02-16
08 31 13 Access Doors and Frames 02-16
08 34 74 Sound Control Wood Door Assemblies
08 41 13 Aluminum-Framed Entrances and Storefronts 08-16
08 51 13 Aluminum Windows 02-16
08 71 00 Door Hardware 01-16
08 71 13 Automatic Door Operators 02-16
08 80 00 Glazing 10-15
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15
09 06 00 Schedule for Finishes 04-15
09 22 16 Non-Structural Metal Framing 06-18
09 24 00 Portland Cement Plastering 10-15
09 29 00 Gypsum Board 06-18
09 30 13 Ceramic/Porcelain Tiling 09-15
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 02-16
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 21 23 Cubicle Curtain Tracks 05-15
10 26 00 Wall and Door Protection 10-15
10 28 00 Toilet, Bath, and Laundry Accessories 02-16
10 44 13 Fire Extinguisher Cabinets 08-18
10 73 16 Canopies
10 81 13 Bird Control Devices
DIVISION 11 – EQUIPMENT
11 73 00 Ceiling Mounted Patient Lift System 01-17
DIVISION 12 – FURNISHINGS
00 01 10 - 3
12 32 00 Manufactured Wood Casework 09-15
12 36 00 Countertops 12-18
12 48 13 Entrance Floor Mats and Frames
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-14
DIVISION 14– CONVEYING EQUIPEMENT (Not Used)
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 12 General Motor Requirements for Plumbing Equipment 09-15
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-15
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 09-15
22 11 23 Domestic Water Pumps 09-15
22 13 00 Facility Sanitary and Vent Piping 09-15
22 14 00 Facility Storm Drainage 09-15
22 40 00 Plumbing Fixtures 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
23 05 11 Common Work Results for HVAC 08-17
23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 08-17
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 02-15
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
23 07 11 HVAC and Boiler Plant Insulation 02-15
23 08 00 Commissioning of HVAC Systems 11-16
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 08-17
23 23 00 Refrigerant Piping 02-15
23 25 00 HVAC Water Treatment 02-15
23 31 00 HVAC Ducts and Casings 03-13
23 34 00 HVAC Fans 02-15
23 36 00 Air Terminal Units 02-15
23 37 00 Air Outlets and Inlets 02-15
23 40 00 HVAC Air Cleaning Devices 02-12
23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 04-11
23 81 23 Computer-Room Air-Conditioners 04-11
DIVISION 25 – INTEGRATED AUTOMATION (Not Used)
Rajesh Polygon
00 01 10 - 4
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 41 Underground Electrical Construction 01-17
26 09 23 Lighting Controls 01-18
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 51 00 Interior Lighting 01-18
26 56 00 Exterior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirement For Communications Installation 06-15
27 05 26 Grounding and Bonding for Communications Systems 09-19
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 15 00 Communications Horizontal Cabling 01-16
27 51 16 Public Address and Mass Notification Systems 10-18
27 52 23 Nurse Call and Code Blue Systems
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and Security 10-18
28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security
28 13 00 Physical Access Control System 10-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 11 Earthwork (Short Form) 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 17 23 Pavement Markings 08-16
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 03-17
33 30 00 Sanitary Sewer Utilities 06-13
DIVISION 34 – TRANSPORTATION (Not Used)