Attachment_B_-_Specifications.pdf

PDF 16 MB Posted

Attached to
Indian River Channel Phase I – Riverside Canal Maintenance Dredging Project
Solicitation number
B-8-26-05
Issued by
Florida

About this file

This technical specifications document supports Brevard County's solicitation for the Indian River Channels Phase 1 Riverside Canal maintenance dredging project, prepared under the responsible charge of professional engineer Leah G. Torres, P.E. (Florida Registration No. 86641). The project involves mechanical dredging of approximately 2,675 cubic yards of accumulated sediments from the Riverside Canal portion of the Indian River Channels to a design depth of -5.5 feet Mean Low Water (MLW) datum, with no over-dredge authorization permitted. The contractor must transport and dispose of all dredged material at designated upland facilities and restore temporary handling areas to pre-construction conditions. Work must comply with conditions set forth in the Florida Department of Environmental Protection Environmental Resource Permit No. 412177-001-EI (expiration date August 12, 2027) and the U.S. Army Corps of Engineers Proffered Letter of Permission Permit No. SAJ-1996-02153(LP-JDP) (expiration date December 7, 2027). The project includes installation and maintenance of floating turbidity barriers, environmental monitoring, hydrographic surveys (pre- and post-construction), mechanical dredging with a minimum capacity of 100 cubic yards per day, dewatering operations, and final restoration with signed as-built surveys. The contractor must maintain a minimum 10-foot buffer from mangroves and other natural resources, observe manatee protection conditions, comply with Eastern Indigo Snake protection measures, and restrict operations to daylight hours (one-half hour after sunrise to one-half hour before sunset), Monday through Friday only.

The specifications establish comprehensive requirements for quality control, environmental protection, and regulatory compliance with oversight by the Brevard County Natural Resources Management Department and construction supervision by the engineer of record (WSP Inc.). Payment methodology includes lump-sum and unit-price bid items covering mobilization/demobilization (not to exceed 10 percent of total bid price), site preparation and restoration, surveys, turbidity barriers, environmental monitoring, mechanical dredging, debris removal, towing and offloading, dewatering, labor, and final material transportation and disposal. The contractor bears all costs for bonds, insurance, permits not previously obtained, labor, equipment, materials, and any necessary permit modifications. Interim surveys are at contractor expense, and final payment is contingent upon acceptance of post-construction surveys and site restoration completion. The project anticipates completion within three work weeks, with the contractor responsible for all site safety, utility location verification, traffic maintenance per Florida Department of Transportation standards, and compliance with federal, state, and local environmental regulations.

View the file

Other files

File Type Posted
Public_Meeting_Notice.pdf PDF
Bid_Tabulation.pdf PDF
Bid_Tabulation_-_Names_Only.pdf PDF
Addendum_5.pdf PDF
Revised_Attachment_A_-_Price_Sheet.xlsx XLSX spreadsheet
Revised_Attachment_C_-_Drawing_Set.pdf PDF
Revised_Attachment_B_-_Specifications.pdf PDF
Addendum_4.pdf PDF
Addendum_3.pdf PDF
Addendum_2.pdf PDF
Addendum_1.pdf PDF
Attachment_A_-_Price_Sheet.xlsx XLSX spreadsheet
Attachment_E_-_Draft_Contract.pdf PDF
Attachment_C_-_Drawing_Set.pdf PDF
Attachment_D_-_Sediment_Chemistry.xlsx XLSX spreadsheet
B-8-26-05_INV_&_SPECS.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B � Technical Specifications Brevard County Indian River Channels Phase 1 Riverside Canal

TECHNICAL SPECIFICATIONS

Brevard County District 2 Navigation Dredging Committee

Indian River Channels Phase 1 Riverside Canal

Navigation Dredging Project

00 41 00 Bid Schedule

01 11 00 Summary of Work

01 20 00 Measurement and Payment

01 32 16 Construction Progress Schedule

01 33 00 Submittal Procedures

01 35 05 Environmental Protection

01 45 01 Quality Control Procedures

01 71 13 Mobilization/Demobilization

01 77 00 Closeout Procedures

02 21 00 Surveys

31 22 19 Finish Grading

31 25 00 Erosion and Sedimentation Controls

35 24 00 Dredging

Appendices

B-1 Florida Department of Environmental Protection Environmental Resource Permit File No. 412177-001-

EI, Oculus Facility ID Search: ERP 412177. Permit Construction Expiration Date: August 12, 2027.

B-2 U.S. Army Corps of Engineers Proffered Letter of Permission Permit File No. SAJ-1996-02153(LP-JDP).

Permit Construction Expiration Date: December 7, 2027.

B-3 Hydrographic Survey / Geotechnical Data (Land & Sea) - March, 2021

B-4 Natural Resources Figures (Wood/WSP) – July, 2021

The Engineering material and data contained in the Contract Drawings and Technical Specifications in relationship to the Indian River Channels Phase 1 Riverside Canal Dredging Project were compiled under the responsible charge of the undersigned:

Leah G. Torres, P.E.

Florida Registration No. 86641

SECTION 00 41 00 1 September 25, 2025

SECTION 00 41 00

BID SCHEDULE

PART 1 – GENERAL

1.01 SCOPE

A. The project consists of the dredging, transportation, and disposal/beneficial reuse of approximately

2,675 cubic yards of sediment from the Indian River Channels Phase 1 Riverside Canal project area.

Actual dredge volumes will vary from estimates provided herein, as they are dependent on field conditions.

