This is a Price Sheet for the Indian River Channel Phase I – Riverside Canal Maintenance Dredging Project solicited by Brevard County Purchasing Services on behalf of the Natural Resource Management Department in Florida. The project encompasses mechanical dredging and material handling services totaling approximately 2,675 cubic yards of sediment removal, along with associated debris removal of 268 cubic yards. The scope of work includes mobilization and demobilization, maintenance of traffic, site preparation and restoration, surveys (pre/post with photo and video documentation), erosion controls, environmental monitoring, hydrographic surveys, and as-built surveys. Additional work items include floating turbidity barrier installation and monitoring, towing to shore and offloading of 2,943 cubic yards of material, dewatering operations, and final transport and offsite disposal of dredged sediment.
The price sheet is structured as a lump sum fixed cost bid format with separate line items for unit-priced work. All cost fields in the submitted price sheet are blank with zero dollar amounts indicated, suggesting this is a template document provided to bidders for pricing purposes rather than a completed bid submission. Bidders are required to populate individual unit costs for various work items as well as lump sum costs for general items and temporary handling site activities. The total bid amount, comprising both fixed lump sum costs and estimated measured quantity costs, is to be calculated by the bidding contractor based on their proposed pricing for labor, equipment, materials, and disposal services associated with the dredging and channel maintenance project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Public_Meeting_Notice.pdf | ||
| Bid_Tabulation.pdf | ||
| Bid_Tabulation_-_Names_Only.pdf | ||
| Addendum_5.pdf | ||
| Revised_Attachment_C_-_Drawing_Set.pdf | ||
| Revised_Attachment_B_-_Specifications.pdf | ||
| Addendum_4.pdf | ||
| Addendum_3.pdf | ||
| Addendum_2.pdf | ||
| Addendum_1.pdf | ||
| Attachment_A_-_Price_Sheet.xlsx | XLSX spreadsheet | |
| Attachment_E_-_Draft_Contract.pdf | ||
| Attachment_C_-_Drawing_Set.pdf | ||
| Attachment_D_-_Sediment_Chemistry.xlsx | XLSX spreadsheet | |
| B-8-26-05_INV_&_SPECS.pdf | ||
| Attachment_B_-_Specifications.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Sheet Indian River Channel Phase I - Riverside Canal Navigation Dredging Project Revised Attachment A - Price Sheet
| Lump Sum Fixed Costs - Base Bid | |||||
| Bid Item | Item Description | Est Qty. | Unit | Unit Cost | Lump Sum Total |
| General Items | |||||
| A1 | Mobilization/Demobilization | 1 | LS | $ - 0 | |
| A2 | Maintenance of Traffic | 1 | LS | $ - 0 | |
| Temporary Handling Site | |||||
| B1 | Surveys (Pre/Post, with Photo & Video) | 2 | LS | $ - 0 | |
| B2 | Erosion Controls and Devices | 1 | LS | $ - 0 | |
| B3 | Site Preparation | 1 | LS | $ - 0 | |
| B4 | Site Restoration | 1 | LS | $ - 0 | |
| Dredging and Material Handling | |||||
| C1 | Floating Turbitidy Barrier and Monitoring | 1 | LS | $ - 0 | |
| C2 | Environmental Monitoring | 1 | LS | $ - 0 | |
| C3 | Hydrygraphic Survey (Pre/Post) | 2 | LS | $ - 0 | |
| C4 | As-Built Survey | 1 | Ls | $ - 0 |
| Bid Item | Item Description | Est Qty. | Unit | Estimated Total |
| Dredging and Material Handling | ||||
| C5 | Mechanical Dredging | 2,675 | CY | $ - 0 |
| C6 | Debris Removal | 268 | CY | $ - 0 |
| C7 | Tow to Shore and Offloading | 2,943 | CY | $ - 0 |
| C8 | Dewatering | 2,675 | CY | $ - 0 |
| Offsite Disposal | ||||
| D1 | Final Transport of Sediment | 2,675 | CY | $ - 0 |
| D2 | Disposal | 268 | CY | $ - 0 |
| Summary of Costs | ||
| TOTAL LUMP SUM FIXED COSTS - BASE BID: | $0.00 | |
| TOTAL ESTIMATED MEASURED QUANTITY COSTS - BASE BID: | $0.00 |
TOTAL BID: $0.00