Revised MA2504 Specification 01505-Job No. MA2504 Revised Specification 01505 Mobilization and Demobilizatin.pdf

PDF 42 KB Posted

Attached to
Lahaina Small Boat Harbor Front Row Piers and Dinghy Dock Repair
Solicitation number
B26002728
Issued by
Maui County, Kaanapali CDP, Hawaii

About this file

This is a specification document for Section 01505 - Mobilization and Demobilization, prepared by the State of Hawaii Department of Land and Natural Resources for the Lahaina Small Boat Harbor Front Row Piers and Dinghy Dock Repair project (Job No. MA2504). The specification defines mobilization as the transporting, assembling, constructing, installing, and preparation of all equipment, machinery, structures, utilities, materials, labor, and incidentals necessary to perform contract work, while demobilization comprises the dismantling, removal of these items, and site cleanup to the Engineer's satisfaction. The project encompasses comprehensive repair and restoration of front row piers and dinghy dock infrastructure, including installation of five new fixed finger piers, three fixed piers with Tahiti mooring slips, two pile-guided floating docks, one pile-guided floating dinghy dock, concrete piles, aluminum gangway systems, fiber-reinforced plastic grating, asphalt pavement, landscaping, water system components, and electrical systems. The project completion timeline is 270 calendar days from the written notice to proceed, with a mandatory pre-bid conference required for prospective bidders and proposals due by May 26, 2026. Bids must be submitted electronically through the State of Hawaii e-Procurement System (HIePRO).

Payment for mobilization and demobilization shall be a lump sum bid not to exceed 10 percent of the total sum bid, with all costs for mobilization, demobilization, permits, environmental compliance, inspections, testing, and compliance documentation included in the bid price. The contractor shall not receive compensation for mobilization and demobilization in excess of amounts specified in the proposal. All equipment, machinery, buildings, utilities, and incidentals mobilized and demobilized shall remain the property of the contractor. Any additional mobilization or demobilization costs incurred on private lands beyond the maximum amounts specified must be absorbed by the contractor. The total contract is estimated at $6,000,000, with liquidated damages assessed at $100 per calendar day for work exceeding the completion schedule. Successful bidders must provide performance and payment bonds equal to 100 percent of the total contract price, maintain comprehensive insurance coverage with minimum limits of $1,000,000 per occurrence, and perform at least 20 percent of the work value with their own organization and immediate superintendence.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mobilization and Demobilization 01505-5

SECTION 01505 – MOBILIZATION AND DEMOBILIZATION

PART 1 - GENERAL

1.1 GENERAL REQUIREMENTS

Mobilization: Mobilization shall consist of the transporting, assembling, constructing, installing, and making ready for use at the job site, all the equipment, machinery, structures, utilities, materials, labor and incidentals necessary to do the work covered by this contract.

Demobilization: Demobilization shall consist of the dismantling and removal of the above- mentioned equipment, machinery, structures, utilities, materials, and incidentals, and cleaning up of the site to the satisfaction of the Engineer.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.1 GUIDELINES: If the Contractor utilizes private lands other than the sites provided by the State for mobilization purposes, the provisions of this section shall apply, and the mobilization and demobilization work on said private lands shall be in accordance with the agreement between the Contractor and the land- owner.

Any and all additional mobilization or demobilization costs in excess of the maximum amounts specified in the Proposal shall be included in the appropriate prices bid in the Proposal. The Contractor shall not receive any compensation for mobilization and demobilization in addition to those specified in the Proposal.

All equipment, machinery, buildings, utilities and incidentals mobilized and demobilized under this section shall remain the property of the Contractor.

PART 4 - MEASUREMENT AND PAYMENT

Mobilization and demobilization will not be measured for payment. Payment for completion of work required under this Section, including all labor, materials, tools, equipment and all incidentals necessary to accomplish the work, shall be the lump sum bid for mobilization and demobilization, not to exceed 10% of the total sum bid.