B. The County intends to award the project to the most qualified, responsible, and responsive bidder with the lowest bid.

C. If the quantity of a unit-priced item in this contract is demonstrated by the Contractor’s pre-construction hydrographic survey to be more than 25 percent of the estimated quantities as defined in the Bid Table, the Contractor may request a change order for the additional amount at the unit price specified. No additional payment will be made for material removed outside of or below the dredge template indicated in the construction drawings and once appropriate setbacks are determined. Change orders will not be considered for additional material removed unless a written request is made to the County and the Engineer in advance of removal. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing with the demand, an extension of time consistent with associated quantity variation. This variation in estimated quantity (VEQ) clause does not apply to all bid items. It only applies to the dredge quantity as measured in cubic yards.

D. This bid shall be for a complete project, and bid item prices shall include all components necessary for successful completion of the work as designed and specified.

E. This Contract is solicited with bid items. Any bid price for items indicated above which are considered unbalanced with the opinion of the County may be rejected. An unbalanced bid is one in which the cost for one or more bid items is considered significantly low and one or more bid items is significantly high.

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

END OF SECTION 00 41 00

SECTION 01 11 00 1 July 15, 2025

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 DESCRIPTION

A. Brevard County District 2 (County) is soliciting licensed and qualified marine Contractors for the maintenance dredging of Indian River Channels Phase 1 Riverside Canal in Brevard County, Florida.

The work consists of furnishing all labor, materials, equipment, and performing all tasks necessary for the excavation, handling, and disposal/reuse of accumulated sediments within the project area.

B. The following general information is based on initial hydrographic surveys and permitting conditions. The width of the Indian River Channels Phase 1 Riverside Canal varies. The width of the canal is bounded by a residential shoreline. The length of the canal is approximately 480 linear feet.

The design dredge template elevation is -5.5 feet Mean Low Water (MLW) datum, with no over-dredge. The dredge template design accommodates setbacks from mangroves.

C. All dredging activities are to be performed using mechanical means. A temporary staging area is indicated in the construction drawings. Only designated areas shown on construction drawings, may be used for offloading and temporary handling of dredged material. The Contractor shall be responsible for restoring the designated dredged material handling facility back to its original condition as documented in pre-construction surveys and photographic documentation. This includes the removal of all temporary structures such as timber mats, fencing, and erosion control devices.

D. The intent of the project is to remove accumulated sediments to the authorized design dredge depth along the length of the Indian River Channels Phase 1 Riverside Canal, without impacting adjacent natural resources or structures. Overdredge is not authorized by regulatory agencies for this project.

E. It is estimated that approximately 2,675 cubic yards of sediment could be removed from the project area. Actual quantities will be confirmed by detailed hydrographic surveys, performed by the

Contractor and approved by the County, prior to dredging.

F. Underground utilities and improvements were not located as part of this survey. It will be the

Contractor’s responsibility to coordinate these locations prior to construction.

G. This work must be completed according to the plans and specifications within the time specified in the contract. The contractor must complete the work while maintaining compliance with the conditions of the Florida Department of Environmental Protection (FDEP), the United States Army

Corps of Engineers (USACE), the Florida Department of Transportation (FDOT), the U.S. Coast Guard, and all local permits.

H. The Contractor is solely responsible for all construction means, methods, techniques, and procedures including construction monitoring, permit compliance, and the sequence of the work.

I. The Contractor shall be responsible for the design, installation, and maintenance of other site elements necessary to support the dewatering and hauling of dredge material.

J. Regulatory permits require turbidity monitoring to be conducted prior to, and for the duration of the project.

K. The Contractor must comply with the applicable Florida Fish and Wildlife Conservation Commission

(FWC) Standard Manatee Conditions for In-Water Work.

SECTION 01 11 00 2 July 15, 2025

L. The Contractor must comply with the USACE Jacksonville District’s Programmatic Biological Opinion

(JaxBO) Project Design Criteria (PDC) for In-Water Activities.

M. The contractor must comply with all permit conditions referenced in the FDEP Environmental

Resource Permit File No. 412177-001-EI and the USACE Proffered Letter of Permission Permit File

No. SAJ-1996-02153(LP-JDP).

N. Canal cut dimensions are contingent on receipt of liability release from the adjacent property owner and acceptance by the County. The County will verify receipt of appropriate releases and will confirm the proposed dredge activity noting any exceptions prior to approval of the construction schedule.

1.02 – ORDER OF WORK

A. The order of work shall generally be:

1- The preparation of the designated offloading and temporary handling site, including all erosion and sedimentation controls prescribed by the FDEP permit conditions.

2- The installation of turbidity controls, sampling, and commencement of dredging.

3- The order and progression of dredging shall be determined by the Contractor to conform to regulatory constraints while maximizing efficiency.

4- The deconstruction of temporary structures, cleanup, and restoration/documentation of the designated temporary handling and offloading areas.

1.03 – LAYOUT OF THE WORK

A. The Contractor shall be responsible for continuously maintaining the position of the dredge or excavating equipment within the prescribed dredging limits. The Contractor shall continuously monitor water levels and depth of dredging to ensure that the designed depth is met. The

Contractor shall have adequate personnel on site with the ability to set accurate controls for continual dredge operations.

B. The following horizontal dredging limits shall apply unless amended for a site-specific location in writing by the County and the Engineer:

1- Channel Markers/Shoreline: The Contractor shall operate within channel markers of channels and, observe a strict buffer from all shoreline structures of 10 feet.

