RFP 24-752-037 THIRD PARTY COMMISSIONING SERVICES
Solicitation number
PE-64410-NONST-2024-000000074
Issued by
Dekalb County, Georgia

About this file

This document is a Price Sheet Sample for RFP No. 24-752-037 for Third Party Commissioning Services issued by the DeKalb County School District in Georgia. The RFP seeks proposals from qualified firms to provide high quality and cost-effective third-party commissioning services for a 140,000 SF sample project with a $70,000,000 budget. The Price Sheet requests offerors to provide the position, number of hours, hourly rate, and total cost for services during the pre-design, design, preconstruction, construction, and close-out phases, including building envelope commissioning, facilities requirements, and operations and maintenance plan development. Offerors must also provide the total hours and total commissioning personnel cost. The RFP includes an owner's contingency of 10% of the commissioning personnel cost.

The Price Sheet emphasizes that the offeror's price must account for reasonable schedule changes, and the person signing the bid form must be legally authorized to bind the company. If the offeror is a joint venture, multiple signatures are required. The offeror must certify that the proposal was derived independently and is fair without collusion or fraud, and agrees to abide by all conditions of the RFP.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 RFP No. 24-752-037 REVISED ATTACHMENT I1 Third Party Commissioning Pricing Form

Project Name:SAMPLE PROJECT #1Size:140,000 SFTemplate Budget: $70,000,000.00
NAME OF OFFEROR:
ADDRESS:
CITY, STATE, ZIP CODE:
EMAIL ADDRESS:TELEPHONE NUMBER:
* List position, number of hours, and hourly rate as indicated.
Pre-deisgn & Design PhasePreconstruction PhaseConstruction PhaseClose-out Phase (including 12‐month
warranty period)Building Envelope CommissioningPrepare Facilities Requirements and Operations & Maintenance PlanProvide a COBie-compliant DatabaseTOTAL HOURSHourly Billing RateTotal Cost per Position
NamePosition
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
$$
Total Hours per Phase
Total Hours for the Project
Commissioning Personnel Cost (fully loaded inclusive of direct and indirect costs, background checks,travel, reimbursable and incidental expenses)$
Owner's Contingency(10% of Commissioning Personnel Cost)$
Commissioning Services Total Cost$
Assumed Schedule Basis ‐ Offeror's Price Must Account for Reasonable Schedule Changes
Please note that Offeror is responsible for checking the accuracy of the information including herein, including calculations and formulas.

The person signing this bid form must be legally authorized to bind the company.

Respectfully submitted_______________________________________________
[typed name of Contractor]
By: ______________________________________________[seal]
[signature]
_________________________________________________
[typed name and title]
_________________________________________________
[date of execution]

[If the Contractor is a joint venture, utilize this section of the proposal form for signatures.]

Respectfully submitted_______________________________________________
[typed name of Joint Venture Partner]
By:_______________________________________________
[typed name of Joint Venture Partner]
By: ______________________________________________[seal]
[signature]
_________________________________________________
[typed name and title]
_________________________________________________
[date of execution]
By:_______________________________________________
[typed name of Joint Venture Partner]
By: ______________________________________________[seal]
[signature]
_________________________________________________
[typed name and title]
_________________________________________________
[date of execution]
By submission of this Proposal, the Contractor certifies that this Proposal has been derived independently, without consultation, communication or agreement as to any matter relating to this Proposal with any other Contractor or with any competitor. The Contractor hereby certifies that this Proposal is made without prior understanding, agreement or connection with any corporation, firm or person submitting a proposal for the same Project and is in all respects fair and without collusion or fraud. The Contractor agrees to abide by all conditions of the Request for Proposal.