2- Mangrove: The Contractor shall maintain a 10-foot buffer from mangroves present around the project area.

3- Other Natural Resources: No dredging shall occur within 10 feet of natural resources present at the time of construction. The horizontal limits of dredging shall be adjusted to meet the actual field conditions at the time of dredging.

C. Vertical dredging limits are prescribed by regulatory authorizations, not to exceed elevation -5.5 feet (MLW datum).

D. The Contractor shall be responsible for the layout of the work per the construction plans.

E. The Contractor shall use HYPACK or comparable software to map the project area, and continuously monitor dredging coordinates and depths. The Contractor is responsible for accurately dredging within the template, side-slopes, and maintaining setbacks as specified in construction drawings, specifications, and regulatory permits.

1.04 - OBSTRUCTION OF CHANNEL:

SECTION 01 11 00 3 July 15, 2025

A. The Contractor may temporarily close Indian River Channels Phase 1 Riverside Canal during dredging activities. It is expected that the project will be completed in less than three (3) work weeks. Outside the temporarily closed areas, in cases where the Contractor’s equipment operation may obstruct navigation or may endanger the passage of vessels, said equipment or operation should be moved as soon as practical on the approach of any vessel to such extent as may be necessary to afford safe passage. Outside the temporarily closed areas, scow barges shall be secured in a position where it does not impede navigation or access to navigational channels, docks, moorings, or other waterfront property.

B. Upon completion of the work, the Contractor shall promptly remove equipment including, markers, buoys, scow barges, and turbidity curtains.

1.05 – SITE CONDITIONS:

A. The work is located in or adjacent to the Indian River Lagoon, therefore exposed to weather conditions which at times may include storms and rough sea conditions requiring temporary suspension of marine construction activities. Additionally, the work area may be subject to wakes generated by passing vessels. The Contractor is responsible for being familiar with these conditions and for taking these condition under consideration during pricing and scheduling of work.

B. It is the Contractor’s responsibility to take precautions to ensure that partially complete work is not subject to displacement or damage due to natural site conditions or vessel wakes. Should any such damage or displacement of partially completed work occur, the Contractor is responsible for repairing any such damage or displacement of partially completed work at no additional cost to the County.

C. A geotechnical exploration of subsurface conditions of Indian River Channels Phase 1 Riverside

Canal was conducted by Land & Sea in 2021. The full report and (dated March 2021), is included as an Appendix in the Bid Specifications. The Contractor shall perform, at the Contractor’s expense, any additional such investigations that the Contractor deems necessary to verify sediment characteristics and dredge quantities.

D. Information and data furnished or referred to herein are provided for the Contractor’s information.

However, it is expressly understood that the County and Engineer shall not be responsible for any interpretation or conclusion made by the Contractor. It is the Contractor’s responsibility to be familiar with local conditions that may in any manner affect the performance of the work.

1.06 - SITE PREPARATION:

A. The sediments removed from the dredge template may be temporarily stored at the designated temporary handling area, and must ultimately be trucked off-site as per the technical specifications.

B. The Contractor shall comply with all site preparation specified by regulatory permits including erosion & sedimentation controls, and accommodation of designated offloading areas.

C. Upon completion and acceptance of the dredging, the Contractor shall restore the temporary handling areas to their pre-construction condition according to the pre-construction condition survey of the designated offloading area.

D. Prior to the restoration of the temporary handling and offloading area, the Contractor shall meet with the County and the Engineer on site to discuss the specifics of site restoration.

1.07 - NOTICE TO MARINERS:

SECTION 01 11 00 4 July 15, 2025

A. The Contractor shall be responsible for notifying the Coast Guard in sufficient time to allow for publication of a notice to mariners. The local Coast Guard District contact is:

7th Coast Guard District

Brickell Plaza Federal Building

909 S.E. First Avenue, Room 406

Miami, Florida 33131-3028

Attn: (LMN)

Telephone: (305) 415-6750

B. The Contractor shall obtain approval from the U.S. Coast Guard for all buoys, markers, and other dredging aids prior to installation. Dredging aids, lights or targets shall not be placed or colored in a manner that they will obstruct or be confused with navigation aids.

1.08 – ENVIRONMENTAL PROTECTION:

A. The Contractor shall exercise due caution as not to damage existing native vegetation along or near the shoreline of the offloading area, natural resources within and around the project area, access ways, handling areas, and staging areas. Any native vegetation or seagrass outside the dredged template damaged by the Contractor during the course of work shall be restored by the Contractor at the Contractor’s expense.

B. In order to ensure that manatees are not adversely affected by construction activities as described by these specifications, the Contractor is required to strictly adhere to the FWC Standard Manatee

Construction Conditions for In-Water Work (2011) which identify specific requirements for the protection of manatees.

C. The Contractor will comply with the National Marine Fisheries Service’s “Sea Turtle and Smalltooth

Sawfish Construction Conditions” dated March 23, 2006.

D. The Contractor is responsible for the installation of floating turbidity barriers around the dredge area and adhering to all turbidity controls and monitoring as specified by regulatory permits.

1.09 – PERMITS:

A. The Contractor is required to obtain any permit (Federal, State, and local) required to complete the project as their operations dictate, which has not been previously obtained by the County. Copies of all previously obtained permits are included with the bid documents.

B. A permit modification for the existing FDEP and USACE permits will be required to accommodate any deviations from dewatering methods and/or final disposal location authorized by issued permits (including Federal, State, and local permits). The Contractor is responsible for securing permit modifications.

1.10 - GENERAL CONSTRUCTION NOTES

A. All elevations in plans refer to North American Vertical Datum of 1988 (NAVD88) vertical datum as established by the National Oceanic and Atmospheric Administration (NOAA).

B. Elevation -5.5 feet MLW datum is equal to -6.23 feet (NAVD88) according to data published by

NOAA.

C. The Contractor shall make a determination of the quantities of work required to complete the construction shown on the plans. The Contractor shall also make an independent assessment of the

SECTION 01 11 00 5 July 15, 2025 site and work required prior to bidding and any discrepancies, errors or omissions, shall be brought to the attention of the County representative before the due date.

D. The Contractor is responsible for verifying the location of all underground utilities or other objects prior to commencing work at the site. Any utilities or other items damaged during construction shall be repaired by the Contractor at no cost to the County.

E. All areas or items that are damaged or disturbed by the Contractor shall be restored to the original condition or better condition at no cost to the County.

F. The Contractor shall check plans for conflicts and discrepancies prior to construction. The

Contractor shall notify the Engineer of record of any conflict before performing any work in the affected area.

G. The Contractor is responsible for repairing any damage to existing facilities, above or below ground, which may occur as a result of the work performed by the Contractor at no cost to the County.

H. It is the Contractor’s responsibility to become familiar with the permit, sampling, monitoring, and inspection requirements of the various governmental agencies.

I. All specifications and documents referred to shall be of latest revisions and/or latest edition unless otherwise noted.

J. The Contractor is responsible for maintaining horizontal and vertical accuracy during dredging, QA/QC procedures must be submitted and approved by the County and Engineer.

K. All work performed shall comply with the regulations and ordinances of the various governmental agencies having jurisdiction over the work.

L. Repair and replacement of all private and public property affected by this work shall be restored to a condition of equal to, or better than existing conditions.

M. Contractor shall provide a dust management plan to the Engineer of record and the County for approval prior to initiating construction. Approval of the plan shall not obligate the Engineer or the

County in any way and shall not alleviate the Contractor’s responsibility to control fugitive dust.

N. Contractor shall provide a plan for offloading sediment by means of the designated offloading area.

The plan shall include methods to manage disturbance to the shallow offshore areas, beach area, and the upland path to the designated temporary handling areas. The plan shall be submitted to the Engineer of Record and County for approval prior to initiating construction. Approval of the plan shall not obligate the Engineer or the County in any way and shall not alleviate the Contractor’s responsibility to avoid impacts on the offloading area or to restore any areas to their original condition upon the completion of construction activities.

O. Construction traffic shall not impede the safe and efficient use of the surrounding roadways. The

Contractor shall follow the FDOT standard indices 600 series for maintenance of traffic during construction.

P. Contractor shall be responsible for the timely removal of any fugitive dust, sand, or debris which may be caused by the Contractor’s operations.

Q. The Engineer of Record is the Engineer responsible for the design of the project

Contact:

Leah G. Torres, P.E.

WSP Inc.

6256 Greenland Road

Jacksonville, FL 32258 USA

Tel. +1 904-328-2629 (Teams)

R. Engineer of Record (WSP) is also the Engineer hired to supervise the observation of construction.

S. Other contact information will be provided as necessary.

SECTION 01 11 00 6 July 15, 2025

T. The Contractor shall not occupy private land outside of any easements or rights of way unless written authorization has been signed by the property owner and provided to the County. Prior to the use of private lands, the Contractor shall submit a copy of the agreement(s) to the County. All agreements shall include language granting the County and Engineer unrestricted rights to access the property in association with the performance of their responsibilities concerning this project. In the event that the Contractor uses private property for any purpose without first having the necessary approvals from the property owner or provided the necessary agreement to the County, the County will direct the Contractor to cease using such property immediately. Prior to application for final payment, the Contractor shall provide documentation from the owner of each piece of private property for which an agreement for use was provided, or for which the County has issued written notification to the Contractor, that each owner is satisfied with the manner in which the

Contractor has restored the property. Final payment of or reduction in retainage shall not be paid until such documentation is received by the County.

U. Under no circumstances will the use of explosives for excavation be permitted.

V. Material removed from beyond the vertical or horizontal dredging limits as specified on the contract drawings shall be considered excessive dredging for which no payment will be made. The

Contractor shall be responsible for all Federal, State, and local regulatory permits, implications, violations, and/or fees as a result of excessive dredging.

W. Any dredged materials deposited at locations other than as designated or approved by the County shall be considered misplaced material and shall not be paid for until the Contractor, at the

Contractor’s expense, removes and re-deposits such misplaced material to the approved disposal site. The removal and the redeposit of the misplaced material and any necessary disposal site restoration work shall not be the basis for a time extension or additional compensation under this contract.

X. Debris, such as stumps, rocks, rock fragments, roots, logs, trash, vegetation, etc. And any other objects (except archeological or historical resources) that exist within the project area or are unearthed during the dredging operations, shall be removed, transported, and disposed of at an appropriate disposal site and will not constitute a change of condition to the contract/agreement.

Removal and disposal of debris will be the sole responsibility of the Contractor in its entirety. If archeological or historic resources are encountered the Contractor shall notify the County immediately and stop work until directed to restart. Removal and disposal of debris and obstructions shall not be provided separately from payment. All costs associated with the required disposal of debris shall be included in the contract price for dredging.

Y. Contractor shall be responsible for the removal of any material that accumulates in the dredged channel or other areas as a result of the Contractor’s activity and/or operations.

Z. The work is to be completed within the area shown on the plans. If additional area is required for storage of equipment or materials, arrangements for such storage facilities shall be the responsibility of the Contractor. No staging, offloading, or parking may occur on vacant lots within the residential neighborhoods (per County code) without written permission from the landowner and County for approval.

AA. Special measures shall be taken to prevent bilge pump waste, or effluent, chemicals, fuels, oils, greases, and bituminous materials from entering the water.

BB. Disposal of any materials, wastes, effluent, trash, garbage oil, grease, chemical, etc., in and adjacent to the project site shall not be permitted. If any waste materials are dumped in unauthorized areas, the Contractor shall remove the material and restore the area to the original condition. If necessary, SECTION 01 11 00 7 July 15, 2025 the contaminated ground shall be excavated, disposed of as directed by the Engineer of record, and replaced with suitable fill material.

CC. Dredged material will be transported offsite to the pre-approved location.

DD. The County has performed a pre-construction survey that is included in the contract drawings. This pre-construction survey was used to calculate an estimated quantity of material to be dredged. This quantity is considered an estimate only. Payment for this work shall be based on the actual volume upon survey verification of dredging, as identified by the final construction survey provided at the

Contractor’s cost. The Contractor shall make an assessment of this and any other relevant information necessary, in the judgment of the Contractor, in determining the expected volume to be removed. All interim surveys (necessary for interim pay requests) will be done by the Contractor at the Contractor’s expense. Complete survey requirements are provided in the specifications.

EE. Contractor shall coordinate temporary removal and reinstallation of all aids to navigation within the dredge template with the asset owner.

1.11 - SAFETY NOTES:

A. It shall be the sole responsibility of the Contractor to comply with and enforce all applicable safety regulations. The information herein has been provided for the Contractor’s information only and does not imply that the County, County’s Engineer, or Engineer of record will inspect and/or enforce safety regulations.

B. During the construction and/or maintenance of the project, all safety regulations are to be enforced.

The Contractor shall be responsible for the control and safety of personnel. Labor safety regulations shall conform to the provisions set forth by the Occupational Safety and Health Administration

(OSHA) in the federal register of the department of transportation.

C. It is the Contractor’s responsibility to ensure that all personnel in the project area wear proper personal protection equipment, including but not limited to safety vests, hard hats, safety boots, eye protection, hearing protection, and personal floatation devices.

1.12 - DEWATERING

A. The FDEP permit specific conditions for dewatering must be met by the Contractor at all times.

B. Contractor shall provide dewatering details regarding location, specifications, procedures, and permits to the County and Engineer of record for review prior to mobilization. No equipment or personnel may occupy any lands or easements not owned directly by the County.

C. Contractor shall install an FDOT approved silt fence and construction fencing around the entire temporary handling area. The Contractor is responsible for maintaining this fencing at all times.

D. Contractor shall implement and maintain those measures necessary to prevent, control and abate any erosion of the ground surface or shoreline banks caused by the work. The use of best management practices such as straw bales, erosion screens, and turbidity screens shall be used for this portion of the work. The Contractor shall construct or install temporary and permanent erosion and sediment control measures dictated by specifications, contract drawings, and permit authorizations.

E. Turbidity, erosion and sediment control measures shall be maintained until the completion of work.

1.13 – PRESERVATION OF PROPERTY

A. The Contractor shall Preserve from damage, all property along the line of the Work, in the vicinity of or in any way affected by the Work, the removal or destruction of which is not called for by the

SECTION 01 11 00 8 July 15, 2025

Drawings. Preserve from damage, public utilities, trees, lawn areas, building monuments, fences, pipe and in water/underground structures, sea walls, docks and public streets. Whenever damages occur to such property, immediately restore to its original condition. Costs for such repairs are incidental to the Contract.

B. In case of failure on the part of the Contractor to restore property or make good on damage or injury, the County, upon 24 hours written notice, proceed to repair, rebuild, or otherwise restore such property as may be deemed necessary, and the cost thereof will be deducted from any moneys due or which may become due the Contractor under this Contract. If removal, repair or replacement of public or private property is made necessary by alteration of grade or alignment authorized by the

County and not contemplated by the Contract Documents, the Contractor will be compensated, in accordance with the General Conditions, provided that such property has not been damaged through fault of the Contractor or the Contractor's employees.

C. The prosecution of the work shall ensure the stability of subaqueous utility crossings, buried and overhead utilities, parallel runs, utility poles and lines, guys and anchors, culverts, pipes and other structures or trees and vegetation or existing slope protection lying on or adjacent to the site of the work, insofar as structures that may be jeopardized by dredging operations. The Contractor shall be responsible for repair of damage resulting from construction operations, insofar as such damage may be caused by variation in locations or depth of dredging, or both, from that indicated or permitted under the contract.

D. Miscellaneous Structures: The Contractor assumes and accept responsibility for all injuries or damage to culverts, in-water structures, building/bridge foundations and walls, sea/retaining walls, or other structures of any kind met with during the prosecution of the Work. Assume and accept liability for damages to public or private property resulting therefrom.

END OF SECTION 01 11 00

SECTION 01 20 00 1 July 15, 2025

SECTION 01 20 00

MEASUREMENT AND PAYMENT

PART 1 – GENERAL

1.01 MEASUREMENT OF QUANTITIES

A. All work completed under the Contract will be measured by the County based on observed and/or measured progress of each item specified on the schedule of values.

B. This contract is being awarded on the lowest base bid presented by qualified Contractors. Bid items will be paid on a lump sum cost or measured quantity unit price cost as identified in the description for each bid item.

C. The lump sum and unit prices specified on the Bid Pricing Form shall include all costs necessary for the complete and successful completion of the project, including equipment, labor, direct charges, indirect charges, profit, incidental cost, taxes, and/or any other cost associated with that item, whether or not it is specifically identified in the plans or specifications. All appropriate costs shall be applied to the closest applicable item.

D. The method of measurement and computations to be used in the determination of quantities of material furnished and of work performed under the Contract are identified in the description for each bid item.

E. The term "lump sum," when used as an item of payment, will mean complete payment for the work described for that item.

F. The term "unit price," when used as an item of payment, will mean complete payment for the work described for that item.

G. An inspector designated by the County will observe all work. The inspector shall confirm that work has been completed in accordance with the contract documents and all work has been completed to the satisfaction of the County.

H. The Contractor is responsible for all work until it is inspected and accepted by the County. This includes replacing or repairing damages from wind, waves, and storms to the satisfaction of the

Engineer.

I. All allowable payable percentages listed in the following bid item descriptions do not account for retainage.

J. Payment will not be made for work done in any area designated by the County until the full depth required under the contract is secured in the whole of such areas.

1.02 BID ITEMS

A. GENERAL ITEMS

1. Mobilization/Demobilization

a) This bid item shall include all costs associated with the mobilization and demobilization of laborers and equipment for performance of the work at the temporary handling site and all costs associated with the preparatory work and operations necessary in mobilizing and demobilizing the dredge, dredge support equipment, boats, and equipment for the transportation of dredged material to the temporary handling site. In addition, the cost of bonds and required insurance, required plans and submittals, and any other pre-construction expenses necessary for the start of work (excluding the cost of construction materials) or post-construction expenses necessary for closeout shall also be included in

SECTION 01 20 00 2 July 15, 2025 this section. The cost of any items or work not included under a specific lump sum or unit price bid on the Bid Pricing Form shall be included as part of the lump sum price for

Mobilization and Demobilization. The price for this bid item shall not exceed 10% of the

Total Bid price.

b) The work specified under this section shall be paid for at the Contract lump sum price with

60% allowable at the commencement of dredging and the remaining 40% allowable at the completion of the project.

2. Maintenance of Traffic

a) This bid item shall include all costs associated with the maintenance of traffic within the temporary handling facility and the coordination of trucks entering and exiting the facility.

b) The work specified under this section shall be paid for at the Contract lump sum price.

B. TEMPORARY HANDLING SITE

1. Surveys

a) This bid item shall include all costs associated with initial control set up, construction staking, pre- and post-construction surveys associated with the temporary handling facility.

This bid item shall also include photos and overall video records as part of the pre- and post- construction surveys. Dredge surveys are not included in this bid item.

b) The work specified under this section shall be paid for at the Contract lump sum price.

2. Erosion Controls and Devices

a) This bid item shall include all costs associated with installation, maintenance, stabilization, and removal of all temporary erosion control devices and loading/offloading stabilization devices at the temporary handling facility

b) The work specified under this section shall be paid for at the Contract lump sum price.

3. Site Preparation

a) This bid item shall include all costs associated with the set-up of the temporary dredged material handling facility including marking, fencing, and staging not specifically covered in another bid item.

b) The work specified under this section shall be paid for at the Contract lump sum price.

4. Site Restoration

a) This bid item shall include all costs associated with the complete restoration of the temporary handling facility (deconstruction, debris removal, regrading, seeding, and planting) to pre-construction conditions, as documented in pre-construction surveys and determined acceptable by the County.

b) The work specified under this section shall be paid for at the Contract lump sum price. A maximum of 75% will be payable prior to acceptance of the final temporary handling site post-construction survey, with the remaining 25% payable after acceptance of the final survey.

C. DREDGING AND MATERIAL HANDLING

1. Floating Turbidity Barrier and Monitoring

a) This bid item shall include all costs involved in the installation, stabilization, maintenance, and removal of a floating turbidity barrier and associated turbidity monitoring, as specified in permit documents, surrounding the dredging project area.

SECTION 01 20 00 3 July 15, 2025

b) The work specified under this section shall be paid for at the Contract lump sum price based on the estimated percent complete of that section.

2. Environmental Monitoring

a) This bid item shall include all costs associated with environmental monitoring and other measures specified by permits not included in other bid items. This may include, but is not limited to, endangered species observation, spill prevention, and full compliance with

Standard Manatee Conditions for In-Water Work.

b) The work specified under this section shall be paid for at the Contract lump sum price based on the estimated percent complete of that section.

3. Hydrographic Survey (Pre/Post)

a) This bid item includes all costs associated with the pre- and post- construction hydrographic surveys associated with the project area for the purposes of establishing the pre-dredge bathymetry, setting the dredge templates, evaluating progress, determining pay quantities, and providing a record of post-dredge bathymetry.

b) The work specified under this section shall be paid for at the Contract lump sum price. A maximum of 75% will be payable prior to acceptance of the post-construction survey, with the remaining 25% payable after acceptance of the post-construction survey.

4. As-Built Survey

c) This bid item includes all costs associated with the final as-built survey signed and sealed by a licensed surveyor providing a record of post-dredge bathymetry. The As-Built must be approved by the County and Engineer of Record.

d) The work specified under this section shall be paid for at the Contract lump sum price. A maximum of 75% will be payable prior to acceptance of the post-construction survey, with the remaining 25% payable after acceptance of the post-construction survey.

5. Mechanical Dredging

a) This item shall include all quantity-based costs associated with the mechanical dredging of the designated project area as per Contract Drawings and Specifications. This includes all labor, equipment, and ancillary support required to complete dredging to the required depths within the constraints of the Project Area while preserving the stability of shoreline structures and respecting offsets from natural resources.

b) The work specified under this section shall be paid for at the Contract unit price. Payments will utilize the cumulative quantity/volume based on the sediment dredging quantities.

6. Debris Removal

a) This item shall include all quantity-based costs associated with the debris removal from the project area. This includes all labor, equipment, and ancillary support required to complete debris removal within the project area. Debris is defined as any materials, items, rubbish, inorganic or organic, not otherwise identified as water or sediment. Transport and lawful disposal of debris is covered in a separate bid item.

b) The work specified under this section shall be paid for at the Contract unit price. Progress and final payments will utilize the cumulative quantity/volume based on the debris dredging quantities.

7. Tow to Shore and Offloading

SECTION 01 20 00 4 July 15, 2025

a) This item shall include all quantity-based costs associated with the transportation of dredged sediments and debris from the project area to the designated temporary handling area.

b) The work specified under this section shall be paid for at the Contract unit price. Progress and final payments will utilize the cumulative quantity/volume based on the sediment dredging quantities.

8. Dewatering

a) This item shall include all quantity-based costs associated with dewatering within the constraints of regulatory authorizations.

b) The work specified under this section shall be paid for at the Contract unit price. Progress and final payments will utilize the cumulative quantity/volume based on the sediment

9. Labor

a) This bid item includes all quantity-based labor associated with dredging, not included in other bid items.

b) The work specified under this section shall be paid for at the Contract unit price. Progress and final payments will utilize the cumulative quantity/volume based on the sediment

D. OFFSITE DISPOSAL

1. Final Transportation of Sediments

a) This bid item includes all quantity-based costs associated with the transportation of dredged material from the temporary handling site to the permanent disposal/beneficial re-use site. This may include, but is not limited to, trucking, offloading, and any other handling not included in other bid items.

b) The work specified under this section shall be paid for at the Contract lump sum price. The work specified under this section shall be paid for at the Contract unit price. Progress and final payments will utilize the cumulative quantity/volume based on the sediment dredging quantities.

2. Disposal

a) This bid item includes all quantity-based costs associated with the transportation and lawful disposal of debris or sediments not dedicated for beneficial re-use. This may include landfill tipping fees or other costs associated with disposal.

b) The work specified under this section shall be paid for at the Contract lump sum price. The work specified under this section shall be paid for at the Contract unit price. Progress and final payments will utilize the cumulative quantity/volume based on the quantity of material not suitable for beneficial re-use.

PART 2 – PRODUCTS (Not Used)

END OF SECTION 01 20 00

SECTION 01 32 16 1 July 15, 2025

SECTION 01 32 16

CONSTRUCTION PROGRESS SCHEDULE

PART 1 – GENERAL

1.01 SUBMITTALS

A. Within fifteen (15) days of Notice to Proceed, Contractor shall prepare and submit to the County for review and acceptance a Construction Progress Schedule in the form of a Bar Chart Schedule.

B. The schedule shall include all mobilization/demobilizations and anticipated work schedule in accordance with all regulatory permit restrictions, as well as construction and restoration of the temporary handling site and offsite disposal area. Contractor shall carefully plan the dredging schedule.

1.02 ACCEPTANCE

A. The acceptance of a Baseline Construction Schedule is a condition precedent on:

1. Contractor starting work on the construction stages of the contract.

2. Processing Contractor’s invoice(s) for construction activities/items of work.

3. Review of any schedule updates.

B. Submittal of the Construction Progress Schedule and subsequent schedule updates, must be understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor’s plan on how the work must be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced.

1.03 SCHEDULE FORMAT

A. Bar Chart Schedule: The Bar Chart must show work activities, submittals, County review periods, material/equipment deliveries, temporary handling site preparation, dredging sections, transportation, dredged material removal and disposal/reuse, environmental monitoring, demobilization/mobilization, inspections, and closeout activities. The Bar Chart must be time scaled and generated using an electronic spreadsheet or scheduling program.

B. Schedule Submittals and Procedures: Submit Bar Chart Schedules and updates in hard copy and digital format to County and Engineer. Submit a digital copy of the Construction Progress Schedule in a format that is acceptable to the County.

1.04 WEEKLY SCHEDULE UPDATES

A. Update the Construction Progress Schedule and submit to the County and Engineer at the weekly

Construction Meetings or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining Work. With each updated schedule submitted the Contractor shall provide a concise report with the following items:

1. Schedule updates

2. Critical path

3. Date/time constraints other than those required in the Contract

4. Changes in original durations for activities that have not started

5. Status of completion date and interim milestones

6. Anticipated delays (and corrective actions to minimize delays)

SECTION 01 32 16 2 July 15, 2025

7. A description of foreseeable schedule problem areas

1.05 WEEKLY PROGRESS MEETINGS

A. The Contractor shall prepare for and participate in a weekly progress meeting with the County for the purpose of jointly reviewing the actual progress as compared to the planned progress, and to review planned activities for the current week and the upcoming two weeks. Use the currently approved schedule update for the purposed of this meeting.

END OF SECTION 01 32 16

SECTION 01 33 00 1 July 15, 2025

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.01 SUMMARY

A. The County may request submittals in addition to those specified when deemed necessary to adequately describe the Work covered in the respective sections.

B. Units of weights and measures used in all submittals are to be the same as those used in the

Drawings.

C. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with the Contract requirements.

D. Contractor's Quality Control Manager is to check and approve all items prior to submittal and stamp, sign, and date accordingly the action taken. Proposed deviations from the Contract requirements are to be clearly identified. Include within submittals items such as the Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including but not limited to catalog cuts, diagrams, operating charts of curves; test reports, samples; certifications; and other such required submittals.

E. Submittals requiring County/Engineer approval are to be scheduled and made prior to the acquisition of the item covered thereby

F. County or their Engineer may develop a project team site to more efficiently track the project submittals. If developed, Contractor shall use the team site to submit project deliverables.

1.02 SUBMITTALS

A. Construction Progress Schedule (See Section 01 32 16 Construction Project Schedule)

B. Weekly Progress Schedule Updates (See Section 01 32 16 Construction Project Schedule)

C. Daily Progress Reports - The Contractor shall record the following daily information on Daily

Progress Reports:

1. Date and signature of the author of the report;

2. Field notes of all surveys;

3. Notes on all inspections;

4. Details of Health and Safety inspections and meetings;

5. A brief description of any Change Orders, Field Orders, Claims, Clarifications, or Amendments;

6. Condition of all navigation aids (i.e., warning signs, lighted marker buoys)

7. and any repairs performed on them;

8. Weather conditions (adverse weather day, wind speed and direction, temperature, wave height, precipitation, etc.);

9. Basic production details for dredging.

10. The amount of time lost to severe weather, personal injury, turbidity violations, encounters with threatened or endangered species, etc.;

11. Notes regarding compliance with the Progress Schedule;

12. Visitor log.

D. A template of the Contractor’s Daily Progress Report shall be submitted to the County at least 14 days prior to the Pre-Construction Conference. The County shall have seven (7) days to perform a review and have the Contractor make any necessary revisions prior to acceptance of the report template. The daily progress reports shall be submitted to the County at the Weekly Progress

SECTION 01 33 00 2 July 15, 2025

Meetings in both hard copy and digital format (Adobe Acrobat® Format, or approved equal). The typical form for Daily Progress Reports shall be developed by the Contractor and incorporated into the Work Plan.

E. Dredge Plan: The Contractor shall prepare and submit no less than fourteen (14) days prior to the commencement of dredge activities to the County a dredge plan that identifies the Contractor’s order of execution of the dredging operations. The plan shall also describe the approach and methodologies for the before dredge survey and after dredge survey.

F. Disposal Plan: Contractor shall prepare and submit no less than fourteen (14) days prior to commencement of dredge activities to the County a disposal plan. The Disposal Plan must be approved by the County and the Engineer of Record before commencement of work. The Plan shall include, but not be limited to the following:

1. Material Characterization Plan: Contractor shall develop a material/sediment characterization plan to confirm that present conditions are consistent with the construction Plans and identify anything that is not consistent as part of this plan.

2. Disposal Site Information: Contractor shall identify an appropriate disposal site for all materials/sediments not deemed appropriate for beneficial re-use by the County. Contractor shall also specify the delivery of sediments approved for beneficial re-use to a County-approved facility for the benefit of public re-use.

3. Transportation Plan: Contractor shall develop a plan for transportation of all sediments and debris dredged from within the project dredge template to respective final destinations. The

Plan shall include the proposed means of transport, and a figure depicting the route of transport to final destinations.

G. Hurricane and Severe Storm Plan: Contractor shall develop and maintain a written Hurricane and

Severe Storm Plan. The Plan shall include, but not be limited to, the following:

1. Identify the type of actions will be taken before a storm strikes at the Project area.

2. The plan should specify what weather conditions and/or wave heights will require shutdown of the Work and removal of equipment, personnel, etc.

3. Notes from continuous monitoring of NOAA marine weather broadcasts and other local commercial weather forecasts.

4. Equipment list with details on their ability to handle adverse weather and wave conditions.

5. Methods of securing equipment.

6. Methods which will be used to secure equipment left on-site during adverse weather conditions.

7. Evacuation or immediate reaction plans to be taken by personnel for sudden storm occurrences.

8. Operations procedures which will be used to secure critical dredging equipment such as spuds, swing wires, anchor wires, or tugs during adverse weather conditions.

9. Communications protocol with local law enforcement and fire and rescue agencies.

10. The Hurricane and Severe Storm Plan shall be submitted to the County at least fourteen (14) days prior to the Pre-Construction Conference. The Contractor shall incorporate the Hurricane and Severe Storm Plan into a comprehensive Work Plan. The County and Engineer are not responsible for the adequacy of this plan.

H. Environmental Protection Plan (See Section 01 35 05 Environmental Protection) : The

Environmental Protection Plan shall be submitted to the County at least fourteen (14) days prior to the Pre Construction Conference.

SECTION 01 33 00 3 July 15, 2025

I. Health and Safety (See General Conditions, Safety, and Health Standards) : The Health and Safety

Plan shall be submitted to the County at least fourteen (14) days prior to the Pre-Construction

Conference.

J. Quality Control (QC) Plan: The…